Download as pps, pdf, or txt
Download as pps, pdf, or txt
You are on page 1of 34

Lean Manufacturing – eLearning Program

SYBEQ

Lean Principles

Click to proceed

1
Lean Manufacturing – eLearning Program
SYBEQ

Lean Principles

• Continuous flow manufacturing


• Takt time
• Non-value added activities
• Cycle time reduction

Click to go back

2
Lean Manufacturing – eLearning Program
SYBEQ

Principle 1:
Continuous Flow Manufacturing

3
Lean Manufacturing – eLearning Program
SYBEQ

Continuous Flow Manufacturing

• Material should always move one piece at a time


at the rate determined by the customer.

• Flow of product must be smooth and


uninterrupted.

4
Lean Manufacturing – eLearning Program
SYBEQ
Batch Production
• Groups similar machines and similarly skilled people
together. Material handling moves material between
these groups.

• Perceived Benefits - Economics of scale, Scheduling Flexibility

• Disadvantages
• Lot of Work in Process (WIP)
• Sitting inventory hides problems on the floor
• Time delay each time the material enters a group
increasing lead times.
5
Lean Manufacturing – eLearning Program
SYBEQ
Batch Production Vs Single Piece Flow
An Example
Consider a simple Radio Manufacturing process.
1. One group assembles the radio
2. Second one fits the speaker
3. Last group tests the radio

Material handling moves batches of size 50


radios between the groups at a time.

6
Lean Manufacturing – eLearning Program
SYBEQ
Radio Manufacturing Process - Batch

Radio Speaker Testing


Assembl fitting
y

Packing
&
Shipping
7
Lean Manufacturing – eLearning Program
SYBEQ
Batch Production Vs Single Piece Flow
Batch Process
Each group takes about 30 seconds per radio to
complete the tasks assigned.

So it takes 50 x 30 = 1500 sec or 25 min.for a batch


of radios to move between groups.

Ignoring the material handling time, it would take


25 x 3 = 75 min. to make and test the first batch of
50 radios.
8
Lean Manufacturing – eLearning Program
SYBEQ
Batch Production Vs Single Piece Flow

Batch Process
Thus, it takes 75 min. to get the first batch of
radios ready to ship, even though only 1.5minutes
of value-added work is needed to make a radio.

9
Lean Manufacturing – eLearning Program
SYBEQ
Batch Production Vs Single Piece Flow
Single piece flow
For the same example, lets organize the process
into a single-piece flow work cell.

The equipment needed for assembly, fixing the


speaker and testing are put next to each other.
Thus, we have created a cell.
No Inventory is allowed to build up between these
3 operations.
10
Lean Manufacturing – eLearning Program
SYBEQ
Batch Production Vs Single Piece Flow
Single piece flow – Cell layout

Radio Assembly Cell

Radio
Assembly
Packing
&
Shipping
Testing

Speaker
fitting

11
Lean Manufacturing – eLearning Program
SYBEQ
Batch Production Vs Single Piece Flow

Single piece flow


Since there are 3 operations, each taking 30 sec,
The first radio is processed in just…
30 x 3 = 90 sec. or 1.5 minutes.

Thus the single piece flow takes only 1.5min.


to get the first radio ready to ship.

12
Lean Manufacturing – eLearning Program
SYBEQ

Continuous Flow : Advantages


• Delivers a flow of products to the customer with
less delay
• Reduces cost of inventory
• Creates real flexibility
• Improves productivity and safety
• Requires less storage and transport
• Lowers the risk of losses through damage,
deterioration or obsolescence

13
Lean Manufacturing – eLearning Program
SYBEQ
Continuous Flow Layout
• Production steps arranged in a straight line or U
shaped cell.

• No WIP.

• Use of single piece flow.

• Each operator and station work with complete


reliability.

14
Lean Manufacturing – eLearning Program
SYBEQ

Principle 2: Takt time

15
Lean Manufacturing – eLearning Program
SYBEQ
Takt Time

• Time needed to produce as per customer


requirements.

• Used to determine pace of production in


continuous flow manufacturing.

16
Lean Manufacturing – eLearning Program
SYBEQ
Takt Time

Takt time = Net operating time per period


Customer requirements per period

where
Net operating time = (Time per shift) – (Time for breaks,
lunch)

Customer requirements = Products required per day

17
Lean Manufacturing – eLearning Program
SYBEQ
Takt Time - Example
A fastener company called DLK Ltd supplies
Screws to Great Cars Inc.
Great cars needs 50,000 screws each day.

DLK runs 1 shift of 8hours each day for


producing screws for Great cars. They have
30min lunch and 2 breaks each 10min long.

What is DLK’s Takt time?


18
Lean Manufacturing – eLearning Program
SYBEQ
Takt Time - Example
Takt time = Net operating time per period
Customer requirements per period

Takt time = (8 x 60) – 30 – (2 x 10)


50,000

Takt time = 480 – 30 – 20 = 430


50,000 50,000

Takt time = 0.0086 minutes/screw


19
Lean Manufacturing – eLearning Program
SYBEQ

Principle 3:
Non-value added activities

20
Lean Manufacturing – eLearning Program
SYBEQ
What are Non-value added activities?

• Waste that exists in the process.

• Activities not important to the customer.

• Work elements that the customer will not pay for.

21
Lean Manufacturing – eLearning Program
SYBEQ
Non-value added activities: Categories

1. Overproduction
2. Inventory
3. Repair / Rejects
4. Motion
5. Processing
6. Waiting
7. Transport

22
Lean Manufacturing – eLearning Program
SYBEQ
Overproduction

• Producing too much.

• Occurs because products are made


earlier or faster or more than is needed by
the next process.

• Uses extra space, raw materials, utilities,


transportation, scheduling costs.

23
Lean Manufacturing – eLearning Program
SYBEQ
Inventory
• Raw material, parts, WIP, supplies, finished
goods are all inventory.

• Uses extra space, transportation, labor,


interest on materials.

• Inventory sitting around gathers dust,


deteriorates, becomes obsolete, gets
damaged in handling.

24
Lean Manufacturing – eLearning Program
SYBEQ
Repair
Process
Repair
- labor
- additional material
Conforming Non conforming - normal continuous
product product flow gets affected.

Repair
Delivered to Inspection
customer OK Not OK
Delivered to Scrap
customer

25
Lean Manufacturing – eLearning Program
SYBEQ
Motion
• Extra unneeded movements
like excessive walks, lift heavy
loads, bend awkwardly, reach
too far, etc. are waste.

• Design new tools to help with strenuous and


tiring motions.

• Redesign workplace layout to take advantage


of the ergonomics.
26
Lean Manufacturing – eLearning Program
SYBEQ
Processing

• Additional steps in the manufacturing process.

• Examples
a. Removing burr
b. Reshaping a piece due to poor dies
c. Extra handling process due to lack of space
d. Maintaining extra copies of information

27
Lean Manufacturing – eLearning Program
SYBEQ
Waiting

• Operator remains idle waiting for the next


operation.

• Some causes for waiting are machine


downtime, lack of parts, line stoppages,
long changeover times, batch flow of
material.

28
Lean Manufacturing – eLearning Program
SYBEQ
Transport
• All forms of transportation are waste.

• Some examples are use of forklifts,


conveyors, trucks.

• Transportation waste is caused by poor plant


layout, poor cell design, use of batch
processes, long lead times, large storage
areas, scheduling problems.

29
Lean Manufacturing – eLearning Program
SYBEQ

Principle 4: Cycle-time reduction

30
Lean Manufacturing – eLearning Program
SYBEQ
Cycle-time reduction
• The amount of time needed to complete
a single task and move it forward in the
process.

• To make the line flow, all operations


must be completed under the takt time.

• Cycle time reductions improve quality,


reduce waste, increase capacity,
simplify the operation.
31
Lean Manufacturing – eLearning Program
SYBEQ
Cycle-time and Takt time (Example)
Process
Operation 1 Operation 2 Operation 3

Consider a process that has 3 operations.


Each operation has a pre determined takt time
based on the customer requirements and net
operating time available.
Cycle time is the total of takt times for all three
operations.

To reduce cycle time, each task must be completed


below the takt time. 32
Lean Manufacturing – eLearning Program
SYBEQ
Cycle-time and Takt time (Example)
Process
Operation 1 Operation 2 Operation 3

Operation Takt time


1 52 sec
2 45 sec
3 65 sec
Total 162 sec Cycle Time

33
Lean Manufacturing – eLearning Program
SYBEQ
Cycle-time reduction
• Kaizen teams take up cycle time reduction
projects.

• The project involves..


a. Data collection and analysis.
b. Work sampling, pace studies, line balancing,
elemental analysis, motion studies and takt
time calculations.

34

You might also like