Download as pdf or txt
Download as pdf or txt
You are on page 1of 3

TECHNICAL AND REGULATORY NEWS No.

22/2019 – TECHNICAL

TESTING OF STANDBY GENERATORS


WITHOUT CLASS ATTENDANCE
Relevant for ship owners and managers.

November 2019

Many ship operators do not seem to be familiar with our rule requirement updates released in
June 2018. Since then, the ship’s crew has been allowed to conduct the annually required class
test of the standby generator functionality without class attendance. Ship operators thereby
benefit from increased flexibility. This technical news summarizes the improved test procedures.

Background and necessity of the requirements The only way to discover these issues, to ensure that the vessel
The rules for annual surveys (Pt. 7, Ch. 1, Sec. 2 [3.1.5]) specify can restore power after a blackout and avoid even more
that “For all E0, AUT or AUT-nh vessels (built at any time) and dangerous situations, is by testing the systems. This test must
all vessels constructed on or after 1998-07-01 where electricity therefore be carried out, and, importantly, it must be carried
is necessary for propulsion and steering, test of the automatic out correctly. Simulating a blackout, i.e. triggering the standby
start and connection to the switchboard of the standby gen- generator to come on line without shutting down the single
erator set shall be carried out.” generator as required, will not reveal all hidden failures.

Where the vessel’s normal seagoing load is covered by a single Testing difficulties
generator, this test shall be conducted by shutting down the For various reasons, it is often difficult to conduct the test as
running generator, i.e. creating a blackout. For vessels where required: oil/gas terminals do not allow vessels to immobilize,
the normal seagoing load is covered by two or more genera- cargo operations are disrupted, the crew is afraid of damaging
tors, the test shall be conducted by shutting down one of the electronic equipment, etc. Whilst many of these challenges can
running generators. be overcome through good planning and preventive measures
such as shutting down non-critical equipment, this testing
Long-term experience shows that restarting the machinery requirement still inconveniences the vessel.
plant after a blackout is often problematic. This may be caused,
for instance, by incorrect system settings, crew unfamiliarity, New procedure for annual testing
empty or faulty UPS units or, not least, empty internal batteries To minimize the impact of the annual testing, class attendance
on chipboards or PLCs. during the standby functionality test is no longer required. This
allows for the test to be conducted at a more suitable time.

Page 1/2
If conducted less than three months before the annual survey, Recommendations
the test may be accepted during the annual survey. The test By preparing test procedures and conducting tests prior to the
shall be conducted according to a written procedure which, for annual surveys, vessels can limit the impact of annual surveys
ships where the normal seagoing load is covered by a single on the daily operations.
generator, shall include a blackout.
References
In general, the procedure shall address the relevant items ƒƒ DNV GL rules for classification: Ships (RU-SHIP):
listed in the Appendix (see page 3) under Annex I: Guidelines Pt. 7 Fleet in service, Ch.1 Survey requirements for fleet in
for standby functionality test procedure. This procedure does service – Sec. 2 [3.1.5]
not require class approval but should be presented to the Document code: DNVGL-RU-SHIP-Pt7Ch1
attending surveyor for his/her acceptance.
Appendix
The successful test shall be documented by a log book entry, a Annex I: Guidelines for standby functionality test procedure
signed statement by the Chief Engineer and a copy or screenshot
of the alarm log. If the test has not been conducted by the vessel
at the time of the annual survey, or the operator simply wishes to
conduct the test during the annual survey, this is still possible.

The test shall always be witnessed by class during renewal


surveys on all vessels and during annual surveys for vessels
where a poor condition and/or poor maintenance is registered.
CONTACT
Summary For customers:
In short, the testing of the generator standby functionality, DATE – Direct Access to Technical Experts via My Services on Veracity.
sometimes referred to as the “blackout test”, is no longer Otherwise:
required to be carried out during the annual survey. The test Email us at Hull.Machinery@dnvgl.com or
may, under certain conditions, be carried out without class use our office locator to find the nearest DNV GL office
attendance prior to the annual survey.

DNV GL – Maritime, Brooktorkai 18, 20457 Hamburg, Germany, Tel: +49 40 36149 0, www.dnvgl.com/maritime DNV GL Disclaimer of Liability
Appendix

ANNEX I: GUIDELINES FOR STANDBY FUNCTIONALITY ƒƒ Success criteria


TEST PROCEDURE ƒƒ If one (1) generator covers the normal seagoing load:
The standby generator shall supply power to the equipment
The test procedure shall as a minimum address the following: necessary for propulsion and steering and for ensuring the
safety of the vessel within 45 seconds.
ƒƒ Frequency and timing of testing ƒƒ If two (2) generators cover the normal seagoing load:
ƒƒ Minimum seagoing load as documented in the vessel The load shedding (tripping/load reduction) system shall
electrical load balance ensure that the remaining generator supplies power to the
ƒƒ Capacity of the installed generator sets equipment necessary for propulsion and steering and for
ƒƒ Various combinations of generators required to cover the ensuring the safety of the vessel.
normal seagoing load, if applicable ƒƒ Further testing of the standby functionality by shutting
ƒƒ Minimum equipment required to be running before and after down the running generator, i.e. creating a blackout, is
the test recommended but not required.
ƒƒ Disabling of the emergency generator ƒƒ If the load shedding (tripping/load reduction) system is
ƒƒ Disabling of the emergency generator by switching to unable to prevent the remaining generator from over-
“manual” is only required if the emergency generator would loading, the standby generator shall supply power to the
interfere with the standby generator’s starting sequence. equipment necessary for propulsion and steering and for
ƒƒ Method of triggering the standby functionality test ensuring the safety of the vessel within 45 seconds.
ƒƒ If one (1) generator covers the normal seagoing load, this ƒƒ Re-enabling the emergency generator, i.e. changing back to
is done by initiating the shutdown of the running generator “automatic” mode
to cause a blackout. ƒƒ Documenting the testing
ƒƒ If two (2) or more generators cover the normal seagoing ƒƒ Alarm log printout or screenshot
load, this is done by initiating the shutdown of one (1) ƒƒ Engine room log entry
running generator. ƒƒ Chief Engineer statement, including a reference to the
ƒƒ Description of the number and combination of generators to time taken to restore power and propulsion
be tested ƒƒ Errors observed and lessons learned
ƒƒ Different combinations are expected to be tested during ƒƒ Not necessarily limited to the restoration of power alone;
subsequent tests to ensure functionality with any combina- any other issues noted, such as malfunctioning emergency
tion of generating sets. lighting and UPS.

DNV GL – Maritime, Brooktorkai 18, 20457 Hamburg, Germany, Tel: +49 40 36149 0, www.dnvgl.com/maritime DNV GL Disclaimer of Liability

You might also like