20200311 Site observation

VH 06 50 MWP
1. THE WEATHER: Sunny
2. QUALITY PROBLEMS:
VH 06 SOLAR POWER PV POWER PLANT – EPC CONTRACTOR CHINT
BACKFILL WORKS

LOCATION: Backfill from P1 to P30 DESCRIPTION

Comment: Finished backfill, real


backfill area in site is about 60m2, not
yet compacted, contractor need to
compact soil and do compaction density
test then submit result to consultant for
review
Contractor is also requested to submit
approved topographic survey drawings
which show data of each ponds to be
backfill.

Total backfill is 164.022m2 (CHIN’s


number), The required compaction
density is 95%. (report on addition soil
investigation)
Comment: Finished backfill, not yet
compacted, contractor need to compact
soil and do compaction density test then
submit result to consultant for review
Contractor is also requested to submit
approved topographic survey drawings
which show data of each ponds to be
backfill.

Total backfill is 808.261m2 (CHIN’s


number), The required compaction
density is 95%. (report on addition soil
investigation)
Comment: Finished backfill, not yet
compacted, contractor need to compact
soil and do compaction density test then
submit result to consultant for review
Contractor is also requested to submit
approved topographic survey drawings
which show data of each ponds to be
backfill.

Total backfill is 216.445m2 (CHIN’s


number), The required compaction
1
20200311 Site observation
VH 06 50 MWP
density is 95%. (report on addition soil
investigation)
Comment: Finished backfill, not yet
compacted, contractor need to compact
soil and do compaction density test then
submit result to consultant for review
Contractor is also requested to submit
approved topographic survey drawings
which show data of each ponds to be
backfill.

Total backfill is 1651.962m2 (CHIN’s


number), The required compaction
density is 95%. (report on addition soil
investigation)
Comment: Finished backfill, not yet
compacted, contractor need to compact
soil and do compaction density test then
submit result to consultant for review
Contractor is also requested to submit
approved topographic survey drawings
which show data of each ponds to be
backfill.

Total backfill is 226.369m2 (CHIN’s


number), The required compaction
density is 95%. (report on addition soil
investigation)
Comment: Cannot reconige, look like
original ground. Contractor is requested
to submit approved topographic survey
drawings which show data of pond to be
backfill
P25

Total backfill is 217.629m2 (CHIN’s


number), The required compaction
density is 95%. (report on addition soil
investigation)
Comment: Finished backfill, not yet
compacted, backfill material look like
original soil. Contractor need to compact
soil and do compaction density test then
submit result to consultant for review.
Contractor is requested to submit
approved topographic survey drawings
which show data of pond to be backfill

Total backfill is 674.018m2 (CHIN’s


number), The required compaction
2
20200311 Site observation
VH 06 50 MWP
density is 95%. (report on addition soil
investigation)
Comment: Finished backfill, not yet
compacted, backfill material look like
original soil. Contractor need to compact
soil and do compaction density test then
submit result to consultant for review.
Contractor is requested to submit
approved topographic survey drawings
which show data of pond to be backfill
P23

Total backfill is 203.445m2 (CHIN’s


number), The required compaction
density is 95%. (report on addition soil
investigation)
Comment: Finished backfill, not yet
compacted, backfill material look like
original soil. Contractor need to compact
soil and do compaction density test then
submit result to consultant for review.
Contractor is requested to submit
approved topographic survey drawings
which show data of pond to be backfill

Total backfill is 573.503m2 (CHIN’s


number), The required compaction
density is 95%. (report on addition soil
investigation)
Comment: Cannot reconige, look like
original ground. Contractor is requested
to submit approved topographic survey
drawings which show data of pond to be
backfill

P21
Total backfill is 132.8072m2 (CHIN’s
number), The required compaction
density is 95%. (report on addition soil
investigation)

3
20200311 Site observation
VH 06 50 MWP
Comment: Finished backfill, not yet
compacted. Contractor need to compact
soil and do compaction density test then
submit result to consultant for review.
Contractor is requested to submit
approved topographic survey drawings
which show data of pond to be backfill

Total backfill is 960.844m2 (CHIN’s


number), The required compaction
density is 95%. (report on addition soil
investigation)
Comment: Finished backfill, not yet
compacted. Contractor need to compact
soil and do compaction density test then
submit result to consultant for review.
Contractor is requested to submit
approved topographic survey drawings
which show data of pond to be backfill

Total backfill is 929.832m2 (CHIN’s


number), The required compaction
density is 95%. (report on addition soil
investigation)
Comment: Cannot reconige, look like
original ground. Contractor is requested
to submit approved topographic survey
drawings which show data of pond to be
backfill P18

Total backfill is 159.107m2 (CHIN’s


number), The required compaction
density is 95%. (report on addition soil
investigation)
Comment: Cannot reconige, look like
original ground. Contractor is requested
to submit approved topographic survey
drawings which show data of pond to be
backfill P17

Total backfill is 129.711m2 (CHIN’s


number), The required compaction
density is 95%. (report on addition soil
investigation)
Comment: Cannot reconige, look like
original ground. Contractor is requested
to submit approved topographic survey
drawings which show data of pond to be P16
backfill

Total backfill is 690.201m2 (CHIN’s


4
20200311 Site observation
VH 06 50 MWP
number), The required compaction
density is 95%. (report on addition soil
investigation)
Comment: Finished backfill, not yet
compacted. Contractor need to compact
soil and do compaction density test then
submit result to consultant for review.
Contractor is requested to submit
approved topographic survey drawings
which show data of pond to be backfill

Total backfill is 618.832m2 (CHIN’s


number), The required compaction
density is 95%. (report on addition soil
investigation)
Comment: Finished backfill, not yet
compacted, backfill material look like
original soil. Contractor need to compact
soil and do compaction density test then
submit result to consultant for review.
Contractor is requested to submit
approved topographic survey drawings
which show data of pond to be backfill

Total backfill is 660.251m2 (CHIN’s


number), The required compaction
density is 95%. (report on addition soil
investigation)
Comment: Finished backfill, compacted.
Contractor need to do compaction
density test then submit result to
consultant for review.

Total backfill is 443.349m2 (CHIN’s


number), The required compaction
density is 95%. (report on addition soil
investigation)
Comment: Finished backfill, compacted.
Contractor need to do compaction
density test then submit result to
consultant for review.

Total backfill is 533.5089m2 (CHIN’s


number), The required compaction
density is 95%. (report on addition soil
investigation)

5
20200311 Site observation
VH 06 50 MWP
Comment: Finished backfill, not yet
compacted. Contractor need to compact
soil and do compaction density test then
submit result to consultant for review.
Contractor is requested to submit
approved topographic survey drawings
which show data of pond to be backfill

Total backfill is 672.941m2 (CHIN’s


number), The required compaction
density is 95%. (report on addition soil
investigation)
Comment: Finished backfill, not yet
compacted. Contractor need to compact
soil and do compaction density test then
submit result to consultant for review.
Contractor is requested to submit
approved topographic survey drawings
which show data of pond to be backfill

Total backfill is 926.39m2 (CHIN’s


number), The required compaction
density is 95%. (report on addition soil
investigation)
Comment: Finished backfill, not yet
compacted. Contractor need to compact
soil and do compaction density test then
submit result to consultant for review.
Contractor is requested to submit
approved topographic survey drawings
which show data of pond to be backfill

Total backfill is 739.23m2 (CHIN’s


number), The required compaction
density is 95%. (report on addition soil
investigation)

6
20200311 Site observation
VH 06 50 MWP
Comment: Finished backfill, compacted.
Contractor need to do compaction
density test then submit result to
consultant for review.

Total backfill is 1320.363m2 (CHIN’s


number), The required compaction
density is 95%. (report on addition soil
investigation)
Comment: Not yet finished backfill,

Total backfill is 3675.091m2 (CHIN’s


number), The required compaction
density is 95%. (report on addition soil
investigation)
Comment: Cannot reconige, look like
original ground. Contractor is requested
to submit approved topographic survey
drawings which show data of pond to be
backfill.

P6
Total backfill is 314.804m2 (CHIN’s
number), The required compaction
density is 95%. (report on addition soil
investigation)
Comment: Cannot reconige, look like
original ground. Contractor is requested
to submit approved topographic survey
drawings which show data of pond to be
backfill.

Total backfill is 1251.796m2 (CHIN’s


number), The required compaction
density is 95%. (report on addition soil
investigation)
Comment: Cannot reconige, look like

7
20200311 Site observation
VH 06 50 MWP
original ground. Contractor is requested
to submit approved topographic survey
drawings which show data of pond to be
backfill. P4

Total backfill is 5610.156m2 (CHIN’s


number), The required compaction
density is 95%. (report on addition soil
investigation)
Comment: Cannot reconige, look like
original ground. Contractor is requested
to submit approved topographic survey
drawings which show data of pond to be
backfill.

Total backfill is 2472m2 (CHIN’s


number), The required compaction
density is 95%. (report on addition soil
investigation)
Comment: Finished backfill, not yet
compacted. Contractor need to compact
soil and do compaction density test then
submit result to consultant for review.
Contractor is requested to submit
approved topographic survey drawings
which show data of pond to be backfill

Total backfill is 1616.08m2 (CHIN’s


number), The required compaction
density is 95%. (report on addition soil
investigation)
Comment: Finished backfill, not yet
compacted. Contractor need to compact
soil and do compaction density test then
submit result to consultant for review.
Contractor is requested to submit
approved topographic survey drawings
which show data of pond to be backfill

Total backfill is 8665.596m2 (CHIN’s


number), The required compaction
density is 95%. (report on addition soil
investigation)

8
20200311 Site observation
VH 06 50 MWP
Note :
1. Contractor is requested to submit approved topographic survey drawings which show
data of pond to be backfill. This is for confirm backfill quantity.
2. Contractor need to compact soil and do compaction density test then submit result to
consultant for review.

9
20200311 Site observation
VH 06 50 MWP

PONDING QUANTITY
Ponding
area Area in Datum of Exisiting Bottom Avg Depth of
number Sqm Filling Level Filling Qty in Cum Site Observation
P1 8665.60 15.700 15.500 0.100 867 Finished backfill, not yet compacted.
P2 1616.08 16.100 15.760 0.170 275 Finished backfill, not yet compacted.
P3 2472.00 16.400 16.280 0.060 148 Cannot reconige, look like original ground
P4 5610.16 16.400 16.270 0.065 365 Cannot reconige, look like original ground
P5 1251.80 17.500 16.900 0.300 376 Cannot reconige, look like original ground
P6 314.80 19.100 18.820 0.140 44 Cannot reconige, look like original ground
P7 3675.09 17.500 16.470 0.515 1893 Not yet finished backfill
P8 1320.363 19.300 19.100 0.100 132 Finished backfill, compacted.
P9 739.23 19.300 19.100 0.100 74 Finished backfill, not yet compacted
P10 926.39 19.200 19.150 0.025 23 Finished backfill, not yet compacted
P11 672.941 18.500 18.390 0.055 37 Finished backfill, not yet compacted
P12 533.5089 19.300 19.200 0.050 27 Finished backfill, compacted.
P13 443.349 19.400 19.120 0.140 62 Finished backfill, compacted.
P14 660.251 19.400 19.210 0.095 63 Finished backfill, not yet compacted
P15 618.832 19.300 19.030 0.135 84 Finished backfill, not yet compacted
P16 690.201 17.400 17.310 0.045 31 Cannot reconige, look like original ground
P17 129.711 17.300 17.160 0.070 9 Cannot reconige, look like original ground
P18 159.107 17.300 17.170 0.065 10 Cannot reconige, look like original ground
P19 929.832 19.200 19.070 0.065 60 Finished backfill, not yet compacted
P20 960.844 19.100 19.030 0.035 34 Finished backfill, not yet compacted
P21 132.8072 19.400 19.290 0.055 7 Cannot reconige, look like original ground
P22 573.503 19.400 19.310 0.045 26 Finished backfill, not yet compacted
P23 203.445 19.400 19.340 0.030 6 Finished backfill, not yet compacted
P24 674.018 19.400 19.340 0.030 20 Finished backfill, not yet compacted
P25 217.629 19.400 19.010 0.195 42 Finished backfill, not yet compacted
P26 226.369 14.400 14.100 0.150 34 Finished backfill, not yet compacted
P27 1651.962 13.600 12.800 0.400 661 Finished backfill, not yet compacted
P28 216.445 11.200 11.130 0.035 8 Finished backfill, not yet compacted
P29 808.261 9.400 9.000 0.200 162 Finished backfill, not yet compacted
P30 164.022 9.400 9.170 0.115 19 Real backfill area is about 60m2, not yet compacted