Professional Documents
Culture Documents
Terra Et Aqua 158 Complete 02 04 2020 PDF
Terra Et Aqua 158 Complete 02 04 2020 PDF
CONTRACT SELECTOR
Procure a project with a
quantifiable contract model
NATURE’S CURE
To solve large-scale problems
with nature or not is the question
PROTECTIVE SAND
FROM IDEA
TO REALITY:
THE UK’S FIRST
SANDSCAPING
PROJECT
CONTENTS
CONTRACTS
ENVIRONMENT
Nature-based
solutions: challenge
or opportunity?
Can nature-based solutions be
mainstream solutions? Nature-based
solutions have obvious advantages
but have not been embraced at wider 32
scale. The barriers which can hinder
wide-scale application and the topic’s
PROJECT
relevance to the dredging community
are discussed.
From idea to reality: the UK’s
first Sandscaping project
The Bacton Sandscaping scheme is a
large-scale beach nourishment designed to
protect the Bacton Gas Terminal from cliff
and beach erosion while also reducing flood
and erosion risk to the communities of Bacton
21 and Walcott, buying the time they need for
adaptation to coastal change.
46 50
4 TERRA ET AQUA
EDITORIAL
MANAGING
RISKS:
HOW TO
SELECT THE
APPROPRIATE
DREDGING
CONTRACT
6 TERRA ET AQUA
The contracting environment for dredging and
offshore works is diverse. Moreover, increasing
financial and/or managerial constraints are requiring
contracting parties to change the apportionment
of commercial risk. Contractors and suppliers have Different types
to adapt to the contractual set-up, which is chosen of dredging have
unilaterally by the owner, and they need to reconsider
how to manage their risks and how to procure different inherent
their service providers. Turnkey and engineering, risks and require
procurement, and construction (EPC) contracts different procurement
are becoming more common in the industry and
bring their own benefits and challenges. solutions in order
to be effective.
The Working Group on Effective Contract 3. The third part combines the output of the a whole (i.e., depending on a user’s specific
Type Selection (WGECS) proves guidance on first two parts, resulting in an objective requirements, value can be gained from
contracting for key stakeholders participating scoring methodology that allows users referring to only one section or the document
in a contract. This article has three component to compare their specific project with as a whole in assisting the selection of a
parts: various standardised contract types. suitable contract type).
1. The first part is a generic procurement
process flowchart that visualises the The principle of this guidance article is Further, this article is specifically designed
procurement process as a whole. Five two-fold. Firstly, it is meant to provide a to be able to be read alongside, and be
stages are described and explained that simple, easy-to-access guide to the general complementary to, the CEDA Checklist for
set out the main considerations to be procurement path, including the overall Successful Dredging Management (CEDA,
taken into account by those procuring process, important points of consideration 2017). Together, these publications set forth
works, resulting in the selection of the that may be taken into account, and guidance tailored guidance that can be utilised by
contract type; on the various factors influenced by certain organisations involved in the practical and
2. The second part, a table setting out certain standard contract types. Secondly, it contractual delivery of dredging projects
key aspects that may be taken into account provides a more in-depth, analytical method worldwide.
when assessing the contracting method, of objectively measuring a user’s specific
ties seamlessly in with the CEDA Checklist project and related requirements/constraints Procedure for contract/procurement
for Successful Dredging Management. and comparing this measurement against selection
The strength of this table is that it is standardized contract types. This allows a Introduction
established by a DMC-recognised group user to apply a more scientific, auditable, and Choosing an effective contract type for
of specialists operating at both sides of demonstrable basis for the ultimate contract dredging projects is not just a simple decision
dredging and offshore industry – both selection, and it compares with the more made by selecting an ‘off the shelf’ standard.
owners and contractors. The table includes generic and basic methods of selection. It takes time to properly consider the risks
six key aspects of procurement route/ and the conditions of the project. In Figure 1,
contract selection and details numerous The drafting of this guidance article is CEDA seeks to provide a structured approach
sub-aspects that can be used to assess specifically made to allow each part of it to to the relevant steps and options that bear
the optimum procurement strategy; be used either independently or together as consideration.
8 TERRA ET AQUA
FIGURE 2
The CEDA Checklist for Successful Dredging finance], different contracts for various opportunity that the overall project contract
Management (CEDA, 2017) can be of further geographical locations where works expenditure is less.
assistance to gather all elements that need have to be performed or through another
further consideration. logical combination of works relating to After careful analysis of the division of work
market characteristics and the number and risks and opportunities associated
Step 2: Packaging of work of potential competitors); therewith, project owners should decide
(iterative with step 3) 0 which party has the best capacity to which division is most appropriate for it and/
If the project is sufficiently defined, the phase prepare, tender, execute, and manage (a or the project. During a risk/opportunity
of packaging of the project work commences. particular type of) the contract works; analysis, at least the following elements
Packaging of work can best be achieved by 0 more contracts increase the should be considered: technical aspects,
dividing the project into different components dependency of various contractors and legal and financial matters, geographical
of work. Most projects are based on a work lead to more interfaces. locations, and spatial and safety elements.
breakdown structure to assist the engineering. For the main work components, it is
The following non-limitative questions merit Step 3: Risk/opportunity analysis important to properly consider what
consideration: A risk and opportunity analysis needs to negative consequences there may be and
• The ‘make or buy’ decision: Is outsourcing be performed to establish a procurement if and how these can be avoided. Elements
the best decision for each component of strategy. The packaging of work should be like health and safety, the environment,
work? If so, in how many contracts are the considered simultaneously with the risks and the schedule, budget overruns, and the
works divided? While considering which and opportunities involved in a particular division of quality of work should be considered, as well
how many contracts are outsourced, the works. While considering various combinations as what the causes might be of negative
following should be considered: for the division of works, the risks involved with consequences and which party is best
0 what type of contracts are appropriate each combination should be weighed. Dividing suited to take and to influence the risk.
(i.e., integrated contracts, stand-alone works into various contracts may lead to more
contract for various disciplines and interfaces and, consequently, a risk for the A good market analysis, including an
contract work types (e.g., basic and owner to be responsible for disputes arising estimation of the equilibrium of demand (for
detailed) engineering, surveys, civil out of improper alignment of the interfaces. services) and supply (of providers), is very
construction, blasting, maintenance, The same division may also lead to the useful in procurement. Such an analysis
TABLE 1
In the following table, a number of standard contract types with different risk allocations are set out. The last column gives boundary conditions and
key checks to be considered.
*This is based on a generalisation — the specific risk allocation is always dependent upon the specific terms of a particular contract.
Owner Contractor
Construct only • Price variable – per m3/ • Production risk • Availability of • Knowledge of what is suitable
Charter (for capital and hour • Quality/outcome risk equipment equipment for the dredging
maintenance work) • Flexible arrangements • Risk of quantities needs
• Less information needed • Soil conditions • Ability to give the right
• Availability can be defined • Availability equipment directions
in the contract • Inspection of performance
needed
Construct only • Volumes are measured by • Risk of quantities • Production risk • Correction of tender volumes
Remeasurable (for in- and out-survey • Soil conditions • Performance risk after in-survey
capital and maintenance • Quantities can be defined • Design
work) in the contract
Construct only • Clear scope required to • Scope change/flexibility • Production risk • Allocation of risk
Lump sum (for capital allow effective pricing • Lack of flexibility/ability • Result risk • Setting clear scope
work) • Rick for unknowns to be to influence • Risk of quantities • Design development
allocated
Maintenance • Price is higher • Level of price • Production risk • Having historical data to
Performance-based • Result is described and • Lack of flexibility/ability • Result risks calculate the needed volumes
Lump sum contracted to influence • Risk of quantities to be dredged
• Focus on performing to • Soil conditions • Ability to control the quality and
contract • Risk availability of result (performance)
• Less flexible equipment reduces
Design & construct • Higher risk on contractor • Production is as • Output • Quality of preliminary design
• Owner has to clearly foreseen/expected • Quantities • Permits/approvals
define scope • Sufficiency of • Soil conditions • Clear scope of work and/or
• Lack of flexibility for owner preliminary design • Quality functional requirements
• Soil conditions • Design responsibility/ • Define design liability
liability
• Resource availability
Design & construct • Highest risk on contractor • High cost • Output • Quality of preliminary design
++/EPC • Owner has to clearly • Definition of scope • Quantities • Permits/approvals
define scope • Lack of ability to • Soil conditions • Clear scope of work and/or
• Lack of flexibility for owner influence • Quality functional requirements
• High cost of changes • Design responsibility/ • Define design liability
liability
• Resource availability
10 TERRA ET AQUA
TABLE 2
F. Price & Valuation How much security of price does the owner
want?
TABLE 3
A. Project scope
Sub-category Remarks/clarifications
(Environmental) Permitting Final (environmental) permitting can be granted before a tender is issued, or environmental
permitting might be made during tendering phase, or even with input by contractor, after
project award.
Complexity of project Complexity of project to be appreciated by owner for contract and procurement type
selection, influencing content or project outlining documents and determining pricing and risk
assessment by contractor.
Fitness for purpose Checks to be made by owner if deliverables/products are fit for purpose.
Achievability of the owner’s Owner to verify if requirements indeed can be/are met, contractor to accept during
requirements contracting.
Selection of placement site Selection of placement site to be defined as often restricted by authority regulations, largely
affecting pricing of the works.
Design effort needed Design effort needed to be reflected by party in charge of design development: (consultant on
behalf of) owner, (consultant on behalf of) contractor, or jointly.
Design requirements Design requirements to be unambiguously specified, in principle by owner, but depending on
contract type, with input by contractor, especially when cost savings are achievable.
Measurement of volumes Method of volume measurement to be specified and adhered to, as basis for acceptance and
payment.
Survey requirements Survey requirements are to be specified, to provide essential data for contract evaluation.
Material supply Owner’s specifications on material supply to be priced, accepted and adhered to by contractor.
Quality control Owner’s specifications on quality control procedures to be priced, accepted, and adhered to
by contractor.
should lead to a balanced decision as to should, amongst other things, consider the • It is also important to consider the
what procurement strategy is employed, following questions during this step: number of possible competitors and the
how work is divided, and which party can • Is it clear what the result of the contract complexity of the projects, the contract
be best suited in controlling and managing should be (functional, designed, and the risk allocation standard, and an
risks. engineered, service provided, needed understanding of whether there should
production capacity of equipment hired, be a dialogue between stakeholders
Step 4: Contract type selection number of hours equipment rented)? to manage expectations and clarify
After a work division is decided upon • Is it reasonable and calculable to ask for requirements.
following a risk and reward assessment, the a lump-sum price or should there be unit • How much time and dialogue are needed
question turns to which type of contract rates or a mixture of both? for contractors to understand the
is best suited to allocate the risks and • What is the right proportion to allocate contract, to investigate the situation,
rewards in accordance with the outcome of the risks in terms of money (think of the to calculate their price, and to offer the
steps 2 and 3. If the previous steps lead to mentioned aspects of dredged material, quality needed? The extent of the time
the conclusion that various project works survey, weather, tide, permits, etc.)? and input needed will be dependent
are combined, this will lead to an integrated • Is the project owner capable of managing upon a number of factors, which should
contract. In addition, in this phase the the contract and the specified result? be allowed for.
risk allocation of the work packages is
important. Although the previous steps may Step 5: Procurement method Step 6: Procurement process
result in shifting risks towards a contractor, If the project is designed and the leading to contract award
it may not always be feasible to exclude contract(s) is designed, the way to select If the previous choices are made, the
all risks sought to be shifted away. It will a contractor needs to be chosen. For procurement strategy is designed, and
therefore be necessary to consider which public authorities, in many countries there the user will pass step 6. Thereafter, it
party is best equipped to absorb certain are public procurement laws that should will further be important for the project
types of risk. be complied with. For private clients, it stakeholders to consider the ways to
is important also to consider alternative control the execution of the project. There
Among the important risks are the procurement mechanisms. Important should be a verification mechanism to learn
quantities of material to be dredged, the questions are: if the contract deliverables are met and the
probability of variance of scope, the • Should the contract be awarded only on quality is acceptable. Choices are to be
physical site conditions, the chemical price or also weighted between price and made on:
substance of dredged material, and quality? This depends on whether the • relying on quality management and
weather and wave conditions. The ability to owner requires added value and whether certificates of the contractor;
ascertain if there is insufficient information a contractor can add value upon the • monitoring systems or mankind control
may lead to one contract type or another. minimum quality defined in the contract of amounts or constructions;
and if one is able to measure this added • independent inspection to be hired.
General aspects such as permits, a legal value and verify the promised efforts
framework, stakeholder engagement, during the course of the contract.
financial boundaries, environmental impact, • Should the number of competitors be
and political pressure might also play a limited? What are minimum requirements
part in the type of contract used. Parties for subscribers?
12 TERRA ET AQUA
TABLE 5
TABLE 6
TABLE 7
FIGURE 3
14 TERRA ET AQUA
TABLE 8
Key Aspects
A. Project scope
When assessing the most suitable
10
procurement method/contracting type, CEDA 9
8
considers the matter to comprise certain 7
‘key aspects’, being general categories of 6
5
consideration of significant importance, which F. Price & valuation B. Physical/environmental site conditions
4
even those influencing the owner’s interests. In this ‘Visualisation of Owner’s Uncertainty’, the higher value indicates increased
The users can utilise, amend, or prioritise the uncertainty.
TABLE 9
Standard/typical types
Construct only
Construct only
/ maintenance
D&C++/EPC
– lump sum
– lump sum
– lump sum
– lump sum
– charter
16 TERRA ET AQUA
sub-aspects, giving relevant weight in ‘scoring’ variability/fixity the user can accept, based • Design & construct – Lump sum;
these items. The key aspects and their sub- on matters such as the ability to manage and • D&C++/EPC – Lump sum.
categories are found in Tables 3-8. control risk, or the level of knowledge/certainty For each contract type noted, typical scores
of a specific key aspect. against each of the key aspects are found in
For example, for key aspect ‘project scope’, the Table 9.
first listed sub-aspect is the ‘(environmental) In assessing the score for each key aspect, the
permitting’. The user may wish to consider user can choose to utilise or develop its own This plotting of the key aspect scores
how much of the permitting process has been sub-aspects and to weight the importance of graphically illustrates the differences between
completed, how many permits are secured at each of these sub-aspects within each key the contract requirements/parameters in
the start of the procurement process, and what aspect. For example, for key aspect 1 – project question against the six standard contract
implications will the permitting conditions have scope, CEDA has identified 13 subcategories. types listed in Table 9. The farther away from the
on the project scope. An assessment of this centre of the chart, the higher the uncertainty/
sub-aspect, if included, can be made by the user The user may consider these are all relevant variability of the key aspect for the user.
and appropriate weighting applied. or may wish to remove some or add others. In
addition, the user may then wish to place more As an example: lump sum contracts (should
The remarks/clarifications on the right side importance on half of the sub-aspects and can have) greater fixity of outturn
of the table provide (limited) information on carry out objective scoring on that basis. cost than a remeasurable or charter/hire form
why and how the specific sub-aspect might of contract. Accordingly, for the
influence procurement and contract type Each of the six ‘scored’ key aspects can ‘price & valuation’ key aspect, this scores
selection, and possibly indicate directions then be plotted against other, standardised highly for ‘Construct only – Charter’ and low for
on how the user can prepare a suitable results, providing valuable insight, advice, lump sum forms of contract (see Figure 4).
procurement process. and guidance to inform the user on what
the optimum contract type may be for any This approach can be utilised by a user wishing
The scoring matrix particular project. to carry out a comparative assessment. It
Introduction can also be used to illustrate the basis of a
The principle of the method developed by Standard Scoring Charts decision on the type of contract that may be
CEDA in advising the procurement route/ Six standard types of contract model are appropriate for the project to be procured,
contract type selection is the ‘scoring’ and addressed including: which can be presented or used accordingly
subsequent comparison of the six key aspects • Construct only – Charter; internally within the user’s organisation.
set out in Tables 3-8. For each of the key • Construct only – Remeasurable;
aspects, a relative ‘score’, ranging from 1 to • Construct only – Lump sum;
10, can be assessed and applied. This scoring • Maintenance – Performance-based –
range can relate to either the amount of Lump sum;
TABLE 10
– lump sum
Lower end Upper end
Key aspects (score = 1) (score = 10)
A. Project scope Fully fixed Very open/uncertain 5 0.50 0.71 1.00 2.50 1.67 5.00
B. Physical/environmental Fully explored Very uncertain 7 0.70 1.17 1.75 2.33 2.33 3.50
site conditions
C. Risk allocation/liabilities Risks and liabilities Risks and liabilities 10 1.00 1.25 1.67 5.00 3.33 10.00
with contractor with owner
D. Owner’s control/ Contractor freedom to Owner in control 10 1.00 1.67 2.00 5.00 3.33 10.00
contractor’s flexibility operate
E. Time & schedule Strict time frame Flexible time frame 5 0.50 0.83 1.00 2.50 1.25 2.50
F. Price & valuation Fully fixed Remeasurable based 5 0.50 0.71 1.00 1.67 1.67 5.00
on rates
Example: utilisation of the scoring These sample scores can then be dashed line) closely to ‘Construct only –
method compared, on a proportional basis, against Remeasurable’ (the orange line) based on
Against this standard table, users can the standardised scoring for each key the summation of each proportional scoring
apply and compare their own assessed key aspect and each standard contract type. assessment. This scoring method provides
aspect ‘scores’. This comparison can be This comparison is represented by way valuable assistance to the user when
made either to the standardised scores in of variance, as a factor, from each of the making an informed decision on the contract
the table or using the radar charts. standardised scores for each specific item. mechanism to be adopted.
18 TERRA ET AQUA
processes and procedures. From this, users
may adjust, amend, or otherwise update their
A. Project scope processes as may be deemed appropriate.
10
9
8 Stage 2 allows users to look at, consider,
7
6
and appraise their own specific project and
F. Price & valuation 5
B. Physical/environmental site conditions contract key aspects. These are based upon
4
3 the six listed key aspects which include
2 numerous sub-categories (which will be
1
0
of greater or lesser relevance to individual
users) and can be taken into account when
determining the most appropriate contracting
route.
E. Time & schedule C. Risk allocation/liabilities
Finally, users can quantify the various key
aspects based on their specific and project
requirements. This quantification can be
D. Owner’s control/contractor’s flexibility directly compared with the standard contract
Construct only – charter type scores. This can provide helpful, visual
Construct only – remeasurable assistance in considering the optimum
Construct only – lump sum contracting route, along with the ability to
Performance-based / maintenance – lump sum calculate the level of overall parity between
Design & construct – lump sum
a specific project and the standard profiles
D&C ++ EPC – lump sum
explained.
Sample score
Summary
This paper has been prepared by the Central Dredging Association (CEDA) Working Group on Effective Contract Type
Selection (WGECS). The Working Group was initiated by the CEDA Dredging Management Commission (DMC).
The WGECS was established by the DMC to follow on from and complement its Checklist for Successful Dredging
Management (CEDA, 2017). This checklist has been produced by a group of industry experts with various backgrounds,
perspectives, and a broad range of expertise and experience with dredging projects. It presents a number of topics and
subtopics that may give rise to problems/issues in the different stages of a (dredging) project. The first edition of this
checklist is currently freely available for download from the CEDA website to all CEDA members (www.dredging.org).
The contents of this paper are © Central Dredging Association (CEDA). Permission is given to reproduce this document, in
whole or in part, provided that the copyright of CEDA and the source are acknowledged.
CEDA (2017).
CEDA’s Checklist for Successful Dredging Management. Information Paper.
Available at: http://www.dredging.org/media/ceda/org/documents/resources/
cedaonline/2017-checklist.pdf [Accessed October 2019]
CITATION
CEDA (2019).
Effective Contract-Type Selection in the Dredging Industry. A Guidance Paper.
[Online] Available at: http://www.dredging.org/media/ceda/org/documents/resources/
cedaonline/2019-12-ECS.pdf
on Effective
Contract Type
Members of the CEDA Working Group on Effective Contract-type Selection
Selection (WGECS).
Charles Wilsoncroft (Chair) Harry Zondag
HKA Ministry of Infrastructure and Water
Management, Rijkswaterstaat
Claudia Knijnenburg
Port of Rotterdam Kathleen De Wit
IMDC
David Gwillim
BDB Pitmans LLP Johny Van Acker
DEME
David Kinlan
Kinlan Consulting Luc Imbrechts
Imbrechts & Van den Nest
Dirk-Jan Karssen
Fugro Murat Ege
Arti Proje
Dirk Roukema
Blue Pelican Associates Ralph Hubert
Wasserstrassen- und Schifffahrtsamt
Gerard van Raalte
Bremerhaven
GRA Consultancy
Stan Putter
Conway Advocaten & Attorneys
at Law
20 TERRA ET AQUA
ENVIRONMENT
NATURE-BASED
SOLUTIONS:
CHALLENGE OR
OPPORTUNITY?
#158 - SPRING 2020 21
ENVIRONMENT
Nature-based
solutions are actions
to protect, sustainably
The European Dredging Association (EuDA)
participated in a Horizon 2020 project sponsored by the manage, and restore
European Union. The project named ThinkNature had natural or modified
as objective to promote the application of nature-based ecosystems.
solutions (NBS). NBS have obvious advantages but
have not been embraced at wider scale. In this article,
the authors reflect as to why NBS are not mainstream
solutions, why it is necessary to promote the concept
and whether there are barriers that hinder wide-scale
application. In this article the authors describe how
relevant the topic is to the dredging community.
What are nature-based solutions? to nature-based solutions as sustainable Even with this more explicit description,
The concept of nature-based solutions responses to specific societal challenges: the concept of NBS still remains very
(NBS) is relatively recent. It has emerged · solutions that are inspired and supported broad covering a wide variety of ecological
during discussions at the United Nations by nature, approaches and ecosystem-based disciplines.
Framework Convention on Climate Change · which are cost-effective, In other words, NBS can be viewed as an
(UNFCCC) in 2009. This concept has the · simultaneously provide environmental, umbrella concept that covers more common
advantage of encompassing a broad range of social and economic benefits and, terminology such as conservation, restoration,
diverse approaches and is thus convenient · help build resilience. mitigation, adaptation or more familiar
for promotional purposes. Nevertheless, a approaches such as building with nature,
definition is needed for practical use. Such solutions bring more, and more diverse, ecological engineering and so forth.
nature and natural features and processes
The International Union for Conservation into cities, landscapes and seascapes, through Table 1 illustrates this large scope. It should
of Nature (IUCN) has proposed a useful locally adapted, resource-efficient and be noted that there is considerable overlap
definition: systemic interventions. between the various categories or approaches.
Nature-based solutions are actions to
protect, sustainably manage, and restore
natural or modified ecosystems. NBS address
societal challenges effectively and adaptively, TABLE 1
simultaneously providing human well-being An overview of possible categories of NBS and examples of each category.
and biodiversity benefits.
Categories of nature-based approaches Examples
The IUCN also clarified that:
Ecosystem restoration approaches Ecological restoration
NBS are designed to address major societal
Ecological engineering
challenges, such as food security, climate
Forest landscape restoration
change, water security, human health, disaster
risk, social and economic development. Issue-specific ecosystem-related Ecosystem-based adaptation
approaches Ecosystem-based mitigation
It is clear that IUCN considers NBS as a very Climate adaptation services
wide-ranging concept that should play a role in Ecosystem-based disaster risk reduction
solving humanity’s main challenges. In order to
Infrastructure-related approaches Green infrastructure
make it more operational, the concept needs
Building with nature
more focus and further refinement. To this end,
Engineering with nature
the European Commission (EC, 2015) refers
22 TERRA ET AQUA
The ThinkNature project The prime examples of such problems are Via this framework, it becomes evident that the
In view of the large number of possible found in the consequences of climate change dredging sector can tackle many problems or
approaches, the TN project took a pragmatic (temperature, precipitation, drought and sea threats in river and/or coastal environments by
start by listing good examples. They made an level rise) and the disasters they may cause. implementing NBS. It is therefore important to
inventory of case studies that are thought ‘Green’ projects can form building blocks for articulate the major role that dredging and
to be representative of NBS and compiled climate change adaptation. marine contracting can play in this context.
them in a data bank OPPLA which is publicly
available (https://platform.think-nature.eu). In the current OPPLA data base some 80% of So, why have NBS not been embraced at
the reference cases relate to urban situations. wider scale? Why is it necessary to promote
Next, the project reviewed the conditions for As representatives of the dredging sector the concept? Are there barriers that hinder
wider application of NBS type projects. This participating in the project, the authors pointed wide-scale application?
resulted in an overview of barriers and benefits out that besides solving urban problems, the
of these NBS projects. While the benefits of NBS concept can be meaningfully applied The ThinkNature project explored these
nature-based approaches may be apparent, to broader fields. There is a huge potential issues. Hereafter, the article discusses the
they are not yet well known by the public at for instance to use ‘green’ or ‘blue’ civil major aspects that distinguish NBS from more
large. Moreover, several institutional barriers infrastructure to combat risks of flooding and traditional approaches. A more exhaustive
related to financing, procurement practices natural disasters. coverage of these topics may be found in the
and organisational structures slow down ThinkNature Handbook (ThinkNature, 2019).
wide-scale introduction of innovative The authors proposed a framework as shown in
solutions, including NBS. Table 2, which clearly differentiates the various Wide range of ecosystem benefits
NBS approaches used in urban environments, Variability
A further step in the analysis considered more rural landscapes, river catchments and for As explained with Table 2 above, Nature-based
specifically the type of problems for which coastal protection. Two cases – in Seoul and Solutions (NBS) necessarily build on natural
a nature-based solution would be required. West Africa – illustrate this. processes and functions, both of biological and
TABLE 2
I. Pressures/issues II. Drivers/catalysts III. Relevant ecosystem process IV. Typical NBS responses
Coastal zones Sea level increase Sediment transport Restore natural sea defences
Increased erosion Storm intensity Energy dissipation (sandy, mangrove, marsh, etc.)
Coastal flooding Wave energy Hydrodynamics Stimulate natural defences
Wave attack Bioturbation (sediment supply, barriers, etc.)
Sediment shortage Carbon cycling Combinations of soft and hard defences
Urbanisation Management strategies
Two Examples
Seoul Mangroves in West Africa
Problem/causes: A densely built-up city experiences negative Problem: In a West African country a long period of drought
effects such as heat islands (I) during high temperature (II) (II) has caused the death and destruction of a mangrove
periods. forest in brackish water causing poor flora (I). The local
Processes and NBS: Providing open space in a city section population has lost a significant source of income (e.g.,
could be combined with a process of evaporation (III). A firewood,, shrimps culture, medicinal plants); also the
river flows through the town, but has been covered since groundwater is now subject to siltation because the barrier
many years (poor smells!). The water quality of the river provided by mangrove roots is no longer there.
has improved over the years and there is the possibility to
re-open the river and develop river banks inside the city by Processes and NBS: Once the period of drought is over,
de-culverting (IV). support to the local population to replant the mangroves for
buffering (III) is an effective NBS leading to restoration (IV).
Results: The effect will be to lower the temperature during
a hot spell (water temperature lower, evaporation), and by Results: The local economy will be re-established, the local
developing the banks as green space there are multiple society is stabilised and the benefits of this ecosystem
benefits for nature and for the population. The example of materialise again. Wider ecosystem benefits include also the
Seoul that can be found in the data base illustrates this positive effects for the carbon balance, since mangroves
solution very well. form important carbon sinks.
24 TERRA ET AQUA
Pressures
Hazard
Structure (physical, biological)
Ecosystems benefits
FIGURE 1 FIGURE 2
of physical nature. This observation points takes place and as a consequence the (nitrogen, carbon and phosphorus cycling;
immediately to the first difficulty experienced system can evolve towards higher levels of see Figure 1).
when implementing NBS: the evolution of biodiversity; they usually have the capacity to
natural systems can be influenced by human recover from disturbances (resilience). Ecosystem benefits
action to some extent, but there remains Healthy functioning ecosystems provide
always an element of uncertainty and limited Within the ecosystem one can further benefits for nature and for mankind. In the
predictability. The limits of predictability and distinguish several aspects or attributes: Millennium Assessment (2005) these
knowledge represent the first significant · Ecosystem structure refers to the internal benefits have been called ecosystem services
barrier to the acceptance of NBS. Project organisation of the ecosystem and the and have been classified as provisioning,
proposals encounter scepticism, simply relationship between its various elements regulating, cultural and supporting services,
because the outcome of the projects cannot (habitats, species populations, etc). It is but other classifications are possible. Besides,
be guaranteed in the same manner as for helpful to differentiate between the a-biotic the terminology ‘ecosystem services’ has not
traditional grey infrastructure projects. structure (type of substrate, special been uniformly accepted. (R.Gunton, 2017;
habitats) and the biological structure (the S.Diaz, 2018). Therefore, in this article the
Ecosystems as cornerstone interaction between biotic elements and general term ‘ecosystem benefits’ is used
Ecosystems form the building blocks of NBS. the a-biotic substrate). in accordance with the definition of NBS
The majority of NBS involve the creation or · Ecosystem processes are any changes suggested by the European Commission. A
restoration of ecosystems. This category or reactions, physical, chemical or distinction is made between environmental,
of solutions is commonly referred to as biological, that occur within the system social and economic benefits.
ecosystem-based approaches. It is therefore and which influence the flows, storage
relevant to recall some propensities of and transformation of materials and Benefits are by definition ‘beneficial’,
ecosystems. energy. These processes connect also the so what is the problem? The main issue
trophic levels via food chains. Processes with environmental, social and economic
An ecosystem is defined as a biologically include production and reproduction, benefits is the differences in valuation: not
qualified open system formed by a dynamic decomposition and purification. all environmental and social aspects can be
complex of living organisms within a well- · Ecosystem functions are the outcome of quantified, some need qualitative evaluations
defined boundary where the organisms physical, chemical and biological activities which cannot always be meaningfully
interact with each other and with their a-biotic that uphold the stability and biodiversity of compared with other quantified variables. This
environment. the ecosystem. They may be seen as the may lead to a lack of mutual understanding and
result of the interaction between structure endless discussions between stakeholders.
Note the importance of ecosystems as open and processes. Here one distinguishes
systems; this implies that energy and mass between production functions (food, raw Moreover, ecosystems provide a variety
exchange with the surrounding environment materials, etc) and the regulating functions of benefits, but for different categories of
Risk
Risk can be seen as the probability to High
HighHigh
resistance,
resistance,
resistance, Medium
Medium
Mediumresistance,
resistance,
resistance, Low resistance,
LowLowresistance,
resistance,
experience serious losses (disaster). This is fast
fastrecovery
fast
recovery
recovery slowslow
slow recovery
recovery
recovery slow recovery
slowslow recovery
recovery
a concept used by the insurance industry.
This risk concept can be further refined
as ‘the probability that a hazard results in
severe consequences’. Or, in a formula: (Risk) FIGURE 4
= (Probability of hazard) x (Vulnerability of A schematic depiction of ecosystem resilience. High resistance with fast recovery (A), medium
defences) x (Exposure to hazard effects). (see resistance with slow recovery (B) and low resistance with slow recovery (C).
Figure 2).
26 TERRA ET AQUA
climate change. Human actions can also A
influence the risk by reducing the vulnerability
Backshore Foreshore Breaker Zone Surf Zone Offshore
(strengthening defences) and/or by limiting
exposure to hazards. Vulnerability is the Berm
crest
trickier element of the three. Vulnerability
Mean High Water (MHW)
is generally described as ‘predisposition for Mean Sea Water (MSW)
damage and/or loss’, but in the context of risk Mean LowWater (MLW)
Dune Dune
it must be applied strictly to the effectiveness crest toe
of defences against extreme events.
overall risk. But nature-based solutions have Natural coastal defence systems in a sandy beach system (A) and mangrove system (B)..
no direct results for exposure. A thorough
discussion of these issues is provided in a
TABLE 3
28 TERRA ET AQUA
The provision of nature- based sustainable of 1 tonne of CO2?’) and thus uncertainty the International Institute for Sustainable
infrastructure requires business models that for the business case; estimating Development (IISD) welcomed the important
involve long-term exchange-value creation. A environmental benefits is important, role that nature-based solutions can play in
business case must be developed that is both but the valuation in monetary terms is sustainable infrastructure development. She
comprehensive and convincing. questionable: it provides little indication on challenged the audience to mainstream NBS
the quality improvement of the environment and cross the ‘valley of death’ to make NBS a
For traditional grey infrastructure a cost- and the positive impact on society; viable alternative in the infrastructure market.
benefit analysis (CBA) is developed at this · as mentioned already, a further In her experience the preconditions are that
stage which considers mainly the upfront complication is that many of the benefits NBS have to meet the criteria of:
investment costs. For the case of NBS, there may not be of interest to the investor, but · verifiability: demonstrate robust track
are other important factors that need to be accrue somehow to the local population records (monitoring performance over time,
taken into account: or neighbourhood; should third parties be achieving design criteria);
· firstly, total life-cycle costs, including the invited to become partners in the NBS · predictability: (sufficiently) predictable in
build-operate-maintain-decommission project, to share some of the risks and to their performance;
phases, must be assessed; while upfront co-invest in exchange of their share of · comparability: be functionally comparable
investment for NBS projects may be higher social or environmental benefits? under varying conditions (e.g., geo-zones).
than for traditional infrastructure, the · for those NBS projects playing a critical
maintenance costs over the life cycle are role in reducing the risks of extreme events The concrete suggestion to the contracting
likely to be lower; (fluvial flooding, coastal threats, etc), the industry was that the time has come to
· as referred to above, NBS life cycle vulnerability of the landscape needs to be move beyond the pilot stage and propose ‘a
evolution is not predictable in the same quantified somehow, in order to develop catalogue of NBS products’. But can these
way as for grey infrastructure; there remain an estimate of reduced vulnerability due criteria be satisfied?
elements of uncertainty in predicting the to and avoided damage costs thanks to Important work has already been done by
dynamics of the project over time. In a the project; this needs to be assessed as it the EcoShape foundation. The NBS pilots
cost-benefit context this means a negative should translate in lower insurance costs. realised under the EcoShape platform
evaluation for lack of guarantees; have been closely monitored and their
· the total suite of expected benefits must Through a number of workshops and performance compared to predictions or
be valued and these benefits are typically conferences, The ThinkNature project led a theoretical modelling. The evolution of other
much broader than for the traditional reflection on these issues, but this has not yet pilots is similarly being followed with detailed
case; when ecosystems are at the heart provided final answers. It should nevertheless monitoring campaigns such as the US Army
of the NBS, they will bring a range of be pointed out that one possible approach is Corps of Engineers' programme Engineering
benefits that can conveniently be split up to compare the three alternative scenarios: with Nature.
into environmental, social and economic NBS, grey infra or ‘do nothing’. On that basis
benefits; (see separate Box to appreciate the advantages of NBS can be shown, even if
the wide range of benefits associated with no complete monetary valuation can be made.
replanting coastal mangroves);
· with regard to direct economic benefits One thing is clear: the classic cost-benefit The NBS pilots
the valuation should not be an issue, as analysis cannot be applied as such to NBS.
they are calculated and expressed in New business models, other governance realised under the
monetary value; there may also be long term models and different decision-making rules
economic benefits that will materialise only are required to support the development, and EcoShape platform
over time; there is uncertainty in estimating the valuation of NBS projects.
and quantifying the latter, and then there is have been closely
the question if and how expected benefits It may also be apparent that large scale NBS
should be discounted; projects lend themselves better to financing monitored and their
· for expected social benefits (cohesion from public sources than by private investors.
of society, room for recreation, aesthetic Nevertheless, even in the public sector there performance compared
enjoyment, etc) the question is: how should are fundamental barriers. There is a long
these be valued? Shadow pricing is hardly tradition in public procurement to award to predictions or
a credible proposition and, in any case, projects to the bidder that offers the lowest
does not capture the real added value for price for the initial construction work (building theoretical modelling.
society; nevertheless, they must somehow phase). This model is not compatible with the
be accounted for in the business case; characteristics of NBS projects.
· similarly, for environmental benefits (carbon
capture, contribution to biodiversity, air Can NBS compete?
purification,etc) shadow pricing will likely During the EuDA annual conference in
lead to disagreements (‘What is the cost November 2019, Mrs Oshana Perera from
The criteria of robust performance and purification), in other cases NBS will function
reasonable predictability appear to be within in tandem with grey solutions and form hybrid
reach. systems. In these cases, the choices are not
But there remain other issues that distinguish between green and grey, but it becomes a
NBS from grey infrastructure in a fundamental matter of optimising design alternatives.
manner:
· as remarked, evolution in nature is never We conclude this section by observing that Nature-based
entirely predictable and performance a catalogue of ‘off-the-shelf’ nature-based
cannot be guaranteed in the same manner solutions is not realistic, because there are solutions represent
as for grey infrastructure. Some form of too many variables involved (climate zone, type
adaptive management is necessary; of hazard, existing features, hybrid systems, valid options for
· NBS will have a degree of vulnerability etc). Nevertheless, a variety of nature-based
under extreme events. This must be approaches is available for application in river integration into
quantified to some extent and the outcome catchments and for coastal defences.
influences the predictability; coastal and flood
· the third test of comparable performance Conclusions
under varying conditions may be too much Nature-based solutions represent valid defences.
to ask. options for integration into coastal and
· Indeed, NBS need to be functional in flood defences. They can be applied as
different climate zones under widely purely nature-based or combined with grey
different conditions, and the specific infrastructure to form hybrid systems. The
applications may therefore be different. evolution of nature-based features over time
Mangrove development along coastal implies an element of uncertainty. Traditional
zones is realisable in many areas in tropical public procurement methods, decision-making
and semi-tropical zones, but in temperate and governance as well as the traditional cost-
climate zones similar defensive functions benefit assessment models are not suitable
can be realised only by other NBS (e.g., for nature-based solutions and projects. The
seagrass beds, bio-engineering on business case for nature-based solutions
sandbanks, etc). needs to account for a range of specific
issues, including life-cycle costs and benefits
Finally, while there are natural solutions that estimates, assessment of vulnerability,
function as alternatives to grey infrastructure allocation of multiple benefits, different types
(for ex. constructed wetland for water of guarantees.
Summary
The concept of nature-based solutions (NBS) is relatively recent. It has emerged during discussions at the United Nations
Framework Convention on Climate Change (UNFCCC) in 2009. This concept has the advantage of encompassing a broad
range of diverse approaches and is thus convenient for promotional purposes. A definition is needed for practical use.
The European Dredging Association (EuDA) participated in a Horizon 2020 project sponsored by the European Union.
The project named ThinkNature had as objective to promote the application of NBS. NBS have obvious advantages but
have not been embraced at wider scale. In this article, the authors reflect as to why NBS are not mainstream solutions, why
it is necessary to promote the concept and whether there are barriers that hinder wide-scale application. In this article the
authors describe how relevant the topic is to the dredging community.
30 TERRA ET AQUA
REFERENCES
32 TERRA ET AQUA
The northeast Norfolk
coast has been subject
to long-term coastal
The Bacton Sandscaping scheme is a large-scale change. It is likely that
beach nourishment designed to protect the Bacton Gas the cliffs have been
Terminal from cliff and beach erosion while also reducing
flood and erosion risk to the communities of Bacton eroding at around the
and Walcott, buying the time needed for adaptation to present rate for the
coastal change. The scheme was inspired by the Sand last 5,000 years.
Engine project in The Netherlands but has translated
the concept to the different geography and governance
setting of the UK. It can be seen as the Sand Engine’s
‘little nephew’.
The northeast Norfolk coast has been subject The Bacton Gas Terminal is situated on buried within the cliffs and beach. There was
to long-term coastal change. It is likely that the the North Norfolk coast, approximately 30 therefore an urgent need to provide protection
cliffs have been eroding at around the present kilometres north of Great Yarmouth. The against further erosion. In January 2017, due
rate for the last 5,000 years. The cliffs are Terminal has infrastructure near the cliff to the immediate risk, Shell constructed a
made of soft deposits – mainly sand and soft edge, within the cliff and under the beach. temporary coast protection solution along
clays – which are very vulnerable to erosion. It is a piece of nationally important critical critical lengths of their section of the Terminal
This long-term coastal change puts pressure infrastructure supplying up to one third of frontage. This temporary solution consisted of
on communities, infrastructure and business the UK’s gas demand from the North Sea rock-filled gabion baskets placed at the toe of
in the coastal zone. extraction fields and to and from the continent. the cliffs on a gabion mattress and backfilled
The Terminal is owned by Shell, Perenco as with sand. The temporary solution was
well as other oil and gas businesses. The Gas designed to provide intermediate protection
Terminal requires protection from cliff erosion and assumed construction of a full permanent
and beach lowering for as long as the Terminal scheme would be performed in the near
is needed to avoid national impacts in the future. The vulnerability of the Gas Terminal
event of the gas supply being interrupted. infrastructure to erosion was highlighted again
in the storm surge event of January 2017
The Terminal was defended by a series of which caused significant lowering of the beach
timber groynes which sought to manage beach and damage to the existing timber revetment
levels and a timber revetment to reduce cliff and the temporary coast protection solution
erosion (see Figure 1). These structures were which was in the process of being constructed.
more exposed due to beach lowering, suffered
damage during storm events and only provided Southeast of the Bacton Gas Terminal,
protection against 10% Annual Exceedance continued coastal protection of the villages
Probability (1:10 per year) storms. of Bacton and Walcott (referred to as ‘the
Villages’ within this article) was only likely
Despite these defences, cliff erosion at the to be economically viable in the short-term
Terminal had progressed rapidly over the years, under current UK treasury rules. The Villages
notably during storm surges in November form an integral element of the community
2007 and December 2013. Following the and socio-economic structure of northeast
December 2013 storm it became clear Norfolk, providing residential areas supporting
FIGURE 1 that erosion was starting to threaten the the population and overall housing stock of
Defences at Bacton Gas Terminal prior to infrastructure at the Terminal. This included the area. They contribute to the important
Sandscaping. the cliff top infrastructure itself and pipelines tourism potential to the area and sustain small
FIGURE 2
34 TERRA ET AQUA
Fine-tuning
● Analysis ● Analysis
● Analysis
● Contractor engagement
● Contractor engagement ● Contractor engagement
● EIA
● EIA ● EIA The northeast Norfolk
Initial design Finalisation
coast has been subject
to long-term coastal
change. It is likely that
FIGURE 3
FIGURE 4
The team made a the Marine License and Planning Permission. conceptual model was agile enough for
The team followed an iterative approach with optioneering while fully representing the beach
special effort to three parallel tracks: processes. The conceptual model uses the
1. analysis (including modelling), one dimensional Litline model as the central
engage closely with 2. environmental study, and engine and uses the other tools to add cross
3. engagement with contractors sectional processes which cannot be captured
all contractors on the (see Figure 3). by the one-dimensional model on its own. This
relates specifically to the loss of sediment
Environment Agency The iterations concerned sediment volume, toward deep water and the development of the
various configurations and shapes, distribution cross-sectional shape of the beach (i.e. the
framework throughout between Terminals and Villages, sediment size. long-term balance between offshore losses
The process converged gradually toward the and onshore recovery). The overall shape and
the design process. finally chosen selection, informed by insights volume of nourishment at the Terminal was
derived from each of the three workstreams. technically assessed and optimised using
cross-sectional modelling. The Terminal
Modelling and analysis element was designed to provide protection
To assess the technical performance, a against cliff erosion in storms up to a 0.01%
conceptual model was used that combined Annual Exceedance Probability (1:10,000
the strengths of a one-dimensional (Litline) per year) event. The team developed an
and a two-dimensional area model (coupled innovative approach using hydrodynamic wave
wave, TOMAWAC, flow, TELEMAC-2D and modelling with AMAZON to compare design
sediment transport, SISYPHE, models within wave loading on the cliff face with known
the TELEMAC-MASCARET modelling system; historic storms that did not cause erosion. In
run by HR Wallingford) with appropriate use addition, plume modelling was carried out to
of expert knowledge and judgement and local inform the Environmental Impact Assessment
information (in particular from the Coastal (EIA) and for wind-blown sand, a research
Monitoring Programme). The resulting model developed for the Dutch Sand Engine
FIGURE 5
36 TERRA ET AQUA
A B
SE SE
NW NW
FIGURE 6
Schematic overview looking from north to south along the coast, before (A) and after (B).
was used to test impacts on the terminals important for a scheme like this – which was up to 80 metres, and then sloping down to
and community as well as inform the design dominated by dredging and nourishment the existing sea bed. The existing outfall pipes
of mitigating measures. Modelling studies operations – because operations depend on were replaced with a new single buried pipe.
considered placing greater volumes of sand the specific (often commercially sensitive)
around the Terminal in a hemispheric shape, characteristics of the contractors’ equipment. Element 2: Villages
similar to the Dutch Sand Engine. However, The team initially considered engaging with This element provides additional protection in
limited benefit was offered by the additional a single selected contractor but the chosen front of the Villages from Bacton to Walcott for
volumes. Modelling showed that tidal currents approach of working with multiple contractors which the proposed scheme is considered the
in the area washed the additional volume away in parallel has proven to work well, also only viable solution. The initial sand placement
very rapidly. because it helped sustain a level playing field improves beach levels which in turn increases
for contractor procurement. This process has the life of the existing sea defences. Over time,
Environmental study influenced size, shape and grain size of the tide and waves will transport sand from the
The environmental study was not only carried nourishment. Terminals nourishment to feed the beaches
out to meet statutory requirements (EIA, of the villages. The higher and wider beach will
Habitats Regulations, Marine Conservation What was proposed? also reduce wave overtopping and therefore
Zone Assessment, Water Framework Directive) The Sandscaping scheme consisted of the flood risk for the Villages. The Villages element
but played a strong and driving role through placement of sand along the coastal stretch runs from the south-eastern end of the
the design process, both in terms of designing between the Terminal and the south-eastern Terminals down to the end of the scheme at
out negative impacts and incorporating end of Walcott. This is a stretch of coast of 5.7 Ostend, Walcott and contains approximately
mitigation as well as in terms of incorporating kilometres. The scheme comprises two distinct 0.8 million cubic metres of sand. The initial
opportunities for enhancement. The project but connecting elements: the nourishments beach level covered the exposed sea wall toe,
identified a chalk bed near the coast within the in front of the terminals and in front of the at 4 to 5 metres AOD with a crest width up to
Marine Conservation Zone and this influenced Villages (as shown in Figure 2). about 25 metres, and then sloped down to the
the design to minimise the risk that the chalk existing seabed. The crest at 4 metres AOD
bed would be impacted by the scheme. The Element 1: Terminals means that there would (at least) initially be
environmental study also influenced the grain This element aims to prevent significant a beach at high water. The coast would still
size and spawned the idea of stimulating dune cliff erosion up to a storm event with a 0.01% erode, including temporary rapid losses during
growth on the nourishment with the added Annual Exceedance Probability (1:10,000 per storm events. However, the scheme would have
benefit of limiting wind-blown sand. year). The initial placement of sand is expected ‘turned back the clock’ by several decades
to last approximately 15 to 20 years from first and the extra sand would make the beach
Contractor engagement placement with the intention to potentially more robust with the ability, under the right
The team made a special effort to engage re-nourish after that period. The terminals conditions, to naturally recover.
closely with all contractors on the Environment element covers the terminals frontage down
Agency framework throughout the design to the adjacent Holiday Park and contains Overall
process. All potential contractors were invited approximately 1 million cubic metres of sand. The total sand volume of 1.8 million cubic
and all became very positively involved, helping The nourishment here is at its widest and metres was extracted from the seabed, from
to optimise scheme design and increasing highest: 3.5 to 5 metres higher than the an existing licensed site, off Great Yarmouth.
confidence in the cost estimates to the current beach at the cliff toe (7 metres Above The extraction sites are approximately 20-25
benefit of the clients. This is particularly Ordnance Datum (AOD)), with a crest width nautical miles from Bacton. The sand grains
will be similar to the current beach (D50 has shown that this alignment is the most timing dependent on weather conditions and
of 0.35mm), or slightly coarser (D50 up to favourable. to be confirmed through ongoing monitoring
1.2mm). Generally, coarser sand is more stable and review). A future placement may be
so will create a more stable beach but it is also The placed beaches will adapt rapidly to designed to continue to protect the Terminals
more expensive to place, and if too coarse, it the natural conditions. The sand will spread – probably without future placements in front
could have impacts on amenity use or habitats. out along the coast in both directions. The of the Villages – depending on considerations
The sand placement in front of the Terminal scheme is expected to provide the required at that time. The improved beach in front
provides immediate protection and narrows level of protection at the Terminal’s coast for of the villages of Bacton and Walcott is
towards the villages (see Figure 6). Modelling approximately 15-20 years (with the exact expected to enhance the lifespan of the
38 TERRA ET AQUA
FIGURE 7
existing sea defences. The sandscaping approximately 400 OMs (Outcome Measures) damages, and the direct damages to the
scheme could delay sea defence failure by under current UK Government funding criteria. Terminal facilities.
15 to 50 years depending on the state of the
seawall and beach development over time. Benefits For the Villages, the scheme is expected to
This significantly delays the loss to erosion The scheme will have very large benefits to delay the loss of the seawall, and thereby
of nearly 300 households. It is also predicted the Gas Terminal, extending its functional life delay the loss to erosion of the coast road and
to reduce flood risk due to overtopping to as a piece of nationally critical infrastructure, nearly 300 households. In addition to these
the coast road and over 100 households. preventing potential (very expensive) national measurable benefits, the scheme is expected
Therefore, the scheme is delivering disruption of supply and its consequential to provide time to the communities to adapt to
coastal change, for which they currently have previous studies, updated to the current Happisburgh and then also at Eccles
very little time and opportunity. date, were used to estimate how the and Sea Palling. Due to the significant
scheme options would generate benefits. uncertainty regarding these possible
Following discussion with DEFRA and the In addition, the number of households benefits, and the fact that its inclusion is
Environment Agency the village element of the for which the scheme options reduce the outside of current policy guidance, these
scheme is eligible for government Flood and probability of flooding, was estimated on additional benefits have not been calculated
Coastal Erosion Risk Management (FCERM) the basis of data from the Environment within the approved business case
Grant in Aid (GiA) funding as set out in the Agency’s coastal modelling study. These submitted to LPRG.
following list: two results were combined to determine
• Properties protected from erosion, the scheme options’ economic benefits The scheme is expected to create other
determined by applying the standard and their contribution to Outcome benefits which are not eligible for GiA
methods from the Environment Agency Measure 2 (households moved from a because they do not relate to reduction of
approved Economic Appraisal Manual. high flood risk category to a comparatively flood and erosion risk. This concerns the
Essentially, the benefits are generated lower category). enhancement of the communities’ capacity
by the delay of the loss to erosion of • Highways protected. The benefits to adapt to coastal change (likely to improve
properties in Bacton and Walcott, using concern the delayed need to reconstruct
appropriate property values to calculate the B1159 road at Walcott on a more
the damage. The year of loss of individual inland alignment. In practice, it is more
properties and their respective access likely that the road would not be repaired,
roads was estimated for each option. For and calculations confirmed that the
the initial situation this was based on the economic impact of the resulting delays
estimated year of seawall failure. For each would be higher. However, in line with
option, the extensive modelling carried out UK Treasury rules the lowest damage
for scheme design was used to determine scenario is used as part of the calculation.
how the enhanced beach would delay this • Loss of recreational value. This was
year of failure. This was combined into a calculated as the loss of visitor spend,
Present Value Damage (PVD) amount based on available economic data.
for each option. Note that this leads to a Alternative analysis based on reduced
‘duration of benefits’ that varies along the value of enjoyment produced higher
frontage, which has been incorporated in impacts, but was considered less reliable.
the calculation of GiA, Therefore, the lower value has been
• Properties protected from flooding. Bacton applied.
and particularly Walcott were vulnerable
to flooding from wave overtopping over a Additional benefits
coastal seawall. Reflecting the relatively low There are also be additional benefits further
importance compared to erosion, the team downdrift from the Villages frontage.
took a pragmatic approach to calculating The scheme is expected to provide additional
the benefits. First, the economic flooding sediment which will, over time, also generate
damages for Walcott Gap calculated in benefits downdrift from Walcott: first at
FIGURE 8
40 TERRA ET AQUA
economic productivity and reduce the burden The loss of existing recreational value work). In addition, the loss of households puts
on the UK’s health care system) and the described above is eligible for FCERM GiA. In an additional burden on health and social care.
improvement of tourism facilities (in addition contrast, the improvement of tourism economy
to prevention of losses, which is potentially concerns the positive impact on the local These non-financial benefits are challenging
eligible for in GiA). These benefits are relevant tourism economy of the options, for example to report quantitatively, but were considered
for alternative sources of funding. by improving the beach. within the choice of the preferred Sandscaping
option.
Local stakeholders showed overwhelming The scheme is also likely to improve the
support for the scheme and were keen to see adaptive capacity of the communities. How it will work
the sandscaping solution implemented. Initial The understanding that a large number of The beach plays an important role of absorbing
concerns regarding potential negative impacts households were expected to be lost in the the energy from the sea before it reaches the
during construction, either to tourism or coming 20 years has far-reaching impacts on cliff and defences while also providing support
fishing, were largely overcome through active people. One key aspect is the loss of mobility and protection to the defence foundations.
engagement and consultation. (i.e. the reduction in house prices restricting The larger beach will absorb more energy and
ability to move elsewhere and therefore find supports the defences. Detailed studies have
the gas terminal. The following funds were and social science aspects. In addition, further
The Bacton scheme intended to be made available to the project. research will be supported and encouraged.
• Terminal’s contribution to the cost of the
will be a very useful Terminal protection and new surface water Sandscaping and wider applicability
outfall, totalling two thirds of the overall in the UK
case study for other funding. Royal HaskoningDHV has been working with
• FCERM GiA capital funding allocated The Crown Estate and other partners since
coastal managers from the Environment Agency’s Flood 2011 to explore the application of sandscaping
and Coastal Erosion Risk Management solutions in the UK. This consisted of
in the UK and Investment Programme; technical work to develop the concept, carry
• North Norfolk District Council contribution; out a UK-wide assessment of potential sites
elsewhere to consider • Local Levy agreed allocation from the and location specific feasibility studies. In
Anglian Eastern Regional Flood and addition, the sandscaping partnership has
sandscaping solutions Coastal Committee (RFCC); engaged with decision makers and influencers
• Environment Agency’s agreed allocation at various levels in order to understand the
for their area. from the Natural Flood Management constraints for and opportunities around this
(NFM) funding stream; innovative solution in the UK. The approach
• Norfolk Business Rates Pool contribution was strongly driven by the clear realisation that
from Norfolk Local Government sources; sandscaping schemes will only happen if it is
• New Anglia Local Enterprise Partnership the right solution locally, and is ‘consentable’
Growth Funds contribution; and, and affordable. As a result, a key aim has been
• Contributions from the local community to convince coastal managers to include
and other beneficiaries collected through sandscaping on longlists for projects and to
the JustGiving account set up by North create a level playing field so that it can be
been done to assess how coastal processes Norfolk District Council. appraised against more traditional options.
along this dynamic stretch of coast will work
with the scheme, and this provides confidence With regards to the NFM funding stream, as There have been a number of specific
that the scheme will perform. Over time, the part of the original application for funding, the engagement initiatives in the UK. In April
bulk of sediment protecting the Terminal importance of post construction monitoring 2015, a workshop was held in London hosted
is expected to feed the beaches in front of was emphasised. As such, and in order to by The Crown Estate. During this workshop,
Bacton, Walcott and beyond, sustaining the maximise the learning from this project, there which encompassed coastal practitioners and
initial sand placement in front of those villages. is an expectation that a proportion of the NFM community representatives from across the
allocation will be attributed to such monitoring. country, the advantages and disadvantages
Experience with the Dutch Sand Engine Post-construction monitoring in beach of such an approach were explored for a
shows that (mainly in the 12 months following nourishment projects is covered by FCERM number of coastal locations from around
construction), the shape of the sediment GiA monies elsewhere (for example the Eccles the country. Concurrent to this, consultants
placements will change and this is to be to Winterton scheme). Royal HaskoningDHV funded by The Crown
expected. With a new ‘dry beach’ above mean Estate, undertook a technical assessment of
high water, there is a risk of windblown sand, The capital funding requirement for the coastal locations. More recently (April 2018),
particularly in the first 18 months. This will need Bacton to Walcott scheme is included in the an event was held at the Dutch Embassy to
to be monitored and managed. Environment Agency’s flood and coastal risk explore sand engine/sandscaping approaches
management investment programme (2015- in the UK environment. The technical
Funding 2021), Terminal investment programmes audience included coastal practitioners
The funding for the Bacton to Walcott Coastal and North Norfolk District Council capital from Environment Agency, Coastal
Management Scheme came from a number of investment programme. The revenue for future Risk Management authorities, DEFRA,
private and public sources. The FCERM GiA maintenance is limited and will be shared as Natural England and Marine Management
was a critical element of the project to enable identified in the Development Agreement. Organisation. Part of the afternoon discussion
the joint Terminal and villages scheme to centred on the potential for a sandscaping
proceed but did not form the primary funding Ongoing costs with regards to maintenance approach to be taken at other locations in
source. The private funding was led by Shell are expected to be low as the scheme will the UK. There was consensus that there were
UK and Perenco UK who oversaw an umbrella naturally decommission over time. Monitoring other specific locations in the UK where such
of other infrastructure provider contributions. costs are to be shared and it is expected that an approach could be valid. However, other
Opportunities for external funding were a significant proportion of the costs can be factors such as already planned interventions
comprehensively explored with the Terminal captured in the Environment Agency’s Anglian could affect timings.
and UK Government. The total cost of the Coastal Monitoring programme. Monitoring
project was approximately £21 million including is likely to include several fields, including: Clearly, after completion of the Bacton to
the re-provision of a surface water outfall for ecological, bathymetric, geomorphological Walcott Sandscaping scheme, the monitoring
42 TERRA ET AQUA
FIGURE 9
Summary
approach for other locations.
Conclusions
The Bacton to Walcott Sandscaping scheme The Bacton Sandscaping scheme is a large-scale beach
shows that it is possible to design, fund and nourishment designed to protect the Bacton Gas Terminal from
gain consent for a sandscaping scheme in cliff and beach erosion while also reducing flood and erosion risk
the UK – a large-scale nourishment that is to the communities of Bacton and Walcott, buying the time needed
designed to work with natural processes and for adaptation to coastal change. The scheme was inspired by
with the intention to achieve multiple benefits. the Zandmotor project in The Netherlands but has translated the
concept to the different geography and governance setting of the
Such an approach not only provides erosion UK. It can be seen as the Zandmotor’s ‘little nephew’.
and flood risk benefits but also has the
potential to improve tourism income and This article describes the context of the challenge, how the
adaptive capacity of communities, while sandscaping approach works and tells the story of how the first
working with natural processes. The higher project of this type outside the Netherlands has developed from
and wider beaches will delay failure of the the seed of an idea to reality. Technical expertise, passion, trust,
defences, reducing uncertainty and providing flexibility and lateral thinking have all been to the fore in a truly
more time for adaptation. Future engagement unique collaboration between multiple private and public sector
around coastal adaptation will be critical, North organisations.
Norfolk District Council continues to engage
locally while also lobbying national for wider This article was presented as a paper at an Institution of Civil
inclusion of adaption in the national approach. Engineers Conference in 2019. It is updated here and published
with permission.
By taking a coastal zone approach, considering
longshore interactions and taking partnership
opportunities, the Bacton scheme has created
a solution to not only protect nationally
important infrastructure but to support the
communities of Bacton and Walcott where this
would otherwise not be possible.
44 TERRA ET AQUA
The success of this collaborative project development has
been due to all parties, private and public, playing their part.
Mark Johnson
Mark has worked for 35 years in various roles for the Environment Agency and its predecessor organisations. For the majority of
this time he has been focused on the East Anglian Coast.
During the last 14 years he has overseen delivery of many large flood and coastal erosion risk management projects, many of which
have realised multiple benefits for the protection of people and property, important wildlife sites and rural land. Mark has been
actively working with various groups on the East Anglian coast to help progress projects where partnership approaches are pivotal
in helping to address the challenges of the UK coast. He has been the Chairman of the East Anglia Coastal Group (EACG) since
2012 and chaired elected members during the development phase of the Shoreline Management Plans.
Gökhan Doygun
Gökhan is a Senior Commercial Advisor at Shell and is currently working as Opportunity Lead/ Commercial Lead on Energy
Transition projects in the Netherlands and in the UK Southern North Sea. He played a key leading role, as the Business Opportunity
Manager(BOM) acting on behalf of Shell UK, in the success of the public and private collaboration for the joint protection of the
nationally critical infrastructure Bacton Gas Terminal and the adjacent Bacton & Walcott villages – UK’s first ‘Sandscaping’ solution
for Bacton to Walcott Coastal Management Scheme.
Jaap Flikweert
Jaap is a flood and coastal management advisor and a Leading Professional with Royal HaskoningDHV, and a Fellow of CIWEM. He
has twenty-five years of experience in flood and coastal management, in the Netherlands, the UK and worldwide. Jaap’s career
started in 1994, working from the Netherlands until 2004 and based in the United Kingdom since then. His expertise covers flood
and coastal management: from detailed design to strategy and policy level, as well as planning, preparation, protection and
response. He produced the guidance for the statutory flood defence assessment in the Netherlands; led three of the 20 Shoreline
Management Plans for England and the review of flood defence performance after several of the recent floods in the UK (including
Winter 2015/16); and established the method that the US Army Corps of Engineers applied to incorporate resilience in New
Orleans’ levees after Katrina. Jaap is the technical lead for the Sandscaping initiative that aims to introduce Dutch Building with
Nature concepts into the UK. He led the RHDHV team that developed the design, Environmental Impact Assessment, business
case and monitoring plan for the Bacton to Walcott Sandscaping scheme.
Gerard Spaan
Gerard is a Senior Civil Marine Engineer at Shell Projects & Technology and is currently working on the development of LNG import
terminals globally, from their early definition to the actual execution. For the Bacton Sandscaping Project, Gerard was the Technical
Lead on behalf of Shell, providing technical assurance and guidance for the design and execution of the works, including concept
selection as well as procurement for the different work packages. Gerard holds an MSc degree in Civil Engineering from Delft
University of Technology in the Netherlands. Prior to joining Shell in 2009, Gerard worked as a Civil and Coastal Engineer at
Deltares, an independent institute for applied research in the field of water and subsurface, and at Van Oord Dredging and Marine
Contractors.
EXPAND HORIZONS
ABROAD
UNEP Sixth Adaptation Futures The sixth such conference – and the first to 2020 Chlorinated Conference
Conference be held in Asia – will be co-organised by the 31 May-4 June 2020
29 September–1 October 2020 Energy and Resources Institute and the World Oregon Convention Center
India Habitat Centre Adaptation Science Programme. India is the Portland, Oregon, USA
New Delhi, India chosen location due to its high reliance on www.battelle.org/chlorcon
http://adaptationfutures2020.in climate sensitive sectors such as agriculture,
water and forestry for resources, and The Twelfth International Conference on
Adaptation Futures is the flagship event livelihoods face an urgent need for adapting to Remediation of Chlorinated and Recalcitrant
of the World Adaptation Science Program the risks posed by climate change. Compounds, known as Battelle’s Chlorinated
which is one of the four components of World Conference, is one of the world’s largest
Climate Programme (WCP) based on the World The Adaptation Futures 2020 envisages to and most comprehensive meetings on the
Meteorological Organisation Congress XVI advance the overall theme of ‘accelerating application of innovative technologies and
Resolution 18. As a premier event in the global adaptation action and knowledge to support approaches for characterisation, monitoring
adaptation spectrum, Adaptation Futures is a action’. The conference seeks to explore this and management of chlorinated and complex
unique platform to facilitate dialogues towards overarching need through multiple thematic sites.
action oriented solutions from a diverse range tracks. Topics to be addressed include
of stakeholders that includes academia, Governance of Adaption, Limits to Adaption, The 2020 Conference will include more
practitioners, scientists and policy makers Fairness and Equity in Adaption, Knowledge for than 1,000 platforms and posters in 88
from across the world. Action, Financing Adaption and Nature Based breakout sessions. Five panel discussions
Solutions, a topic high on the agenda of the will be conducted. Sessions and panels are
global dredging industry. organised according to thirteen major topic
Course.
46 TERRA ET AQUA
FIGURE 2
FIGURE 3
48 TERRA ET AQUA
Mombasa, Kenya (September 1991), Rio de NaCC at COPEDEC 4. Effects of extreme weather, including
Janeiro, Brazil (September 1995), Cape Town, 16-20 November 2020 risk assessments, contingency plans and
South Africa (April 1999), Colombo, Sri Lanka Manila, Philippines warning systems
(September 2003), Dubai, UAE (February https://navclimate.pianc.org 5. Monitoring and adaptive management
2008), Chennai, India (February 2012) and Rio for responding to change
de Janeiro, Brazil (October 2016). Navigating a Changing Climate is a PIANC- 6. Climate change adaptation, including
led international initiative that provides theory and practice, methodologies and
The active mission of the PIANC-COPEDEC a platform for the exchange of technical case studies
Conferences is: advice and information. The initiative aims to 7. Optimising operational resilience,
1. To provide an international forum support the maritime and inland navigation including the role of inspection and
where coastal and port engineers from infrastructure sector in responding to maintenance
developing countries can exchange climate change. NaCC will hold a conference 8. Flexible and adaptive infrastructure
know-how and experience amongst within a conference during PIANC’s design
themselves and with their colleagues COPEDEC X. 9. Nature-based solutions to improve
from industrialised countries; navigation infrastructure resilience
2. To enable the developing countries to On 19 and 20 November 2020, the 10. Other climate change topics
have a sustainable human resource Navigating a Changing Climate partners will
pool of coastal and port development organise a two-day conference as part of the The conference will deepen your knowledge
professionals. 10th International Conference on Coastal and on de-carbonisation and the move to net zero
Port Engineering in Developing Countries greenhouse gas emissions being taken by
As with previous conferences, the emphasis (COPEDEC) to be held in The Philippines, leading organisations in the sector. It will also
on technical subjects remains. Papers will hosted by The Philippine Ports Authority. enable you to find out more about practical
focus on practical applications, planning, approaches to climate change adaptation, and
management and environmental aspects of The themes of this ‘conference within a to intermodal-, system resilience- and nature-
coastal, port and inland waterway engineering conference’ will include: based solutions.
in developing and industrialised countries, 1. Moving towards ‘net zero’ emissions
including documentation of case studies. The of greenhouse gases from port
language of the Conference will be English. infrastructure including the port estate
2. Ports’ role in enabling the reduction
Technical tours and social events will also be of greenhouse gas emissions from
arranged during the week of the Conference. vessels SAVE THE DATE
Pre-conference tours to interesting places 3. Intermodality and system-level climate
in and around Manila and other places of change resilience 61st Seminar
interest in Manila will be arranged. A Final
Announcement including a listing of accepted on Dredging &
papers and detailed practical information such
as registration and hotel booking forms will be Reclamation
issued in April 2020.
5-9 October 2020
Singapore
Call for papers
A reminder that the call for abstracts is now open for the Navigating a Changing Climate
‘conference-within-a-conference’ at COPEDEC in the Philippines in November 2020.
Submission requirements for abstracts can be found here: https://navclimate.pianc.org/about/
navclimate-news/call-for-abstracts-navigating-a-changing-climate-conference-at-copedec
Those that have not yet prepared and submitted their abstracts may be interested to know that
the extended abstracts from the Navigating a Changing Climate conference-within-a-conference
will be included in the COPEDEC conference Book of Abstracts. In this case, however, the
Navigating a Changing Climate conference abstracts will need to be submitted in the same
format as those for COPEDEC. Instructions for submissions can be found here:
https://www.pianc-copedec2020.org/call-for-abstract.
DREDGING ENGINEERING
SPECIAL TOPICS
In dredging, production estimating is carried out
mainly with analytical physical models of the different
dredging processes. This book, the third in a series,
addresses processes not covered in the two
preceding editions including hopper sedimentation
and erosion, water jet fluidisation, cutter head spillage,
pump/pipeline dynamics and clamshell dredging.
In dredging, trenching, (deep sea) mining, drilling, The author views this publication’s compiled Lead Author: Sape Miedema
tunnel boring and many other applications, topics as being too ‘small’ to merit their own Publisher: TU Delft OPEN
sand, clay or rock has to be excavated. The book, but too interesting not to be published. Published: June 2019
productions – and thus the dimensions – of The content will be updated in the future but Price (Hardcover): € 50.20
the excavating equipment range from mm3/ represents the last in the series. The first Price (Digital): Free
sec - cm3/sec to m3/sec. In oil drilling, layers book, The Delft Sand, Clay & Rock Cutting ISBN: 978-94-6366-173-7
with a thickness of a magnitude of 0.2 mm are Model, is about soil mechanics and the
cut, while in dredging, this can be of a magnitude second, Slurry Transport: Fundamentals, Available from
of 0.1 mm with cutter suction dredgers (CSDs) A Historical Overview & The Delft Head https://www.webedu.nl/bestellen/
and metres for clamshells and backhoes. Some Loss & Limit Deposit Velocity Framework, is uniportaal/?action=order&og=
equipment is designed for dry soil while others about two-phase flow: how to transport soil, 14904&orderableobject=22510530
operate under water saturated conditions. sand and water through pipes that can be
Installed cutting powers may range up to 10 MW. hundreds of kilometres long.
For both the design, operation and production
estimation of the excavating equipment, it The series’ three titles are self-published on
is important to be able to predict the cutting Open Textbooks, a platform run by TU Delft Sape Miedema
forces and powers. Library where lecturers can publish their Sape obtained his MSc in Mechanical
textbooks license-free. Launched in late Engineering with honours at the Delft
After the soil has been excavated, it is usually 2018, the digital platform is part of the Delft University of Technology in 1983 and his
transported hydraulically as a slurry – over a University of Technology’s effort to make PhD in 1987. From 1987 to the present,
short or long distance, with TSHDs or CSDs scientific education available to as wide an he has been an assistant, then associate,
respectively – or mechanically. Estimating audience as possible, an initiative supported professor at the Chair of Dredging
the pressure losses and determining whether by the author. Textbooks can be downloaded Technology, then as a member of the
or not a bed will occur in the pipeline is of for free by anyone, anywhere in the world and management board of Mechanical
great importance. Fundamental processes of includes a print-on-demand option. Engineering and Marine Technology.
sedimentation, initiation of motion and erosion From 1996 to 2001, he was appointed
of the soil particles determine the transport In addition to accessibility, Open Textbooks educational director of Mechanical
process and the flow regimes. In TSHDs, the brings another benefit: ease with which Engineering and Marine Technology
soil has to settle during the loading process additions and/or corrections can be made. whilst remaining associate professor
where also sedimentation and erosion will be The platform allows authors to upload a new of Dredging Engineering. In 2005, he
in equilibrium. In all cases, soil and high density edition whenever a change is made, the library was additionally appointed educational
soil water mixtures as well as its fundamental automatically requests a new ISBN. director of the MSc programme of
behaviour are dealt with. Special topics like Offshore Engineering.
cutter spillage and waterjet production have
been added to this edition.
50 TERRA ET AQUA
IADC
ALWAYS
READY
TO MEET NEW
CHALLENGES
www.iadc-dredging.com
1 TERRA ET AQUA