Name of Work: Maynaguri Burnish Road from 0.00 kmp to 2.

60 km

Observation Sl. OLD DPR NEW DPR Remarks


No.
1) Sl. No. (1): “Dismantling Item has been Deleted
of Flexible pavement…..”
1) Sl. No. (3) “Picking up old Sl. No. (1) Rectified
bituminous …….”
2) Sl. No. (4): “Box cutting or Sl. No. (3): “Box cutting or Here upto 300mm
filling….” filling….” has been considered
becoz Cutting reqd
for CC Block Shoulder
275mm thk & for
Hard Shoulder 225
mm thk.
3) (i) N.A. Sl. No.15 New item added
3) (ii) Sl. No. 15 Sl. No. 14 Rectified
4) i) Overhead Gantry Design is done as per
Signboard- Design drawing
4) ii) Overhead Gantry PWD SOR (Vol-III) Rectified
Signboard: PWD NH
Schedule
4) iii) Overhead Gantry Estimate has been made Rectified
Signboard- Estimate considering the items as
per PWD SOR (Vol-III)
5) CD Structures: Item Single item has been Rectified
repetition made for 2 Type of CD

6) Concrete Lining: PCC Concrete Lining: PCC Rectified


grade- M20 [PWD SOR 1:2:4 [PWD SOR -Vol(I)]
-Vol(III)]
7) & (8) Sl. No. of Rate Analysis & Sl. No. for Rate Analysis = Rectified
Sl. No. of Abstract Sl. No. for Abstract
Estimate / Qty Estimate Estimate = Sl. No. Qty.
Estimate