HEC-HMS Training Manual : Water Resources Group, RSAA

RUNOFF ESTIMATION USING"HEC-HMS"


1. Open HEC-HMS.

2. Open the .hms project file created using HEC-GeoHMS. Browse for the file

saved in the folder.

3. Once the project is open, you can see four folders in the Watershed Explorer

viz., Basin Models, Meteorologic Models, Control Specifications and Time-

Series Data. Expand Basin Models and click on project created by you.

National Remote Sensing Centre, ISRO, Hyderabad


1
HEC-HMS Training Manual : Water Resources Group, RSAA

Note:Right click on the Desktop and then Background Layers to add Sub-basin boundary

and River network.

4. Click on each subbasin listed in Basin model (W60 to W100) to check

subbasin information under component editor. Here basin characteristics

computed using HEC-GeoHMS, can be seen.

Curve Number computed from CNGrid

Sub-basin Area Basin Lag Time

National Remote Sensing Centre, ISRO, Hyderabad


2
HEC-HMS Training Manual : Water Resources Group, RSAA

5. Expand reach R30and R50 in Basin Models to check the specifications for
reach and routing. For R30, give Muskingum K (HR)as1 and Muskingum X as
0.3 and for R50, give Muskingum K (HR)as 1 and Muskingum X as 0.3

6. Now click on the time series folder in the Watershed Explorer. You can see
there is a gage associated with each sub-basin. Click on a Gage in
Watershed Explorer and then change the time interval to 1 day under Time-
Series Gage in component editor. Similarly, go to Time Window and change
the Start Date / Time to 01Jul2014 08:00 and End Date / Time to 31Jul2014
08:00. Do the same procedure for rest gages.

National Remote Sensing Centre, ISRO, Hyderabad


3
HEC-HMS Training Manual : Water Resources Group, RSAA

7. Copy and Paste the rainfall data from Excel sheet into table of these gages.

8. Once, the rainfall gauge is defined, this gauge can be associated with the
corresponding sub-basins by using Meteorologic Model. To do that, expand
the Meteorologic model-> Project ->Specified Hyetograph->Sub basins. Model
will automatically take gages to the associated subbasin.

9. Go to "Control Specifications Manager"in the watershed explorer, expand it


and click on project control. Change the Start Date / Time to 01Jul2014
08:00and End Date / Time to 31Jul2014 08:00, and time interval 1day.

National Remote Sensing Centre, ISRO, Hyderabad


4
HEC-HMS Training Manual : Water Resources Group, RSAA

10. Now go to Compute in the menu bar, then select Create Compute ->

Simulation Run. A dialog box will appear to give this simulation run a name.

To continue, click next till end and finish.

11. Now to run the model,select compute->expand simulation run ->Run 1, and

then go to compute in the menu bar ->click Compute Run[Run 1].

National Remote Sensing Centre, ISRO, Hyderabad


5
HEC-HMS Training Manual : Water Resources Group, RSAA

12. Once the simulation is completed successfully, results can be checked in a


tabular format, under Results tab-> Global Summary Table.(Menu Bar)
13. Results of individual basins can also be seen by expanding the simulation run
folder under the results tab in the Watershed Explorer.

Also, the final Hydrograph at the outlet can also be seen by select outlet in the
Watershed Explorer.