ESTIMATE

AGT AMOUNT
S.NO. NAME OF WORK AMOUNT AGT NO. & DATE
IN LAKHS IN LAKHS

Rehabilation of Thimmaraju Obulapathi Tank


1 (Independent ) in Mundlapadu (V) Giddaluru (M) 310.73 325.56 114/18-19;
Prakasam Dt Under APIIATP (WORLD BANK 12/27/2018
PHASE-II)

Rehabilation of Damarla Tank (INDEPENDENT ) in 112/18-19;


2 Komarole (V) Komarole (M) Prakasam Dt Under 195.36 204.97
APIIATP (WORLD BANK PHASE-II) 12/27/2018

Rehabilation of CIRCAR Tank (INDEPENDENT ) in 111/18-19;


3 Palakaveedu (V) RACHERLA (M) Prakasam Dt 102.01 107.05
Under APIIATP (WORLD BANK PHASE-II) 12/27/2018
NAME OF AGENCY AS PER ESTIMATE

Tank bund
Sluice
M/s Sri SAI BALAJI
CONSTRUCTIONS Surplus weir No.1 & 2
Supply channel
Irrigation Channel
Tank bund
Sluice No1 & 2
M/s KVSR CONSTRUCTIONS
Surplus weir
Irrigation Channel
Tank bund
M/S A V RAMBABU INFRA Sluice
PVT LTD Surplus weir
Irrigation Channel
STAGE OF WORK

EWE for embankment in progress


M15 for foundation completed
Surplus weir No.1 M15 for foundation completed &
Surplus weir No.2 EWE for foundation completed
Not Started
Not Started
EWE for embankment in progress
Not Started
EWE for foundation completed
Not Started
EWE for embankment in progress
Not Started
EWE for foundation completed
Not Started