Download as pdf or txt
Download as pdf or txt
You are on page 1of 11

See discussions, stats, and author profiles for this publication at: https://www.researchgate.

net/publication/260113612

Concession period for PPPs: A win–win model for a fair risk sharing

Article  in  International Journal of Project Management · October 2014


DOI: 10.1016/j.ijproman.2014.01.007

CITATIONS READS

68 1,798

3 authors:

Nunzia Carbonara Nicola Costantino


Politecnico di Bari Politecnico di Bari
62 PUBLICATIONS   1,142 CITATIONS    86 PUBLICATIONS   882 CITATIONS   

SEE PROFILE SEE PROFILE

Roberta Pellegrino
Politecnico di Bari
61 PUBLICATIONS   644 CITATIONS   

SEE PROFILE

Some of the authors of this publication are also working on these related projects:

A book titled "Relational methodologies and epistemology in economics and management sciences" View project

All content following this page was uploaded by Roberta Pellegrino on 18 July 2016.

The user has requested enhancement of the downloaded file.


Available online at www.sciencedirect.com

ScienceDirect
International Journal of Project Management 32 (2014) 1223 – 1232
www.elsevier.com/locate/ijproman

Concession period for PPPs: A win–win model for a fair


risk sharing
Nunzia Carbonara, Nicola Costantino, Roberta Pellegrino ⁎
(DMMM)Department of Mechanics Mathematics and Management, Polytechnic of Bari, Viale Japigia 182 70126, Bari, Italy

Received 22 October 2013; received in revised form 16 January 2014; accepted 21 January 2014
Available online 7 February 2014

Abstract

Public Private Partnership (PPP) is adopted throughout the world for delivering public infrastructure. Despite the worldwide experience has
shown that PPP can provide a variety of benefits to the government, to fully gain them several critical aspects related to a PPP project need to be
managed, among these the determination of the concession period.
This paper provides a methodology to calculate the concession period as the best instant of time that creates a ‘win–win’ solution for both the
concessionaire and the government and allows for a fair risk sharing between the two parties. In other words, the concession period is able to satisfy
the private and the government by guaranteeing for both parties a minimum profit, and, at the same time, to fairly allocate risks between parties. In
order to take into account the uncertainty that affects the PPP projects, the Monte Carlo simulation was used. To demonstrate the applicability of
the proposed model, a Build–Operate–Transfer (BOT) port project in Italy has been used as case study.
© 2014 Elsevier Ltd. APM and IPMA. All rights reserved.

Keywords: Concession period; Public Private Partnerships; Risk allocation; Monte Carlo simulation

1. Introduction provide a variety of benefits to the government. In particular,


PPPs can increase the “value for money” spent for infrastructure
In the last decades, due to public budget constraints and the services by providing more-efficient, lower-cost, and reliable
severe need for new or upgraded infrastructure, more and more services; improve the quality and efficiency of infrastructure
governments have fostered private sector involvement in public services, and promote local economic growth and employment
investment projects. For this reason, Public Private Partnerships opportunities. Furthermore, PPPs allow the public sector to
(PPPs) have become a major scheme in delivering public transfer risks related to construction, finance, and operation of
infrastructure (Hodge and Greve, 2007; Kwak et al., 2009). projects to the private sector and to keep public sector budget
PPPs are “agreements where public sector bodies enter into deficiencies down (Kwak et al., 2009).
long-term contractual agreements with private sector entities for However, to fully gain the above listed benefits several
the construction or management of public sector infrastructure critical aspects related to a PPP project need to be managed.
facilities by the private sector entity, or the provision of services Among these: the assessment of risks associated with the PPP
by the private sector entity to the community on behalf of a public project; the identification of suitable risk allocation and mitigation
sector entity” (Grimsey and Lewis, 2002). The idea of allowing strategies; the definition of a sound financial plan; the selection of
private firms to finance projects of public infrastructure results in the appropriate concessionaire; and the determination of the
the emergence of PPPs (Li and Akintoye, 2003; Tang et al., concession period. Researchers have proposed several conceptual
2010). The worldwide experience has shown that PPPs can models, tools and techniques to support the decision processes
related to these critical aspects (Garvin and Ford, 2012; Li et
⁎ Corresponding author at: Viale Japigia 182, 70126 Bari Italy. Tel.: + 39
al., 2005; Schaufelberger and Wipadapisutand, 2003; Zhang,
0805962850.
2005a, 2005b).
E-mail addresses: ncarbonara@poliba.it (N. Carbonara), This paper focuses on the length of concession period,
costantino@poliba.it (N. Costantino), r.pellegrino@poliba.it (R. Pellegrino). considered one of the most important issues in the PPP contracts.
0263-7863/$36.00 © 2014 Elsevier Ltd. APM and IPMA. All rights reserved.
http://dx.doi.org/10.1016/j.ijproman.2014.01.007
1224 N. Carbonara et al. / International Journal of Project Management 32 (2014) 1223–1232

In the common international practice, the government usually indicating the span of time within which the private sector is
presets the concession period to a fixed length, requests the responsible for the construction phase and operation phase in
concessionaire to bid for other project aspects, and guarantees the BOT projects. Concession period is a key decision variable in
concessionaire a certain level of internal rate of return (Zhang, the arrangement of a PPP contract. The length of concession
2009). This practice, however, does not generally lead to an period is mainly related to the recovery of investment and return
efficient selection of concessionaires and it also induces the required by the concessionaires. The general principle for
frequent failure or renegotiation of concession contracts (Gustavo determining its length is that the concession period should be
and Rus, 2004). To overcome these problems, there is a need long enough to allow the concessionaire to recoup investment
for the government to use a methodology that appropriately costs and earn reasonable profits within that period (Smith,
calculates the concession period. Recently, some researchers 1995).
attempted to determine a reasonable concession period. Generally, a longer concession period is more beneficial to
Most of the models proposed in the literature use the net the private investor, but a prolonged concession period may
present value (NPV) of the project cash flow as criterion for induce loss to concerned government. Alternatively, if the
calculating the concession period. Some of these determine the concession period is too short, the investor will either reject the
concession period considering only the maximization of the contract or be forced to increase the service fees in the
concessionaire's benefits. For example, Engle et al. (2001) and operation phase. Consequently, the risk burden due to the short
Vassallo (2006) suggest the least-present-value of revenue concession period will be shifted to the party who uses and
(LPVR) method to determine the concession period of toll pays for the facilities. Therefore, establishing an appropriate
roads. Other models adopt a win–win approach, which means that concession period is important for the success of a PPP project
the concession period is determined in order to maximize benefits (Ng et al., 2007b; Ruizheng and Li, 2010).
of both the government and the concessionaire (Shen et al., 2002; Each concession has its duration, which may be fixed or
Zhang and AbouRizk, 2006). Among these, only few models take variable. The choice depends on various risk factors such as
into account the risk exposure of both partners (Chan et al., 2011; completion time, product price and market demand. Usually,
Hanaoka and Palapus, 2012; Shen and Wu, 2005), but none of the concession has a fixed period, in which risk factors are
these allows one for a fair risk sharing between the parties. managed through tariff design supplemented by other mea-
Finally, most of the developed models determine the sures. Sometimes, the concession has a variable period, which
concession period as a time interval within which a specific may be extended if the specified risk factors are worse than
concession period could be agreed upon by the government expected or shortened if they are better than expected. For
and the private sector and very few of the previous methods example, in order to deal with demand risk, the concession
calculate the concession period as the instant of time within period can be varied according to the market demand. If the
which the concession must end. market demand is lower than expected, the concession period will
In order to overcome the above discussed limitations, the be extended to allow the concessionaire to earn a reasonable
present paper develops a model for calculating the concession return, and vice versa.
period as the best instant of time that creates a ‘win–win’ Different models have been developed and proposed in the
solution for both the concessionaire and the government and literature to quantitatively determine the optimal value of the
allows for a fair risk sharing between the two parties. In other concession period. Most of these models, with the due differences
words, the concession period is able to satisfy the private and and specificity, use the Net Present Value (NPV) of the project
the government by guaranteeing for both parties a minimum as a basic parameter for calculating the optimal value of the
profit, and, at the same time, to fairly allocate risks between concession period. An exception is the study of Ng et al. (2007a)
parties. In order to take into account the uncertainty that affects that considers the internal rate of return (IRR) as criterion for
PPP projects, the Monte Carlo simulation is used. project evaluation and calculates the concession period that is less
To demonstrate the applicability of the proposed model, risky to the concessionaire by fixing the minimum, expected, and
we apply it to a Build–Operate–Transfer (BOT) port project maximum IRR acceptable to the concessionaire.
launched by the Municipality of Bari (Southern Italy) to construct, Shen et al. (2002, 2007) develop an analytical deterministic
operate and maintain the “San Cataldo Port of Bari”, consisting method (BOTCcM) for determining the length of the conces-
in a tourist port, a dock for cruise ships, and six multi-purpose sion period to be granted to the private sector in BOT projects
buildings. that can protect the interests of both the host government and the
Section 2 of this paper reviews the existing methodologies private investor. BOTCcM proposes an interval for a concession
for determining concession period. In the third section, we period negotiation that consists of two critical points: the first
present the win–win concession period model and in the next point, called the starting point of the interval, aims at protecting
section we apply it to a Build–Operate–Transfer (BOT) port the interests of the private investor; the second point, called the
project in Italy. Conclusions end the paper. endpoint of the interval, aims at protecting the interests of the host
government. Wu et al. (2012) improve BOTCcM by considering
2. Concession period at project's transfer time its net asset value that is usually
significantly greater than zero and represents a revenue for the
Concession period starts from the signing of the concession government. Hanaoka and Palapus (2012) propose a methodol-
agreement between the government and the private sector ogy to determine a reasonable concession period that considers
N. Carbonara et al. / International Journal of Project Management 32 (2014) 1223–1232 1225

the effect of risks on uncertain concession items in project 2) models that calculate the concession period as a time interval
evaluation. In particular, by using Monte Carlo simulation and within which the concession contract must end.
bargaining game theory the methodology generates a concession The second aspect involves the uncertainties and risk factors
period interval within which a specific concession period could affecting PPP projects. By reviewing the literature, we found
be agreed upon by the government and the private sector. Any models which do not take into account risks and uncertainties
point within the interval could be considered as the optimal that affect over a long period many of the input variables; and
concession period that would be advantageous to both BOT models in which uncertainties are accounted for. In the first case a
players. Ye and Tiong (2003) evaluate the mean net present value deterministic approach is adopted to calculate the concession
(NPV), variance and NPV-at-risk of different concession period period, while in the second case stochastic models have been
structures through Monte Carlo simulation, so that both the developed, in which each variable affected by uncertainty is
government and the concessionaire can understand their risk modeled by a statistical distribution and the concession period is
exposure and rewards. Zhang (2009) proposes a win–win determined by using simulation methods.
concession period determination methodology, in which BOT Finally, the third aspect concerns the perspective adopted in
projects are addressed as a principal-agent maximization problem. calculating the concession period, in terms of interest to safeguard
In this research both deterministic and simulation-based methods and party to satisfy. In this respect, some models, focusing only
are provided to determine the concession period, with detailed on the private party perspective, require that the concession
step-by-step procedures. should be long enough to allow the concessionaire to obtain a
Engel et al. (2001) suggest the least-present-value of revenue reasonable profit. Recently, in contrast with this approach, in
(LPVR) method to determine the concession period of toll roads order to safeguard the multiple interests of the public sector and
so that the franchise length is adjusted endogenously to demand the profit-making interest of the private sector, some researchers
realization. proposed a win–win approach to determine the concession period
Other researchers use the fuzzy approach to determine the that takes into account both the government and investor interest
concession period appropriately. Mostafa et al. (2010) adopt a perspective. Each of these studies implements the win–win
Fuzzy-Delphi technique to calculate the length of concession approach in different ways. For example, according to Zhang
period considering uncertainties. In particular, they determine (2009) the win–win approach is implemented by posing the
the values of different uncertain factors affecting a BOT project following two constraints: 1) the concession should be long
by considering the opinions of a group of experts (Delphi), enough to allow the concessionaire to obtain a reasonable IRR
and then calculate the NPV value by taking into account the and 2) the concessionaire acts in the interest of the government,
resulted aggregated values of uncertain input parameters, finally for example, the concessionaire may be required to continuously
determine the concession period using the fuzzy approach. The improve efficiency, cost effectiveness and service quality; sustain
proposed methodology offers a fuzzy number for the length a stable and public-affordable price regime; and transfer excessive
of concession period. Ng et al. (2007b) develop a fuzzy multi- profits to the government. Following the win–win approach,
objective decision model to evaluate and establish the most Hanaoka and Palapus (2012) employ the bargaining game
satisfactory concession item options for BOT projects. theory to find a reasonable concession period. Thus, the specific
Table 1 lists the existing models developed to determine concession period is considered as a bargaining process wherein
the concession period, classified with respect to three key (i) the government and the private sector act as the players in
aspects. reaching a BOT agreement, (ii) the benefit to be generated within
The first aspect concerns the computation of the concession the concession period interval within which the end of the
period. Respect to this, the discussed models can be classified concession period could occur, is the conflict of interest, and (iii)
in two main categories: 1) models that allow the calculation of the negotiation does not end until an agreement of both BOT
the instant of time within which the concession must end; players is reached.

Table 1
Models for concession period calculation.
Model Concession period calculation Uncertainty/risk factors Satisfied party Source
Instant of time Time interval Private Public Both parties
LPVR X X Engle et al., 2001; Gomez-Lobo
and Hinojosa, 2000; Vassallo, 2006.
Fuzzy-Delphi X X X Mostafa et al., 2010.
Fuzzy multi-objective X X X Ng et al., 2007b
Fuzzy Petri Net–genetic algorithm X X X Shen and Wang, 2010
Simulation model X X X Ng et al., 2007a
MC-PDM X X Zhang and AbouRizk, 2006.
BOTCcM X X Shen et al., 2002; Wu et al., 2012.
CPM-MCS X X X Zhang, 2009
MCS-bargaining game theory X X X Hanaoka and Palapus, 2012
BOTCcM-R X X X Chan et al., 2011; Shen and Wu, 2005
1226 N. Carbonara et al. / International Journal of Project Management 32 (2014) 1223–1232

Finally according to Wu et al. (2012), creating a win–win - Rmin is the investor's expected minimum return rate from his
situation means both assuring that the private investor not only capital investment
recoups the investment but also earns a profit during the - r is the discount rate
franchise operation period, and protecting the government in - tconstr. is the construction period.
recouping the project depreciation costs incurred during the
post-transfer operation period in a way that the cumulative cash Eq. (1) expresses the principle that the net present value of
flow during its post-transfer operation period are greater than the project's cumulative net cash flow should be no less than
the net asset value at its transfer. the private investor's expected minimum return on investment.
Table 1 shows that there is not a model that addresses all the
three key aspects. Furthermore the methodologies adopting a win– NPVC ≤ IC Rmax ð2Þ
win approach do not deal with the concept of a fair risk sharing
between the two parties. Therefore, none of the previous models
has the capability to support the government decision-making in Where:
the choice of a concession time that satisfies the interests of both
parties by taking into account unforeseen risks and uncertainties - Rmax is the maximum return rate allowed by the government
and that allows a fair risk sharing between parties. to investors.
To overcome this limitation, we propose a win–win concession
period determination methodology, which calculates the conces- Eq. (2) expresses the condition that the net present value of
sion period as the instant of time within which the concession the project's cumulative net cash flow should be no higher than
must end, takes into consideration risks and uncertainties, and a cap rate of return fixed by the government in order to avoid
safeguards the interests of both parties involved in the concession lucrative conditions.
contract, the public sector and the private sector, by fairly
allocating the risk between the two parties. NPVG ð FÞ≥ 0 ð3Þ

3. The win–win model Where:

In the following, we propose an innovative win–win concession - NPVG (F) is the net present value of the project's cumulative
period model that addresses the following issues: net cash flow during the post-transfer operation;
- F is the end of the life time of the project.
1. Taking into consideration the win–win principle, in the
sense that the estimated value of the concession period Eq. (3) expresses the principle that the net present value of
should be able to protect the interests of the private investor the project's cumulative net cash flow during the post-transfer
and the government simultaneously and to assure that the operation and calculated at the end of the life time of the project
interests of the two parties are satisfied in a balanced way; (F) should be no less than zero.
2. Calculating the instant of time within which the concession By solving Eq. (1) we obtain the minimum value of the
must end; and concession period (tmin), i.e. the instant of time before which
3. Considering the effect of uncertainty. the project should not be transferred because it does not allow
the private investor to receive the expected minimum return on
To address these issues, we develop a methodology that investment.
calculates the optimal instant of time in which the concession By solving Eq. (2) the maximum value of the concession
should end (Tc) as result of the following equations: period (tmax) is calculated. This is the instant of time after which
the granting of the project should not continue, in order to avoid
NPVC ≥ IC Rmin ð1Þ an excessive profit to the private sector.
Where: Eq. (3) allows the calculation of tc, that is the instant of time
before which the investor should transfer the project to the
- NPVC is the net present value of the of the project's government, in order to guarantee its interests.
cumulative net cash flow The time interval within which fix the concession period is
defined by tmin, tmax and tc (see Fig. 1). Three possible situations
can occur:
Xn
C Ft
t¼0 ð 1 þ r Þt 1. tc b tmin: in this situation it is impossible to determine a
concession period that jointly satisfies the interests of the
private investor and the host government;
- IC is the total investor's capital investment
2. tc ≥ tmax: in this situation the concession period of the
tX
constr project can assume any value within that interval [tmin–tmax];
C Ft
IC ¼ 3. tmin ≤ tc b tmax: in this case the interval for a concession-
t¼0 ð1 þ rÞt period negotiation is fixed between the two points tmin and tc,
N. Carbonara et al. / International Journal of Project Management 32 (2014) 1223–1232 1227

therefore the concession period can assume any value within The variables used as input to the model are categorized into:
that interval [tmin − tc]. 1) deterministic/certain and 2) uncertain variables. Deterministic
variables are defined in this paper as variables of which values
Once the interval for a concession period negotiation has could be considered as stable over time. Uncertain variables, on
been derived through the previous procedures, namely the time the other hand, are those inputs which may be subject to change
interval that jointly satisfies the interests of the private investor and high level of uncertainty over time since their future values
and the host government, it is possible to determine the instant are difficult to predict.
of time within which the concession must end (Tc). In order to The deterministic variables are:
satisfy the win–win condition, Tc is calculated as the instant
of time that minimizing the difference between NPVC and - The construction period and project life time: the first is the
NPVG, by solving the objective function given by the following period from the project start-up date until the target date of
equation: completion. While in reality construction period may change
due to some events that may occur during construction
Tc э′MinðNPVC −NPVG Þ ð4Þ preventing the project to be delivered on time, it is assumed
equal to 3 years. The project life time is assumed equal to
Eq. (4) expresses the condition that both parties, the private 60 years.
investor and the host government, are equally satisfied, that is, - The investment cost and the residual value of the project: the
it assures that the interests of the two parties are satisfied in a first includes expenditure items needed until the completion
balanced way. of the project, equal to € 28.096.177. The residual value of
Concession period Tc is a function of a set of variables the project at the transfer time is € 5.6 million, equal to 20%
affected by uncertainty. To take into consideration the effect of of the investment cost of the project.
uncertainty, we adopt the Monte Carlo simulation. In particular, - The maximum return rate allowed by the government to the
first we develop a stochastic model by assigning to each investor (Rmax), equal to 15% and the minimum rate of
random variable a statistical distribution, which requires the return for the investor (Rmin), equal to 8%.
selection of a suitable theoretical distribution function and - The discount rate r, that in the case of Monte Carlo
the estimation of its parameters. Then, by running the model at simulation is generally a risk free rate (Brealey and Myers,
the end of simulation we derive the statistical distribution of 2000), since the risk is already included in the project cash
the concession period (Tc). flows that depend on the randomly-chosen values of the
Once the distribution of Tc is known we determine the value input parameters. The risk-free discount rate can be taken as
of Tc that allows the difference between the risks of loss borne the interest rate on Government bonds. In particular, in this
by the two parties to be minimized. These risks are measured as case r is fixed at 5%, taken the average interest rate on long
follow: term Italian Government Bonds as a proxy.
- Expenses during operation, including items such as the state
- risk borne by the concessionaire = Prob (NPVC b Ic ∗ Rmin); concession fee, regular annual maintenance costs, overhead
and operating costs, and insurance.
- risk borne by the government = Prob (NPVG(F) b 0). - Revenues from real estate activities (rental fees for commercial
and services areas).
4. Case study
The uncertain variables are:
We applied the developed model to the case of the BOT
tourist port project launched by the Municipality of Bari, - Revenues associated on the operation period and determined
located on the South-East coast of Italy. The port includes: a by the services management. These come from port dues,
cruise terminal, floating docks with a capacity of 447 boats, mooring dues, and parking space rent. The port dues cover
accessible by boats up to 30 m, a parking for 577 vehicles, the use of the nautical port infrastructure (such as pilotage
office, service, and multifunctional buildings (covering an area and docking fees) and are paid by cruise ships. The mooring
of about 8000 m2), a bunkering area, and 104 storage spaces. In dues consist of: long-term leases, annual leases, and transit
the operation phase the revenues mainly consist of port dues, fees. These are determined by the unitary fee to be charged
land rent, mooring dues, and parking space rent. The port dues to the users of the specific services and the number of users
cover the use of the nautical port infrastructure (such as pilotage expected for those services. In particular, as for the mooring
and docking fees) and are paid by cruise ships. The mooring services, the users are the vessel owners, for parking service
dues consist of: long-term leases, annual leases, and transit fees. the users are both the vessel owners and port visitors. As for
The operation costs mainly consist of management expenses, the nautical port infrastructure, the users are the cruise ships.
operations and maintenance costs, insurance, and State Govern- - Costs associated on the operation period and due to the
ment concession fee. services management. These are assumed equal to the 12%
The estimation of the operating revenues and costs has been of the operating revenues, thus their distribution over
based on historical data, data collected on similar projects, and time follows the distribution of the revenues related to the
experts' opinions. corresponding service.
1228 N. Carbonara et al. / International Journal of Project Management 32 (2014) 1223–1232

Table 2 Table 3
Statistical distribution of input random variables. Statistics of tmin, tmax and tc.
Input random variables Probability distribution Parameters Mean Std dev Minimum Maximum
function
tmin 39.05 1.88 0.00 55.00
Number of seasonal rented moorings Binomial distribution n = 45 tmax 54.72 13.87 0.00 6000
p = 80% tc 43.39 18.05 0.00 5400
Number of full year rented moorings Binomial distribution n = 224
p = 90%
Number of transit rented moorings Binomial distribution High season
n = 43 in the literature (Garvin and Cheah, 2004; Iyer and Sagheer,
p = 95% 2011; Pichayapan et al., 2003). The stochastic evolution of
Middle season traffic volume (Q) that follows a GBM can be modeled in
n = 43
yearly periods as a function of the value in previous period
p = 80%
Low season according to the following equation:
n = 43 μ 2  pffiffiffiffi
Q σ
p = 60%
Qtþ1 ¼ Qt e − 2 Δtþσε Δt
Traffic volume of cruise ships Geometric Brownian μQ = 1.5%
motion σ = 10%
Number of occupied parking Binomial distribution n = 162
Where:
spaces for port visitors p1 = 5% a
p2 = 10% μQ is the expected traffic growth rate;
p3 = 20% σ is the annual volatility of the variable;
p4 = 30% ε ~ N(0,1) is the standard Wiener process.
p5 = 50%
p6 = 60%
p7 = 70% This model implies that the traffic can never be negative and
p8 = 90% its evolution can be completely specified considering only its
Number of occupied parking Binomial distribution n = 415 initial value Q0, a yearly growth rate and the volatility of the
spaces for vessel owners p1 = 20% process, which we assume to be constant during the concession
p2 = 30%
period.
p3 = 50%
p4 = 60% After establishing the input data modeling, the Monte Carlo
p5 = 70% simulation approach has been used for calculation of NPV. In
p6 = 90% particular, in each computer iteration, the random values of the
a
On the basis of the historical data, we have fixed different values of p, each stochastic input variables are generated on the basis of their
corresponding at different monthly occupancy rates. statistical distributions as established in input data modeling.
Each simulation consists of 1000 computer runs.
The outcome of the simulation model, taking into account
The assumptions used for modeling the statistical distribu- the project variables above, is the distribution of the project's
tions of the uncertain variables are summarized in Table 2. In cumulative net cash flow over the life-time of the project F.
particular, the table shows for each input random variables the By solving Eqs. (1)–(3) we calculate the probability distribu-
corresponding probability distribution function and its defining tions of tmin, tmax and tc (see Table 3).
parameters, defined on the basis of the historical empirical data. The instant of time within which the concession must end
Notice that, the discrete input variables, namely the number (Tc) is contained in the interval [Tcmin–Tcmax], where:
of rented moorings and the number of occupied parking spaces,
and the related revenues, have been modeled with the binomial - Tcmin = lower bound concession interval = tmin and
distribution that is a discrete probability distribution, where the - Tcmax = upper bound concession interval = min[tc;tmax].
random variable is the number of “successes” (i.e. rented
moorings or occupied parking spaces) in n independent trials Figs. 2 and 3 show the probability distribution of Tcmin and
(i.e. available moorings or parking spaces) with a probability of Tcmax.
success constant and depending on the seasonal occupancy Tc is then determined by solving the objective function
rates. The conditions of applicability of the binomial probabil- Min(NPVC–NPVG).
ity distribution are satisfied since there is a fixed number of n Fig. 4 plots the statistical distribution of Tc derived after 1000
trials (i.e. available moorings or parking spaces); the outcome computer iterations.
of a given trial is either a “success” (rented/occupied) or “failure” The simulation returns a value of 0 in all situations/scenarios
(not rented/not occupied); the probability of success (p) remains where the conditions of the model are not satisfied, i.e. it is
constant from trial to trial (seasonal occupancy rates); and the impossible to determine a concession period that jointly
trials are independent. satisfied the interest of both parties.
Instead, we have assumed that the traffic volume of cruise Tc range within the interval [45–51] years with a probability of
ships, and the related revenues, will vary stochastically in time 80% (the 20th percentile is 45 years), with a mean 40.55 years,
following a geometric Brownian motion (GBM), as is standard mode 48.00, and median equal to 47 years.
N. Carbonara et al. / International Journal of Project Management 32 (2014) 1223–1232 1229

Fig. 1. Cash flow profile and time interval for the concession period determination.

Fig. 2. Probability distribution of the lower bound concession interval (Tcmin).

Fig. 3. Probability distribution of the upper bound concession interval (Tcmax).


1230 N. Carbonara et al. / International Journal of Project Management 32 (2014) 1223–1232

Fig. 4. Probability distribution of the concession period (Tc).

In order to define the optimal value of Tc we have conducted To get a feel for the likely impact of the interest rate r on
a risk analysis. For each values of Tc within the interval movement of the model outcome, sensitivity analysis was carried
[45–51], we have calculated the probability that the net present out, yielding the results shown in Fig. 7.
value of the project's cumulative net cash flow is below the The sensitivity analysis indicates that the increase of Tc is
private investor's expected minimum return on investment more than proportional to the increase of r. In this case we
(private risk) and the probability that the net present value of found that for r = 6% it is impossible to determine a concession
the project's cumulative net cash flow during the post-transfer period that jointly satisfies the interests of the private investor
operation calculated at the end of the life time of the project is and the host government, since the instant of time before which
less than zero (public risk). the investor should transfer the project to the government, in
Fig. 5 depicts the risk borne by the two parties. order to guarantee its interests (tc) is lower than the instant of
Notice that at Tc = 49 years the difference between the risks time before which the project should not be transferred because
of loss borne by the two parties is minimized, so as having the it does not allow the private investor to receive the expected
best risk allocation between the two parties. minimum return on investment (tmin).
Fig. 6 (a and b) shows the probability distributions of NPVC The results of the sensitivity analysis therefore show that the
and NPVG calculated for the optimal value of the concession interest rate affects on the choice of the concession period, so
period (Tc = 49 years) and indicates the value of risk borne by much that there could not be an instant of time that jointly
the two parties. satisfies the interests of the private investor and the host

100,00%

90,00%

80,00%

70,00%

60,00%

50,00%

40,00%

30,00%

20,00%

10,00%

0,00%
45 46 47 48 49 50 51
Private risk (Prob(NPVc-Ic*Rmin)<0) Public risk (Prob(NPVg<0)

Fig. 5. Risk borne by the concessionaire and the government for each value of Tc.
N. Carbonara et al. / International Journal of Project Management 32 (2014) 1223–1232 1231

Fig. 6. Probability distributions of NPVC and NPVG for Tc = 49 years.

government within the life time of the project. The outcome of demarcating the authority, responsibility, and benefits between
the sensitivity analysis can be also useful for supporting the the private party and the government.
choice of the rate during the negotiation. This paper provides a new model for calculating the
concession period as the best instant of time that creates a
5. Conclusion ‘win–win’ solution for both project promoter and the host
government and allows one for a fair risk sharing between the
A key factor of a PPP project is the agreement on the length two parties. In other words, the concession period is able to
of concession period. The concession period is one of the most satisfy the private and the government by guaranteeing for both
important decision variables for arranging a successful PPP parties a minimum profit, and, at the same time, to fairly
contract because its value decides when ownership of a project allocate risks between parties. In order to take into account the
will be transferred from the investor to the government, thereby uncertainty that affects the PPP projects, the Monte Carlo
simulation technique was used, which requires establishing the
55
statistical distributions of the random input variables.
A case study on a BOT port project launched by the
50 municipality of Bari located in Southern Italy were used to
45 check the applicability of the proposed model for determin-
ing the reasonable length of the concession period that
TC

40
safeguards the multiple interests of the public sector and the
35 profit-making interest of the private sector and allows for a
fair risk sharing between the public and private sectors, by
30
minimizing the difference between the risks of loss borne by
25 the two parties.
2% 3% 4% 5% 6%
r The application shows that the developed model can be a valid
tool for supporting the public authority in the decision-making
Fig. 7. Sensitivity analysis results. process about the length of the concession period.
1232 N. Carbonara et al. / International Journal of Project Management 32 (2014) 1223–1232

The application of the model requires, as usual in this kind Kwak, Y.H., Chih, Y., Ibbs, C.W., 2009. Towards a comprehensive understanding
of problems, some assumptions on input parameters. However, of public private partnerships for infrastructure development. Calif. Manage.
Rev. 51 (2), 51–78.
we have done a sensitivity analysis on one of the most critical Li, B., Akintoye, A., 2003. An overview of public–private partnership. In:
parameter of the model, namely the discount rate, and proven Akintoye, A., Beck, M., Hardcastle, C. (Eds.), Public–Private Partnerships:
that even if the concession period is affected by the selected Managing Risks and Opportunities. Blackwell Science Ltd., UK.
value of the interest rate the model keeps its usefulness for Li, B., Akintoye, A., Edwards, P.J., Hardcastle, C., 2005. The allocation of risk
in PPP/PFI construction projects in the UK. Int. J. Proj. Manag. 23 (1),
supporting the negotiation process in choosing an appropriate
25–35.
discount rate, thus avoiding costly renegotiation. Mostafa, K., Farnad, N., Majid, A., 2010. Using Fuzzy-Delphi technique to
It can be observed that the validity and usefulness of the determine the concession period in BOT projects. Proceedings of the 2nd
model has been proven through a single case study. However, IEEE International Conference on Information and Financial Engineering,
it is important to observe that the structure of the model and its 17–19 September. ISBN: 978-1-4244-6927-7, pp. 442–446.
equations do not change from case to case, thus assuring the Ng, S.T., Xie, J.Z., Skitmore, M., Cheung, Y.K., 2007a. A fuzzy simulation
model for evaluating the concession items of public private partnership
generalizability of the model. The main limitation indeed schemes. J. Autom. Constr. 17, 22–29.
relies on the input data modeling, which is a critical step Ng, S.T., Xie, J.Z., Cheung, Y.K., Jefferies, M., 2007b. A simulation model for
inherent in the simulation-based approach, affecting the optimizing the concession period of public–private partnerships schemes.
outcome. In fact it may not be easy for decision-makers to Int. J. Proj. Manag. 25 (8), 791–798.
accurately predict the uncertain parameters and their proba- Pichayapan, P., Kishi, K., Hino, S., Satoh, K., 2003. Real Option Analysis
(ROA) in evaluation of expressway projects under uncertainties. J. East.
bility distributions. Asia Soc. Transp. Stud. 5, 3015–3030.
Further research will be devoted to apply the proposed Ruizheng, F., Li, W., 2010. The optimal concession period in the built–
methodology to other PPP projects which may have operate–transfer project. Proceedings of the International Conference on
different cash flow structure to strength its effectiveness Management of e-Commerce and e-Government, Washington, DC, USA,
and prove its validity beyond the specific case analyzed by pp. 223–227. http://dx.doi.org/10.1109/ICMeCG.2010.53.
Schaufelberger, J.E., Wipadapisutand, I., 2003. Alternate financing strategies for
the present study. Future works may also focus on further build–operate–transfer projects. J. Constr. Eng. Manag. 129 (2), 205–213.
refinement of the simulation model by gathering more Shen, J., Wang, S., 2010. The decision-making model of TOT concession
information on key variables to accurately assign their period based on Fuzzy Stochastic Petri Net. Proceedings of the Management
probability distribution. and Service Science International Conference, Wuhan. http://dx.doi.org/
10.1109/ICMSS.2010.5576927.
Shen, L.Y., Wu, Y.Z., 2005. Risk concession model for build/operate/transfer
contract projects. J. Constr. Eng. Manag. 131 (2), 211–220.
References Shen, L.Y., Li, H., Li, Q.M., 2002. Alternative concession model for build
operate transfer contract projects. J. Constr. Eng. Manag. 128 (4), 326–330.
Brealey, R., Myers, S., 2000. Principles of corporate finance, 6th edition. Irwin Shen, L.Y., Bao, H.J., Wu, Y.Z., Lu, W.S., 2007. Using bargaining-game
McGraw-Hill, Boston. theory for negotiating concession period for BOT-type contract. J. Constr.
Chan, A.P.C., Yeung, J.F.Y., Yu, C.C.P., Wang, S.Q., Ke, Y., 2011. Empirical Eng. Manag. 133 (5), 385–392.
study of risk assessment and allocation of public–private partnership Smith, N.I., 1995. Engineering project management. Blackwell Science,
projects in China. J. Manag. Eng. 27 (3), 136–148. Boston.
Engel, E.M.R.A., Fischer, R.D., Galetovic, A., 2001. Least-present-value of Tang, L., Shen, Q., Cheng, E.W.L., 2010. A review of studies on Public–
revenue auctions and highway franchising. J. Polit. Econ. 109 (5), Private Partnership projects in the construction industry. Int. J. Proj. Manag.
993–1020. 28, 683–694.
Garvin, M.J., Cheah, C.Y.J., 2004. Valuation techniques for infrastructure Vassallo, J.M., 2006. Traffic risk mitigation in highway concession projects.
investment decisions. Constr. Manag. Econ. 22 (4), 373–383. J. Transp. Econ. Policy 40 (3), 359–381.
Garvin, M.J., Ford, D.N., 2012. Real options in infrastructure projects: theory, Wu, M., Chau, K.W., Shen, Q., Shen, L.Y., 2012. Net asset value-based
practice and prospects. Eng. Proj. Organ. J. 2 (1–2), 97–108. concession duration model for BOT contracts. J. Constr. Eng. Manag. 138,
Gomez-Lobo, A., Hinojosa, S., 2000. Broad roads in a thin country: 304–308.
infrastructure concessions in Chile. Research Paper 2279The World Bank, Ye, S., Tiong, R.L.K., 2003. The effect of concession period design on
Washington DC. completion risk management of BOT projects. Constr. Manag. Econ. 21,
Grimsey, D., Lewis, M.K., 2002. Evaluating the risks of public–private 471–482.
partnerships for infrastructure projects. Int. J. Proj. Manag. 20 (2), 107–118. Zhang, X.Q., 2005a. Financial viability analysis and capital structure optimization
Gustavo, N., Rus, G., 2004. Flexible-term contracts for road franchising. in privatized public infrastructure projects. J. Constr. Eng. Manag. 131 (6),
Transp. Res. A Policy Pract. 38 (3), 163–179. 656–668.
Hanaoka, S., Palapus, H.P., 2012. Reasonable concession period for build–operate– Zhang, X.Q., 2005b. Criteria for selecting the private-sector partner in public–
transfer road projects in the Philippines. Int. J. Proj. Manag. 30, 938–949. private partnerships. J. Constr. Eng. Manag. 131 (6), 631–644.
Hodge, G.A., Greve, C., 2007. Public–private partnerships: an international Zhang, X.Q., 2009. Win–win concession period determination methodology.
performance review. Public Adm. Rev. 67 (3), 545–558. J. Constr. Eng. Manag. 135 (6), 550–558.
Iyer, K.C., Sagheer, M., 2011. A real options based traffic risk mitigation model Zhang, X.Q., AbouRizk, S.M., 2006. Determining a reasonable concession
for build–operate–transfer highway projects in India. Constr. Manag. Econ. period for private sector provision of public works and services. Can. J. Civ.
29 (8), 771–779. Eng. 33 (5), 622–631.

View publication stats

You might also like