Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 1

Sl. No.

Description Number of Days of Tentative start dates Tentative completion dates Remark
Activity

Completion of KEC 132KV work (OH+UG)-Erection Portion 6-Apr-20

Excavation of Cable Trench


Cable Section 4 (Mohitnagar
1a GIS to Composite Tower No. 2 3/Mar/20 5/Mar/20
1/0 (Open trench fdn-54
meter)

HDD at Cable Section 4


1b (Mohitnagar GIS to Composite 2 5/Mar/20 7/Mar/20
Tower No. 1/0 ( Pool Pit 1 to
Pool Pit 2- 34 meter)

HDD at Section 4 (Mohitnagar


1c GIS to Composite Tower No. 1 7/Mar/20 8/Mar/20
1/0 (HDD- Pool Pit 3 to Pool
Pit 4- 12 meter)

Laying of Power Cable and ECC


1d at Section 4 (Mohitnagar GIS to 2 9/Mar/20 11/Mar/20
Composite tower no. 4)-462
meter

Excavation of Cable Trench at


2a Cable Section 1 Star Cement 7 27/Feb/20 5/Mar/20
Gantry to Joint Bay 2 (Open
trench fdn-446 meter)

HDD Section 1 Star Cement


2a Gantry to Joint Bay 2 (Pool pit 2 9/Mar/20 11/Mar/20
5 to pool pit 6 -50 meter)

Laying of Power Cable and ECC


2b at Section 1 (Star Cement 3 12/Mar/20 15/Mar/20
Gantry to Joint Bay 2)-1581
meter

Excavation of Cable Trench at


3a Cable Section 2 Joint Bay 2 to 7 6/Mar/20 13/Mar/20
Joint Bay 1 (Open trench fdn-
362 meter)

HDD Section 2 Joint Bay 2 to


3b Joint Bay 1 (Pool pit 3 to pool 2 11/Mar/20 13/Mar/20
pit 4 -50 meter)

Laying of Power Cable and ECC


3c at Section 2 (Star Cement 5 14/Mar/20 19/Mar/20
Gantry to Joint Bay 2)-1581
meter

Excavation of Cable Trench at


4a Cable Section 3 Joint Bay 1 to 7 6/Mar/20 13/Mar/20
Composite Tower No.4 (Open
trench fdn-364 meter)

HDD Section 3 Joint Bay 1 to


4b Composite Tower No.4 (Pool 2 13/Mar/20 15/Mar/20
pit 1 to pool pit 2 -69 meter)

Laying of Power Cable and ECC


4c at Section 3 (Joint Bay 1 to 4 19/Mar/20 23/Mar/20
Composite Tower No 4/0)-
1299 meter

5a Cable Termination at 3 12/Mar/20 15/Mar/20


Mohitnagar GIS-3 nos

5b Cable Termination at Star 3 16/Mar/20 19/Mar/20


Cement Factory-3 nos

5c Installation of Jointing Kit at 3 20/Mar/20 23/Mar/20


Joint Bay 1 - 3nos

5d Installation of Jointing Kit at 3 20/Mar/20 23/Mar/20


Joint Bay 2 - 3nos

5e Cable Termination at 4 23/Mar/20 27/Mar/20


Composite Tower End(CT 1/0)

5f Cable Termination at 4 23/Mar/20 27/Mar/20


Composite Tower End(CT 4/0)

6 Backfilling with cover slabs, 10 27/Mar/20 6/Apr/20


testing and commissioning

You might also like