DAILY PROGRESS REPORT

Project: OSTT- SSJetty Submarine Pipeline,

Location:SS Jetty, SALPG, Durga Beach, Visakhapatnam


REPORT - DPR/OSTT-SSJ pipeline/HPCL/434 Date 20/05/2019
A) HIGHLIGHTS OF THE DAY
LFP AREA
pipe pulling arrangements going on ( sand bags arrangements )

MECHANICAL
ostt jetty pipe line painting works on going
launcher modification base plate sloted hole drilling work is going on ( 26 mm X 55 mm size solted hole 30 no's completed out of 58 no's )

civil works
in ss jetty pedstal concreat works is on going

ELECTRICAL
150 mm cable try bends fabrication 7 no's done in ss jetty
cable try supports shifting to OSTT jetty
cable try supports 65 mm angle welding done on 25 no's

B) QA/QC ACTIVITIES OF THE DAY


qc documentation works going on for final dossier

C) SAFETY HIGHLIGHTS

D) AREA OF CONCERN
IN SS jetty hot work stoped full day due to LPG un loading, mechanical works stopped

E) ACTIVITIES PLANNED FOR NEXT 24 hrs

F) (i)MANPOWER DETAILS
OCS-Infinite EPC
mechanical working crew 3
electrical contractor working crew 6
other contractor workers 15
Staff 7
(ii)EQUIPMENT compressure 1
excavator 1
Hydra 1
JCB

G) REMARKS

OCS INFINITE EPC Client Representative( DAPPOLONIA/HPCL)

OCS-INFINITEEPC/006/OPR/001 Rev0 OCS-INFINITE EPC