Daily Progress Report: LFP Area
Daily Progress Report: LFP Area
MECHANICAL
ostt jetty pipe line painting works on going
launcher modification base plate sloted hole drilling work is going on ( 26 mm X 55 mm size solted hole 30 no's completed out of 58 no's )
civil works
in ss jetty pedstal concreat works is on going
ELECTRICAL
150 mm cable try bends fabrication 7 no's done in ss jetty
cable try supports shifting to OSTT jetty
cable try supports 65 mm angle welding done on 25 no's
C) SAFETY HIGHLIGHTS
D) AREA OF CONCERN
IN SS jetty hot work stoped full day due to LPG un loading, mechanical works stopped
F) (i)MANPOWER DETAILS
OCS-Infinite EPC
mechanical working crew 3
electrical contractor working crew 6
other contractor workers 15
Staff 7
(ii)EQUIPMENT compressure 1
excavator 1
Hydra 1
JCB
G) REMARKS