التقارير التاسع لمصنع الشريف
التقارير التاسع لمصنع الشريف
:
Student’s name and Registration no.:khalid Zawahrah (21711467).
Date: From: 28/ 8 /2019 To: 3 / 8 /2019
1.
We were told that there was a malfunction in the bar that transported beverage
bottles from the tired station to the closing station
2.
Where the electrical panel consists of inverter and insulator
3.
Where the electrical panel consists of inverter and insulator
4.
First the inverter was disconnected and left to work on the connector
5.
It works normally but at an incorrect speed
6.
We checked the inverter and found it wrong and we changed the inverter
Lessons Learned
1.
Identify the problem first
2.
Learn how to check your inverter
3.
Learn how to connect it