Download as pdf or txt
Download as pdf or txt
You are on page 1of 23

0957–5820/04/$30.00+0.

00
# 2004 Institution of Chemical Engineers
www.ingentaselect.com=titles=09575820.htm Trans IChemE, Part B, March 2004
Process Safety and Environmental Protection, 82(B2): 105–127

REVIEW PAPER

FLIXBOROUGH: THE EXPLOSION AND ITS AFTERMATH


J. E. S. VENART*
Department of Mechanical Engineering, University of New Brunswick, Fredericton, New Brunswick, Canada

T
he Flixborough explosion was the largest-ever peacetime explosion in the UK. There
were 28 fatalities as well as the near complete destruction of the NYPRO plant in North
Lincolnshire by blast and then fire. An official Court of Inquiry was established and
charged with the responsibility of determining the cause(s) of the disaster and any lessons to be
learnt. This paper reviews the disaster, its investigation and inquiry, its attributed cause, and an
alternative possibility, and this redraws the lessons to be learnt for modern chemical plant
design and accident investigation. The reanalysis suggests that the failure was caused by a
complex two-step mechanism that resulted from the initial failure of only one bellows, a release
of about 10–15 tonnes of cyclohexane, and the detonation of the consequent vapour cloud with
an explosive effect of some 280 tonnes of TNT. This is compared with the single-step failure
process reluctantly acknowledged by the Court; the amount of release accepted, 40–60 tonnes
of cyclohexane, and its explosive effect, 6–16 tons of nitroglycerine. The results should be of
interest to industry, regulators, and loss prevention and risk assessment specialists.

Keywords: Flixborough; disaster; vapour cloud explosion; cyclohexane; loss prevention; risk
assessment.

BACKGROUND Office buildings. Adjacent, to the east, were Sections 7 and


27 (the Caprolactam Plant). The reactor train, which was the
On June 1, 1974, at about 15:53 UT, there was an explosion source of release, was aligned primarily north–south and on
and fire at the Nypro (UK) Ltd works near Flixborough. An the side of the section.
accidental release of cyclohexane at approximately Exactly 2 months before the explosion a temporary
0.96 MPa and 155 C resulted in an vapour cloud explosion 508 mm outside diameter (o.d.) 304L stainless steel (SS)
(VCE) which caused 28 fatalities, the near-total destruction pipe assembly was used to bridge the space between reactors
of the 24 ha plant, severe injury to the public, significant R4 and R6 as R5—which was leaking—had been removed.
damage to many structures in the surrounding countryside This reactor was placed in waste ground in front of the
(Secretary of State for Employment, 1975), and scattered Project Office and alongside the Section. At the time of the
debris as far as Anlaby on the outskirts of Hull 32 km away. incident the wind was blowing from South-Southwest
The plant was located on the east bank of the river Trent, 4–7 m s1. The perceived centre of the explosion, as deter-
a tributary of the Humber, about 50 km west of the port of mined by several investigators, was identified as being at the
Grimsby. On the west bank of the river, opposite the works, roadway just in front of the Main Office (Figure 1).
was the village of Amcotts; the village of Flixborough was on In the original oxidation sequence, all reactors were
a small rise to the East; the town of Scunthorpe was about connected by 711 mm inner diameter (i.d.) bellows and
1.5 km SE of the location: all suffered major distress though 711 mm o.d. stub-pipe assemblies (Figure 2). Each 12-
no loss of life (Figure 1). convolution 750 mm mean diameter bellows was made
The catastrophe was initiated in section 25A of the from 316L SS sheet 1 mm thick. The convolutions were
process stream during start-up while the mostly cyclohexane 37 mm high and at a 33.9 mm pitch; all were about 230 mm
feedstock, inerted with nitrogen, was under hot recycle long overall and welded to 316L 711 mm o.d., 6.75 mm
through the reactor train, R2521–R2526 (here called R1– wall, loose flanged stub-pipes. The bellows and a backing
R6); only one-third of the 70 kg s1 full production flow ring were fillet welded to each stub pipe (Foley, 1974a). In
was circulating at the time. Section 25A was South of the the modification, however, the temporary 4.8 mm wall
Laboratory and midway between it and the Project and Main thickness pipe-bridge, which used the two original bellows
and their 316L SS stub-pipe assemblies, had been installed
between R4 and R6 (Figure 3).
*Correspondence to: Dr J.E.S. Venart, Department of Mechanical Engi-
neering, University of New Brunswick, Fredericton, New Brunswick,
The 5 m high by 3.5 m diameter reactors were made from
Canada, E3B 5A3. 13 mm mild steel with a 3 mm SS weld inlay liner. Each was
E-mail: jvenart@unb.ca fitted with an interior overflow weir and inlet baffle plate to

105
106 VENART

Figure 1. NYPRO site plan showing Section 25A: the reactors; explosion origin, X; and CFD study area, cross hatched (modified from Figure 1, Secretary of
State for Employment, 1975, under the terms of Crown Copyright Policy Guidance issued by HMSO).

ensure level control and bottom feed as well as a gas sparger ization between reactors was provided by individual off-
for oxidation and a line for catalyst addition. The height of gas lines connected to a common header with pressure
flow over the weir was about 115–130 mm under full pro- relief.
duction and 40 mm at the time of the incident (Artingstall, The interconnecting pipes and their bellows had originally
1974). All but one reactor, R4, had an agitator (Artingstall, permitted the hot pressurized feedstock to flow over the outlet
1974). A 13 mm mild steel flanged skirt served as the reactor weir in the upstream reactors, through the bellows stub-pipe
base and this was affixed to a 460 mm thick reinforced connection into the downstream reactors with a fixed eleva-
concrete slab atop stepped concrete plinths. Pressure equal- tion difference of 178 mm at a velocity of about 0.3 m s1
through the nearly full pipes of full production flow. The
original freeboard of 230 mm also provided additional
pressure equalization capability, although, if pipes became
full and the off-gas vents blocked—say by a two phase
mixture—pressure balance could be compromised. The
‘dog-leg’ pipe adaptation, now, however, doubled the head
between R4 and R6 to 356 mm so there was a significant
weir ‘waterfall’ (velocities from 1.8 to 2.6 m s1 dependent
upon production—full=recycle) in addition to hydraulic
jumps in the very complex flow structure (Figure 4).
At full production the R4–B4 stub-pipe was nearly half
full at a velocity of about 0.5 m s1. Immediately after the
bellows, with transition into the 508 mm section, the flow
accelerated and became supercritical, ending in a significant
hydraulic jump near the lower mitre bend nearly filling the
pipe—due to a reduced freeboard of 120 mm—and then
Figure 2. Section 25A during construction (before vessels were insulated)
slugging into the lower B6 bellows and thence into R6;
showing the six reactors and their connections (source J. I. Cox, 1976, here the flow was quiescent (Teng-yang et al., 2000);
reproduced with permission from J. I. Cox). velocity at full production was again about 0.3 m s1.

Trans IChemE, Part B, Process Safety and Environmental Protection, 2004, 82(B2): 105–127
FLIXBOROUGH 107

Figure 3. Reconstruction of the R5 bypass assembly showing the two bellows and stub pipes, the 508 mm dogleg pipe and support scaffolding (source
Secretary of State for Employment, 1975, is reproduced under the terms of Crown Copyright Policy Guidance issued by HMSO).

Under the conditions of hot recycle the weir overflow thermal expansion of the reactors. And, finally, there were
generated greater velocity and turbulence due to the the significant discharge and flow modifications.
increased fall. The process fluid in this portion of the plant, cyclohexane
The modification made was thus much more than just a (C6H12, MW 84), is a colourless liquid similar in some of its
geometric alteration. Significant changes were made to the properties to gasoline [flash point 20 C, auto-ignition
statics, the dynamics and the flow. First, due to the dog-leg temperature (AIT) 245 C]. It has a normal boiling point
shape of the bridging pipe and the differences in pipe of 80 C and at 150–155 C saturation pressures, psat, of
diameters, there were a couple which latterly loaded 0.55–0.60 MPa. When the liquid was saturated with nitro-
the pipe and the bellows in the vertical direction. Second, gen, or air—as when oxidation was occurring in the reactor
the assembly was a mass–spring system with very little stream—the pressure was 0.96 MPa. Under these condi-
support provided by the scaffolding, especially upon vertical tions the liquid was 99.5–99.6% C6H12 saturated with

Figure 4. Reactor vessels R4 and R6 with the temporary bypass indicating liquid levels at full production (source Teng-yang et al., 2000, reproduced with
permission from IChemE).

Trans IChemE, Part B, Process Safety and Environmental Protection, 2004, 82(B2): 105–127
108 VENART

0.5–0.4% N2 or air; the vapour would have consisted of east, are the remains of the warehouse and flaking plant
about 61–68% C6H12 and 39–31% N2 or air (NIST, 1999). where there were four fatalities. Note that the damage to
The lower flammable (LFL) and upper flammable limits vehicles in the car park suggests very large over-pressures—
(UFL) of a vapour–air mixture by weight, under atmo- out in this area there were two deaths, a chemical worker
spheric conditions, are 3.5 and 20 wt% (1.3; 7.8 vol%), found 55 m from the plant entrance and 12 m from the car
respectively. park perimeter and the Main Gate security guard found
The scale of the disaster and damage can be appreciated 120 m from the centre of the explosion and 30 m from the
from photographs taken soon after the explosion and shown car park perimeter. A tanker truck, in the centre background,
in Figures 5 and 6. was completely crushed and its contract driver found nearby
In Figure 5 we are looking north over the rubble pile of at the plant weigh-bridge, some 120 m from the explosion
the Main Office building at Section 27. Notice the crushed centre.
columns to the right (east) of the Section and the, amazingly,
still near-vertical lamp-post, all indicators that this location
THE COURT OF INQUIRY
was near the center of the explosion. Note also that the
columns and vessels on the west (left) side of the section are An Official Court of Inquiry was immediately appointed
uncrushed. Had the explosion occurred during the week by the Secretary of State for Employment, Michael Foot, ‘to
the three-storey Main Office would have been occupied. establish the causes and circumstances of the disaster and to
In Figure 6 the car park to the southeast of the Main point out any lessons . . . to be learned therefrom’. The
Office building is shown. This spot is near where the main Court comprised R. J. Parker, QC (Chairman), J. A. Pope
entrance and Gate House would have been. To the right, the (Deputy Chairman), J. F. Davidson and W. J. Simpson and
heard from over 170 witnesses over a period of 70 sittings.
The essential problem faced by the Court was ‘to determine
what had caused the rupture of the by-pass.’ However, the
only possibilities considered in detail were: ‘(i) rupture of
the by-pass assembly through internal pressure; (ii) rupture
of the assembly in two stages; a small tear in the bellows
[B4] leading to an escape and a minor explosion causing
final rupture; and (iii) rupture of the ‘8 inch’ line at the
50-inch split leading also to a minor explosion causing
rupture of the by-pass assembly’.
Processes (ii) and (iii) were interpreted to require an
external minor explosion to trigger events; little evidence
for this could be determined, however. All required greater
than normal internal pressure. Possibility (ii) was ruled out
early in the investigations as extensive testing of six new
bellows showed that pressures in excess of those required to
activate the pressure relief system were necessary and also
that low cycle fatigue would not extend the very small
resulting tears (Batstone, 1975). So, despite a large internal
Figure 5. Looking north over the rubble of the Main Office Building into tear found in bellows B4 (Foley, 1974a), and compelling
Section 27 (photograph reproduced with permission from the Scunthorpe
Evening Telegraph, www.thisisscunthorpe.co.uk=photosales). eyewitness evidence, only three paragraphs in the final report
and a few pages in the Court’s record, no definitive studies
were further devoted to the two-stage rupture possibility.
Processes (i) and (iii) only were examined in depth and in
near equal measure in the Report of the Inquiry, the Records
of the Court and the supporting studies. Other possibilities
considered for an internal initiating event (e.g. peroxide
decomposition and the operation of a nitrogen purge) were
excluded, as was the likelihood of fatigue and a water–
cyclohexane superheated explosive boiling interaction (King,
1975, 1977, 1999). In this case recent experiments under-
taken for the UK Health and Safety Executive on behalf of
the Minister of the Environment (Snee, 2004) indicate that
water trapped in the bottom of R4 did not play a significant
role in the event; further experiments to examine the
influence of venting are planned.
On the basis of expert evidence by Professor D.E.
Newland (Newland, 1976), based on a dynamic analysis
and assessment of energy requirements for both bellows to
squirm and the by-pass pipe to buckle as one event, the
Figure 6. The NYPRO car park to the east of the Main Office Building Court concluded, albeit with low probability, ‘that the
(photograph reproduced with permission from the Scunthorpe Evening disaster resulted from a one stage failure of the 20-inch
Telegraph, www.thisisscunthorpe.co.uk=photosales). assembly’—as a result ‘of conditions of pressure and

Trans IChemE, Part B, Process Safety and Environmental Protection, 2004, 82(B2): 105–127
FLIXBOROUGH 109

temperature more severe than any which had previously in Hz, p is the bellows pitch (m), and V is the mean flow
prevailed but no higher than careful and conscientious plant velocity (m s1). The flexibility of expansion joints makes
operators could be expected to permit.’ This failure process them susceptible to self-excited vibration, resulting in bend-
was supported only partially by an extensive full-scale ing stresses that may produce fatigue failure (Weaver and
experiment (Games and Waterhouse, 1974), which indicated Ainsworth, 1989). Gigacycle fatigue damage to the thin wall
that bellows squirm and pipe-bridge buckling of the assem- bellows may thus have occurred since between 20 million
bly (as shown in Figure 3) would occur in about 100 ms. and over 300 million cycles were possible within the range
Other experiments and bellows tests at the same and more of potential excitations present during the 2-month operating
severe operating conditions were also conducted (Batstone, period. In the fatigue testing of steels, trials are usually
1975). All these experiments were, however, unable to terminated before 100 million cycles since a ‘fatigue limit’
reproduce fully the failure process accepted, the physical is normally registered between 1 and 10 million cycles. How-
evidence, and the experience of witnesses within their ever, tests conducted with high-frequency random vibration
observation time-frames. The Court did state, though, that (similar to those associated with the natural resonance of a
their conclusion ‘would be readily displaced if some [other structure) show that the fatigue limit of steels can disappear
event of] greater probability to account for the rupture could and that fatigue failures occur (Miller, private communica-
be found’ (Secretary of State for Employment, 1975). tion 1999; Au-Yang, 1999).
The Court’s qualified conclusion as to cause has been the It is worthwhile to review the Court’s concerns on fatigue.
subject of considerable controversy, especially regarding the The only serious questioning on the subject was raised by
actual failure process (e.g. Ball, 1975, 1976; Butler, 1975; Dr Pope, Deputy Chair of the Court, and a mechanical
Cox, 1976; Gugan, 1976; King, 1977; Warner, 1975; engineer, in his questions to Dr Foley (Foley, 1974d).
Warner and Newland, 1975), the amount of cyclohexane Drs Gill and Kitching (Gill, 1974; Kitching, 1974) as well
released, and whether the unconfined vapour cloud formed as Dr Ryder (Ryder, 1974) also raised concerns regarding
in the release detonated (e.g. Gugan, 1979, 1980a,b; Ale and flow induced and other vibrations and fatigue. Dr Foley had
Bruning, 1980a,b; Fu and Eyre, 1974; Phillips 1981). The earlier stated that ‘detecting fatigue failure in thin sheets is
debate and study continue to this day (e.g. Gugan, 2000; difficult’ (Foley, 1974e). In order to determine evidence for
Høiset et al., 2000; King 2000; Kletz 2000; Swan 2000). fatigue in the bellows, over 26 m of failure surface would
In view of the role this event has played in the chemical have had to have been carefully examined. Dr Foley had
and insurance industries and its pivotal function to loss stated (Foley, 1974b,c) that his inspection was only made by
prevention and regulation, a further reexamination now ‘eye and a small lens’ and thus the possibility of fatigue,
appears warranted. In this, greater attention will be focused especially at the interior tear in the upstream B4 bellows,
on possibility (ii)—rejected by the Court—as a two-stage cannot be ruled out since a more careful examination would
event was certainly experienced by most witnesses. In what have necessitated greater magnification. Dr Miller, too, was
follows the bellows, the bridging pipe and its assembly into questioned on this subject (Miller, 1974).
the by-pass are modelled and a release scenario that consid-
ers the likely sequence of events initiated by the crack noted
in B4 is advanced. This is done because flow-induced THE EVIDENCE
excitation and fatigue of bellows was not considered in
The Safety and Mines Research Establishment (now the
depth by the Court and this may have been responsible for
Health and Safety Laboratory of the Health and Safety
the initiation of events.
Executive) was responsible for the work of recovery, identi-
Each bellows had a first natural frequency of about 65–
fication and examination of the wreckage and the conduct of
71 Hz axially and between 325 and 416 Hz in the transverse
further testing. Creamer and Warner, Consulting Chemical
direction. The system (pipe, stub-pipes and bellows) reso-
Engineers, were appointed technical advisors to the Court.
nance frequency, as determined for a straight pipe, was
HM Coroner was A. A. Collins. The Home Office Patho-
3.9 Hz axial, 15.7 Hz lateral (ends of the spool pipe in
logist was Dr A. Usher of the University of Sheffield (Usher,
phase), and 27.2 Hz for the rocking mode (EJMA, 1993).
1979).
The excitation of this very complex spring–mass system was
now such that resonance with portions of the flow was
possible (Teng-yang et al., 2000). Most of the lower
Witness Statements
frequencies could have been excitable by the very broad
range of flow velocities present, particularly near the Humberside Police were in charge of the accident inves-
hydraulic jump and regions of flow acceleration. The jetting tigation (Humberside Police, 1974). Interviews were
at the base of the weir outfall could also result in the axial conducted, and statements taken from nearly 300 indivi-
resonance of the bellows since these were about one pipe duals. These included 43 shift survivors, 54 off-site
diameter away. witnesses, 78 employees on the June 1 7 a.m.–3 p.m. and
With flow-induced vibration of bellows, no significant 8 a.m.–4 p.m. shifts, as well as 114 other employees and
response is observed up to some critical velocity and then, contractors. Dr J. I. Cox worked with many of the survivors
as the velocity is increased further, the convolutions become and witnesses to reconstruct events and confirm the timings
unstable. For uniform mean flows the critical Strouhal made in statements (Cox, 1976).
number is St ¼ 0.45 (Weaver and Ainsworth 1989); for In 1974 Nypro had grown to employ 560 persons of
non-uniform flows, as at the exits of elbows leading to whom some 260 were shift workers (Westgate, 1975). June 1
bellows and perhaps the weir outfall region, St ¼ 0.57 was a Saturday and so only about 70 persons, employees
(Jakubauskas and Weaver, 1998a,b). The Strouhal number, and contractors, were on site. Of these, Humberside police
St ¼ ( fp)=V, where f is the bellows axial natural frequency were able to take statements from 43 individuals; nearly all

Trans IChemE, Part B, Process Safety and Environmental Protection, 2004, 82(B2): 105–127
110 VENART

(42) indicated that the lead up to the explosion had consisted Blast
of some noisy events in the vicinity of the southwest end The Main and Project Office buildings (Figure 1) were
of section 25A—a ‘bump’, a release of high-pressure gas totally destroyed, likewise the Laboratory and Main Control
(‘like a PRV vent’) for about 2–4 s, deep rumbling, more Room. W. Thomas, of Amcotts, saw what appeared to be the
noise—a ‘bang’—with debris being scattered upwards, a interior explosion of the Project Office immediately prior to
‘roar like a jet engine’, massive upward and southern the main explosion (Humberside Police, 1974). The 0.4 m
releases concurrent with a westward developing ground thick concrete second floor of the southeast corner of
flow, and small fires about the base of the reactors, all Section 27 was displaced downwards (Roberts and Pritch-
taking place over about 30 s prior to the explosion. In the ard, 1982), suggesting an aerial flammable cloud at this
3–4 s initial period some observed something like a ‘tank location. A tanker truck (cf. Figure 6), located about 150 m
top’, or ‘sheet of metal’ 1 m diameter, being thrown up east of the southern end of Section 27 was completely
and spiraling downwards, one on site, L. Harry, and three crushed by an overpressure estimated to be about 1 MPa
off-site, J. A. R. Cooke, S. Hill, and H. Toyne. Many then (Gugan, 1976). A manhole cover, located on the roadway, in
observed debris and dust being thrown upwards followed by front of the Main Office building and midway between the
vertical and then horizontal jets of discharged material Gatehouse and Section 25A was broken by a similar over-
(Humberside Police, 1974; Harry, 1974). pressure (Gugan, 1976).
Of the eight survivors from the Laboratory, seven gave Physical damage to steel chemical plant components, for
evidence. Of these, five were specific in the description of example some of the reactors and strong pressure vessels
a slowly developing vapour cloud moving to the west over located in sections 25A, 7 and 27, and closest to the Main
the time period of their observation, 8–12 s. This cloud Office building, exhibited crushing of their skirts or bases,
was described as being about 1.5–2 m high and moving which indicated overpressures of the order of 1 MPa. R5,
at 5–6 m s1 along the ground across the clear space located in the waste ground north of the Project Office,
between the Laboratory and the Project Office. Its origin however, only experienced crushing to its skirt on its eastern
was described as either being near the top of R4 or at its perimeter, whereas its western base and the upper sides of
base, but at least between the two (R4 and R6) reactors. the weaker cylindrical section were undamaged [compare
None of the these witnesses described any northward flow, Plate 7 in Secretary of State for Employment (1975) with
i.e. any flow coming towards them. One described debris Figure 2.4 in Center for Chemical Process Safety (1994a)].
being thrown up into the air very early into the event. Crushing was also evident around the base of R6 but not the
Other individuals, one about 90 m east and some 60 m upstream reactors (Plate 8 in Secretary of State for Employ-
north of the Main Office building described a cloud of dust ment, 1975): the fact that the base of R6 was crushed but not
and smoke coming round the southern end of Section 27 its weaker barrel suggests that this was under pressure at the
(Colquhoun, 1974). Another, some 500 m to the west time of the explosion. In the failure mode accepted by the
observed the development of the cloud from its initiation Court, both reactors R4 and R6 would have discharged
as a ‘whisper of ‘‘steam’’’ to its enlargement into a ‘roaring’ together. Since the upstream reactors had greater inventory
jet going up-river (i.e. south) and ending up ‘like a fog’ (there were five reactors; the non-return valve after R6
across the car park (Ayre, 1974). limited the downstream capacity to that of R6 only), their
Various off-site witnesses, e.g. King (1974) about 500 m discharge would have lasted longer than that from R6 and it
away, reported seeing ‘dirty steam’ going up into the air, should have emptied earlier and not been under pressure.
followed by ‘what appeared to be an explosion that blew Additionally the Goodchild cine film as well as Plate 5 of
vapour sideways into the works’ and then the major explo- the Court’s report, both taken after the explosion, show a
sion; Dickinson (1974), about 200 m away, saw a flash like a significant torch fire from the south end of the section.
large ‘creamy coloured torch’ coming towards him (i.e. Process columns to the southeast in Sections 25A, 7 and
eastward) before the explosion. One described a ‘kettle 27 exhibited considerable crushing at a variety of elevations
spout’ and another a ‘swan neck pipe’ in the vicinity of [e.g. Figure 6; Plate 8 in Secretary of State for Employment
Section 25A (Humberside Police, 1974). (1975), Sections 25A and 27; and Figure 2 in Roberts and
A cine film taken immediately after the explosion indi- Pritchard (1982)]. High pressure crushing damage was not
cated what appeared to be a short duration moving and apparent, however, into the northern sections of the plant
bifurcated near-vertical torch-like fire from the southern end (Gugan, 1976). This pattern is consistent with the explosion
of the section (Goodchild, 1975). of both a ground level (to the west out nearly to R5) and an
elevated flammable cloud that encompassed the Main Office
and Project buildings and the southern end of the plant. That
only the southern and SE outer perimeter of plant appeared to
Physical Evidence
have been subjected to such great pressures suggests that the
The enormity of the disaster can only be appreciated by initial extent of the fuel air cloud had not penetrated exten-
reference to the many photographs included in references sively into the northern sections of the plant such as would
(Secretary of State for Employment, 1975; Sadee et al., have been necessary by the simultaneous dual bellows failure
1976=1977; Gugan, 1979; Roberts and Pritchard, 1982) and scenario accepted by the Court. Furthermore, the determined
others available in reports prepared for the investigation. center of the explosion, just immediately north of the Main
Photographs from the press, particularly those taken by Office building, and stated to have been at an elevation
the Scunthorpe Evening Telegraph, reveal the extent of the of about 20–30 m (Sadee et al., 1976=1977), coincides
destruction, especially out into the car park south of the closely with the cloud development and its centre of mass
offices where most automobiles were completely crushed for the R4-only discharge, as will be shown later in the CFD
(Figure 6). studies.

Trans IChemE, Part B, Process Safety and Environmental Protection, 2004, 82(B2): 105–127
FLIXBOROUGH 111

Pressures sufficient to crush the bases of the reactors can


possibly only be obtained with the detonations of fuel drop–
air vapour clouds where values of 1.9 MPa may occur
(Fishburn et al., 1981; Center for Chemical Process Safety,
1994b; Høiset et al., 2000). Pressures in closed vessel
deflagrations do not normally exceed 0.8 MPa. Detonations
of unconfined fuel–air clouds require significant ignition
energy (Fishburn et al., 1981; Center for Chemical Process
Safety, 1994b), thus requiring, perhaps, a prior gas explo-
sion (Harris, 1983) of, possibly, the Main Office and=or the
Project Office building to act as a ‘precursor’ or trigger for
the detonation. Ionospheric measurements made in the close
range suggested that there might have been a precursor, or
smaller disturbance, to the main explosion (Jones and
Spracklen, 1974) such as could have occurred with one or
both of these buildings exploding. Photographs of the rubble Figure 7. Reactors R4 and R6 after the explosion showing reactors R4 and
and debris of both (Secretary of State for Employment, R6, their stub pipes, the buckled dog-leg pipe lying on top of the R5 plinth,
1975; Sadee et al., 1976=1977) also suggest that an interior the cross-walkway deformation, and damage to R6—dent in northwest side
explosion may have occurred there first followed by the and crushed support skirt (Flixborough file photograph, HSL Library,
Sheffield, reproduced under the terms of Crown Copyright Policy Guidance
major blast. Alternately, jet-fire initiation is also possible issued by HMSO).
(Harris and Wickens, 1989).

Other evidence the dead load of the fluid inventory. Pressure was applied by
Metallographic examination of the surfaces of the brid- nitrogen gas. Strains in the pipe were also measured. There
ging pipe, stub pipes and bellows indicated no unusual were eight test runs, three at ambient temperature, three at
features except on the surface and attached bellows 155 C, and two at 160 C. The maximum pressure utilized
remnants of stub pipe R4. This showed a heavy grain- was 0.964 MPa in all but the last two cases; for these the
boundary network of carbides which extended into the bellows were squirmed at 1.06 MPa and then ‘burst’ at
structure (Foley, 1974a). Grain-boundary carbide networks 1.53 MPa.
can be produced in austenitic steels by prolonged heating in In the experiments at ambient temperature, internal pres-
a carburizing atmosphere (i.e. cyclohexane vapours) within sure caused the B4 end of pipe to move upward and the
the sensitizing range (400–800 C; Foley and Nicholson, scaffolds there were only lightly loaded. With increase in
1974). Two-phase jetting from R4 should have cooled this pressure, the B4 end rose off the scaffold support as the B6
structure and thus prevented carbide formation. Upon cessa- end moved downwards and the scaffolds there carried
tion of a R4 discharge, however, the impact of a R6 jet fire greater load. However, under operating conditions, 150–
could have resulted in the carbide formation. Carbide 155 C, the assembly was mostly unsupported since the
formation, along with zinc embrittlement, formed by high reactors expand upwards about 6 mm.
temperature exposure and molten zinc contamination, was
found on portions of the ‘8-inch’ pipes. From this it was Bridging pipe
possible to infer probable temperature distributions within Experiments on the 4.8 mm thick wall dog-leg pipe were
that piping structure (Foley and Nicholson, 1974). also carried out (Batstone, 1975). Two 75 mm pin joints
Figure 7 and Plate 9 of the Court’s report show that were located at the centre of the bellows at each end of the
portions of the scaffold supports and the plinth crossing original assembly where the bending moment was zero. An
walkway, in front of R6, have been impacted by something axial load was applied horizontally at the lower end through
and swept towards the base of R6. There was also an two pre-calibrated hydraulic rams each of 100 tonnes
unexplained impact dent in the front, i.e. facing R4, side capacity with 152 mm stroke. In order to support the vertical
of R6 (Figure 7 and Artingstall, 1974). The inlet baffle plate force on the ram, two double row, self-aligning ball bearings
of R6 had been torn off and had impacted the agitator shaft, were located on the extended pin of the joints. These were
bending it through an angle of 15 (Artingstall, 1974, free to move on two horizontal supports mounted on the
Gugan, 1979). floor as the rams extended but were prevented from twisting.
Two strengthened adapter pieces were welded to blank
Experiments flanges bolted to both ends of the pipe and pivoted on pin
joints fixed to vertical support columns. The pipe itself was
Dog-leg pipe-bellows assembly filled with water and internal pressure applied with a hand
A test of the assembly was conducted at Flixborough pump. The axial load applied via the ram maintained the
using a new pipe built according to the original design and internal pressure according to the relationship:
inserted in place of reactor 3 (R3) (Secretary of State for
Employment, 1975; Games and Waterhouse, 1974). The F ¼ pA (1)
bellows utilized were new with axial stiffness of 498 and
482 kN m1 for the B4 and B6 bellows, respectively. Scaf- where F was the horizontally applied axial load, p the
folding, similar to that in the original installation, could also internal pressure, and A the effective cross-sectional area
be used. Axial and lateral deflections were measured, both of bellows (deff ¼ 747 mm). The internal pressure and
cold and hot (155 and 160 C), with a chain used to simulate deflections at several positions were measured and recorded.

Trans IChemE, Part B, Process Safety and Environmental Protection, 2004, 82(B2): 105–127
112 VENART

This pipe failed, i.e. buckled at its lower mitre joint at  As a result B6 rapidly expands and compresses B4 due to
1.89 MPa. this unequal pressure distribution, Figure 8(b), and the
now superheated and supersaturated cyclohexane starts to
Bellows and stub-pipes boil with a ‘rumbling’ sound; the boiling becomes more
Batstone (1975) also conducted four individual water- vigorous with time. The B4 bellows are hard compressed
filled bellows tests with a facility designed to simulate half from 228 down to 50 mm and all the convolutions
the dog-leg pipe=double bellows assembly. As the distance creased; B6 expands from 228 to 400 mm.
from the mid-point between the two mitre bends to the first  Owing to local boiling, a two-phase swell rapidly fills R4,
convolution of each bellows only differed by 17.5 mm, only its top vent, and its R3 inlet as well as B4 and its stub pipe.
the lower, R6, bellows was evaluated. Axial and shear forces This restricts pressure equalization with R6. As nitrogen
on the bellows were measured as functions of internal comes out of solution and the fluid boils, the increase
pressure along with vertical deflection measurements. The in pressure, from the cyclohexane saturation pressure back
pivot point of the pipe assembly was fixed 0.178 m above to operating conditions, generates a dynamic two-phase
the centreline of the bellows at zero internal pressure at a head space impact and dynamic re=over-pressurization
distance of 2.4 m to the first convolution. The ends of the (Gromles, 1984; Ramier and Venart, 2000). This immedi-
bellows were welded to stub-pipes and these bolted to blank ately causes the compression of the downstream, B6,
flanges, the fixed end being bolted to the support frame and bellows, the extension of B4, and the initiation of its
the free end being welded to an I-beam which supported the upwards ‘squirm’, Figure 8(c)–(e). Squirm is a result of
pivot point of the assembly. the extension, >170 mm, and due to fluid distribution in
The bellows all failed, i.e. squirmed, at an internal the pipe. There is first the ‘thud’ as B4 is compressed and
pressure of about 1.2 MPa. In one of the tests, pressures then a minor ‘rumbling’ of the boiling process in the B4
were cycled over selected ranges of up to 3456 times. In this region of the pipe-bridge, and then a further ‘thud’ as B6 is
test, cracks did not occur until further pressurization to now hard compressed by the repressurization occurring in
1.5 MPa. These cracks were sealed and the test cycles R4 and B4, Table 1.
continued for 900 cycles (1.0–1.1 MPa) and a further 400  The compression of B6, by this local overpressure, fixes
cycles (1.07–1.2 MPa); there was only a slight increase the constraint of the dogleg pipe at its R6 connection and
(2 mm) in the three cracks which had formed at the ‘crimple’ causes the process of B4 squirm to act over the full
points due to squirm. In a few experiments a 48 mm 356 mm eccentricity, Figure 8(d), with much less force
diameter 1.82 m long scaffold support was provided with a than needed by Newland’s 178 mm offset single stage
6.4 mm space between stub-pipe flange in order to evaluate analysis (Newland, 1976).
the influence these had on the behaviour. It was this  This results in the collapse, by buckling, of the 0.5 m
experiment that the Court used to rule out its possibility (ii). pipe, at its lower mitre joint, as the B4 bellows continues
to squirm, then balloon, burst and is ripped off at its
normal operating pressure due to the ‘p–V’ work of the
A POSSIBLE INITIATING MECHANISM expanding two-phase fluid, Figure 8(f), the unresisted
squirming force, and the massive reduction in the pipe’s
A potential initiating mechanism consistent with the
moment of inertia caused by buckling, Figure 8(g). It
possibility of fatigue and the evidence outlined above first
should be noted that there is a reduction in moment of
requires the initiating tear found near the top of the
inertia from a thin-walled cylinder to collapsed tube
upstream, B4, bellows (Secretary of State for Employment,
greater than 4000 to 1.
1975; Foley, 1974a; Foley and Nicholson, 1974). The
 The B4 squirm, once past about 50 mm vertically, cannot
topmost convolutions of the B4 bellows nearest R4 are most
be resisted and the collapse of the pipe and destruction of
highly stressed (Venart and Tan, 2000) and the convolutions
B4 continues. B4 is torn into three pieces.
susceptible to excitation by the flow.
 The ripped off topmost section of B4 is projected
The various steps in the failure process are portrayed in
upwards and sails into the air and appears, to some
Figure 8 and a tabulation of the sights and sounds that
as a ‘blown off ‘‘tank top’’’; it was found only two
would have been expected indicated in Table 1. The very
months later under extensive debris between the line
complex process can be summarized as follows.
of reactors and the after-reactors (Foley and Nicholson,
 The instability of the assembly and the near-resonance of 1974); all other portions of both the B4 and B6
the upstream, B4, bellows with the forcing fluid flow bellows were located immediately by investigators
initiates fatigue damage which accumulates in the most (Foley, 1974a).
highly stressed, and least damped (i.e. the vapour space),  The shape of the buckled pipe is now somewhat like the
regions of the unit. Small cracks form. ‘swan neck’, Figure 8(g)–(h), noted by some (Marshall,
 Sufficient damage accumulates to cause the cracks to join 1974; Gugan, 1974) with a significant jet discharge such
and initiate a tear which further opens, due to pressure, that it resembles a ‘tea kettle spout’. The B6 bellows
and local vapour–gas depressurization occurs, Figure through all of this is, however, still intact, although
8(a). There is a bang and a sound like a pressure relief possibly severely damaged.
valve going off, Table 1. The vapour space of R4 and  In the buckling process, Figure 8(g)–(h), the 250 kg liquid
B4 rapidly, 3–4 s, depressurizes down to the saturation contents of the lower end of the 0.5 m diameter pipe are
pressure of the cyclohexane, 0.55–0.60 MPa. forcibly ejected into R6 and this impulse tears off its inlet
 Pressure reduction to this level is nearly immediate in the baffle and causes this to impact and bend the internal
structure whereas the pressure response times are three to 154 mm diameter SS agitator shaft (Artingstall, 1974;
15 times slower in the fluids. Gugan, 1979).

Trans IChemE, Part B, Process Safety and Environmental Protection, 2004, 82(B2): 105–127
FLIXBOROUGH 113

Figure 8. Successive stages in a crack-initiated two-stage bellows and pipe-bridge failure (reproduced from Venart, 1999, with permission from
INTERFLAM, www.intercomm.dial.pipex.com).

 The above processes would have been very noisy as the  The major explosion occurs which strips off most of the
bellows burst and the dog-leg pipe buckled. Some of the local pipe and vessel insulation.
overhead scaffolding would have been projected upwards  The now swinging pipe is swept through the scaffolding
along with other debris and discharged material. In the below by the force of the blast toward the base of the
process some pieces of scaffolding boards and insulation R6 reactor (see Figure 7 and Plate 9 of Secretary of State
material (insulation and its aluminum sheet cover) are for Employment, 1975) and it deflects further and its
caught in the ‘nip’ of the collapsed pipe (Foley, 1974a; lower surface impacts the side of R6 denting it (Arting-
Secretary of State for Employment, 1975). There would stall, 1974) as well as flattening the bottom of the pipe
have been also the development of a ‘roar’ due to the after the lower miter-bend further (Foley, 1974a), Figure
massive two-phase discharge from R4 and the lesser two- 8( j). This effectively cuts off all flow through the pinch.
phase discharge from fluid trapped in the B4 end of the Additionally, the topmost portion of B6 is stretched out
pinched pipe-bridge additional to the ‘rumbling’ of the flat, without any convolutions being left, unlike the
boiling of the superheated cyclohexane in R4, Table 1. companion piece of B4, where some convolution creases
 The R6 internal pressure now expands B6 and frees its were still intact (Foley and Nicholson, 1974). The posi-
constraint, Figure 8(h). The reaction of the ‘choked’ two- tions of the ‘crimple’ points in B6 also differ significantly
phase discharge, which occurs through the B4 end of the from those in B4 (Foley and Nicholson, 1974), indicating
buckled pipe-bridge, bends and distorts the bellows a different distortion process for this bellows.
forcibly expanding and stretching its topmost elements  In this dynamic process, the B6 bellows are torn off and
to their full extent. The pipe now appears as a ‘swan neck’ the rebound from the R6 impact and the impulse of the
or a ‘tea kettle spout’. two-phase release from the now open R6 end of the pipe

Trans IChemE, Part B, Process Safety and Environmental Protection, 2004, 82(B2): 105–127
114 VENART
Table 1. Sights and sounds in the Flixbourgh by-pass pipe-bridge failure; Figure 8.

Time (s) Event (Figure 8) Sound Sight Comment


1–2 (a) ‘PRV’ vent Wisp to jet of ‘steam’ Many observers
3 (b) ‘Thud’ Jets of ‘steam’
3–4 (c)–(d) Bang and rumble Two-phase jet
4þ (e) Greater rumble, larger jet B4 bellows squirms
5þ (f)–(g) More severe rumbling Upward debris, large kettle spout Bellows off, pipe buckles
5–25 (h)–(i) Roar ‘like a jet engine’ Vertical venting ‘swan-neck’ pipe R4 jet discharge
25þ (j) First explosion—detonation Works office ‘white flash’
26 (j) Pipe bangs R6 Vertical flames Dent in R6, B6 tears off
27 (k–l) Crash and thud Bypass impacts R5 plinth R6 jet-fire on B4 remnants
27þ (l) New rumbling R6 jet fire Eight-inch line failures

spins the assembly clockwise downwards, Figure 8(k), production flow (Artingstall, 1974). The inlet–outlet pipes
such that the flanges, after the lower mitre bend and its R6 of all reactors would thus have been nearly full aside from
stub-pipe, impact the top of the 0.46 m thick reinforced the outlet pipe leaving R4. Here the level at the foot of the
concrete R5 plinth puncturing it, Figure 8(l) (Secretary overflow weir would have been much lower and under full
for State for Employment, 1975). In this process only the production flow, 0.125 m3 s 1, the 0.71 m discharge pipe
R6 stub end of the pipe and its flanges are severely would have been only about half full.
distorted at the point of impact (Foley, 1974a). The With the release mechanism outlined earlier (Figure 8,
pipe, after impact, rebounds and falls over. In the mechan- Table 1), the discharge would have initially been a vapour jet
ism accepted by the Court the buckled end of the pipe or jets through the fatigue cracks, which then would have
should have impacted the plinth slab. extended by pressure to the extent noted by Foley (1974a) in
 These later sequences, Figure 8(i)–(l), occur after, the the B4 bellows remnant. The volume of vapour discharged
major explosion. would essentially be that amount trapped in the top of R4
 Once the B6 bellows blows off, the resulting horizontal and in the upper reach of the B4 end of the dog-leg,
northward developing torch flame is split by the R4 approximately 12.5 m3. A determination of the quantity
reactor and the eastern half envelopes the now distorted and an estimate of the time can be made based upon the
bare ‘8-inch’ pipes causing the inferred temperature assumption of sonic vapour-only flow through a crack the
distributions, observed creep swelling, zinc contamina- length noted by Foley (1974a). Then, dependent upon
tion and failures (Foley and Nicholson, 1974; Cottrell and the assumed crack width (2 mm) and its discharge coeffi-
Swan, 1976). The bifurcated R6 jet flame explains the cient (1.0), a discharge of about 0.1 tonnes could occur in
cine film taken by a witness (Goodchild, 1975) and obser- about 10 s. This assumes that the discharge process is
ved by others (Carter, 1974). High temperature carburiza- choked and takes place down to a condition where the
tion is found only on the R4 stub-pipe and its attached liquid will just commence boiling, i.e. 0.55 MPa, the satura-
remnants of the B4 bellows (Foley, 1974a; Foley and tion pressure of pure cyclohexane.
Nicholson, 1974). No carbide formation was observed Next it is assumed there is a point before all the vapour is
on the R6 stub-pipe nor its B6 bellows remnants as would exhausted where there will be sufficient superheat in the
be required from the simultaneous jet fires resulting from liquid for it to commence boiling and swell up and fill the
the Court’s accepted mechanism. R4 vessel. At the same time the pressure differences
between the reactors will cause each connection between
The major consequence of this sequence of events is that the reactors to fill and essentially two-phase ‘choke’ such
a discharge through reactor R4 alone occurs prior to the that the discharge process after the vapour release will
main explosion and is thus responsible for the blast. This is consist of the sequential two-phase choked discharge from
only sufficient to provide a release of some 370 kg s1 of each reactor in turn starting from R4. Further discharge from
cyclohexane for probably less than the 30–40 s determined this point in time will have R4 essentially acting as a
for initial events (Cox, 1976). This vent, of some 10–15 separator for the subsequent discharges from the upstream
tonnes (Leclude and Venart, 1996, 1997), is very much reactors R3 to R1. The inlet baffles and the outlet weirs of
smaller than the 40–60 tonne estimates previously attributed each reactor will essentially aid in this process as they will
to the explosion (Sadee et al., 1976=1977; Roberts and additionally restrict flow beyond that provided by the two-
Pritchard, 1982; Bjerketvedt et al., 1997), since once the phase chokes of the reactor inlet–outlet nozzles.
flashed inventory of R4 is exhausted the two-phase choke The energy for boiling comes at the expense of a loss of
from R3 now limits its (R4’s) function to that of a ‘knock internal energy of the liquid and a determination of the
out’ vessel. amount of material that must be vaporized to fill the R4
Any estimate of the amount of cyclohexane released must vessel can be made using mass and energy conservation as
take into account the very complex interior geometry of the well as Clausius Clapeyron considerations in order to
reactor stream flow path in addition to the composition and deduce pressure. Since the quantity of nitrogen dissolved
thermodynamic state of the flow. Figure 3 partially illus- in the cyclohexane is small (0.2%), the vapour phase
trates the interior of the reactors and the ‘by-pass’ pipe depressurization is assumed complete when the pressure
assembly. Under the hot recycle flow conditions existing at has fallen to 0.54 MPa (i.e. just sufficient superheat to
the time of the accident (0.04 m3 s1), the levels in the evaporate enough liquid to fill the reactor). At this point
reactors would have been 130–150 mm lower than under full the vapour discharge is complete and the bellows squirms

Trans IChemE, Part B, Process Safety and Environmental Protection, 2004, 82(B2): 105–127
FLIXBOROUGH 115

and blows off. A two-phase discharge now commences from The Bellows
the full 0.71 m R4 outlet.
For small deflections (i.e. elastic behaviour), bellows can be
The average void fraction in R4 is based upon the original
simplified by only half a convolution. The axial and transverse
vapour volume, i.e. 0.2. To estimate the initial discharge
stiffness from such an analysis can be regarded as a reference
void fraction the non-homogeneous bubble distribution in
base for the verification of any later more detailed, and
the vessel must be considered, (Gromles, 1984), where a
therefore necessarily less refined, FE model. Although the
distribution factor (Kataoka and Ishii, 1987) is taken. From
results are somewhat dependent upon the physical properties,
this we can now deduce all the necessary properties for the
Venart and Tan (2000) made an analysis using 2688 eight-
fluid at the entrance to the nozzle.
node isoparametric two-dimensional symmetric elements
The level within the R4 reactor must now be tracked and
with 8753 nodes of a model of the Flixborough bellows that
here the rate of vapour production is compared with the rate
resulted in a determined cold axial stiffness of 403.8 kN m1
that volume can separate via the pool free surface (Wehmeier
and transverse stiffness of 5558 kN m1.
et al., 1994), where the velocity of separation (Kataoka and
With large transverse deflections, contacts between adja-
Ishii, 1987) can be utilized. When the separated volume
cent convolutions occur and half a whole bellows must be
exceeds that being produced, the volume of the two-phase
modelled. The shape of the bellows is asymmetric, i.e. the
swell diminishes and the preceding reactor (R3) will com-
overall shape of the deformed structure possesses 180
mence discharging into R4. Using a variety of two-phase
rotational symmetry about the mid-point of the neutral
flow models (Leclude and Venart, 1996) with discharge
axis. Three dimensional (3D) shell and surface contact ele-
coefficients of 0.5 and over the pressure range 0.55–
ments are thus necessary. An element size of 12  12 mm
0.45 Mpa, it is estimated that about 10 tonnes flash from
yields 11,760 elements and 11,979 nodes to mesh half
R4 and are discharged in between 10 and 18 s, dependent
a bellows. The computational requirements for this are
upon the flow model chosen.
extremely large.
Both reactor R3 and R4 must now be considered since R4
An extension of this work by Li et al. (to be published)
is now essentially full of vapour at a pressure of 0.43 MPa.
increased the total number of elements to nearly 3000 and
R3 now starts to discharge into R4. Finally only about
considered in detail elastic and plastic behaviour of bellows
10–16 tonnes of cyclohexane are discharged and not the
as functions of pressure as well as large-scale extension and
40–60 tonnes previously thought.
compression. Figure 9(a) illustrates the model used to
Thus far, the postulated complex behaviour of the
consider axial loading with large-scale compressive and
bellows–pipe assembly has been described, such as might
tensile loading. Axial elastic spring rates under ‘zero’
has been initiated by a fatigue-initiated tear in the B4
pressure for compression and extension are 516 and
bellows. Finite element analyses of the full-scale experi-
527 kN m1, respectively (Figure 9b); in these simulations
ments undertaken for the Court are described next and then
the axial elastic spring rate increases slightly (1%) with
the remainder of the paper examines the discharge processes
pressure increase to 1.1 MPa. Experimental values, obtained
for the case postulated by the Court and that which would
from the manufacturer, and presumably not under pressure
have resulted under the circumstances outlined above; it will
(Batstone, 1975), were between 485 and 578 kN m1. Large
thus compare the developments of the vapour cloud noted
deformation behaviour (Figure 9c) indicates that as the
by witnesses and the consequences of its ignition.
bellows are compressed the convolution crests and roots
start to plastically deform, and that at about 50 mm and
22 kN, with very small increase in load, the bellows
shorten to 110 mm where greater resistance sets in due
FINITE ELEMENT ANALYSES
to convolution compaction—with further compression, to
ANSYS 5.3–5.5 (Swanson Analysis, 1994) non-linear 160 mm, the joint is now effectively rigid and the load
elastic-plastic large deformation finite element (FE) rises to 170 kN. In extension, plastic deformation com-
models were made of the individual bellows and the mences again at about 50 mm and a load of 21 kN. The
assembly of bellows, stub pipes and dog-leg illustrated in roots and crests plastically deform as the sheet straightens
Figure 3. Additional simulations of the experiments carried out to about to 230 mm at 31 kN—further extension now
out for the Court were also conducted. The required requires greater load and the bellows extend finally to
mechanical properties of 304L and 316L SS were deter- 733 mm and start to tear at a load of 900 kN with the
mined either from test (Venart and Tan, 2000) or from the critical elements experiencing a 37% reduction in area.
report of Foley (1974a) and the literature. These results indicate that, if a pressure difference of only
The elastic lateral stiffness of a bellows decreases linearly 0.1 MPa developed between R4 and R6, the respective
with increasing pressure (EJMA, 1993; Newland, 1964; bellows sets, if axially constrained, would be compressed
Snedden, 1981, 1985) and, upon sufficient increase, the and extended 160 mm due to the difference between the
bellows can become unstable, usually resulting in rapid bellows mean diameter and the 508 mm pipe; this could
gross lateral deflection or ‘squirm’. The lateral stiffness occur if the R4 vent and the lower section of the bridging
and response of a universal expansion joint, i.e. two bellows pipe became full of two-phase fluid and ‘choked’. Under
interconnected by a straight length of pipe or ‘spool’ piece, operational conditions with little or no vertical support
has been considered by Newland (1964). The lateral stiff- or upwards restriction, incipient squirm may have been
ness for two bellows connected by an offset spool piece, possible.
such as here, was undertaken by Newland (1976); however, The ‘zero’ pressure transverse, or lateral, elastic spring
no determination appears to exist for the determination of rate of the model was 7474 kN m1 (the lateral elastic spring
natural frequency for this case. rate decreases 25% with pressure increase to 1.1 MPa).

Trans IChemE, Part B, Process Safety and Environmental Protection, 2004, 82(B2): 105–127
116 VENART

Experimental values, obtained from the manufacturer, and The weights of the heavy flanges, with its bolts, nuts and
again presumably not under pressure (Batstone, 1975), were washers, the adapters and the fluid-filled pipe were
between 7567 and 9015 kN m1. The differences in these converted into equivalent density variations of the shell
results could be due to non-isotropy due to the forming and beam elements similar to that used in the bellows
process and the choice of a uniform wall thickness in the simulation. Internal pressure and axial force were applied
model formed bellows that were thinner at their crests and to the pipe in a step-wise fashion until failure. Both room
roots. Figure 10(a) shows the deformed shape of the bellows temperature and hot evaluations were conducted. Large-
joint at an internal pressure of 0.96 MPa and a transverse scale axial loading of the structure was also carried out at
displacement of 42 mm. Figure 10(b) illustrates the trans- an internal pressure of 0.96 MPa.
verse loads required to effect the lateral displacement at The room temperature simulation failed by bucking at the
0.96 MPa as a function of extension. Four main stages can lower mitre joint at 2.16 MPa; the hot simulation failed at
be observed. The first stage is a linear elastic range; here the 1.87 MPa; Batstone (1975) recorded a similar cold failure
load–deflection curve is linear and the stress in the bellows pressure, i.e. 1.89 MPa. The large-scale deformation simula-
is below the yield strength. In the second stage primary tion at 0.96 MPa required over 800 kN to initiate failure
yielding occurs localized at the tops or bottoms of the (Figure 12b).
convolutions where stress levels are high. With increased In order to evaluate the influence of end constraint on
loading, the bellows go into a third stage where contact pipe behaviour a further FE study was conducted using this
between convolutions occurs. This stiffens the bellows in the model (Figure 13a and b). However, this employed a ‘hard’
lateral direction. The final stage is one of general plastic or fixed constraint at the B6 end that restricted rotation of
deformation where the whole bellows yields and the slope of the pipe and thus simulated the constraint of a compressed
the load–deflection curve decreases until the bellows B6 bellows. This model indicated that an internal pressure
becomes unstable and final rupture may occur if bellows of only 1.09 MPa could initiate buckling failure of the pipe
movement is not resisted. at its lower mitre bend. Further, at an internal pressure of
Snedden (1981) experimentally obtained similar load– 0.96 MPa, an axial force of only about 400 kN is required to
deflection curves up to the point of instability. He developed initiate buckling of the pipe, Figure 13(c). Relaxing the B6
simplified analyses to determine the collapse pressure and constraint would obviously increase the required pressure
evaluate the deformations observed (Snedden, 1985). He and load. However, such a result indicates that, had a
considered the lateral stiffness, once convolution contact differential pressure occurred across the two reactors, such
occurred, to be infinite and thus any constraint to be ‘rigid’ as could have happened by only one bellows suddenly
though, as can be seen from his results, this is far from the tearing and depressurizing, the subsequent repressurizing
case (Figure 7 of Snedden, 1985), and a more gradual of R4 coupled with the squirm of B4 could lead to buckling
approach to failure develops in reality and the FE model. of the pipe assembly—all now possible at near-operating
The limiting internal design pressures, based on column pressure.
instability (both ends rigidly supported) and no axial exten-
sion, were estimated by EJMA (1993) methods to be 2.1 and
The Bridging Pipe–Bellows Assembly
1.8 MPa for the cold and hot bellows, respectively.
Both static and dynamic FE analyses for an assembly
made of the dog-leg pipe, its two stub pipes and the bellows
Bridging Pipe
joined to the reactor stub pipes were made based on the
A model was constructed to simulate the experiment on previous models (Venart and Tan, 2000). The model setup,
the bridging pipe alone (Batstone, 1975) described earlier loads and weight conversions were similar to those used
(Li et al., to be published). Internal pressure in this model earlier. The main difference was that the pipe was not fully
was increased gradually and the axial loads at the pivot as filled with cyclohexane (Teng-yang et al., 2000), and that a
well as the vertical deflections computed. Two cases were scaffold system could be set to support the pipe assembly
considered; one that for a ‘new’ pipe, i.e. as constructed, the (Figures 3 and 14).
other plastically deformed to give a pre-test axial set of Four load steps were used in the FE simulation of the
19 mm. A comparison between measured and simulated complete assembly: (1) initially the by-pass pipe rested on
loads is shown in Figure 11. This indicates that failure of the the scaffolding without internal pressure; (2) the system was
pre-plastically deformed pipe occurs at a similar pressure. next pressurized; then (3) the assembly was set free due to
Although there are some differences in the results, agree- the upward thermal expansion of the reactors (6.4 mm); and
ment is reasonable, with the FE model generally more (4) finally the pipe was allowed to thermally expand axially
compliant. The final measured and simulated squirming (approximately 10 mm) along with the radial expansion of
pressures are, however, very nearly the same (1.89 MPa). each reactor and its stub-pipe (about 2.5 mm). At the lower
or R6 end contact and deformation of the scaffolding was
permitted if the downward assembly deflection exceeded
Bridging Pipe and Stub Pipes
6.4 mm.
The FE simulation of this modification of the experiment In the model it was assumed that the upper pipe was half
conducted by Batstone (1975), was simpler than that for the full and the lower pipe full of liquid cyclohexane. It was also
bellows assembly (Venart and Tan, 2000). The half pipe and assumed that the scaffolds were made from normal structural
its stub pipes were represented with over 2200 shell steel; these were simulated by beam elements with contact
elements with strengthened adapter pieces, which connected elements to prevent any loading when the pipe contact was
the blank flanges in turn connected to pin joints, as shown in lost. Elastic–plastic load–deflection relationships were used to
Figure 12(a), which additionally illustrates the deformation. simulate the pipe, the bellows and the scaffolding.

Trans IChemE, Part B, Process Safety and Environmental Protection, 2004, 82(B2): 105–127
FLIXBOROUGH 117

Figure 9. Axial load–extension of the finite element model of the Flixborough bellows; (a) the bellows model, (b) small extension–load behaviour, (c) large
extension–load behaviour (Li et al., to be published).

Trans IChemE, Part B, Process Safety and Environmental Protection, 2004, 82(B2): 105–127
118 VENART

Figure 10. Transverse load–deflection of a finite element model of the Flixborough bellows (Li et al. to be published); (a) three-dimensional FE model—
lateral loading: equivalent Von Mises strain at 0.96 MPa at 0 m axial extension. The FE results are based on surface-to-surface contact with a 0.4 friction
coefficient; the lateral deflection is 41.75 mm. (b) three-dimensional FE model—lateral loading as a function of extension at 0.96 MPa. FEM simulations
based on point-to-point contact elements.

Trans IChemE, Part B, Process Safety and Environmental Protection, 2004, 82(B2): 105–127
FLIXBOROUGH 119

(vertical) frequency (coupled with bending of the pipe),


f2 ¼ 12.35 Hz; and third natural frequency(rocking mode)
f3 ¼ 30.16 Hz. The equivalent EJMA (1993) determinations
are 3.93, 15.7, and 27.2 Hz respectively. The axial mode
agrees well but the inclusion of the offset pipe and its
bending appears to reduce the transverse and increase the
rocking modes.
Three main harmonic forces are induced with the flow
system (Teng-yang et al., 2000). One is the axial load that
results from the flow fluctuations at the diameter change in
the upstream pipe. Another is the transverse loading due to
the change in fluid mass at the lower hydraulic jump. Both
these forces are in phase and at the same frequency as the
hydraulic-head change. Owing to the hydraulic jump after
the upper mitre bend the mass in the lower half of the pipe
would have oscillated by about 60 kg (3.5% of the total
system mass) at a frequency of between 1 and 2.5 Hz. A
Figure 11. Comparison of Cremer and Warner dog-leg pipe experiments third force is the level fluctuation in the weir waterfall pools;
with the FE simulation of the dog-leg pipe (Batstone, 1975), where: (s) FE
simulation0 is based on a new pipe; (m) FE simulation was based on the pipe
levels in similar sized outfalls vary with a frequency of
with 0.75 inch (19 mm) axial plastic deformation (Li et al. to be published); about 7 Hz (Rajaratnam and Chamani, 1995). Further, the
and (----) experiment; failure at 1.89 MPa. plunge pool jet velocity, especially at the lowest flow, is
sufficient to excite axial resonance of the bellows.
The comparison between the finite element models and
the experiments undertaken above indicate that the models
The vertical deflections at the two ends of the pipe, reasonably represent the behaviour of the bellows, bellows
obtained for an internal pressure or 0.96 MPa, are listed in and stub-pipes as well as the bridging pipe.
Table 2. Compared with the experimental measurements, the
trends are similar, however, there are some differences in the
values, particularly for the upper bellows where the experi-
THE CFD ANALYSES
mental deflections exceed the FE results by some 35%.
The maximum stresses occur along the tops and bottoms A transient three dimensional CFD model was developed
of the convolutions, particularly at the second to last for a 130 (x) by 130(z) by 30 (y, elevation) m volume of the
convolutions of both ends at normal operating conditions. region around Section 25A (Venart, 1999). This area
Some parts of these regions appear to be coincident with encompassed the reactors and after-reactor vessels and
portions of the internal tear noted by the Court (Secretary of their plumbing (especially the ‘8-inch’ lines) in addition to
State for Employment, 1975; Foley, 1974a). Stress levels in Section 7 (and a portion of Section 27), the Laboratory, the
the lower bellows are similar to those in the upper bellows; Control Room, as well as the Main and Project Office
however, damping is greater due to the fluid inventory. The buildings (Figure 1). The computations were carried out
stresses in the experimental bellows at B4 would, however, using the commercial code FloSYS (Flomerics, 1994),
have exceeded these values since deflections were larger. which is a CFD solver operating in Cartesian coordinates.
At temperature and pressure, the upper (R4) end of the Solution were performed throughout the rectangular
pipe moves towards R4 by 0.67 mm; the absolute axial cuboid domain for the velocities u, v, w in the x, y, and z
displacement of the other end of the bellows is away from directions respectively, fluid static pressure, p, temperature, T
R4 by 2.89 mm so that the axial compression of the B4 in the gas and solid regions, and concentration of the secon-
bellows is 3.55 mm. At the lower (R6) end of the pipe the dary medium (cyclohexane), c. Several tests were evaluated
assembly moves away from R6 by 0.037 mm with the for solution convergence, and as a compromise between
absolute axial displacement of other end of the bellows accuracy, computational requirements, and resources, a grid
moving away from R6 by 3.08 mm; the axial compression of system of 98  41  68 nodal points in the x, y and z
B6 is thus 3.05 mm. The pipe, between bellows, shortens directions, respectively, was selected. The smallest cell size,
under these conditions by 3.51 mm compared with a mea- commensurate with the smallest scale of detail, the ‘8-inch’
sured value of between 5 and 7 mm (Games and Water- pipe, was 0.1 m in the x and z directions and 0.05 m in the y
house, 1974), Table 2. direction; the largest cell sizes were on the upper domain
A FE modal analysis of this model was also carried out in corners; these were typically 3  2.3  3.3 m in the x, y and z
order to evaluate the first three natural frequencies and directions, respectively. The grid, where required, was set
vibration modes of the cranked pipe assembly. In this automatically to reconcile with internal solid surfaces, parti-
instance the mass of fluid was converted into a density cularly in the reactor near field.
increase as a function of location. The total weight of the The equations solved formulate the principles of conser-
pipe, flanges, bolts, bellows and insulation was about 1.13 vation of mass, momentum in all directions, thermal energy
tonnes and its liquid inventory some 600 kg, of which about and mass of secondary medium (cyclohexane). Turbulence
375 kg were distributed in the lower half of the pipe under modeling is performed by using a ‘standard’ two-equation
full production conditions. The first three natural frequen- (k–e) turbulence model with near-wall grid node ‘wall
cies and vibration modes were found to be: first natural axial functions’ used to evaluate surface friction and surface
frequency, f1 ¼ 3.98 Hz; second natural, and transverse heat transfer. The effects of turbulence are represented via

Trans IChemE, Part B, Process Safety and Environmental Protection, 2004, 82(B2): 105–127
120 VENART

Figure 12. (a) Flixborough dog-leg pipe FE model, B6 ‘pin–pin’ constraint model, equivalent Von Mises stress contours for the pipe when Ux ¼ 0.365 m and
Uy ¼ 1.0675 m at the left pin as predicted by the FE model. (b) Nodal force load Fx (kN) vs deflection, Ux (axial) at the left pin predicted by FE simulation,
pin-pin model.

a turbulent viscosity and thermal diffusivity where these Plant equipment, pipe racks and supporting structures,
quantities are linked by the turbulent Prandtl number, which other than the five reactors and the associated after vessels
takes a constant value of 0.9. and plumbing, were treated as flow obstacles with a uniform
Buoyancy effects due to thermal expansion and the heavy resistance and porosity of 0.5. Buildings and other large
vapour dispersion of the evaporated cyclohexane are structures (the Main Office, the Project Office, the Labora-
included in the y direction as a gravitational source term. tory and the Control Room) were assumed to be impervious
The variation of properties, in this particular case, density, is to the flow and adiabatic. The prevailing wind was assigned
assumed to be governed by the ideal gas laws. The mole- by steady vector components as boundary conditions on the
cular viscosity, thermal conductivity and diffusivity were free boundaries of the domain. The surface of the ground
taken to be those for air and constant. was set to a uniform roughness of 0.01 m.

Trans IChemE, Part B, Process Safety and Environmental Protection, 2004, 82(B2): 105–127
FLIXBOROUGH 121

Figure 13. (a) Flixborough dog-leg pipe FE model, B6 ‘hard’ constraint, Fx ¼ pA, failure initiated at 1.08 MPa. (b) Flixborough dog-leg pipe FE model, B6
‘hard’ constraint, Fx ¼ pA, failure at 1.08 MPa, axial (x) and vertical (y) deflections as a function of ram load, Fx. (c) Equivalent Von Mises strain contours for
the pipe when Ux ¼ 0.365 m and Uy ¼ 1.0675 m at the left pin as predicted by the FE model. (d) Nodal force load Fx (kN) vs deflection, Ux (axial), Uy
(vertical) at the left pin predicted by FE simulation, pin–fixed model.

The mass source terms, representing the flashing two- cyclohexane and its dissolved nitrogen were obtained from
phase discharges from the reactors, were evaluated from the NIST (1999) mixture property program, STRAPP.
prior choked flow determinations and the assumption of A near-field isometric view of the reactor train as may
sonic, vapour only, flow at the reactor, R4 and R6, outlet have been seen from the Main Office is shown in Figure 15
nozzles (Leclude and Venart, 1997). The properties of as represented in the Flomerics code. In the figure, the

Trans IChemE, Part B, Process Safety and Environmental Protection, 2004, 82(B2): 105–127
122 VENART

Figure 13. Continued.

walkways along the reactor train are represented by porous (UFL) flammable limit (0.037 and 0.198 wt.%, respectively)
resistance areas, and the ‘8-inch’ pipes connecting the two and provide interactive visualization through time-
after vessels together are indicated. The cuboid representa- sequenced plots of the iso-surfaces.
tions of the vessels are also shown. Simulations were preformed for two cases: (i) the simul-
The FloSYS ASCI output files were used as input files to taneous discharge from both R4 and R6, as the base case
be processed by Tecplot (Amtec Engineering Inc., 1996) to representing that process accepted by the Court, and (ii) a
extract the iso-contours for the lower (LFL) and upper discharge from only R4 prior to the explosion. In both

Trans IChemE, Part B, Process Safety and Environmental Protection, 2004, 82(B2): 105–127
FLIXBOROUGH 123

Figure 14. FE model of the Flixborough by-pass assembly and its supports (reproduced from Venart and Tan, 2000, with permission from ICPVT).

Table 2. FE analysis of the assembly and comparison with test data (Games and Waterhouse, 1974), vertical deflections (Venart and Tan, 2000).

Deflection at upper, B4, Deflection at lower, B6,


Case Condition end of pipe, mm end of pipe, mm
FE Initial (a) Full scaffold support no internal pressure 0.72a 0.77
FE @ 20 C (b) Partial scaffold support, 0.964 MPa 3.41 3.77
FE @ 150 C (c) Partial scaffold support, 0.964 MPa 6.93 4.49
(a)–(b) FE cold Scaffold support, 0.964 MPa, cold 4.13 [10.66]b 3.00 [3.26]
(a)–(c) FE hot Partial scaffold support, 0.964 MPa, hot 7.65 [10.27] 3.72 [3.26]
a
(þ ) Upwards, () downwards displacement. bAverage experimental values.

instances, the discharges were taken as choked sonic cyclo- cloud distribution at 12 s as it would have been seen from
hexane vapour at 370 kg s1 and 150 C. The results are near the top of the Hydrogen Plant.
available in the form of ‘movies’ or animations both for the
‘far field’ and ‘close in’ regions of the computational
domain. Simultaneous Discharge from both R4 and
In the figures discussed here the view is as from near the R6 (Figure 16, ‘Movie’ 1)
top of the Hydrogen Plant looking towards the Main Office
building (Figure 1) at about 30 s into the discharge process. Even at 1 s into the event the simultaneous discharge
The UFL is represented as the panelled interior, and the process accepted by the Court results in an aerial cloud from
LFL, the wire-frame exterior, surfaces. the discharge of R4 riding up and over both the jet discharge
The transient development of the cyclohexane vapour from R6 and the top of this vessel and reaching a height of
cloud at its LFL and UFL over a period of 30 s is now
briefly described. Figures 16 and 17 illustrate the LFL=UFL

Figure 15. A near-field view from southeast of the reactor train and the Figure 16. Southeast view from the top of the Hydrogen Plant looking
after-reactors as might have been seen from the roof of the Main Office towards the Main Office Building: simultaneous discharge of R6 and R4 at
building (reproduced from Venart, 1999, with permission from INTER- 12 s, LFL and UFL envelopes (reproduced from Venart, 1999, with
FLAM, www.intercomm.dial.pipex.com). permission from INTERFLAM, www.intercomm.dial.pipex.com).

Trans IChemE, Part B, Process Safety and Environmental Protection, 2004, 82(B2): 105–127
124 VENART

After 18 s, the R6 UFL envelope has reached the Control


Room and has topped the two-storey Laboratory building.
Both the LFL and UFL envelopes have exited from the
western boundary of the domain towards the hydrogen plant.
The R4 discharge LFL cloud continues to exit between the
Main Office block and the southerly ends of sections 25 and
7 as well as southerly between the space with the Project
Office; the UFL of this envelope has now mounted the
northwest corner of the office block.
By 22 s, the R6 LFL and UFL envelopes have both
surmounted the Laboratory and the Control Room and are
proceeding across the western domain boundary towards the
hydrogen plant. The centre of gravity of the main body of
this cloud is situated just north of R1. Both the LFL and
UFL R4 envelopes are now exiting from the southern
domain boundary between the two offices and into the car
park; the eastward LFL cloud still exits from the eastern
boundary in the space between the Main Office and the
southern end of section 7.
At 30 s, the R6 discharge clouds have proceeded northerly
Figure 17. South-east view from the top of the Hydrogen Plant looking past the Control Room and Laboratory. The R4 discharge
towards the Main Office building: R4 discharge only at 12 s, LFL and UFL cloud is still split by the Main Office block into two sections;
envelopes (reproduced from Venart, 1999, with permission from INTER- one exiting into the car park, the other to the east between
FLAM, www.intercomm.dial.pipex.com).
the office and the southern ends of sections 25A and 7.

Single Discharge from R4 (Figure 17, ‘Movie’ 2)


about 20 m. This cloud proceeds southerly into the prevail-
ing wind and towards the opening between the two office The transient development of this vapour cloud differs
blocks. At the same time, the R6 discharge is split by R4 significantly from that above. At the commencement of the
into two jets and channeled, by the R4 jet above, the reactor event, a series of choked vapour discharges as from a slit, set
train walkways and the after-reactor and reactor vessels to to be approximately similar in area to that noted in the piece
form a dense gas cloud moving predominately at ground of the B4 bellows by Foley (1974a), is portrayed for about
level along the reactor train in a NNW direction. After 2 s, 4 s. This set appears as a vertical jet that increases and then
the LFL of this cloud has reached the northern end of the diminishes in flowrate.
reactor train, i.e. R1; there is, however, relatively little The first portion the discharge from the R4 is a westward
westward development of this cloud due to the intense proceeding jet developing over a time span of 1 s. The next
momentum of the R6 discharge split by the R4 reactor. sequences show the interaction of the jet impact from R4 as
At 8 s, the R4 cloud is still airborne (24 m elevation at it hits R6 when the B4 bellows is blown off and the jet
the LFL) and much larger and starts to slump towards the formed is deflected upwards. By a further 4 s, the shape of
ground in a southerly direction. The LFL makes a footprint both the LFL and UFL envelopes are roughly cylindrical;
around the northwest corner of the Main Office building and the height of the LFL cloud is about 25 m high with a
commences exiting from the domain in a southerly direction cylindrical ground footprint of some 30 m diameter for the
between the two buildings (i.e. into the car park); the cloud LFL and 15 m for the UFL.
does not, however, contact the Project Office. The R6 cloud, At 10 s, the prevailing wind is distorting the LFL envel-
though, now has developed its LFL envelope up to 16 m ope; both the UFL and LFL footprints commence a west-
elevation, and is, at its north-northwest ground boundary, ward progression across the open space in front of the
approaching the Laboratory with little westerly develop- Project Office and northward to the base of the R2 reactor
ment. The height of this cloud would no doubt have been (LFL). The LFL southern envelope approaches the north-
restricted by the floors in the rest of the open plant structure west corner of the Main Office building.
of section 25A and so the 16 m vertical extent of the LFL is In 12 s (Figure 17), the LFL envelope’s southeast extre-
perhaps an artefact induced by the use of uniform porosity mity has impacted the northwest corner of the Main Office
and resistance. building and has commenced exiting from the eastern
By 12 s (Figure 16), part of the R4 UFL envelope has domain boundary between the southern ends of section
touched down between the office buildings and the LFL cloud 25A and 7 and the northern wall of the office building.
has proceeded out into the car park at a mean velocity of some The base of the LFL footprint has progressed northward to
4 m s1. The other portion of the R4 LFL cloud has exited the base of R1 with the northern boundary of the UFL just
to the east from the space between the north face of the past the base of R4.
three-storey Main Office building and the southern end of At 16 s, the momentum of the jet has pushed the UFL
sections 25 and 7. The R6 LFL envelope by this time has envelope to the northwest corner of the Office building. The
started to surmount the two-storey Laboratory building and is LFL envelope in its eastern branch is now greater in
commencing contact with the Control Room; the westerly elevation than the office building with a southern branch
spread of the LFL has reached the westernmost end of the pushing past the west wall of the Office building and
Laboratory. commencing to exit from the southern domain boundary

Trans IChemE, Part B, Process Safety and Environmental Protection, 2004, 82(B2): 105–127
FLIXBOROUGH 125

into the parking lot. The northern extent of the LFL compared with the results of the CFD simulations of events
footprint has developed just midway of the last after-reactor. show remarkable agreement with the cloud development
Westward development of the cloud has just reached the portrayed in the two-stage event.
northeast corner of the Project Building with the edges of The two CFD simulations of the possible accidental
both the LFL and UFL in line with the east–west axis of R6 cyclohexane releases in the Flixborough disaster permit
pushing some 20 m past R6 at somewhat less than 1 m s1. the following conclusions.
Within 20 s, due to the continuing momentum of the R4
 In both cases, the R4 discharge results in ground level
jet, the UFL envelope detaches from the eastern wall of the
vapour clouds that exit to the east, from around the
office block to also progress in the direction of the parking
southern end of sections 25A and 7, and to the south as
lot. The LFL southern branch fills the space between the two
a jet channelled between the works and Main Office
offices and further pushes out into the parking lot at over
buildings out into the parking lot.
8 m s1; the eastern LFL development has topped the Main
 As well, both instances exhibit conspicuous vertical
Office block and is exiting eastward at some 4–5 m s1.
cloud-like accumulations near the southern ends of
Westward development of both envelopes has now hit the
Sections 25A, 7 and 27 and located on the determined
northeast corner of the Project Office and progressed
focus of the blast.
westward some 8 m along its northern wall in the case of
 Only in the case of the single discharge from R4 is there
the LFL.
the significant westward development of a ground-level
By 21 s, the LFL envelope at ground level has progressed
cloud that corresponds directly to witness recollections.
westward some 20 m along the Project Office northern wall
 In the situation with the two simultaneous discharges, a
with the UFL cloud only 8 m behind. The northern devel-
strong split jet (from R6) is formed that develops into a
opment of the LFL envelope has only just reached within
rapidly northward moving ground-level cloud, with little
22 m of the Laboratory as a rather flattened pancake-shaped
westward progression. This cloud reaches the Laboratory
cloud. Both the LFL and UFL envelopes have pushed
and Control Room areas in less than 12 s.
southward out into the parking lot; the UFL cloud has
 In the case of the R6 discharge the LFL=UFL distribution
become completely detached from the Main Office block
around the ‘8-inch’ pipes, if ignited as a jet fire, can be
and slides along the eastern wall of the Project Office. The
used to explain the inferred temperature distribution to
LFL envelope continues its eastern progression over the top
these pipes.
of the Main Office block and around behind sections 25A
and 7, exiting eastward at some 4–6 m s1.
In the sequence of frames following 21 s, a pseudo-steady
state has developed for the southern and easternmost exiting
domain discharges; there is a strong UFL and LFL ground BLAST MEASUREMENTS
jet into the parking lot along with a less strong, but Grover (1974) made seismic recordings of the Flixbor-
volumetrically greater, one at the LFL to the east channelled ough explosion and determined that the time of the explo-
by the north wall of the Main Office building. Aside from sion was 15:52:15.5  2.1 UT. Analyses of infrasound
these two discharges to the west, both the LFL and UFL measurements were also made. Both were compared with
continue to enlarge with little northern development. The a large blast at sea recorded by the same set of instruments;
western ground cloud has progressed towards the eastern this suggested that the bast was equivalent to between 6
edge of R5. and 16 tons of nitroglycerine, or 8.6–23 tonnes of TNT
(Meyer, 1987).
Jones and Spracklen (1974) made six Doppler ionosphere
Summary of the Results of the CFD Simulations
records of the Flixborough explosion using two transmitters.
There were 28 fatalities in the explosion; of these 18 No estimate of blast was given but its occurrence was
individuals were in the Control Room area as well as three estimated to be at about 15:50:35 UT.
each in the Gate House and Warehouse=Flaking Plant In a reanalysis of the ionospheric records, Table 3,
(Humberside Police, 1974). In the Laboratory (separated Krasnov et al. (2003), determined that the explosive yield
by less than 12 m from the Control Room, Figure 1) the was equivalent to 283  38 tonnes of TNT and that the blast
eight survivors were able to observe the release over a period took place at 15:52:08  6 UT. A comparison of this yield
estimated to be 8–12 s. They then appreciated the threat with that resulting from the detonation of fuel-drop–air
and ran from the building. Other witnesses, further away, clouds (Fishburn et al., 1981) suggests that the Flixborough
likewise directly observed the developing vapour cloud, the explosion was the result of the detonation of only 14  2
resultant fires and the explosion. These observations, when tonnes of cyclohexane.

Table 3. Analysis of the Flixborough ionospheric records of Jones and Spracklen (1974) and Krasnov et al. (2003).

Radio trace Y (degree) j (degree) D (km) hr (km) te (UT) Q (tonne TNT)


T1 7 R1 10.0 206 65.8 228 15:52:16 210  35
T2 7 R1 15.8 176 101.2 228 15:52:27 290  35
T3 7 R1 15.2 214 104.8 228 15:52:18 390  55
T1 7 R2 18.2 205 118.5 218 15:52:06 405  50
T2 7 R2 22.7 192 167.7 222 15:51:54 230  40
T3 7 R2 22.6 212.3 173.7 224 15:51:47 175  40
Mean — — — — 15:52:08  6 283  39

Trans IChemE, Part B, Process Safety and Environmental Protection, 2004, 82(B2): 105–127
126 VENART

DISCUSSION AND CONCLUSION Center for Chemical Process Safety (CPPS), 1994a, Guidelines for evaluat-
ing the characteristics of vapor-cloud explosions, flash fires, and BLEVEs
The evidence and studies outlined above support the case (American Institute of Chemical Engineers, New York, USA), Section
that the Flixborough explosion was caused by a two-stage 2.4, Fig. 2.4, p 12.
Center for Chemical Process Safety (CPPS), 1994b, Guidelines for evaluat-
event that resulted in a release from only one reactor, R4, ing the characteristics of vapor-cloud explosions, flash fires, and BLEVEs
that was limited to about 10–15 tonnes of cyclohexane. The (American Institute of Chemical Engineers, New York), Appendix F,
initiation of this failure may have been fatigue of the B4 pp 363–382.
bellows. A subsequent release from R6 was responsible for Colquhoun, D.C., 1974, Minutes of Proceedings at the Court of Inquiry; into
the exposure to the ‘8-inch pipes’ and the carbide formation the disaster which occurred at Nypro (UK) Ltd, Flixborough, Third Day,
September 11.
on the R4 stub pipe and its bellows remnants. A blast in the Cottrell, A.H. and Swan, P.R., 1976, A metallurgical examination of the
Main Office building, the Project Office building, or both eight-inch line, Chem Eng, April: 266–274.
together, and=or the R4 jet-fire may have ‘triggered’ the Cox, J.I., 1976, Flixborough—some additional lessons, Chem Eng,
detonation of the cloud formed; if true, this is one of a very May: 353–358, 387.
Dickinson, J., 1974, Minutes of Proceedings at the Court of Inquiry; into the
few genuine vapour cloud detonations. disaster which occurred at Nypro (UK) Ltd, Flixborough, Second Day,
The consequences of these results should: September 10.
EJMA, 1993, Standards for the Expansion Joint Manufacturers Association,
 prompt industry, insurers, and regulators to initiate Inc., 6th edition (Tarrytown, NY, USA).
reviews of ‘reportable’ inventories in chemical plant and Fishburn, B., Slagg, N. and Lu, P., 1981, Blast effect from a pancake shaped
in transportation, fuel-drop–air cloud detonation (theory and experiment), J Hazard Mater,
 initiate further, more detailed, studies of chemical plant 5: 65–75.
safety, security and placement by industry, government Flomerics, 1994, FloVent Reference Manual, Document no.
FloVent=RM=0994=1=0 (Flomerics Ltd, Surrey).
and universities; and Foley, J.H., 1974a, Metallurgical examination of the damaged pipes from
 revise the accepted cause and consequences of the Flix- section 25A, Report no. 1, Part I, Safety in Mines Research Establishment
borough explosion. (SMRE), September 10.
Foley, J.H., 1974b, Minutes of Proceedings at the Court of Inquiry; into the
In addition finite element and computational fluid dyna- disaster which occurred at Nypro (UK) Ltd, Flixborough, Thirty-third
mics analyses of accidents, such as used in this study, can be Day, November 14, pp 34–35.
useful tools in incident investigations. Though these tools Foley, J.H., 1974c, Minutes of Proceedings at the Court of Inquiry; into the
disaster which occurred at Nypro (UK) Ltd, Flixborough, Thirty-fourth
were not widely available at the time of the incident their use Day, November 15.
today should be mandatory. Foley, J.H., 1974d, Minutes of Proceedings at the Court of Inquiry; into the
As a further point of concern in these times of heightened disaster which occurred at Nypro (UK) Ltd, Flixborough, Thirty-seventh
security it should be noted that many local delivery services Day, p 26–27.
Foley, J.H., 1974e, Minutes of Proceedings at the Court of Inquiry; into the
routinely transport 10–15 tonnes of product, e.g. LPG, disaster which occurred at Nypro (UK) Ltd, Flixborough, Thirty-seventh
which if released to form a vapour cloud and then deliber- Day, p 21, para 5.
ately detonated could cause similar blast damage and even Foley, J.H. and Nicholson, C.E., 1974, Metallurgical examination of the
greater loss of life than in this case; a possibility that should damaged pipes from Section 25A, Report no. 1, Part III, Safety in Mines
be of special concern to security services. Research Establishment (SMRE), November 8.
Fu, W.B. and Eyre, J.A., 1974, Unconfined vapour cloud explosions, Letter,
Chem Eng, 359=360: 368.
Games, G.A.C. and Waterhouse, D., 1974, Construction of and tests on a
reconstructed bridging pipe assembly, Report no. 2, Part II, Safety in
REFERENCES Mines Research Establishment (SMRE), November 10.
Gill, S.S., 1974, Minutes of Proceedings at the Court of Inquiry; into
Ale, B.J.M. and Bruning, F., 1980a, Unconfined vapour cloud explosions, the disaster which occurred at Nypro (UK) Ltd, Thirty seventh Day,
Letter, Chem Eng, 352: 47–49. pp 51–52.
Ale, B.J.M. and Bruning, F., 1980b, Unconfined vapour cloud explosions, Goodchild, M.B., 1975, Minutes of Proceedings at the Court of Inquiry; into
Letter of reply, Chem Eng, 358: 494. the disaster which occurred at Nypro (UK) Ltd, Flixborough, Fifty-fourth
Amtec Engineering Inc., 1996, Tecplot User’s Manual, version 7 Day, January 24, pp 24–26.
(Bellevue, WA). Gromles, M.A., 1984, A simple approach to transient two-phase level swell,
Artingstall, G., 1974, Appraisal of the damage in the reactor vessels in Multi-phase Flow and Heat Transfer III, Vol 1 (Miami Beach, FL, USA),
Section 25A, Report no. 4, Part I, Safety in Mines Research Establishment pp 527–538.
(SMRE), September 11. Grover, F.H., 1974, Infrasonic and seismic wave records from the Flix-
Au-Yang, M.K., 1999, Common mistakes and misconceptions in flow- borough and St Bridget explosions, AWRE Report no 046=74, p. 27.
induced vibration and coupled fluid-structural dynamics analysis, ASME Gugan, K., 1974, Minutes of Proceedings at the Court of Inquiry; into the
PVPD, 29: 6.1–6.17. disaster which occurred at Nypro (UK) Ltd, Flixborough, Thirty-ninth
Ayre, E., 1974, Minutes of Proceedings at the Court of Inquiry; into the Day, p. 17, November 22.
disaster which occurred at Nypro (UK) Ltd, Flixborough, Thirty-fourth Gugan, K., 1976, Flixborough—A combustion specialists view, Chem Eng,
Day, November 15. 341–352, 387.
Ball, J.G., 1975, After the Flixborough Report: do we know the real truth?, Gugan, K., 1979, Unconfined Vapour Cloud Explosions (IChemE, Rugby,
Proc Eng, 56(12): 39–46. UK).
Ball, J.G., 1976, Was this what caused the Flixborough explosion?, Proc Gugan, K., 1980a, Unconfined vapour cloud explosions, Letter of reply,
Eng, 57(1): 53–60. 0
Chem Eng, 358: 491–493.
Batstone, R.J., 1975, Description and results of bellows test program and 20 Gugan, K., 1980b, Unconfined vapour cloud explosions, Letter of reply,
dog leg pipe tests, Cremer and Warner Report no. 7, January 7. Chem Eng, 359=360: 567.
Bjerketvedt, D., Bakke, J.R. and van Wingerden, K., 1997, Gas explosion Gugan, K., 2000, Flixborough kicking, Letter, Chem Eng, 25: 30.
handbook, J Hazard Mater, 52: 1–150. Harris, R.J., 1983, The Investigation and Control of Gas Explosions in
Butler, P., 1975, The lessons to be learned from the Flixborough inquiry, Buildings and Heating Plant (E&FN Spon, London, in association with
Engineer (GB), 241(6247): 20–24. British Gas, UK).
Carter, B., 1974, Minutes of Proceedings at the Court of Inquiry; into the Harris, R.J. and Wickens, M.J., 1989, Understanding vapour cloud
disaster which occurred at Nypro (UK) Ltd, Flixborough, Fourth Day, explosions—an experimental study, 55th Autumn Meeting of the Institute
September 12. of Gas Engineers, Kensington, London, UK.

Trans IChemE, Part B, Process Safety and Environmental Protection, 2004, 82(B2): 105–127
FLIXBOROUGH 127

Harry, L., 1974, Minutes of Proceedings at the Court of Inquiry; into the Secretary of State for Employment, 1975, The Flixborough Disaster
disaster which occurred at Nypro (UK) Ltd, Flixborough, Third Day, (HMSO, London).
September 11. Snedden, N.W., 1981, The strength and stability of corrugated bellows
Høiset, S., Hjertager, B.H., Solberg, T. and Malo, K.A., 2000, Flixborough expansion joints, PhD Thesis, Churchill College, Cambridge, UK.
revisited—an explosion simulation approach, J Hazard Mater, Snedden, N.W., 1985, Analysis and design guidance for the lateral stiffness
77(1–3): 1–9. of bellows expansion joints, Thin-Walled Structures, 3: 145–162.
Humberside Police, 1974, Major Incident files, Explosion, Nypro (UK) Ltd, Snee, T., 2004, Flixborough: water hypothesis laid to rest?, TCE, February,
June 1, 1974. Books 1–4 plus photograph albums 1–6. pp 28–29.
Jakubauskas, V.F. and Weaver, D.S., 1998a, Transverse vibrations of bellows Swan, R., 2000, This is beginning to look like a cover-up, Editorial, Chem
expansion joints. Part I: fluid added mass, J Fluids Struct, 12: Eng, April 6: 2.
445–456. Teng-yang, R., Sollows, K.F. and Venart, J.E.S., 2000, Froude modeling of
Jakubauskas, V.F. and Weaver, D.S., 1998b, Transverse vibrations of bellows the Flixborough ‘By-pass’ pipe, Hazards XV, IChemE Symp Ser, 147:
expansion joints. Part II: beam model development and experimental 139–154.
verification, J Fluids Struct, 12: 457–473. Usher, A., 1979, The Flixborough disaster, Med Leg J, 43(3): 84–102.
Jones, T.B. and Spracklen, C.T., 1974, Ionospheric effects of the Flix- Venart, J.E.S., 1999, Flixborough; a final resolution?, INTERFLAM’99, Vol
borough explosion, Nature, 250: 719–721. 1, Grayson, S. (ed.), pp 257–272.
Kataoka, I. and Ishii, M., 1987, Drift flux model for large diameter pipe and Venart, J.E.S. and Tan, D.M., 2000, Flixborough; twenty-five years after, the
new correlations for pool void fraction, Int J Heat Mass Transfer, 30(9): final resolution?, Proceedings of ICPVT-9, Sydney, April 9–14, Vol 2, pp
1927–1939. 525–539.
King, E., 1974, Minutes of Proceedings at the Court of Inquiry; into the Warner, F., 1975, The Flixborough, Chem Eng Prog, 71(9): 77–84.
disaster which occurred at Nypro (UK) Ltd, Flixborough, Second Day, Warner, F. and Newland, D.E., 1975, Flixborough Explosion—Mechanical
September 10. engineering provides the key, Chart. Mech. Eng. (GB), June: 76–81.
King, R., 1975, Flixborough—role of water re-examined, Proc Eng, Weaver, D.S. and Ainsworth, P., 1989, Flow induced vibration in bellows,
September, 69–72. ASME J Press Vessel Technol, 111: 402–406.
King, R., 1977, Latent superheat—a hazard of two-phase liquid systems, Wehmeier, G., Westphal, F. and Friedel, L., 1994, Pressure relief system
Chem Proc Haz IChemE Symp Ser, 49: 139–145. design for vapour or two-phase flow?, Trans IChemE, Part B, Proc Safe
King, R., 1999, Flixborough, 25 years on, Process Eng, June: 27–28. Env Prot, 72: 142–148.
King, R., 2000, Flixborough: re-open public inquiry, Letter, Chem Eng, Westgate, K., 1976, Flixborough—the human response, University of
May 25: 30. Bradford, Disaster Research Unit, Occasional Paper no. 7, January 1975
Kitching, R., 1974, Minutes of Proceedings at the Court of Inquiry; into the (reprinted September 1976).
disaster which occurred at Nypro (UK) Ltd, Flixborough, Thirty seventh
Day, 51–52.
Kletz, T., 2000, Flixborough, no whitewash, Letter, Chem Eng, April 20: 18.
Krasnov, V.M., Drobzheva, Ya.V., Venart, J.E.S. and Lastovicka, J., 2003, A
re-analysis of the atmospheric and ionospheric effects of the Flixborough
explosion, J Atmos Solar-Terrest Phys, 65: 1205–1212. ACKNOWLEDGEMENTS
Leclude, J. and Venart, J.E.S., 1996, Single and two-phase discharge from a
pressurized vessel, Rev Gen Therm, 35: 503–516. Many individuals have contributed to this work. Specifically, the staff at
Leclude, J. and Venart, J.E.S., 1997, Determination of the amounts the Health and Safety Laboratory Library in Sheffield, and in particular
discharged in the Flixborough disaster, unpublished work, University of Linda Heritage, are thanked for their help in making the Minutes of
New Brunswick, Canada. Proceedings of the Court of Inquiry and many other documents and reports
Marshall, H., 1974, Official Statement to Humberside Police, H Div., dealing with the disaster available over an extended period of time; C.E.
Scunthorpe, June 9, 1974, Humberside Police Book 1, pp 167–169. Nicholson gave permission to reference many of the SMRE and other
Meyer, R., 1987, Explosives, 3rd edition (revised) (VCH, New York, USA) reports available. The Scunthorpe Evening Telegraph, and in particular Ms
pp 239 and 367. Jackie Cole, provided access to many photographs and material from their
Miller, K.J., 1974, Minutes of Proceedings at the Court of Inquiry; into the archives dealing with their staff’s coverage of the accident. Professors
disaster which occurred at Nypro (UK) Ltd, Flixborough, Fifty-first Day T.B. Jones and Terry Robinson of the University of Leicester gave freely of
and Fifty-second Day, pp 16 and 27. their time to explain and elaborate on the ionospheric effects of the
Newland, D.E., 1964, Buckling of double bellows expansion joints under Flixborough explosion; V. Krasnov and Ya Drobzheva of the Institute of
internal pressure, J Mech Eng Sci, 6: 270–277. Ionosphere, Ministry of Science and Education, Kazakhastan helped
Newland, D.E., 1976, Buckling and rupture of the double bellows analyse these records. Dr John I. Cox provided details of his precis on
expansion joint assembly at Flixborough, Proc R Soc Lond, A351: the statements and re-enactments of eyewitness made for the Inquiry and
525–549. other material. Ralph King and his colleague, Ronald Hirst, provided details
NIST, 1999, Standard Reference Database 4; Thermophysical Properties of regarding what influence water in the reactors may have had on the accident.
Hydrocarbon Mixtures, Supertrapp, Version 3.00 (National Institute The personnel at the BBC Film Archive Unit in London assisted in the
Standards and Technology, Gaithersburg, MD, USA). review of the background video and cine film records for the event. BBC
Phillips, H., 1981, Unconfined vapour cloud explosions: a new look at North, and especially Christine Hamill and Close-up North series producer
Gugan’s book, Chem Eng, 369: 286–287. Ian Cundall made arrangements for an interview with one of the Laboratory
Rajaratnam, N. and Chamani, M.R., 1995, Energy loss at drops, J Hydraul eyewitnesses, Brian Pettitt, and prepared a programme historically reviewing
Res, 33: 373–384. the event and its consequences. The northeast Lincolnshire Archivists,
Ramier, S. and Venart, J.E.S., 2000, Boiling liquid expanding vapour J. Wilson and J. Veltham, allowed access to their comprehensive files on the
explosions: dynamic re-pressurization and two-phase discharge, Hazards incident at the as well as details of the coroner’s report. My colleagues at the
XV, IChemE Symp Ser 147: 527–537. University of New Brunswick and many graduate students have all
Roberts, A.F. and Pritchard, D K., 1982, Blast effect from unconfined vapour substantially contributed through discussion, critiques, and other studies.
cloud explosions, J. Occup Accidents, 3: 231–247. Drs D.M. Tan and G. Li conducted the ANSYS finite element (FEM)
Ryder, D.A., 1974, Minutes of Proceedings at the Court of Inquiry; into the analyses and assisted in the preparation of the Tecplot ‘movies’ of the
disaster which occurred at Nypro (UK) Ltd., Flixborough, Thirty seventh Flomerics CFD and the FEM results. Any errors and omissions are the
Day, pp 57–58. author’s alone.
Sadee, C., Samuels, D.E. and O’Brien, T.P., 1976=1977, The characteristics
of the explosion at the Nypro (UK) Flixborough Plant on 1st June 1974, The manuscript was received 14 July 2003 and accepted for publication
J Occup Accidents, 1: 203–235. 7 January 2004.

Trans IChemE, Part B, Process Safety and Environmental Protection, 2004, 82(B2): 105–127

You might also like