Professional Documents
Culture Documents
Method Statement Stone Column
Method Statement Stone Column
Page
SRGeo/ICT/MST/01 1 of
10
METHOD STATEMENT Rev. No R0
Name of Work : Carrying out Ground Improvement Works Using Stone Columns For
Reinforced Soil Wall foundation for MNB at chainage 126+134
Kumbakonam, Tamilnadu
METHOD STATEMENT
FOR
ISSUE
CONTENTS
1 Preface 5
2 Purpose 5
3 Scope 5
5 Materials 6
6 Method of Work 7
7 Records 9
1.0 Preface
The construction of vibro stone columns involves partial replacement of weak soil with the
stones (aggregates). The installation of stone column creates a composite material of overall
lower compressibility and higher shear strength than the virgin weak soil
A layer of drainage material is provided on the top of stone columns to allow the drain water
to come out. The typical section of the soil treated with the stone columns is shown below.
The Improved capacity of the soil can be verified by conducting the load test as per IS 15284
Depth
As per Your Design, These columns will be made up of stone aggregate. The depth of the
stone column in this region is between 6.0 to 7.0 m below EGL
2.0 Purpose
The purpose of this document is to define the method to be followed for the Soil
Improvement Using Top wet feed and Bottom Feed Vibro Stone Columns
3.1 Scope
The work consists of ground improvement using stone columns by bottom feed vibro-
displacement method up to design depths. The Scope of work is broadly divided in following
activities –
1. Filling of the soil for the working platform by client
2. Installation of Stone Columns
3. Quality Control
Prepared By:- Reviewed By:-
Free hanging Vibrofloat with feeder hopper for aggregate and Tremie Pipe accessories
Crawler mounted Crane of Minimum 40 T capacity 1 N0s
Power pack and Vibrofloat of Penning Make 1 Nos
Loader / JCB / Excavator for Loading the Aggregate in 1 Nos
5.0 Material
Stones / Aggregates
The backfill stones should be clean, durable, angular, hard and resistant to breakage.
Stones used in the work shall be quarry crushed.
For Wet top Feed/ Bottom Feed: It shall be well graded stone of 40 mm down to 10 mm
size.
6.1.4 Compaction
The aggregates shall then be transported from the stock pile to the installation point by
loader and bucket of the aggregates shall be introduced into the Hopper. The vibrations
shall be applied to the Vibroflot to drive the stones laterally to form the column of the
required diameter. The Vibroflot shall be slightly lifted and lowered until the stone
charge is completely compacted at the tip of Vibroflot. The compaction of the stones
will be indicated by the increase in rig pressure by 10 to 20 bar (In idle condition the
pressure is about 130 bar. The process shall be repeated in lifts of 1.0 m to 1.50 m till
the stone column is formed to the ground level.
After completion of the process the compact stone columns will be constructed to
effect the stabilization of the treated ground.
7.0 Records
The Following records shall be registered for each stone column –
1. Identification number of column; Date and time of start of Installation
2. Time required for completion of column
3. Depth of the column
4. Pressure during Installation
Ensure that after the stones are dumped down the hole the Vibroflot is lifted and dropped a
short distance (1-2 m) several times to insure the stones reach the bottom and does not arch
across the hole. The Vibroflot should not be completely removed from the hole during
stroking.