FLARE TOWER COLUMN STATUS

DESCRIPTION WPS NO OF JOINTS


FIT-UP WELDING VISUAL NDT PWHT NDT REMARKS

630SR (GTAW + 1 joint repair at two location 1. D26-36


DIA 914 X 63.5
SAW)
3 3 3 3 3 2 L37mm 2. d 39-48mm L27mm

DIA 914 X 63.5 with 1049 PWHT


50mm plate
50 -----
(SMAW)
3 3 3 3 1
DIA 914 X 44.45 with
0 ------ 3
50mm plate
12000+3027+7306+
DIA 914 X 44.45 25333
3000
9 7 7 7 6 NA

DIA 914 X 28.58 15211 3 3 3 3 3 NA 1 joint repair

DIA 914 X 28.58 WITH


1000 3
CONE
Cone 914x 711 with
0 3
pipe

DIA 711 X 28.6 5105

DIA 711 X 19.05 12410

Pipe with Cone 711x


1000 3
508x 19.1
Cone 711x 508x 19.1
0 3
with pipe 508
DIA 508 X 19.05 with 484
DIA 508 X 15.88
10212 4104 + 10108
(GTAW+SMAW)
3 3 3
Pipe with Cone 508x 484
356x 15.9
750 750
(GTAW+SMAW)
3 3 3
Cone 508x 356x 15.9
0 3
with pipe 355.6

DIA 355.6 X 15.88 8757

DIA 355.6 X 9.53 3703


DIA 355.6 X 7.14 with 484
3703 2503+1200 3
DIA 355.6 X 9.53 (GTAW+SMAW)
DIA 355.6 X 9.53 with 484
DIA 355.6 X 7.14
2603 +2603
(GTAW+SMAW)
3 3 3
DIA 355.6 X 7.14 with 484
DIA 355.6 X 9.53
1200 +1200
(GTAW+SMAW)
3 3 3
DIA 355.6 X 9.53 with 484
DIA 355.6 X 7.14
2603 +2603
(GTAW+SMAW)
3 3 3
DIA 355.6 X 7.14 with 484
DIA 355.6 X 9.53
1200 +1200
(GTAW+SMAW)
3 3 3
DIA 355.6 X 9.53 with 484
DIA 355.6 X 7.14
2203 +2203
(GTAW+SMAW)
3 3 3
DIA 355.6 X 7.14 with 484
DIA 355.6 X 9.53
2596 +2596
(GTAW+SMAW)
3 3 3
DIA 355.6 X 9.53 with 484
DIA 355.6 X 15.88
1000 +1000
(GTAW+SMAW)
3 3 3

TOTAL 100639 66 43 43 16
FLARE TOWER COLUMN STATUS
DESCRIPTION WPS NO OF JOINTS
FIT-UP WELDING VISUAL NDT PWHT NDT REMARKS

630SR (GTAW + 1 joint repair at two location 1. D26-36


DIA 914 X 63.5
SAW)
3 3 3 3 3 2 L37mm 2. d 39-48mm L27mm

DIA 914 X 63.5 with 1049 PWHT


50mm plate
50 -----
(SMAW)
3 3 *3 Welding is ongoing

DIA 914 X 44.45 with


0 ------ 3
50mm plate
12000+3027+7306+
DIA 914 X 44.45 25333
3000
9 7 7 7 6 NA 1 joint repair

DIA 914 X 28.58 15211 3 3 3

DIA 914 X 28.58 WITH


1000 3
CONE
Cone 914x 711 with
0 3
pipe

DIA 711 X 28.6 5105

DIA 711 X 19.05 12410

Cone 711x 508x 19.1


1000 3
with pipe 711
Cone 711x 508x 19.1
0 3
with pipe 508
DIA 508 X 19.05 with 484
10212 4104 + 10108 3
DIA 508 X 15.88 (GTAW+SMAW)
Cone 508x 356x 15.9
750 3
with pipe 508
Cone 508x 356x 15.9
0 3
with pipe 355.6

DIA 355.6 X 15.88 8757

DIA 355.6 X 9.53 3703


DIA 355.6 X 7.14 2503

DIA 355.6 X 9.53 1200

DIA 355.6 X 7.14 2603

DIA 355.6 X 9.53 1200

DIA 355.6 X 7.14 2603

DIA 355.6 X 9.53 1200

DIA 355.6 X 7.14 2203

DIA 355.6 X 9.53 2596

DIA 355.6 X 15.88 1000

TOTAL 100639 42
ECCDB & FR PROJECT
WEEKLY RT & PAUT STATISTICS

WEEK ENDING:20-26 July 2014


RT /PAUT STATUS- WELDING
TOTAL JTS RT
DESCRIPTION AREA SUN MON TUE WED THU FRI SAT
OUTSTANDING TOTAL JOINTS
(20.07.14) (21.07.14) (22.07.14) (23.07.14) (24.07.14) (25.07.14) (26.07.14)

RT PAUT RT PAUT RT PAUT RT PAUT RT PAUT RT PAUT RT PAUT RT PAUT

0
NO. OF JOINTS 0 0 0 0 0 19 0 0 0 0 0 9 0 38 0
REQUESTED
Note 1 Note 2 Note 1 Note 2 Note 3 Note 2 Note 2 Note 2 Note 2 Note 2

NO. OF JOINTS EGF 24 0


0 0 0 0 0 15 0 0 0 0 0 8 0 23 0
COMPLETED

NO. OF CREWS 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0
NO. OF JOINTS 0 0 0 0 0 25 5 0 0 0 0 0 0 25 5
REQUESTED
Note 1 Note 2 Note 1 Note 2 Note 3 Note 2 Note 1 Note 2 Note 1 Note 2 Note 1 Note 2 Note 1 Note 2

0
NO. OF JOINTS PKG-1 29 0 0 0 0 0 21 2 0 0 0 0 0 0 21 2
COMPLETED

NO. OF CREWS 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

1. NO RT SCHEDULED
2. NO PAUT SCHEDULED
3. NO RT SAFETY PERMIT ISSUED BY PU5
ECCDB & FR PROJECT
WEEKLY RT & PAUT STATISTICS

WEEK ENDING: (27 July -02 August 2014)


RT /PAUT STATUS- WELDING
TOTAL JTS RT
DESCRIPTION AREA SUN MON TUE WED THU FRI SAT
OUTSTANDING TOTAL JOINTS
(27.07.14) (281.07.14) (29.07.14) (30.07.14) (31.07.14) (01.08.14) (02.08.14)

RT PAUT RT PAUT RT PAUT RT PAUT RT PAUT RT PAUT RT PAUT RT PAUT

0
NO. OF JOINTS 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
REQUESTED
Note 1 Note 2 Note 1 Note 2 Note 1 Note 2 Note 1 Note 2 Note 1 Note 2

NO. OF JOINTS EGF 24 0


0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
COMPLETED

NO. OF CREWS 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0
NO. OF JOINTS 0 0 0 0 0 13 0 0 0 12 0 0 0 25 0
REQUESTED
Note 1 Note 2 Note 1 Note 2 Note 1 Note 2 Note 2 Note 1 Note 2 Note 3

0
NO. OF JOINTS PKG-1 29 0 0 0 0 0 13 0 0 0 6 0 0 0 19 0
COMPLETED

NO. OF CREWS 0 0 0 0 0 0 1 0 0 0 1 0 0 0 2 0

1. NO RT SCHEDULED
2. NO PAUT SCHEDULED
3. RT was only 6 jt. Done. ( Only one team was available, Tech. need an urgent RT shooting on other area.)