Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 4

1. 300 m3 Settling Tank x 6Nos.

2. 500m3 Settling Tank x 2nos.


3. 430 m3 Settling Tank x 6Nos.

ITEM DESCRIPTION UNITS REQUIRED OFFERED


1. GENERAL DATA
As per
PE19EF006QA-
RFQ_Site_Fabricat
1.1 Site Conditions - ed_Storage_ To be inspected
Tanks_Package-1
(Requisition No-
GT19101900)
1.2 Number of tanks - 6/2/6 6/2/6
1.3 Interior / Exterior - Exterior Exterior
1.4 KKS numbers - Not mentioned ------
1.5 Type - Site tank Site Tank
Outdoor built at
1.6 Installation - Outdoor
site
PRODUCED PRODUCED
1.7 Service - WATER WATER
2. DESIGN DATA
PRODUCED PRODUCED
2.1 Fluid
WATER WATER
2.2 Net Working Capacity m³ 300 / 500 / 430 ~300 / 500 / 430
350 / 575 / 510 ~350 / ~575 /
2.3 Maximum Capacity
(TBC) ~510
Steel
2.4 mm TBC
structure
NA(Internal NA(Internal
2.5 Shell mm
Corrosion Coating) Coating)
Allowances Roof & NA(Internal NA(Internal
2.6 mm
Structure Coating) Coating)
Bottom NA(Internal NA(Internal
2.7 mm
Plate Coating) Coating)
2.8 Roof kN/m² To be Specified To be Specified
2.9 Live Loads Platforms kN/m² To be Specified To be Specified
2.10 Stairs kN/m² To be Specified To be Specified
2.11 Design Tank API 650 API 650
2.12 Standard Vents API 2000 API 2000
2.13 Material
Pressure
2.14 barg Atmospheric Atmospheric
Min amb: 7 °C, Min amb 7 Deg
Temperature
2.15 °C design 60 °C C, Design 60 Deg
C
2.16 Dynamic Viscosity P 0.46 – 1.3 0.46 – 1.3
2.17 Internal Diameter m 6.5 / 8.0 / 7.5 6.5 / 8.0 / 7.5
9000 / 9000 / 9000 / 9000 / 9000
2.18 Height (Straight) mm
9000
To be confirmed To be confirmed
2.19 Height (total) mm
after Design Cal. after Design Cal.
Not mentioned To be confirmed
2.20 Shell mm
after Design Cal
Not mentioned To be confirmed
2.21 Thickness Roof mm
after Design Cal
Not mentioned To be confirmed
2.22 Base mm
after Design Cal
2.23 Roof type - Fixed Roof (Cone) Fixed Roof (Cone)
Not mentioned To be confirmed
2.24 Roof radius mm
after Design Cal
Siphon Drain (D) Yes
2.25 Draw-Off sump
mentioned
2.26 X-rays inspection Not mentioned TBD
2.27 Penetrating liquids inspection Not mentioned TBD
2.28 Foundation type Not mentioned Client Scope
3. TECHNICAL FEATURE
3.1 Pumping rates
322.0 / 513.0 /
3.1.1 Pumping rate IN m³/h Excluded
438.0
3.1.2 Pumping Rate OUT m³/h 81.0 / 81.0 / 81.0
3.1.3 Maximum velocity IN m/s Not mentioned
3.1.4 Maximum velocity OUT m/s Not mentioned
3.2 Joints
3.2.1 Bottom Plates Joint Type - Not mentioned TBD
3.3 Anchor Bolts
3.3.1 Material Not mentioned Excluded
3.3.2 Quantity Not mentioned Excluded
DN /
3.3.3 Size Not mentioned Excluded
Length
3.4 Firefighting Ring
3.4.1 Yes / NO - NO NO
3.4.2 Qty / Ring C.L Diam - / mm Not applicable
3.4.3 Nominal diam / Sch Not applicable
3.4.4 Type of Sparge Nozzles Not applicable
3.4.5 Number of Sparge Nozzles Not applicable
4. AUXILIARY EQUIPMENT
Yes - See Data Sheet
Tag Nos. 12-13-14-
T-4XX1A/B
Fittings, Nozzles and
4.1 Tag No. 31-T- Yes
Fittings 4XX1A/B
Tag Nos. 22-23-24-T-
4XX1A/B
4.1.1 Inside pipes to the bottom Yes - See Data Sheet Yes
for any filling line Tag Nos. 12-13-14-
T-4XX1A/B
Tag No. 31-T-
4XX1A/B
Tag Nos. 22-23-24-
T-4XX1A/B
Yes - See Data Sheet
Tag Nos. 12-13-14-
T-4XX1A/B
4.2 Vents Tag No. 31-T-
4XX1A/B
Tag Nos. 22-23-24-T-
4XX1A/B
Yes - See Data Sheet
Tag Nos. 12-13-14-
T-4XX1A/B
4.3 Manhole (with davit) Tag No. 31-T-
4XX1A/B
Tag Nos. 22-23-24-
T-4XX1A/B
To be confirmed
4.4 Design Plates Not mentioned
after Design Cal.
4.5 Cathodic Protection Not Required Excluded
Lugs, brackets for earth
4.6 connection (earth net by Yes Yes
others)
Overpressure / Vacuum
4.7 Not mentioned Not considered
valve
mmH2
4.7.1 Max Over pressure Not mentioned To be considered
O
4.7.2 Max Depression Not mentioned To be considered
5 SCOPE
5.1 Mechanical Scope
Nozzles of equipment or
terminal points of pipes at
5.1.1 Not mentioned Excluded
the limit of the skid in the
case of packaged systems
Platforms, stairs, ladders
5.1.2 Ladder Ladder is included
and other steel structures
Piping supports at tank
5.1.3 Not mentioned TBD
shell
As per PE19EF006QA-
RFQ_Site_Fabricated_Sto
5.1.4 Painting rage_ Tanks_Package-1 Not in Scope
(Requisition No-
GT19101900)
5.2 Electrical scope
3 lugs every 120º and the
5.2.1 possibility to install - Not in Scope Not in Scope
arrestors
5.3 Services scope
5.3.1 Project management Not in Scope Not in Scope
5.3.2 Engineering Yes Yes
5.3.3 Quality assurance Not in Scope Not in Scope
5.3.4 Factory/shop tests Not in Scope Not in Scope
5.3.5 Packing Not in Scope Not in Scope
5.3.6 Guarantees
Legalization of
5.3.7 project/installation with Not in Scope Not in Scope
local authority
5.4 Site services/works scope
5.4.1 Erection supervision Not in Scope Not in Scope
Commissioning and start-
5.4.2 Not in Scope Not in Scope
up supervision
5.4.3 Complete erection works Not in Scope Not in Scope
Complete commissioning
5.4.4 Not in Scope Not in Scope
and start-up works
5.4.5 Site tests Not in Scope Not in Scope
Training for operation
5.4.6 Not in Scope Not in Scope
staff
5.5 Spare parts/consumables/special tool scope
Special tools required for
5.5.1 operation and maintenance Not in Scope Not in Scope
of the equipment supplied
Spare parts for 2 years of
5.5.2 Not in Scope Not in Scope
operation
First filling of
5.5.3 Not in Scope Not in Scope
lubricants/chemicals
6 Guarantees
Maximum Velocity –
6.1 Not in Scope Not in Scope
In/Out
6.2 No Leakage through Joints Not in Scope Not in Scope

You might also like