Download as pdf or txt
Download as pdf or txt
You are on page 1of 6

CONSTRUCTION

METHOD

Document Number : WRK-PIP-LBJ-007 Rev. : 1


ELECTRICAL
INSTRUMENT Page Number
PROYEK DERMAGA
LABUAN BAJO CONTROL WORK
1 Of 6

LIGHTING SYSTEM

CLIENT : PT. INDONESIA POWER


CONTRACTOR : PT. WIJAYA KARYA REKAYASA KONSTRUKSI
PROJECT NAME : EPC SISTEM CONVEYOR DARI DERMAGA 2 KE
PLTU 1 BANTEN SURALAYA
LOCATION : SURALAYA - BANTEN
CONSTRUCTION
METHOD

Document Number : WRK-PIP-LBJ-007 Rev. : 1


ELECTRICAL
INSTRUMENT Page Number
PROYEK DERMAGA
LABUAN BAJO CONTROL WORK
2 Of 6

CONTENTS

1. General
2. Scope of Work
3. Responsibilities
4. Installation Procedure
5. List of Tool
CONSTRUCTION
METHOD

Document Number : WRK-PIP-LBJ-007 Rev. : 1


ELECTRICAL
INSTRUMENT Page Number
PROYEK DERMAGA
LABUAN BAJO CONTROL WORK
3 Of 6

1. General
This Installation procedure has been prepared to define detailed definition
of Lighting System to Dermaga Labuan Bajo.

2. Scope of Work
This procedure is applicable for the installation works for Lighting System
and the accessories for PT. Pelabuhan Indonesia, Dermaga Labuan Bajo,
Indonesia.Project.

3. Responsibilities
Superitendent is responsible for all works to be performed in accordance
with this procedure.
Supervisor is responsible to implement and control the field works
ensuring the work is executed according to this procedure.
Foreman is responsible to control the filed crew and to maintain close
contact with the Supervisor’s instruction.
Site supervision will be responsible for practical implementation and
compliance with the loss prevention, Health and Safety Plan.
Indonesia Power Engineer and Subcontractor Field Engineer are
responsible for ensuring construction aids are installed in a manner, which
support safe constructability.

4. Installation Procedure
4.1 Risk Assesment
CONSTRUCTION
METHOD

Document Number : WRK-PIP-LBJ-007 Rev. : 1


ELECTRICAL
INSTRUMENT Page Number
PROYEK DERMAGA
LABUAN BAJO CONTROL WORK
4 Of 6

Prior to the execution of the installation work for Installation of


Transformers, Supervisor or Foreman in-charge shall ensure the following
risk assessment is performed:
a. The tools used are suitable and safe to use.
b. Supervisor or Foreman is present at work site,
c. Scaffolding when used is confirmed "Tagged for Use" by authorized
person.
d. Safety harness are being used by personnel working on high-elevated
platform.
e. Suitable fire extinguishers are available in the area.
f. Precautionary warning signs for this type of work place are visibly kept
in place.
g. Hot Work Permit system is applicable in all buildings

4.2 Receiving, Storage, Hauling of Materials


When the equipment is delivered to the site, every materials should
be checked against the packing list to be sure all parts have been received.
An examination should be made for any damage that may have been
sustained during shipment. If damages resulting from transport, claims the
forwarding agent and report to Indonesia Power.
If immediately installation is not schedule after inspection and
inventory, the equipment should be stored in a protected area.
CONSTRUCTION
METHOD

Document Number : WRK-PIP-LBJ-007 Rev. : 1


ELECTRICAL
INSTRUMENT Page Number
PROYEK DERMAGA
LABUAN BAJO CONTROL WORK
5 Of 6

4.3 Confirmation of The Site Condition


Confirm the site situations for its readiness to commence the
installation works of lighting. Supervisor should confirm the enough space
to set lifting equipment for installaton works. If there is any problem that
will cause disorder of Transformer installation works at site, notify to PT.
Palabuhan Indonesia engineer.

4.4 Preparation of Drawings and Tools


Confirm installation drawings and required vendor documents such
as Instruction Manual. If there is any shortage of materials or tools, notify
PT. Palabuhan Indonesia to get supplementary materials.

4.5 Detail Installation Procedure


- Scaffolding for the installation to be done by people who are
experienced in their field and kompoten
- Base plates or wooden sill plate to be used for the base of the legs of
the scaffolding
- The use of the board for the platform to be really strong
- Toeboard placed on all open sides of the scaffolding ends more than
2.3 meters
- Construction of an iron pole scaffolding must be in excellent condition
should not be bent, broken, etc.
- Ladder must be provided for the installation of access scaffolding
platform
CONSTRUCTION
METHOD

Document Number : WRK-PIP-LBJ-007 Rev. : 1


ELECTRICAL
INSTRUMENT Page Number
PROYEK DERMAGA
LABUAN BAJO CONTROL WORK
6 Of 6

- Scaffolding above protection is needed in the workmanship who work


in high elevation
- Guardrail installed on scaffolding that is more than 2.3 meters
- Screens or nets installed under the scaffolding at heights to protect or
avoid work equipment that fell on the go
- Scaffolding must be installed in a permanent structure or building

5. List of Tools
a. Drill machine
b. Paint brush
c. Cutting / Grinder machine
d. Appliance of meter
e. Hand Tools

You might also like