Professional Documents
Culture Documents
SOP-10 Pre Commissioning and Commissioning Activities
SOP-10 Pre Commissioning and Commissioning Activities
SOP-10 Pre Commissioning and Commissioning Activities
SP – 10
Hindustan Petroleum Corporation Limited
Issue No.
परियोजना एवं पाइपलाइन 01 Issue Date
Projects & Pipelines
Safety Procedure for Pre Commissioning and Page 1 of
Rev No. 0
Commissioning Activities 14
Issue By Approved By
1.0 Purpose
2.0 Scope
3.0 Reference
4.0 Responsibility
5.1 Procedure
5.3 PPEs
1. Mechanical Completion
I. Mechanical completion is the condition that the individual
facility, system or equipment has been physically installed
in accordance with the drawings, specifications and codes
and regulations to the extent to start the pre
commissioning.
II. Upon the mechanical completion of the pipe line system
Contractor shall submit the following documents along with
the "intimation regarding system completion —FORMAT-1"
to the EPMC/Client .
• Pipe book duly completed in all respects
• List of golden tie-In joints (Tie-in joints which are not
subjected to hydrotesting i.e., for jointing the sections which
हिन्दुस्तान पेट्रोलियम कार्पोरेशन लिमिटेड Doc No. SP – 10
Hindustan Petroleum Corporation Limited
Issue No.
परियोजना एवं पाइपलाइन 01 Issue Date
Projects & Pipelines
Safety Procedure for Pre Commissioning and Page 6 of
Rev No. 0
Commissioning Activities 14
2. Physical Completion
Physical completion follows the mechanical completion and
when the certificate of physical completion issued by
OWNER
Upon the physical completion, the facilities and pipeline are
fully ready for the pre-commissioning and commissioning.
3. PRE-COMMISSIONING
1. PRE-COMMISSIONING CHECKS
2. SYSTEM CHECKS
6. SURVEY OF PIPELINE
5.6 Precaution
2. System checks
i. The entire facilities shall be checked against the latest
P&ID's and other design specification/codes
5. SURVEY OF PIPELINE
i. This shall be performed to confirm that proper fitting /supports,
route markers, fencing around SV stations etc., have been
installed along the pipeline.
SAFETY CHECK
हिन्दुस्तान पेट्रोलियम कार्पोरेशन लिमिटेड Doc No. SP – 10
Hindustan Petroleum Corporation Limited
Issue No.
परियोजना एवं पाइपलाइन 01 Issue Date
Projects & Pipelines
Safety Procedure for Pre Commissioning and Page 12 of
Rev No. 0
Commissioning Activities 14
i. In case of Injury
हिन्दुस्तान पेट्रोलियम कार्पोरेशन लिमिटेड Doc No. SP – 10
Hindustan Petroleum Corporation Limited
Issue No.
परियोजना एवं पाइपलाइन 01 Issue Date
Projects & Pipelines
Safety Procedure for Pre Commissioning and Page 13 of
Rev No. 0
Commissioning Activities 14
In case of Explosion
Cut flow of gas.
Inform Client Control Room immediately.
Inform fire station and first aid centre for action.
Cordon off the area by zebra tape immediately.
Start reinstatement after containment the site condition.
Start work, after clearance given by client.
6.0 RECORDS
c. Safety Checklists
d. Accident Reports as per OISD-107
e. Safety Training Record
f. Induction Reports