Professional Documents
Culture Documents
Bim and Modular Mep Systems For Super-Tall and Mega-Tall Buildings
Bim and Modular Mep Systems For Super-Tall and Mega-Tall Buildings
ICSECM2017-465
19
8th International Conference on Structural Engineering and Construction Management, 2017
ICSECM2017-465
systems. Both these concepts can be applied the limitations during construction and easy
to MEP systems, however, there is a strong maintenance during operations.
dependency on the building functionality.
1.2 Conflicts between MEP Systems in the
For example, standardisation can be applied Field
to data centres, where the cooling load of the
building depends greatly on the data centre When compared to the uniform and
size. There are standard sizes for data centres predictable progress of the structural work in
and therefore, the cooling system can also be building construction, MEP work is
standardised to meet the cooling considered to generate the most waste due to
requirement. This is a concept of providing a its uncertainty and instability. A significant
standard, scalable product to function amount of time is wasted in construction
another range of standard products. A set of projects, in doing rework due to design
battery-operated toys can be taken as an changes and conflicts between MEP crews.
example. They all have the same type and Mechanical, electrical and plumbing (MEP)
size of battery; however, the number of systems contribute to 40-60% of the total
batteries depends on the size of the toy and construction cost of commercial buildings
the operation. (Khanzode, 2010). Court et al., (2009)
identified health and safety, congestion on
In commercial buildings such as, hotels, site, crew relationships that creates conflicts
offices and shopping malls, variation in and delays, productivity, worker availability
heating and cooling load due to architectural and skills as the primary issues in MEP
and functional aspects makes it impossible to construction that generate waste and delays
achieve standardisation in HVAC systems. the completion of the project.
In other words, it is very difficult to provide
a standardised product to function within an Labour efficiencies in the mechanical
irregular product range. Another dominant aspects of a projects drop significantly due to
factor that limits standardisation are the the late owner initiated design changes
onsite limitations during construction. Due (Hanna et al., 1999). One such change can
to the late installation of MEP systems, there affect all the inter-connected services in the
are number of limitations on site. Tall building. For example, changing the
buildings in urban areas have MEP systems operation of a space in the building will
located in the basement level of the building require ventilation system to be changed and
and when transporting equipment onsite, therefore, will affect duct sizes and at the
limitations caused by the existing building same time will affect other services such as
structure should be taken into consideration. plumbing that shares the same service shaft.
These structural and architectural limitations This will result in a significant amount of
vary significantly from project to project. The rework, which would lead to delays and
variation in design restricts the use of additional costs.
standardised MEP systems. 1.3 Traditional and Prefabricated MEP
Limitations during construction and Construction Process
variations in design makes modularisation It is important to understand the current
the perfect solution for MEP systems in coordination process in a traditional
commercial buildings. In the construction construction system, to identify the
industry (especially in the case of MEP differences to the prefabricated system. In
systems), unlike in product modularisation, the traditional construction process, the
a constraint-based approach should be scope of the design engineer in design-built
considered from the initial stages of the projects does not include coordination. Once
modularisation process. This gives the MEP the contract is awarded, a speciality
designer the freedom to design the optimum contractor on site is responsible for
system for each building and the development of shop-drawings, which
modularisation process will mainly consider identifies the interferences between the
systems. Once all the interferences are
20
8th International Conference on Structural Engineering and Construction Management, 2017
ICSECM2017-465
resolved, a coordinated shop drawing is The main MEP installation takes place when
submitted to the engineer for approval. This the project approaches its completion date.
coordination process can be time-consuming
According to the Construction Managers,
and can fall on the critical path for system
this late kick-off of MEP installations comes
installation (Tatum & Korman, 1999).
down to insurance issues, equipment
The initial cost of the design can increase warranty issues, security issues and
significantly if the coordinated design varies requirement of storage to maintain the
a lot from the initial design submitted by the original condition of the equipment prior to
engineer. It is important to consider both the commissioning. Therefore, in many cases
construction and operational stages during construction managers prefer to start MEP
the coordination process to confirm the ease installations closer to project completion.
of construction and maintenance. In Especially in Sri Lanka, due to the humid
prefabricated construction, design engineers conditions and the fact that the country is
and speciality contractors have to maintain a surrounded by the ocean, equipment and
strong communication from the initial stages pipe corrosion is a major issue.
of the design process. Unlike in traditional
However, from the design engineers point of
construction, almost all MEP systems are
view, late kick-off for installation is also due
fabricated at a single offsite facility prior to
to the tendency of architects and clients
installation on site. This results in significant
making minor changes to the building while
changes to the project master program.
on-going construction. These changes to the
In conventional construction, MEP function of different spaces in the building
installations during construction can be can have significant effects on the MEP
divided into three main stages as initial installations. To address these changes, MEP
stage, installation stages & testing and designers tend to consider a 20-25% design
commissioning stage. Although, MEP safety factor in HVAC systems. However, in
engineers get involved from design stage (at cases where building original design
least for larger commercial projects), remains unchanged, HVAC system are over-
involvement during construction happens sized resulting in poor energy efficiency.
rather at a later stage where the building
This tentative design approach practiced in
structure is complete or near completion.
the industry is a major barrier for MEP
MEP engineers are however, on site from
prefabrication. In modular prefabricated
beginning of construction to verify that the
construction, all MEP designs shall be
opening/penetrations, building earthing
finalised at the initial design stage prior to
and conduit laying is provided prior to
construction onsite. This allows the
concreting some areas during the initial
concurrent manufacture of building services
stages.
modules while structural & civil work being
done onsite.
ICSECM2017-465
Complete Modules
Offsite
fabrication
Parts/material
Assemblie
Sub-
Componen Construction
Component
Site
manufacture
Parts/m
aterial
Part
Elements
Suppliers
22
8th International Conference on Structural Engineering and Construction Management, 2017
ICSECM2017-465
It is most likely to see all three forms of MEP the basement level or at the roof top of the
products coming to the same construction building. Therefore, when determining the
site. Plantroom modules, riser modules, size of the modules, the dimensions of the
distribution modules and corridor modules corridors and the entrance opening to the
can be considered as fully-modular plant room should be taken into
products. Indoor HVAC equipment, valves consideration. Another challenge in super-
and pipes can be considered as components tall and mega-tall buildings is the
and nuts, bolts, threaded bars, GI-sheets can intermediate service floors. Crane operation
be considers as elements. and forklift operation are almost impossible
in these situations due to the height of the
In prefabricated construction these three
building. Therefore, innovative methods of
product types comes straight to site and
on-site delivery and installation shall be
might also have an interaction amongst
considered.
them before arriving on site. For example,
components and elements are required to Maximum weight of a module is decided
fabricate a fully-modular product. Figure 2 considering the onsite handling equipment.
illustrates construction system model for This varies from cranes for heavy object
prefabricated MEP. lifting, handcarts and folk-lifts for
transportation of modules within the
2. Challenges for Modular MEP Construction
building. This should be discussed with the
Challenges for modular MEP construction management team before the
implementation can be categorised into modularisation process begins.
technical challenges (challenges that directly
Weight of a complete module can be
affect the installation) and design challenges
considered as some of the element weights
(challenges that affect the design). Technical
and this should not exceed 80% of the
challenges include the on-site limitations,
handling equipment capacity. This leaves a
skilled level of labour force, transportation
20% safety factor to address the possible
and availability of a fabrication facility.
weight distributions during onsite
Design challenges include poor
transportation.
communication, availability of fabrication
function in BIM software, Inter-operability of Other than the module size and the weight,
BIM software etc. Samarasinghe et al. (2015) assembly of modules/components onsite
identified the inter-operability issues in BIM can be considered as the third challenge in
software, proposed a BIM software modular MEP installations. The goal of
framework and the required Level of prefabrication is to reduce the number of
Development (LOD) for prefabrication. In onsite assemblies and avoid having to
this study, authors will only concentrate on employ a skilled labour force. Therefore, it is
the technical challenges in modular MEP ideal to have as many components as
construction. possible within a single module that is
constructed offsite. However, due to the
Module transportation, onsite handling and
limitations in module size and weight, this
assembly are the key factors that govern the
ideal situation is not achieved in many cases.
modularisation of MEP systems. The weight
and the size of the module is decided Provision for maintenance and replacements
considering the module transportation should be considered from the design stages
options and onsite module handling options. of the system. This should not affect the
This study considers only the operation of the building. Onsite constraints
modularisation of MEP systems and mentioned above may change during
therefore, it is assumed that the structure of operational stages. Crane and forklift
the building is done conventionally. This operation may not be available for onsite
makes the onsite handling of MEP modules transportation. Ideal modularisation should
very challenging. In many cases the plant address the dismantling of the system as
rooms and other service areas are located in well.
23
8th International Conference on Structural Engineering and Construction Management, 2017
ICSECM2017-465
24
8th International Conference on Structural Engineering and Construction Management, 2017
ICSECM2017-465
(a)
(b)
(c)
ICSECM2017-465
ICSECM2017-465
27
Author/s:
Samarasinghe, T; Mendis, P; Aye, L; Gunawardena, D; Karunaratne, R
Title:
BIM and modular MEP systems for super-tall and mega-tall buildings
Date:
2017-12-07
Citation:
Samarasinghe, T; Mendis, P; Aye, L; Gunawardena, D; Karunaratne, R, BIM and modular
MEP systems for super-tall and mega-tall buildings, 8th International Conference on
Structural Engineering and Construction Management, 2017, pp. 19 - 27
Persistent Link:
http://hdl.handle.net/11343/197525
File Description:
Published version