Download as pdf or txt
Download as pdf or txt
You are on page 1of 10

8th International Conference on Structural Engineering and Construction Management, 2017

ICSECM2017-465

BIM AND MODULAR MEP SYSTEMS FOR SUPER-TALL AND MEGA-TALL


BUILDINGS
T Samarasinghe1*, P Mendis 2, L Aye 3, T Gunawardena4, S Fernando5, R Karunaratne6
12346The
University of Melbourne, Australia
5BuildingServices Engineering Consultants (PVT)Ltd., Sri Lanka
*Correspondence E-mail: tsamarasingh@student.unimelb.edu.au
Abstract: Mechanical, Electrical and Plumbing (MEP) work in high-rise construction can be very
challenging due to the different crews involved during installation. Conflicts between the crews
generally cause delays in project schedule and result in additional cost due to rework. This study
will identify the MEP conflicts in high-rise construction through observations made by the author
during the time spent in case study projects. This study focuses on the use of Modular MEP
systems in high-rise construction to eliminate the current conflicts. Traditional MEP construction
process was reviewed to identify changes to the process when using modular MEP systems.
Challenges in implementing modular MEP in high- rise construction is discussed and an
implementation strategy is proposed. Role of Building Information Modelling (BIM) in modular
MEP construction is highlighted in the study and its involvement during different stages of the
modularisation process is discussed.
Keywords: MEP; High-rise; Modular; Prefabricated; BIM

1. Introduction service crews and poor installation inside


crowded MEP shafts. Building Information
Mechanical, Electrical and Plumbing (MEP)
Modelling (BIM) and Modular MEP can be
also known in the industry as Building
considered as solutions for the above
Services are the active systems in a building
problems. There are however, limitations in
that make the buildings liveable by
modular construction that need to be
providing electricity, communication,
identified before implementing modular
heating/cooling and ventilation, supply and
MEP services for tall buildings. There is a
disposal of water (Barton, Fryer, & Highfield,
notable gap in the industry for a
1983). Scope of Building services
methodology for identification of optimum
engineering has increased significantly with
modules and module division points in
the introduction of modern sophisticated
MEP. The study is focussed on introducing a
high-rise developments. ASHRAE defines a
modularisation methodology that will be
Tall-building as one whose height is more
integrated with BIM that can be practically
than 91m and recently introduced two new
implemented in the construction industry.
building classes as super-tall (taller than
300m) and mega-tall (taller than 1.1 Modularisation and Standardisation of
600m)(Simmonds, 2015). Service design for MEP
these buildings can be very challenging due
Modularisation and standardisation are two
to the height of the building and the capacity
terms that are well known in the
of equipment. Introduction of intermediate
prefabrication and product development
service floors and decentralised services are
industry. Although, these two words are
preferred over centralised services for these
used together in many cases, there is a
types of buildings due to the height and
distinct difference between them when
multi-occupancy arrangements.
applied to product development. (Börjesson,
Most of the services for tall buildings are 2012) has described some of the main
located in the central core of the building and differences of the two concepts when applied
service shafts are shared by different to product development.
electrical and mechanical services, making
Misjudgement of these concepts is one of the
coordination during design and installation
reasons for lack of prefabrication in
a risky and time-consuming task. Rework
Mechanical, Electrical and Plumbing (MEP)
can occur due to conflicts between different

19
8th International Conference on Structural Engineering and Construction Management, 2017

ICSECM2017-465

systems. Both these concepts can be applied the limitations during construction and easy
to MEP systems, however, there is a strong maintenance during operations.
dependency on the building functionality.
1.2 Conflicts between MEP Systems in the
For example, standardisation can be applied Field
to data centres, where the cooling load of the
building depends greatly on the data centre When compared to the uniform and
size. There are standard sizes for data centres predictable progress of the structural work in
and therefore, the cooling system can also be building construction, MEP work is
standardised to meet the cooling considered to generate the most waste due to
requirement. This is a concept of providing a its uncertainty and instability. A significant
standard, scalable product to function amount of time is wasted in construction
another range of standard products. A set of projects, in doing rework due to design
battery-operated toys can be taken as an changes and conflicts between MEP crews.
example. They all have the same type and Mechanical, electrical and plumbing (MEP)
size of battery; however, the number of systems contribute to 40-60% of the total
batteries depends on the size of the toy and construction cost of commercial buildings
the operation. (Khanzode, 2010). Court et al., (2009)
identified health and safety, congestion on
In commercial buildings such as, hotels, site, crew relationships that creates conflicts
offices and shopping malls, variation in and delays, productivity, worker availability
heating and cooling load due to architectural and skills as the primary issues in MEP
and functional aspects makes it impossible to construction that generate waste and delays
achieve standardisation in HVAC systems. the completion of the project.
In other words, it is very difficult to provide
a standardised product to function within an Labour efficiencies in the mechanical
irregular product range. Another dominant aspects of a projects drop significantly due to
factor that limits standardisation are the the late owner initiated design changes
onsite limitations during construction. Due (Hanna et al., 1999). One such change can
to the late installation of MEP systems, there affect all the inter-connected services in the
are number of limitations on site. Tall building. For example, changing the
buildings in urban areas have MEP systems operation of a space in the building will
located in the basement level of the building require ventilation system to be changed and
and when transporting equipment onsite, therefore, will affect duct sizes and at the
limitations caused by the existing building same time will affect other services such as
structure should be taken into consideration. plumbing that shares the same service shaft.
These structural and architectural limitations This will result in a significant amount of
vary significantly from project to project. The rework, which would lead to delays and
variation in design restricts the use of additional costs.
standardised MEP systems. 1.3 Traditional and Prefabricated MEP
Limitations during construction and Construction Process
variations in design makes modularisation It is important to understand the current
the perfect solution for MEP systems in coordination process in a traditional
commercial buildings. In the construction construction system, to identify the
industry (especially in the case of MEP differences to the prefabricated system. In
systems), unlike in product modularisation, the traditional construction process, the
a constraint-based approach should be scope of the design engineer in design-built
considered from the initial stages of the projects does not include coordination. Once
modularisation process. This gives the MEP the contract is awarded, a speciality
designer the freedom to design the optimum contractor on site is responsible for
system for each building and the development of shop-drawings, which
modularisation process will mainly consider identifies the interferences between the
systems. Once all the interferences are

20
8th International Conference on Structural Engineering and Construction Management, 2017

ICSECM2017-465

resolved, a coordinated shop drawing is The main MEP installation takes place when
submitted to the engineer for approval. This the project approaches its completion date.
coordination process can be time-consuming
According to the Construction Managers,
and can fall on the critical path for system
this late kick-off of MEP installations comes
installation (Tatum & Korman, 1999).
down to insurance issues, equipment
The initial cost of the design can increase warranty issues, security issues and
significantly if the coordinated design varies requirement of storage to maintain the
a lot from the initial design submitted by the original condition of the equipment prior to
engineer. It is important to consider both the commissioning. Therefore, in many cases
construction and operational stages during construction managers prefer to start MEP
the coordination process to confirm the ease installations closer to project completion.
of construction and maintenance. In Especially in Sri Lanka, due to the humid
prefabricated construction, design engineers conditions and the fact that the country is
and speciality contractors have to maintain a surrounded by the ocean, equipment and
strong communication from the initial stages pipe corrosion is a major issue.
of the design process. Unlike in traditional
However, from the design engineers point of
construction, almost all MEP systems are
view, late kick-off for installation is also due
fabricated at a single offsite facility prior to
to the tendency of architects and clients
installation on site. This results in significant
making minor changes to the building while
changes to the project master program.
on-going construction. These changes to the
In conventional construction, MEP function of different spaces in the building
installations during construction can be can have significant effects on the MEP
divided into three main stages as initial installations. To address these changes, MEP
stage, installation stages & testing and designers tend to consider a 20-25% design
commissioning stage. Although, MEP safety factor in HVAC systems. However, in
engineers get involved from design stage (at cases where building original design
least for larger commercial projects), remains unchanged, HVAC system are over-
involvement during construction happens sized resulting in poor energy efficiency.
rather at a later stage where the building
This tentative design approach practiced in
structure is complete or near completion.
the industry is a major barrier for MEP
MEP engineers are however, on site from
prefabrication. In modular prefabricated
beginning of construction to verify that the
construction, all MEP designs shall be
opening/penetrations, building earthing
finalised at the initial design stage prior to
and conduit laying is provided prior to
construction onsite. This allows the
concreting some areas during the initial
concurrent manufacture of building services
stages.
modules while structural & civil work being
done onsite.

onsite Testing and


Design procure Assembly
fabrication Commisioning

Figure 1 (a): Traditional MEP Construction Process

offsite Testing and


Design procure Transportation Assembly
fabrication Commisioning

Figure 1(b): Prefabricated MEP Construction


Process
21
8th International Conference on Structural Engineering and Construction Management, 2017

ICSECM2017-465

Introduction of modularisation to MEP Construction managers and MEP site


systems should take place during the managers should have much greater
preliminary concept design stage. However, influence on MEP design from the
major changes shall be made to the preliminary stages, where, site constraints
conventional design process if shall be discussed with the MEP designers
modularisation is to be practiced in the MEP during the concept design stage prior to
industry. Figure (1) illustrates the preliminary designs. These site constraints
conventional design process and the prefab shall be considered during the design stage
design process. In conventional design, the to identify the limitations in module size,
performance of the system is mostly weight and assembly methods. Authors
considered during design stage. Once the involvement in case study projects and the
design is complete, it is pushed into time spent during visits was used to identify
procurement stage where items in the design the typical onsite constraints that will have a
are purchased. Items are then delivered to major influence on modular MEP
site and pushed into fabrication. Once the constructions. Constraint details and the
main equipment and elements are fabricated, inputs required from onsite staff will be
it is then pushed for assembly. Testing and discussed in the next section. Involvement of
commissioning is done once the assembly facility/maintenance managers is important
process is complete. This can be considered to identify the requirements during
as a push process. This process is reversed maintenance. Clustering of certain elements
(pull) when applied to prefabricated in the system to form a single module can
construction. Engineers should design and have adverse effects during maintenance.
procure a system that is commissionable and For example, equipment replacement can be
buildable. This concept is similar to Design difficult if it is permanently connected to
for Manufacture and Assembly (DFMA) in many other elements that do not require
the product development industry. DFMA is replacement. When system modularisation
based on parts reduction, which is the is based on ease of operation, replaceability
reduction of number of part per components of components should be studied to cluster
and reduce the type of components (Barbosa components with similar replaceability
& Carvalho, 2013). When there are other rates(Isaac et al., 2016).
challenges that should be considered during
There are different forms of prefabrication in
design stage such as transportation in the
the MEP industry. Fully modular,
case of prefabrication, DFMA concept
components and elements (parts) are the
changes to DFX (Design for Excellence)
main three forms of prefabrication.
(Bralla, 1996).

Complete Modules

Offsite
fabrication
Parts/material
Assemblie
Sub-

Componen Construction
Component
Site
manufacture
Parts/m
aterial

Part
Elements
Suppliers

Figure 2: Prefab Construction System Model for MEP

22
8th International Conference on Structural Engineering and Construction Management, 2017

ICSECM2017-465

It is most likely to see all three forms of MEP the basement level or at the roof top of the
products coming to the same construction building. Therefore, when determining the
site. Plantroom modules, riser modules, size of the modules, the dimensions of the
distribution modules and corridor modules corridors and the entrance opening to the
can be considered as fully-modular plant room should be taken into
products. Indoor HVAC equipment, valves consideration. Another challenge in super-
and pipes can be considered as components tall and mega-tall buildings is the
and nuts, bolts, threaded bars, GI-sheets can intermediate service floors. Crane operation
be considers as elements. and forklift operation are almost impossible
in these situations due to the height of the
In prefabricated construction these three
building. Therefore, innovative methods of
product types comes straight to site and
on-site delivery and installation shall be
might also have an interaction amongst
considered.
them before arriving on site. For example,
components and elements are required to Maximum weight of a module is decided
fabricate a fully-modular product. Figure 2 considering the onsite handling equipment.
illustrates construction system model for This varies from cranes for heavy object
prefabricated MEP. lifting, handcarts and folk-lifts for
transportation of modules within the
2. Challenges for Modular MEP Construction
building. This should be discussed with the
Challenges for modular MEP construction management team before the
implementation can be categorised into modularisation process begins.
technical challenges (challenges that directly
Weight of a complete module can be
affect the installation) and design challenges
considered as some of the element weights
(challenges that affect the design). Technical
and this should not exceed 80% of the
challenges include the on-site limitations,
handling equipment capacity. This leaves a
skilled level of labour force, transportation
20% safety factor to address the possible
and availability of a fabrication facility.
weight distributions during onsite
Design challenges include poor
transportation.
communication, availability of fabrication
function in BIM software, Inter-operability of Other than the module size and the weight,
BIM software etc. Samarasinghe et al. (2015) assembly of modules/components onsite
identified the inter-operability issues in BIM can be considered as the third challenge in
software, proposed a BIM software modular MEP installations. The goal of
framework and the required Level of prefabrication is to reduce the number of
Development (LOD) for prefabrication. In onsite assemblies and avoid having to
this study, authors will only concentrate on employ a skilled labour force. Therefore, it is
the technical challenges in modular MEP ideal to have as many components as
construction. possible within a single module that is
constructed offsite. However, due to the
Module transportation, onsite handling and
limitations in module size and weight, this
assembly are the key factors that govern the
ideal situation is not achieved in many cases.
modularisation of MEP systems. The weight
and the size of the module is decided Provision for maintenance and replacements
considering the module transportation should be considered from the design stages
options and onsite module handling options. of the system. This should not affect the
This study considers only the operation of the building. Onsite constraints
modularisation of MEP systems and mentioned above may change during
therefore, it is assumed that the structure of operational stages. Crane and forklift
the building is done conventionally. This operation may not be available for onsite
makes the onsite handling of MEP modules transportation. Ideal modularisation should
very challenging. In many cases the plant address the dismantling of the system as
rooms and other service areas are located in well.

23
8th International Conference on Structural Engineering and Construction Management, 2017

ICSECM2017-465

connections are some of main assembly


types in chilled water plant rooms (refer to
figure (5)).

Figure 3: Entrance opening size of


plant room
Table 1: Lifting Equipment Capacities

Figure 4 (a) (b): Lifting and installation of


equipment onsite
2.1 Modularisation Methodology for MEP
In order to identify the optimum division
Module identification in the current
points for module identification, it is
prefabricated MEP industry is a time
important to consider which assemblies
consuming manual process where engineers
require high skilled labour force, installation
mostly use the grid system to divide
time and safety during installation.
modules. The cost and the difficulty of onsite
Components that required the above should
assembly are not taken into consideration.
then be clustered for offsite manufacture. For
Researchers in other industries have adopted
example, quality of a weld connection can be
matrix clustering for identification of
improved significantly if done offsite and it
optimum modules. In the product
improves the safety as well. Coupling is a
development industry, interactions between
difficult task, especially between two heavy
product, process and consumer is mapped
modules. Whereas, flange and flexible
using Design Structure Matrix (DSM) to
connections are ideal for onsite assemblies.
identify possible clusters (Browning, 2001).
Pimmler & Eppinger (1994) used matrix- The modularisation process developed by
clustering for identification of modules for a the authors is divided into three main stages
climate control system in cars and trucks of as pre-processor stage, configuration
Ford Motor Company. generator stage and optimizer stage. A
significant amount of information is required
Absence of a practical methodology for
to identify the module division process. This
division of modules in MEP industry, leads
data can be extracted from the BIM model
to many modular designs not achieving the
during the pre-processor stage, prior to
optimum modularisation that considers the
modularisation. Site constraints can be
ease of assembly on site and the module size
introduced to the modularisation process as
limitations. There are many types of
a set of rules that governs the division of
assemblies associated with mechanical and
modules. The configuration generator stage
electrical installations. Authors have taken
will use a clustering algorithm to identify
HVAC chilled water plant rooms as an
possible clusters of components. Bond
example. Weld connections, flange
Energy Algorithm (BEA) will be used to
connections, coupling and flexible

24
8th International Conference on Structural Engineering and Construction Management, 2017

ICSECM2017-465

perform the clustering of components


ܱ‫ ܫܯ‬ൌ ‫ ܲܥܣ‬൅ ‫ܲܥܪ‬ ሺͳሻ
depending on the assembly type. Elements
extracted from the BIM model are mapped In the case of HVAC chilled water plant
on a design structure matrix and interactions room modularisation, flange and flexible
between elements are identified. Each connection points are considered as
interaction (assembly) is given a cost penalty optimum division points. However, these
depending on the safety, difficulty and the different arrangements can mean that the
quality of the assembly when done on site. assembly cost changes as the number of
Each element is then multiplied by the modules varies and the handling cost varies
elements surrounding it to achieve the Bond with the module weight. Assembly cost
Energy value. Elements with the highest Bon penalty (ACP) and handling cost Penalty
energies (high cost penalties) are clustered (HCP) for each arrangement can be
together and are identified as modules for determined from equations 2 and 3.
offsite fabrication.

Once the module configurations are derived,
‫ ܲܥܣ‬ൌ ෍ ݊௜ ൈ ‫ܲܥ‬௜ ሺʹሻ
modules will be assessed for onsite handling

and installation where, heavy and larger
modules will have to go through the Where,
configuration generator for further division.
In cases where there is a possibility of more ni = Number of assemblies of type i
than one module arrangement, optimizer CPi = Cost Penalty for assembly type i
stage will introduce a cost penalty method

for choosing the optimum configuration
which achieves the minimum cost of ‫ ܲܥܪ‬ൌ ෍ ݉௟ ൈ ܴ‫ܥ‬௟ ሺ͵ሻ
assembly, handling and installation. The ௟
optimum modularity index (OMI) is based
Where,
on assembly cost (ACP) and handling cost
(HCP) and can be calculated using equation ml = Number of modules in the weight
1. Cost penalty and matrix clustering was category l
initially used by (Lapp & Golay, 1997) for RCl = Equipment renting cost for weight
modularisation of nuclear power plants. category l

(a)

(b)

(c)

Figure 2: (a) Flange Connection (b)


Flexible Connection (C) Welding Figure 3: MEP Modularisation
Methodology
25
8th International Conference on Structural Engineering and Construction Management, 2017

ICSECM2017-465

3. BIM in Modular Construction Machines can have different inputs and


models should be adjusted to meet the
Multi-trade prefabrication requires a
requirement. This can be very challenging
significant amount of pre-planning and
and is one of the reasons for lack of
design coordination. Building Information
fabrication functions in BIM software.
Modelling (BIM) is ideal for design
Prefabrication as an industry is still at its
coordination, construction planning, on-site
early stages and it is likely to see
delivery planning, clash detection and
improvements to the BIM software once the
fabrication planning in Modular
fabrication process is more standardised.
construction. Design, Construction and
Operation and maintenance are the three While improving the communication
main aspects that are considered during between the stakeholders, a more technical
MEP coordination (Korman et al., 2010). This use of BIM in modularisation is to obtain the
requires the involvement of many specialists necessary information from the BIM model
from different stages of the project. In for module identification and optimisation
modular construction, onsite delivery and for job site delivery. Modularisation
installation specialist, Construction methodology presented in section 3.1
managers, fabrication plant specialist, design requires information about the type of
engineers and facility managers are involved assemblies, site limitations and element
during the project preliminary/concept details at the pre-processor stage. All this can
design stages. be obtained from the BIM model and can be
automatically extracted in different file
Clear communication between these
formats. Proposed BIM based methodology
individuals is very important to avoid
for module identification and optimisation
additional work onsite and problems during
uses an open source platform (Dynamo)
transportation and installation. BIM
which allows data transfer from different file
improves the communication between the
types to develop a virtual code for
different stakeholders in the project and
modularisation. Python based nodes are
helps to get the designers, construction
developed to perform the different
teams and the maintenance team involved
operations (extract data, element interaction
from the initial stages of the project.
matrix, BEA, etc.) and identify the element
Prefabrication industry is moving towards
arrangement and the OMI of a given MEP
the use of advanced robotic manufacturing
design. BIM based methodology for
equipment. This creates a new requirement
modularisation is illustrated in figure (7).
for BIM software to transfer fabrication
The final aim of the study is to develop an
models directly to manufacturing machines
API for optimum modularisation of a given
such as CNC, 3D printers etc.
design.

Figure 4: BIM Based Modularisation Process


26
8th International Conference on Structural Engineering and Construction Management, 2017

ICSECM2017-465

4. Conclusion Khanzode, A. (2010). An integrated, virtual


design and construction and lean (IVL)
This paper clearly identifies the challenges in
method for coordination of MEP.
Modular MEP construction and explains
Unpublished Technical Report, 187.
how they can be used as constraints in the
Korman, T., Simonian, L., & Speidel, E. (2010).
proposed modularisation methodology.
How building information modelling
Onsite challenges such as assembly and
has changed the MEP coordination
handling were identified as the main
process. Challenges, Opportunities and
constraints of the modularisation
Solutions in Structural Engineering and
methodology, and a cost penalty approach
Construction, Taylor & Francis, London,
was introduced to identify the optimum
959-963.
module division for a given design. MEP
Lapp, C. W., & Golay, M. W. (1997). Modular
challenges in conventional high-rise
design and construction techniques for
construction is discussed with authors
nuclear power plants. Nuclear
experience in the industry and changes to the
Engineering and Design, 172(3), 327-349.
conventional construction process when
Pimmler, T. U., & Eppinger, S. D. (1994).
implementing modular is illustrated in
Integration analysis of product
section 1.3. Application of a BIM based
decompositions.
modularisation process during the design
Samarasinghe, T., Mendis, P., Ngo, T., &
stage was proposed in the study.
Fernando, W. (2015). BIM Software
The proposed methodology for Framework for Prefabricated Construction:
modularisation only considers the onsite Case Study Demonstrating BIM
lifting limitations and assembly difficulty. Implementation on a Modular House. Paper
This concept will be improved in the future presented at the 6th International
to include constraints such as module height, Conference On Structural Engineering
width and length and to consider the And Construction Management.
replaceability rate of components during the Simmonds, P. (2015). ASHRAE Design Guide for
clustering process. The BIM based process Tall, Supertall, and Megatall Building
will be further developed to a user-friendly Systems: ASHRAE.
platform that can be used in the industry. Tatum, C. B., & Korman, T. (1999). MEP
coordination in building and industrial
projects. Center for Integrated Facility
References Engineering.
Barbosa, G. F., & Carvalho, J. d. (2013). Design
for Manufacturing and Assembly
methodology applied to aircrafts design
and manufacturing. IFAC Proceedings
Volumes, 46(7), 116-121.
Barton, P. K., Fryer, B. G., & Highfield, D. (1983).
Building services integration: E & FN Spon.
Börjesson, F. (2012). Approaches to modularity in
product architecture. KTH Royal Institute
of Technology.
Bralla, J. G. (1996). Design for excellence: McGraw-
Hill Professional Publishing.
Browning, T. R. (2001). Applying the design
structure matrix to system
decomposition and integration
problems: a review and new directions.
IEEE Transactions on Engineering
management, 48(3), 292-306.

27

View publication stats


Minerva Access is the Institutional Repository of The University of Melbourne

Author/s:
Samarasinghe, T; Mendis, P; Aye, L; Gunawardena, D; Karunaratne, R

Title:
BIM and modular MEP systems for super-tall and mega-tall buildings

Date:
2017-12-07

Citation:
Samarasinghe, T; Mendis, P; Aye, L; Gunawardena, D; Karunaratne, R, BIM and modular
MEP systems for super-tall and mega-tall buildings, 8th International Conference on
Structural Engineering and Construction Management, 2017, pp. 19 - 27

Persistent Link:
http://hdl.handle.net/11343/197525

File Description:
Published version

You might also like