CHECKLIST FOR ANALYSIS & DESIGN OF NORMAL FOUNDATIONS

Project: Effluent Treatment Plant (ETP) &Hazardous Waste Handling Facilities (Package-2) Job No.: PL/632

Document No.: HRRL-632-ETP-CCAL-203A Rev. No.: R4


Document Title: Pile Load Calculations of OWS Tank
SR. Tick Mark
CHECK/ CONTROL POINTS
NO. as per Legend
1 Founding level/ depth of foundation with respect to HPP/ FGL/ NGL/ EGL/ FFL Ok
(strike out whichever is not applicable).
2 Requirement & Level of plinth/ tie beams. Ok
3 Type, Shape & Dimensions of footing. Ok
4 Adequacy of loading for foundation. Ok
5 Correctness of the design forces as per analysis. Ok
6 Selection of critical loading cases/ combinations. Ok
7 Long/ short column effect for pedestal. N/A
8 Size of pedestal: N/A
a) type of anchor bolts N/A
b) bolt spacing (with respect to clearance between the bolts) N/A
c) edge distance of anchor bolts N/A
d) depth of embedment of anchor bolts N/A
9 Location co-ordinates & Orientation with respect to North direction. Ok
10 Conformance to Geotechnical recommendations: Ok
a) check for SBC at founding depth (w.r.t. settlement/ shear) N/A
b) consideration of ground water table. Ok
c) check for FOS against overturning, sliding N/A
d) increase in SBC (limited to 25% for wind or seismic/ 100% for blast) N/A
e) spacing of piles (within group & inter-group) Ok
f) pile cut-off level Ok
g) load check conforming to pile capacity Ok
h) increase in pile capacities (limited to 50% for vertical & Ok
25% for lateral for wind/ seismic/ 50% for blast)
11 Projection of foundation outside battery limit is co-ordinated with Civil N/A
Department for under-ground piping, etc.
12 Ductile detailing requirements for reinforcement, wherever applicable. Ok
13 Internal co-ordination with all concerned departments. Ok

Date: 04.04.2020 Name & C. Malleswara


Signature Reddy