Saudi Aramco Inspection Checklist: Receiving Inspection of Positive Displacement Pumps SAIC-G-2009 30-Apr-17 Mech

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 18

SAUDI ARAMCO ID/PIEU - 30-Apr-2017 - REV. 2015.03.00 (Standards Cutoff - March 2015) Rev. 2015.03.

00 31-Mar-15
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
Receiving Inspection of Positive Displacement Pumps SAIC-G-2009 30-Apr-17 MECH-
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.

LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.

SCHEDULED INSPECTION DATE & TIME ACTUAL INSPECTION DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIME
SAUDI ARAMCO USE ONLY
SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER WORK PERMIT REQUIRED?

SAUDI ARAMCO INSPECTION LEVEL CONTRACTOR INSPECTION LEVEL

ITEM RE-INSP
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A
No. DATE

A. Document Verification

Final Disposition / Release Report (consisting manufacturing /test reports


Schedule "Q",
A1 as specified on each form SA-175) was reviewed / accepted by the
Att. III, Para. 3.22
Contractor, a copy is submitted to Saudi Aramco.

Final Disposition Report includes the following as a minimum:


a. Narrative details of Quality activities performed during
manufacturing and fabrication of the equipment or material.
b. Copies of SA approved waivers to SA’s requirements.
c. All SA-175 CONTRACTOR witnessed inspections.
Schedule "Q",
A2 d. Copies of supplier quality records as specified in SA-175.
Att. III, Para. 3.24
e. Copies of all NCR's with final dispositions and resolutions.
f. Outstanding punch list items from pre-shipment inspections.
g. Inspection / Shipping Release
Verify that all the requirements specified on the Saudi Aramco
Inspection Requirement form 175-311500 have been met.

Positive Displacement Pumps are designed per 31-SAMSS-009 (Verify SAES-G-006,


A3
Data Sheets & Disposition Reports for conformance). Para. 4.1

Materials exposed to a sour environment are in accordance with the 31-SAMSS-009,


A4
requirements of ISO 15156 Para. 2.13.1.9

Contract data are provided by Vendor as per the requirements of API -


675 para. 5.3 as follows
A) Drawings (API - 675 para. 5.3.2)
B) Technical Data (API -
675 para. 5.3.3) C)
31-SAMSS-009,
A5 Progress Reports (API - 675 para. 5.3.4)
before Section 1
D)Parts List and Recommended Spares (API - 675
para. 5.3.5) E) Installation, Operation,
Maintenance,and Technical Data Manuals (API - 675 para. 5.3.6)
F)Technical Data
Manuals (31-SAMSS-009 para. 5.3.7)

Pump types conform to applicable API 675 & Spec definitions:


A) Controlled volume pumps:
Reciprocating pumps where the precise volume control is provided by
varying effective stroke length. Such pumps are also known as
proportioning, chemical injection, dosing, or metering pumps. (API 675, 31-SAMSS-009
Para. 1.4.2) Section 1
A6 Positive Displacement Pumps (Centrifugal type) are prohibited. (See API 675)
B) Spec 31-SAMSS-009, along with Pump Data Sheet & PO, &
defines minimum mandatory requirments for positive displacement, Para. 1.1.1
controlled volume pumps of diaphragm & packed plunger types.
Diaphragm pumps using direct mechanical actuation are excluded from
Spec. 31-SAMSS-009. (31-SAMSS-009, Para. 1.1.1)

B. Pump Inspection

Saudi Aramco: Company General Use


Pump skid, pump, driver, auxiliary piping and other components are free Schedule "Q",
B1
from any physical damage. Att. IV, Para. 3.3

Material shipped separately are identified with securely affixed corrosion-


resistant metal tags indicating item & serial number of the equipment for
31-SAMSS-009
B2 which it is intended. In addition, crated quipment are shipped with
Section 1
duplicate packing lists, one inside and one on the outside of the shipping
container. (API 675, Para 4.4.3.6)

All alloy casings are provided with plugs of the same material as the 31-SAMSS-009,
B3
casing. Plastic plugs & varying metallurgy are prohibited. Para. 4.4.3.4

Saudi Aramco: Company General Use


SAUDI ARAMCO ID/PIEU - 30-Apr-2017 - REV. 2015.03.00 (Standards Cutoff - March 2015) Rev. 2015.03.00 31-Mar-15
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
Receiving Inspection of Positive Displacement Pumps SAIC-G-2009 30-Apr-17 MECH-
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.

Nameplate stampings (in units consistent with the data sheet):


a) Purchase Order number
b) Vendor’s name
c) The machine’s serial number
d) The machine’s size and type
e) Minimum and maximum allowable design limits and rating data
31-SAMSS-009
(including pressures, temperatures, speeds, and power)
Para. 2.14.3 &
B4 f) Maximum allowable working pressures and temperatures, and
API 675 Para
hydrostatic test pressures
2.14
g) Service
h) Pump mark number
i) Liquid pumped,
j) Pulsation damper charging pressure,
k) Lubricant,
l) Data of manufacturer and bearing numbers

In addition to the nameplate stamping, pump serial numbers are plainly & 31-SAMSS-009
B5
permanently marked on pump casing. (API 675 Par. 2.14.1) Section 1

Rotation arrows shall be cast in or attached to each major item of


rotating equipment in a readily visible location. Nameplates & rotation
31-SAMSS-009
B6 arrows (if attached) are of ANSI Standard Type 300 SS or of nickel-
Section 1
copper alloy (Monel or equivalent). Attachment pins are of the same
material. Welding is not permitted. (API 675, Par 2.14.2)

Pump skid's general arrangement conforms with the Pump P&ID.


P&ID No.
(NOTE: Perform walkthough of the pump and skid assembly using the
B7
Saudi Aramco approved P&ID. This activity may have to be re-scheduled
____________
for pumps & components that were dis-assembled.)

Castings are sound & generally free from porosity, hot tears, shrink
holes, blow holes, cracks, scale, blisters, & similar injurious defects per
31-SAMSS-009
B8 visual reqmts of MSS-SP-55. (API 675, Para. 2.13.2.1). Mould-parting fins Design
Section 1
& remains of gates and risers are chipped, filed or ground flush. See
Attachment 2 Table 1 & MSS-SP-55.

Flat-faced flanges are not acceptable for materials other than cast iron or 31-SAMSS-009,
B9
Ni-resist alloys. Para. 2.3.6.2
The actual pump internal relief valve setting is set between 110% and 31-SAMSS-009,
B10 Design
120% of the rated discharge pressure. Para. 2.7.1
A complete set of spare gaskets and O-rings are included with the 31-SAMSS-009,
B11
equipment when received at site. Para. 4.4.3.9
Anchor bolts are not be used to fasten machinery to the mounting plates, 31-SAMSS-009
B12
(API 675, Para. 3.3.5). Section 1

Unless otherwise specified, equipment will be installed outdoors in a


desert area with relative humidities from zero to 100% (condensing) and
ambient temperatures from 0°C to 50°C (32°F to 120°F). 31-SAMSS-009,
B13 Design
Commentary Note:Metal temperatures can reach 70°C when exposed to Para. 2.1.12
direct solar radiation.The equipment shall be designed to withstand these
conditions.

31-SAMSS-009,
B14 Pump is provided with volumetric air venting valve.
Para. 2.1.21
A diaphragm failure signaling system is provided on double diaphragm 31-SAMSS-009,
B15
pumps. Para. 2.5.5

Wake and natural frequency calculations performed on thermowells in


31-SAMSS-009,
B16 accordance with ASME PTC 19.3 Part 3. The insertion length shall satisfy
Para. 3.4.4.2
a wake to natural frequency ratio of 0.8.

Exposed shafts and shaft coupling are wrapped with waterproof, moldable
31-SAMSS-009,
B17 wax cloth or volatile-corrosion inhibitor paper. The seams are sealed with
before Section 1
oil proof adhesive tape.(API - 675 para. 4.4.3.7)

Flanged opening are provided with metal closure at least 5 mm thick with
elastomeric gasket and atleast four full diameter bolts. For studded 31-SAMSS-009,
B18
openings, all nuts needed for intended service are used to secure before Section 1
closures. (API -675 para. 4.4.3.3)

C. Mounting Plate

Baseplates, or pump frames, have provisions for bolting the complete unit 31-SAMSS-009
C1
rigidly to a foundation, (API 675, Para. 3.3.1). Section 1

Pumps with separate drivers are provided with continuous base plates 31-SAMSS-009
C2
under both pump and driver, (API 675, Para. 3.3.2). Section 1

Anchor bolts are not used to fasten machinery to the mounting plates. 31-SAMSS-009
C3
(API 675, Para. 3.3.5). Section 1

Mounting Plates Vendor has provided stainless steel shim packs ≥ 3 mm


31-SAMSS-009
C4 (1/8") thickness between equipment feet and mounting plates. All shim
Section 1
packs straddle the hold-down bolts, (API 675, Para. 3.3.6).

Jackscrews are provided for vertical adjustment of base plates on units > 31-SAMSS-009
C5
450 kgs (1000 lbs) in overall weight, (API 675, Para. 3.3.9). Section 1

Fully machined flat and parallel Mounting pads are provided for pump &
all drive train components. Pads are larger than the foot of the mounted 31-SAMSS-009
C6
equipment to allow leveling of baseplate without equipment removal (API Section 1
675 Par 3.3.1).

D Auxiliary Piping

Pipe nipples are Sch.160 min. seamless for sizes ≤ NPS 1 and Sch. 80 31-SAMSS-009
D1
min. for a size of NPS 1-1/2, (API 675, Para. 2.3.3.2). Section 1

The pipe nipple are provided with a welding neck or socket-weld flange, 31-SAMSS-009
D2
(API 675, Para. 2.3.3.3). Section 1

Auxiliary piping welded to CrMo alloy steel or 12% Cr steel components


31-SAMSS-009
D3 are of same material, except that CrMo alloy steel pipe may be substituted
Section 1
for 12% Cr steel pipe, API 675, Para, 2.13.4.5.2.

Saudi Aramco: Company General Use


SAUDI ARAMCO ID/PIEU - 30-Apr-2017 - REV. 2015.03.00 (Standards Cutoff - March 2015) Rev. 2015.03.00 31-Mar-15
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
Receiving Inspection of Positive Displacement Pumps SAIC-G-2009 30-Apr-17 MECH-
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
Material & joining methods (per Service) shall meet Attachment 2, 01-SAMMS-017,
D4
Appendix A, Table A-1 (Mat'l Selection & Joining Methods) Para. 1.2

The exterior of all carbon steel piping components are supplied with a
01-SAMMS-017,
D5 protectivecoating as specified in SAES-H-001 and SAES-H-101.
Section 11
Threads / Open ends for field welding and connecting,not painted.

A block valve, 3/4-inch NPS minimum, is installed in each instrument


take-off connection & located close as feasible to line, vessel, or 01-SAMMS-017,
D6
mechanical equipment. Exception:Thermocouples & thermometers are Para. 7.3.6
excluded from 3/4-inch NPS minimum reqmt.

The minimum size of auxiliary piping and tubing for mechanical equipment
01-SAMSS-017,
D7 are 1/2-inch NPS with the exception of air compressor packages which is
Para. 6.2
3/8-inch NPS.

All piping, tubing and valves are adequately supported and fastened in a
manner which facilitates replacement, and prevents vibration, and 01-SAMSS-017,
D8
damage due to incidental loads which may occur during operation or Para. 6.3
maintenance work.

Piping of 1-½ in NPS or smaller was provided with firm, welded gussets or
braces in two perpendicular planes at connections between machinery or 01-SAMSS-017,
D9
auxiliary equipment & first block (root) valve. See AB-036521 for valve Para. 6.4
bracing. See Attachment 2.

All piping systems are provided with vent valves at high points and drain
valves at low points. Horizontal runs in pressure piping are sloped
01-SAMSS-017,
D10 gradually towards drain points. Minimum slope of drain lines shall be 1:50.
Para. 6.7
Note: Gusset welding distortion (AB-036521) often results in drainage
piping sloped upwards (unacceptable).

Auxiliary piping are laid out to minimize interference with access to


01-SAMSS-017,
D11 components or appurtenances as required for routine operation and
Para. 6.5
maintenance.

Flanged or union connections (where permitted) are provided close to


01-SAMSS-017,
D12 equipment & throughout piping systems to allow complete removal of
Para. 6.6
piping, & removal or assembly of the equipment

Unions are not permitted in pressurized lines carrying flammable or toxic


01-SAMSS-017,
D13 fluids unless they are required for removal or assembly of the equipment
Para. 7.4.1
and cannot otherwise be substituted by flanges.

When use of unions are permitted, they shall not be installed in the pipe
section between the pipe run and the root valve. 01-SAMSS-017,
D14
Note: Use of any unions requires approval from the Chairman of Piping Para. 7.4.3
Standards Committee, Consulting Services Department.

01-SAMSS-017,
D15 Bolt holes of flanges are straddle vertical &horizontal center lines.
Para. 8.1

Pipe bends have surfaces free of cracks and buckles. Flattening of the
cross section of bends does not exceed 8% of the nominal pipe diameter. 01-SAMSS-017,
D16
Bending procedures and required heat treatment are in accordance with Para. 8.2
ASME B31.3.

01-SAMSS-017,
D17 Miter fittings such as miter elbows or miter bends are prohibited.
Para. 6.9
01-SAMSS-017,
D18 Flanges mating to cast iron flanges are flat faced.
Para. 7.6.2

Gasket contact surface do not have mechanical or corrosion damage.


31-SAMSS-009
D19 Evaluate Gasket Sealing Surfaces per ASME B16.5 or other criteria. See
Section 1
Attachment 3. (API 675, Para. 2.3.7)

01-SAMSS-017,
D20 Threaded connections are conformed to ASME B1.20.1 Pipe Threads
Para. 7.7.3
01-SAMSS-017,
D21 For throttling service, globe or needle valves are used.
Para. 7.3.5
Instrument valves serving such protected areas as panels & gauge boards 01-SAMSS-017,
D22
may be 1/2-inch instrument type valves. Para. 7.3.7
REMARKS:

REFERENCE DOCUMENTS:
1. SAES-G-006, Positive Displacement Pumps – Controlled Volume, (12 November 2013)
2. SAES-B-053 -- Machine Safety Guarding, Elevators, Escalators, and Conveyors, (7 October 2012)
3. 31-SAMSS-009 -- Positive Displacement Pumps, Controlled Volume Type (12 November 2013)
4. 01-SAMSS-017 -- Auxiliary Piping For Mechanical Equipment, (13 October 2010)
5. Schedule "Q" -- Project Quality Requirements
6. API 675 -- Positive Displacement Pumps-Controlled Volume, (October 1994 Edition)

ATTACHMENTS:
ATTACHMENT 1 - SAES-G-006 & 31-SAMSS-009 POSITIVE DISPLACEMENT PUMP REQUIREMENTS
ATTACHMENT 2 - MISCELLANEOUS REQMTS (INSPECTOR'S CHECKLIST, SASDs, AUXILLIARY PIPING, etc)
ATTACHMENT 3 - DAMAGE ASSESSMENT FOR FLANGE FACINGS (CRITERIA & TECHNIQUE)

Contractor / Third-Party Saudi Aramco


Construction Representative* PMT Representative
Work is Complete and Ready for Inspection: T&I Witnessed QC Record Reviewed Work Verified
Name, Initials and Date: Name, Initials and Date:

QC Inspector PID Representative


Performed Inspection Work / Rework May Proceed T&I Witnessed QC Record Reviewed Work Verified
Name, Initials and Date: Name, Initials and Date:

QC Supervisor Proponent and Others


Quality Record Approved: T&I Witnessed QC Record Reviewed Work Verified
Name, Organization,
Name, Sign and Date:
Initials and Date:

*Person Responsible for Completion of Quality Work / Test Y = YES N = NO F = FAILED

Saudi Aramco: Company General Use


SAUDI ARAMCO ID/PIEU - 30-Apr-2017 - REV. 2015.03.00 (Standards Cutoff - March 2015) Rev. 2015.03.00 31-Mar-15
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
Receiving Inspection of Positive Displacement Pumps SAIC-G-2009 30-Apr-17 MECH-
ATTACHMENT 1 - SAES-G-006 & 31-SAMSS-009 POSITIVE DISPLACEMENT PUMP REQMTS

Saudi Aramco: Company General Use


Saudi Aramco: Company General Use
Saudi Aramco: Company General Use
Saudi Aramco: Company General Use
Saudi Aramco: Company General Use
Saudi Aramco: Company General Use
SAUDI ARAMCO ID/PIEU - 30-Apr-2017 - REV. 2015.03.00 (Standards Cutoff - March 2015) Rev. 2015.03.00 31-Mar-15
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
Receiving Inspection of Positive Displacement Pumps SAIC-G-2009 30-Apr-17 MECH-
ATTACHMENT 2 - MISC. REQMTS (API 675 APPENDIX C, SASDs, AUXILLIARY PIPING, etc)

Saudi Aramco: Company General Use


Saudi Aramco: Company General Use
Saudi Aramco: Company General Use
Saudi Aramco: Company General Use
Saudi Aramco: Company General Use
SAUDI ARAMCO ID/PIEU - 30-Apr-2017 - REV. 2015.03.00 (Standards Cutoff - March 2015) Rev. 2015.03.00 31-Mar-15
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
Receiving Inspection of Positive Displacement Pumps SAIC-G-2009 30-Apr-17 MECH-
ATTACHMENT 3 - DAMAGE ASSESSMENT FOR FLANGE FACINGS (CRITERIA & TECHNIQUE)
ASME B16.5 (Table 3) & B16.47 (Table 16) for Raised Face (RF) FLANGES

TABLE 16 APPLIES TO ASME B16.47 (SA allows


limited use of ASME B16.47 Flgs, or Class 75)

USE METRIC CONVERSION BELOW


Metric Conversions: .06 = 1.5mm, .12 = 3mm, .18 = 4.5mm, .25 = 6mm, .28 = 7mm, .31 = 8mm, .38 = 10mm,
.50 = 12mm, .56 = 14mm, .62 = 16mm
ASME B16.5 & B16.47 (RFWN FLANGES): Flange Facing Finish Imperfections (5-STEP Evaluation Criteria).
1. Imperfections* in the flange facing finish shall not exceed the dimensions shown in Table 3 (B16.5) & Table 16 (B16.47).
2. Adjacent imperfections are separated by a distance of at least four times maximum radial projection*.
3. *A radial projection shall be measured by the difference between an outer radius & an inner radius encompassing the
imperfection where the radii are struck from the centerline of the bore.
4. Imperfections less than half the depth* of the serrations shall not be considered cause for rejection. Note: Serration Depth
varies from 125-250 microns (.003-.006 inches). This is easily measured with a sharp point pit gauge or Press-O-Film Tape (if disputed).
5. Protrusions above the serrations are not permitted. (Repair or replacement is required) ... Regardless of Location!
* Scratches, nicks, gouges, burrs, cuts, & other mechanical damage to serration finish in gasket sealing areas are carefully evaluated to all
criteria listed above. Also, use the 4-step Inspection Technique listed below shall be used to identify the "Sealing area".
ASME B16.5 & B16.47 (RFWN FLG): Determine Location of Sealing Area (4-Step Technique).
NOTE: Imperfections exceeding tables above may be rejected regardless of location (SA Inspector judgement call)
NOTE: Inspectors can accept certain types of damage "IF" located outside of sealing area & protrusion = zero.
1. Center the gasket on the flange & match the gasket inside & outside diameters onto the flange sealing surface.
2. Compensate for Gasket movement within bolt holes (.125" or 3.2 mm). See illustration. Sealing areas can vary 3.2 mm.
EVALUATION: Any Protrusions (whether inside the sealing area or not) are unacceptable. Other damages (listed above)
that exceed the Table 3 Criteria are relevant & rejectable if the damage falls within "SEALING AREA + 3.2 mm".
4. Report flange damage to SA (NCR is not required for isolated damage. Issue NCR for damages due to gross mishandling
TYPICAL SPIRAL WOUND GASKET & RF FLANGE (TOP VIEW OR CROSS SECTION) ... NOTE THAT SEALING CAN VARY BY 3.2mm
1. Find gasket inside diameter.
2. Find gasket outside diameter.
Note that "gaskets" can shift/move
up to 3.2 mm (flange bolt/bolthole
tolerances). Gasket centering ring
OD also has a tolerance. These
tolerances allow installation.

Saudi Aramco: Company General Use


MAKE THE RIGHT CALL!

FIELD REPAIRS ARE PROHIBITED. ONLY APPROVED COMPANIES/MACHINISTS REPAIR FLANGE FACINGS
ATTACHMENT 2 - DAMAGE ASSESSMENT FOR FLANGE FACINGS (CRITERIA & TECHNIQUE)
ASME B16.5 & B16.47 TABLES DO NOT APPLY FOR RING JOINT (RJ) FLANGES.
Note 1: The Illustration below is an Octagonal Ring Groove. Six sides "seal" &
two sides are exposed. Note 2: The two exposed sides (octagonal ring gasket)
may be color coded, but not the 6 sealing sides.
FIELD REPAIRS ARE PROHIBITED. ONLY APPROVED COMPANIES & MACHINISTS REPAIR RJ GROOVES.
ASSESS ASME B16.5 RING JOINT (RJ) FLANGE SEALING SURFACE DAMAGE

ASME B16.5 & B16.47 Ring Joint Groove Imperfections (Evaluation & Acceptance Criteria)
1. Side wall surface finish of ring joint gasket groove shall not exceed 63 microns (essentially machined smooth, .06 mm).
Note: This can be quickly & easily determined with Press-O-Film tape (used in Coating) if disputed. Almost always, excess coating or rust
due to inadequate cleaning (not using power brushing tools) or mechanical damage is cause of rejection.
2. Mechanical damage & groove surface deformation/protrusion is not permitted. (Remachine repair or replace flg)
Note: Scratches, nicks, gouges, burrs, cuts, & other mechanical damage to ring joint groove finish are evaluated per Criteria # 1.
Note: Most commonly, damage occurs to the exposed corner & facing (located as defined by the "F" dimension above).
Note: API Flanges specify a 45 degree "1.5 mm break" on the corners ... ASME B16.5 & B16.47 do not specify such a "break"
3. Lubricant is kept from sealing surfaces and properly limited to application on bolting.
4. Soft Iron octagonal ring gaskets installed shall have color coding paint applied to two outside visible sides only.
5. Rust is not allowed on assembled flanged surfaces. Corrosive pitting is rejected before installation. See 02-SAMSS-011 reqmts.
02-SAMSS-011 (Section 10) Flange Corrosion Protection Requirements (Flange Serviceability Issues)
1. Finish-machined and tested flanges shall be coated overall with a protective finish that does not hide markings.
2. Coatings shall be capable of protecting against corrosion in a marine environment for 12 months.
3. An additional separate strippable coating may be applied over the welding ends and sealing surfaces. The strippable coating need not be
weldable but shall be capable of easy removal without special tools or solvents, and shall not leave residue that will interfere with welding
or gasket seating. Examples: filled highbuild vinyl or urethane or PVC. DEMONSTRATE an effective Pre-Cleaning (Stripping) Method.

Saudi Aramco: Company General Use


4. The Manufacturer may apply tape to the welding ends and sealing surfaces then seal the tape with a protective coating. Tape shall be
easily removed and leave no residue that interferes with gasket seating. Verify tape is removed and no residue build-ups remain.
5. All flanges shall be protected from mechanical damage. Sealing faces shall be protected with suitable wood or plastic or metal covers.
Flanges shall be packaged in steel-banded wooden crates or secured to skids. Verify damages against reqmts (NCR, root cause).
Gasket acceptance criteria is per ASME B16.20 – Available on SA Checklist

Saudi Aramco: Company General Use