Planned Preventive Maintenance Task Sheet: PPM No PPM Equipment Cooling Tower Asset Code Frequency Monthly
Planned Preventive Maintenance Task Sheet: PPM No PPM Equipment Cooling Tower Asset Code Frequency Monthly
Planned Preventive Maintenance Task Sheet: PPM No PPM Equipment Cooling Tower Asset Code Frequency Monthly
PPM No PPM
Equipment Cooling Tower Asset code Frequency Monthly
Equipment Location & Details
Make
Ensure power supply to the equipment is ISOLATED and strictly follow the lock out/ tag out procedures.
Use appropriate PPE.
Use appropriate access ladders.
Ensure electrical tools are well insulated and temporary power cables are routed in a proper way to avoid
electrocution and trip hazard.
Never open A.H.U.access doors while the unit is ON.
Ensure no loose clothes while adjusting the drive belts, fans and rotator parts.
Clean any oil spillage immediately.
Ensure a stand-by person to work along with you if the equipment is located in a remote area i.e. roof, enclosed
room etc.
Ensure the equipment door can be opened from inside else ensure a stand by person for assistance.
Ensure all the above points are ticked and implemented.
Maintenance Plan
Check the chemical level in dozing tanks, clean the foot valve, clean the suction and delivery tubing, open the
bleed off valve and make sure dozing is proper.
Check operation of the bleed off solenoids.
Wash or clean the fins properly.
Check for any unusual noise and vibration.
Lubricate where ever required.
Check the float valves, ball valves, level switches and float switches for proper functioning.
Make sure the drain balancing pipes are properly inserted into the socket.
Check and ensure the balancing valves are fully opened and the water is balancing properly.
Job Information
Date: Consumables
Started Time: Description
Completed Time:
Total Hours:
Tech’s Name /
Sign:
Supervisor’s
Sign: