Professional Documents
Culture Documents
Field Tests On Pile-Supported Embankments Over Soft Ground: R. P. Chen Z. Z. Xu Y. M. Chen D. S. Ling and B. Zhu
Field Tests On Pile-Supported Embankments Over Soft Ground: R. P. Chen Z. Z. Xu Y. M. Chen D. S. Ling and B. Zhu
Abstract: When designing embankments over soft soils, geotechnical engineers face many challenges. These include potential bearing
failure, intolerable settlement, and global or local instability. Pile-supported embankments have been emerged as an effective alternative
successfully adopted worldwide to solve these problems. This paper focuses on three cases in which pile-supported embankments were
Downloaded from ascelibrary.org by Tufts University on 03/25/18. Copyright ASCE. For personal use only; all rights reserved.
used for constructing highways in the eastern coastal region of China. Each case provides a description of the soil profile, construction
procedure, and field monitoring of the settlements, earth pressures, and pore-water pressures. Field monitored data from contact pressures
acting on the piles and the soils, to the settlements of the piles and the soils are reported and discussed. The development of the earth
pressures both on the piles and the soils shows that there was a significant soil arching in the embankment, and the measured earth
pressures acting on the piles are much higher than that acting on the soils between the piles. The measured differential settlements between
the piles and the soils are small. The pore-water pressures are not significant compared to the embankment loads. Most pore-water
pressure dissipated after the complete of filling. The measurements have proven the effectiveness of this technique in reducing total and
differential settlements. Finally, the available design standards and approaches are verified by three cases.
DOI: 10.1061/共ASCE兲GT.1943-5606.0000295
CE Database subject headings: Piles; Embankments; Field tests; Earth pressure; Settlement; Case studies; Soft soils.
Author keywords: Pile-supported embankment; Field test; Earth pressure; Settlement; Case studies.
Introduction project in the north of St. Paul in Brazil 共Alzamora et al. 2000兲,
and the highway construction in Netherlands 共American Associa-
Compared to the traditional soft soil improvement measures, pile- tion of State Highway Officials/Federal Highway Administration
supported embankments provide an economic and effective solu- 2002兲. The first documented application in China was the Hang-
tion for embankment constructed over soft ground. This technique zhou to Ningbo highway widening project 共Jia et al. 2003兲. Then
has many advantages, which are rapid construction, small lateral it was used in many other highways with the recent economic
deformation, and easily controlled settlements. It spreads quickly boom in China 共Liu et al. 2007兲.
around the world, for example, the railway widening project at However, the interactions among piles, pile caps, foundation
Stansted airport in London 共Jones et al. 1990兲, the retaining wall soils, and embankment fills are complex 共Chen et al. 2008b兲.
Under the influence of fill weight, the embankment fills between
1
Professor, Key Laboratory of Soft Soils and Geoenvironmental En- piles have a tendency to move downward due to the larger settle-
gineering of Ministry of Education, Dept. of Civil Engineering, Zhejiang ment of soft foundation soil between piles. The movement of the
Univ., 388 Yuhangtang Rd., Hangzhou, 310058, China. E-mail: chenrp@
embankment fills is restrained by shear resistance generated in the
zju.edu.cn
2
Doctor Candidate, Key Laboratory of Soft Soils and Geoenviron-
fills. These shear resistance reduce the pressure on the foundation
mental Engineering of Ministry of Education, Dept. of Civil Engineering, soil but increase the pressure on the pile caps. This load transfer
Zhejiang Univ., 388 Yuhangtang Rd., Hangzhou, 310058, China. E-mail: mechanism was termed the soil arching effect by Terzaghi 共1943兲.
supbaobao@163.com Many researchers established different kinds of model tests to
3
Professor, Key Laboratory of Soft Soils and Geoenvironmental En- study the piled embankments 共Hewlett and Randolph 1988; Low
gineering of Ministry of Education, Dept. of Civil Engineering, Zhejiang et al. 1994; Chew et al. 2004; Chen et al. 2008a兲. These model
Univ., 388 Yuhangtang Rd., Hangzhou, 310058, China 共corresponding tests mainly focused on the soil arching in the embankment. In
author兲. E-mail: chenyunmin@zju.edu.cn
4 reality, the mechanisms of load transfer are much more compli-
Professor, Key Laboratory of Soft Soils and Geoenvironmental
Engineering of Ministry of Education, Dept. of Civil Engineering, cated than just the soil arching. The expanded applications of the
Zhejiang Univ., 388 Yuhangtang Rd., Hangzhou, 310058, China. E-mail: piled embankments demand a thorough understanding of the in-
Lingdaosheng@zju.edu.cn teraction between the piles, the soils, and the embankment. A
5
Associate Professor, Key Laboratory of Soft Soils and Geoenviron- closed-form solution has been developed for the interaction be-
mental Engineering of Ministry of Education, Dept. of Civil Engineering, tween the piles, the soil, and the embankment 共Chen et al. 2008b兲,
Zhejiang Univ., 388 Yuhangtang Rd., Hangzhou, 310058, China. E-mail: but no geosynthetic reinforcement was considered and the em-
binzhu@zju.edu.cn bankment fill, the foundation soil, and the piles were assumed to
Note. This manuscript was submitted on October 2, 2008; approved
deform one-dimensionally. Numerical methods were frequently
on November 20, 2009; published online on November 25, 2009. Discus-
sion period open until November 1, 2010; separate discussions must be used to investigate the load transfer mechanisms 共Han and Gabr
submitted for individual papers. This paper is part of the Journal of 2002; Pham et al. 2004; Huang et al. 2006兲. Even though numeri-
Geotechnical and Geoenvironmental Engineering, Vol. 136, No. 6, June cal analyzes are effective for investigating the interactions in the
1, 2010. ©ASCE, ISSN 1090-0241/2010/6-777–785/$25.00. pile-supported embankments, they are generally time-consuming
and difficult to be adopted for routine use in practice. There are in three sections of the embankment, which were section of
very few standards and approaches for the design of piled em- K18+ 223 共defined as G1 section兲, section of K18+ 253 共defined
bankments. British Standard BS8006 共British Standard 1995兲 uses as G2 section兲, and section of K18+ 283 共defined as G3 section兲,
Marston’s formula to estimate the vertical stress on the top of the respectively. The detail information of these test sections are
piles. Moreover, the effects of the embankment fill material prop- listed in Table 1.
Downloaded from ascelibrary.org by Tufts University on 03/25/18. Copyright ASCE. For personal use only; all rights reserved.
smaller than those measured on the piles. It can be seen that the
piles carried the majority of the embankment loads and so rela-
tively the soft soil beneath the embankment was subjected a much
smaller compressive load. This implies that there was a load
transfer from the soil onto the pile as a result of soil arching in the
Fig. 1. Cross section and plan views of the embankment, the field embankment fill. The rapid steadility of the earth pressures both
instrumentation, and the arrangement of piles in TJ highway on the piles and soils is attributed to the fact that the piles were
founded on firm pebble layer. Though there is no pore-water pres-
sure measurement, the steady earth pressures, and the settlements
Field Measurements which will be discussed later, indicate the complete of the soil
consolidation after filling. The degree of the soil arching may be
Earth Pressures on Pile Cap and Soil Surface quantified using the load share ratio, n, which is defined as the
Fig. 2 shows the average earth pressures acting on the pile caps load on the pile cap divided by the total weight of the embank-
and the soil surfaces measured by the earth pressure cells which ment fill over the total area
were defined as P p and Ps, respectively. During the first 20 days,
the embankment reached 1.5 m, while the earth pressure on the P p · Ac
pile caps and the soil surfaces increased with the height of the n= 共1兲
␥1 · H · Sa · Sa
embankment fill. The earth pressures on the pile caps increased
sharply with the embankment height. However, the earth pres- where P p = earth pressure on the pile cap; Ac = area of pile cap;
sures reached peaks around 25–60 days, then decreased to rela- ␥1 = unit weight of embankment fill; H = embankment height; and
tive steadily values about 80 days. The decrease of the earth Sa = pile spacing. The load share ratio lies between 0% and 100%.
pressures on the soils is due to the consolidation of the soils and The measured load share ratio were 82.6% in G1 section, 71.2%
the soil arching developed in the fill. When the fill height reached in G2 section, and 87.6% in G3 section at the end of monitoring.
6.0 m at the end of the embankment construction, the pressures on The height of the fill should be high enough so that the soil
the top of caps in G1 and G3 sections were about 380 kPa, while arching can be fully developed. This height is named as the criti-
that measured in G2 section was 288 kPa. The lower steady value cal height. Hewlett and Randolph 共1988兲 pointed that when the
of P p in G2 section attributes to the larger net spacing of caps. fill height is less than the net spacing between the two near edges
However, the pressures on the soil between the piles were far of the piles, there is no soil arching. In Nordic handbook 共NGG
2002兲, it is suggested that the height of the embankment should
be at least 1.2 times as large as the distance between the pile caps.
In Fig. 2, the fill height at which the earth pressures on soil
surface reaches the maximum value can be regarded as the critical
height. The loads of the subsequent filling after the critical height
were transferred to the piles. The critical heights were about 1.3–
1.5 m in G1 section, 1.5–1.8 m in G2 section, and 1.0–1.3 m in
G3 section, respectively. Therefore, the arching height is about
1.1–1.3 times larger than the net cap spacing in these test sections
共see Table 1兲.
Settlements
Fig. 3 shows the measured settlements both on the pile cap 共mea-
sured by surface settlement marker S1兲 and on the soil surface
between the piles 共measured by S2兲. The settlements increased as
the fill height increased. Most part of the total settlements oc-
curred during the embankment construction, and the subsequent
Fig. 2. Earth pressures measured in test sections in TJ highway settlements due to soil consolidation were small. This is mainly
because the piles were founded on firm pebble layer. The mea- is 0.181 m2. Hence, the compression stiffness of the Y-shaped pile
sured total settlements in G2 section were larger than those mea- is 2.5 times that of the tube pile. Under the embankment loads,
sured in other sections, while the data obtained in G3 section the compression of the pile is in millimeter order. So those two
Downloaded from ascelibrary.org by Tufts University on 03/25/18. Copyright ASCE. For personal use only; all rights reserved.
were smallest. It indicates that the pile spacing has significant types of piles can be considered as rigid piles when they are used
impact on the settlements. At the end of the monitoring, the mea- in the embankment.
sured maximum settlements were 72 and 82 mm at the pile cap A test embankment totally 50 m in length 共K25+ 090– K25
and on the soil surface, respectively. + 140兲 were chosen to study the field performance of the piled
In this paper, differential settlement is defined as the difference embankment. There are five test sections, which were section of
in settlement at the top of pile cap and on the soil surface. Similar
K25+ 100 共G4兲, section of K25+ 135 共G5兲, section of K24+ 970
to the total settlements, the differential settlements also increased
共Y1兲, section of K24+ 995 共Y2兲, and section of K25+ 025 共Y3兲.
with the increase of the height of the embankment. But there was
The G4 and G5 sections were improved by prestressed tube piles,
no obvious increase in differential settlement after the construc-
tion of the embankment. The measured maximum differential and Y1, Y2, and Y3 sections were improved by Y-shaped piles.
settlement was about 10 mm. Thus, it is clearly proved that the Table 3 shows the details of the test sections.
needed differential settlement between the pile and soils for the
full development of the soil arching is small when the piles are Site Conditions
embedded in the firm substratum.
There is a thin crust 共ML兲 about 2.5–3.0 m thick under the
ground. The second layer is CL with a thickness of 2.0–4.0 m.
Field Test on Piled Embankment with Soft Below it is a very soft CL layer about 15.0–16.5 m thick. These
Substratum in SJZA Highway two layers have high water content and compressibility, which are
the main soft soils layer. The underlying soil is composed of ML
General Information of Project with a thickness of 18.5–23.2 m. The groundwater level was at a
depth of ⫺0.3 m. The main index and strength properties of the
The total length of the highway is about 89 km. Most of the soils under the test embankment are shown in Table 4.
embankments from K0 to K53 were constructed over deep soft
soils. The thickness of the soft soils is about 30 m. The pre-
stressed tube piles, manufactured in the factory, are widely used Test Setup and Instrument
for their good quality and high strength. However, the producing
The embankment had a crown width of 35 m. The side slope was
cost of prestressed tube pile is expensive. Moreover, it is difficult
1 V to 1.5 H. The fill material consisted mainly of crushed rock
to construct the embankment dealing with tube piles for its varia-
mixed with clayey soil with friction angle of 35°, and an average
tion of pile length in transitional embankment section. As a result,
a new type of pile whose cross section likes the letter Y was also unit weight of 22 kN/ m3. Fig. 4 illustrates the cross section and
used in this project. The construction technique of Y-shaped pile plan views of the test sections, the arrangement of the piles, and
is similar to that of casing pile. It is more economical than the the instruments.
prestressed tube pile and has many advantages, such as larger All piles were arranged in a triangular pattern and were not
surface area, higher bearing capacity, and lower producing cost. founded on the firm layer. The tube piles had square caps on the
Typically the elastic modulus of the concrete of the Y-shaped pile pile heads, whereas the Y-shaped piles had round cap. Detail in-
is 25 GPa, while that of prestressed tube pile is 35 GPa. The cross formation of piles and pile caps were provided in Table 3. The
area of the tube pile is 0.0628 m2, while that of the Y-shaped pile reinforcement consisted of a biaxial polypropylene grid, which
Field Measurements
was laid in one layer on the top of the pile cap. The tensile
stiffness in longitudinal and transverse directions of the geogrid
was 1,500 kN/m.
Earth pressure cells 共E10–E23兲 were placed in the center of
embankment to measure the vertical loads shared by the piles and
the surrounding soils. Two settlement plates were installed in each
test section. The settlement plates were installed both on the top
of the pile caps 共S3 and S5兲 and on the surrounding soils 共S4 and
S6兲. Besides, two settlement gauges 共SS1 and SS2兲 were installed
to a depth of 21 m near the center line of the embankment to
measure the settlements of the substratum.
The instruments were set up from July 15 to August 30 in
2003. In late October, the pile caps were cast in the field after the
installation of the piles, and the observation started from the be- Fig. 6. Earth pressures and pore-water pressure measured in
ginning of the embankment construction in November and lasted Y-shaped pile sections in SJZA highway
eter; L = pile length; Sa = pile spacing; a0 = pile cap width or pile cap
diameter; ␦ = wall thickness of tube pile; mv = coefficient of volume com-
pressibility of soft soil; ␥ = unit weight of soft soil; 关 = 共1
p⬘c /⬘v = 共Cc · a/H兲2 共2兲 − sin ⬘兲tan ⬘兴 = coefficient of skin friction; ␦u = ultimate relative dis-
For H ⬎ 1.4共Sa − a兲 the distributed load on and the force in the soil placement of soils around pile; qu = ultimate resistance at pile toe; and
␦ p = ultimate relative displacement of soils at pile toe.
reinforcement is
1.4Sa · f fs · ␥1共Sa − a兲
WT = 关S2a − a2共p⬘c /⬘v兲兴 共3兲 and German criterion兲 are included for comparisons. These four
S2a − a2
methods give a wide range of prediction of the load share ratio.
where H = embankment height; Sa = pile spacing; a = pile cap BS8006 has a great difference in prediction of the load share ratio
width; Cc = pile type factor; ␥1 = unit weight of embankment fill; compared to the measured values. When the load share ratios are
f fs = partial coefficient for soil load; = strain; and WT=distributed low, BS8006 underestimates the load share ratio. And the German
vertical load acting on the reinforcement. DBGEO design method predicts much higher values of the load
Nordic handbook suggested that the soil arching is calculated share ratio. On the other hand, predictions using the design
by a soil wedge model with a top angle of 30°. The weight of the method in Nordic handbook and the method proposed by Chen
soil wedge, W2D, according to Nordic handbook is et al. 共2008b兲 are consistent with field measurements.
The settlements on the top of the pile caps 共S p兲, the settlements
共Sa − a兲2
W2D = · ␥d = 0.93共Sa − a兲2 · ␥d 共4兲 on the foundation soils between the piles 共Ss兲, and the settlements
4 tan 15° of the substratum 共Sd兲 were pictured in Fig. 10. The prediction of
The weight of the soil in three dimensions, W3D, is calculated as the settlements using the analytical method proposed by Chen et
follows: al. 共2008b兲 is in good agreement with the measured values in TJ
highway in which no geosynthetics was used, and overestimates
1 + Sa/a the settlements in SJZA highway in which one layer geogrid with
W3D = · W2D 共5兲
2 the stiffness of 1,500 kN/m was used.
The influences of geosynthetics on the performance of piled
where ␥d = unit weight of embankment fill per meter in depth.
embankment are concerned by researchers 共Han and Gabr 2002;
However, German DBGEO criterion is based on the method
Pham et al. 2004; Chen et al. 2008a,b兲. By using FLAC program
of Hewlett and Randolph 共1988兲 considering soil arching as a
series of domes of hemispherical shape supported by piles. The
average pressure applied on the reinforcement, ZO,k, is calculated
as follows:
冉
ZO,k = 1 ␥1 +
q0
H
冊
共1 + H2c 2兲− + Hc
4
冉
1 + H2c 2
冊 −
Fig. 10. Comparison between the measured settlements and the com- Acknowledgments
puted values by Chen’s method
The work was supported by the National Natural Science Foun-
dation of China 共Project No. 50878193兲, and Program for New
共finite difference method兲, Han and Gabr 共2002兲 conducted nu- Century Excellent Talents in University 共NCET兲 for financial
merical study to investigate the effect of geosynthetics stiffness support.
on the settlements of embankment. It was found that the geosyn-
thetics with the stiffness of 1,500 kN/m will decrease the maxi-
mum settlement about 22% and maximum settlement about 21%. Notation
By using PLAXIS program 共finite element method兲, Pham et al.
共2004兲 conducted 2D plane-strain numerical analyzes on geopier The following symbols are used in this paper:
embankment. The differences of different settlements and stress Ac ⫽ area of pile cap;
concentration ratio are only about 1–5% when the stiffness of a ⫽ pile cap width;
geosynthetics ranges from 0 to 100,000 lb/ft. Hence, from nu- a0 ⫽ pile cap width or pile cap diameter;
merical studies, the maximum influence of the geosynthetics with Cc ⫽ pile type factor;
tensile stiffness of 1,500 kN/m on settlement and load share ratio c⬘ ⫽ effective cohesion;
is less than 22%. Hence, this accounts for the overestimation of D ⫽ pile diameter 共d兲 or pile cap width 共a兲;
settlements in SJZA highway by Chen’s method. The influence of d ⫽ pile diameter;
geosynthetics stiffness on the settlement is more significant than d0 ⫽ pile diameter or equivalent pile diameter;
that of load share ratio. e0 ⫽ void ratio;
f fs ⫽ partial coefficient for soil load;
H ⫽ embankment height;
Conclusion Hc ⫽ critical height;
I p ⫽ plasticity index;
This paper presents three cases of pile-supported embankments K p ⫽ coefficient of passive earth pressure;
over soft soils in two highways. Based on the results of field kh ⫽ coefficient of permeability in horizontal direction;
monitoring of embankment settlements, earth pressures on piles kv ⫽ coefficient of permeability in vertical direction;
and on soils, and pore-water pressures, the following conclusions L ⫽ pile length;
can be drawn: mv ⫽ coefficient of volume compressibility;
1. The soil arching in the embankment has been observed from n ⫽ load share ratio of pile;
the measurement of earth pressures on pile caps and on soil P p ⫽ pressure applied on the pile cap;
surface. It reduces the loads on soft soils between piles and Ps ⫽ pressure applied on the soil surface;
distributes the embankment loads in a more efficient way to q0 ⫽ surcharge on the embankment;
the top of the pile caps. According to the field measurement Sa ⫽ pile spacing;
of earth pressures, the arching height is 1.0–1.5 times the net Sd ⫽ substratum settlement;
pile cap spacing; Smax ⫽ maximum pile spacing;
2. The load share ratios are in the range of 61.4–89.6%. The S p ⫽ settlement on the foundation soil;
load share ratios from sections improved by tube piles are Ss ⫽ settlement on the top of the pile cap;
much smaller than those from sections improved by W ⫽ water content;
Y-shaped piles. The increase of net cap spacing tends to de- WT ⫽ distributed vertical load acting on the reinforcement;
crease the load share ratio; W2D ⫽ weight of the soil wedge in two dimensions;
3. The measured excess pore-water pressures were small and W3D ⫽ weight of the soil wedge in three dimensions;
dissipated fast during embankment filling. At the end of ␥ ⫽ unit weight of foundation soils;
monitoring 共200 days after the complete of filling兲, the pore- ␥1 ⫽ unit weight of embankment fill;
water pressures dissipated almost completely; ␥d ⫽ unit weight of embankment fill per meter in depth;
4. The substratum settlements count for 50–60% of the total ⬘ ⫽ effective friction angle;
settlements when the piles do not found on firm substratum. ⫽ strain; and
The maximum differential settlements are about 10 mm ZO,k ⫽ average pressure applied on the reinforcement.
162.
Liu, H. L., Ng, C. W. W., and Fei, K. 共2007兲. “Performance of geogrid-
Chen, R. P., Chen, Y. M., Han, J., and Xu, Z. Z. 共2008b兲. “A theoretical
reinforced and pile-supported highway embankment over soft clay:
solution for pile-supported embankments on soft soils under one-
dimensional compression.” Can. Geotech. J., 45, 611–623. Case study.” J. Geotech. Geoenviron. Eng., 133, 1483–1493.
Chen, Y. M., Cao, W. P., and Chen, R. P. 共2008a兲. “An experimental Low, B. K., Tang, S. K., and Choa, V. 共1994兲. “Arching in piled embank-
investigation of soil arching within basal reinforced and unreinforced ments.” J. Geotech. Geoenviron. Eng., 120, 1917–1938.
piled embankments.” Geotext. Geomembr., 26, 164–174. NGG. 共2002兲. Nordic handbook—Reinforced soils and fills, Nordic Geo-
Chew, S. H., Phoon, H. L., Loke, K. H., Lim, L. K., Le Hello, B., and technical Society, Stockholm. Available from www.Nordicinnovation.
Villard, P. 共2004兲. “Geotextile reinforced piled embankment—Full- net/_img/nordisk_handbok_armerad_jord⫽engelsk.pdf.
scale model tests.” Proc., 3rd Asian Regional Conf. on Geosynthetics, Pham, H., Suleiman, M. T., and White, D. J. 共2004兲. “Numerical analysis
GeoAsia 2004: Now and Future of Geosynthetics in Civil Engineer- of geosynthetic-rammed-aggregate pier supported embankments.”
ing, J. B. Shim, C. Yoo, and H.-Y. Jeon, eds., Seoul, Korea, 661–668. Proc., Geo-Trans 2004 Conf.: Geotechnical Engineering for Trans-
Deutsche Gesellschaft fur Geotechnike EV. 共2004兲. Entwurf der empfe- portation Projects, M. K. Yegian and E. Kavazanjian, eds., ASCE
blung ‘bewehrte erdkorper auf punkf-order linienfomigen trag- Geotechnical Special Publication, Reston, Va., Vol. 1, 657–664.
gliendern, Ernst & Sohn, Berlin. Terzaghi, K. 共1943兲. Theoretical soil mechanics, Wiley, New York.