Professional Documents
Culture Documents
Prof. Sam.: Regards
Prof. Sam.: Regards
Generally, Main Contractors inform their subcontractors regarding the deductibles/excess in their
insurance policies and require the Subcontractors to procure their own insurance to cover such
deductibles/excess. If this was the case in your project, then you are liable to replace/repair the
damaged flooring. If not, then the Main Contractor should pay you for doing that.
Regards,
Prof. Sam.
Prof. Indrawansa Samaratunga PhD, DSc
FRICS, FAIQS, FIQSSL, FCIArb, FCIOB, FCMI, FASI, FBEng
Chartered Quantity Surveyor and Registered Arbitrator / Expert
Australian Inst.of Qty.Surveyors-Middle East Representative
PO Box 23461, Dubai, UAE. T +971504588949 F +97143378668
Regards
Suraj
----- Original Message -----
From: Nabil
To: sam99@eim.ae
Date: Sun, 28 Sep 2008 12:33:36 +0400
Subject: RE: Q&A
Dr Sam,
I was part of your June 2008 class and kindly ask if you could answer this scenario for
me
During tendering on a project the BOQ had an item for backfilling – it noted the
following:
The Estimator when pricing did not put excluded and did not put a rate in, Partly due to
the fact that it was not noted on the drawings that backfilling was required and that there
was not backfilling and compaction detail in the Structural Specification.
In the Contract BOQ the following was noted and the contract was signed on this basis;
Now the when analysing the works for construction it was determined that
approximately 10,000 m3 was required for backfilling.
Where do we stand in claiming for these works in a lump sum FIDIC contract? Can we
claim the extra over quantities over and above 1m3?
You do not explain why back filling became necessary at a later stage. If it is due to a
variation then you can ask for payment.
Generally, tenderers are required to obtain information for pricing tenders not only from
the Drawings and Specification, but also by visiting the Site. Although from the
Drawings and Specification you could not have foreseen the necessity of back filling, if a
site visit could have revealed the necessity, then your lump sum price is deemed to be
inclusive of the cost of such back filling. If however you can demonstrate that it was not
practical to visit the site or that you were not allowed to visit the site, then you may still
have a valid claim for payment.
Regards,
Prof. Sam.
Prof. Indrawansa Samaratunga PhD, DSc
FRICS, FAIQS, FIQSSL, FCIArb, FCIOB, FCMI, FASI, FBEng
Chartered Quantity Surveyor and Registered Arbitrator / Expert
Australian Inst.of Qty.Surveyors-Middle East Representative
PO Box 23461, Dubai, UAE. T +971504588949 F +97143378668
Thank you
Nabil Habbouche
Dear Professor Sam,
I was a student of September 2008 session-Sound Contract Administration. I would like ask one question related to
Financial claim.
Situation is : A contractor signed A Construction of Office building Project in the months of June but upto 5 months,
Consultant /Employer could not received the building permit for the project from Dubai Municipality.
But after 3 months of signing of contract, the Contractor got the demarcation permission as well as
mobilization permit from Dubai municipality.
Contractor recruited manpower for project within a month. After mobilization due to some comments on
drawing , Consultant /Employer could not get the Building Permit for next three months from Dubai Municipality .
Can the contractor claim for idle resources, Recruited manpower & idle sitting Manpower in Dubai etc. for
the period of not getting the building permit after signing the contract.
You appear to have a valid claim, but you will also have to demonstrate why you kept those resources idle at site without
deploying them on your other projects etc. in order to show that you discharged your obligation to mitigate costs.
Regards,
Prof. Sam.
Prof. Indrawansa Samaratunga PhD, DSc
FRICS, FAIQS, FIQSSL, FCIArb, FCIOB, FCMI, FASI, FBEng
Chartered Quantity Surveyor and Registered Arbitrator / Expert
Australian Inst.of Qty.Surveyors-Middle East Representative
PO Box 23461, Dubai, UAE. T +971504588949 F +97143378668
I had attended your January 2008 session-Sound Contract Administration. Thank you for
your frequent updates (Q&A) which has helped us tremendously. I have a query which need your
advise. ……………………………………………………………………
………………………………….
…………………………..
Please advise. (Please do not forward the reply to everyone as we want this issue to be discreet
especially to the main contractor.)
This forum can be used to ask questions which are of academic interest and of benefit to all
Alumni of the course. For exclusive advice, your company should make a professional
consultation.
Regards,
Prof. Sam.
Prof. Indrawansa Samaratunga PhD, DSc
FRICS, FAIQS, FIQSSL, FCIArb, FCIOB, FCMI, FASI, FBEng
Chartered Quantity Surveyor and Registered Arbitrator / Expert
Australian Inst.of Qty.Surveyors-Middle East Representative
PO Box 23461, Dubai, UAE. T +971504588949 F +97143378668
Thank you
Regards
Suvarna Kudchadkar
Dear Dr.Sam
Thank you so much for being in a continuous touch with us and sharing very useful
Q&A’s.
Regards,
Prof. Sam.
Prof. Indrawansa Samaratunga PhD, DSc
FRICS, FAIQS, FIQSSL, FCIArb, FCIOB, FCMI, FASI, FBEng
Chartered Quantity Surveyor and Registered Arbitrator / Expert
Australian Inst.of Qty.Surveyors-Middle East Representative
PO Box 23461, Dubai, UAE. T +971504588949 F +97143378668
Arunachalam Murugan
Quantity Surveyor