Download as pdf or txt
Download as pdf or txt
You are on page 1of 7

Design approach for

Kampala BRT pilot project


INTRODUCTION and design philosophy, recognising that
Arup, with ROM (Israel), is undertaking each component has a significant impact Gwyn Ephraim ICE CE
a World Bank funded project (for the on the business case and the financial Associate
Ministry of Works and Transport in sustainability of the system (Figure 1). Arup Cardiff Office, UK
gwyn.ephraim@arup.com
Uganda) to develop a detailed design of a
pilot Bus Rapid Transit (BRT) system in OPERATIONAL CONCEPT
Kampala, the capital city of Uganda. The The pilot BRT system’s Y-shaped network
BRT in Kampala will be operated with ar- will, from the opening, create a true net- Kollan Pillay Pr Eng
ticulated buses on exclusive on-street bus work effect, with passengers able to make Leader
lanes. This article outlines an approach in a variety of radial and cross-city journeys. Transport Business Development
Arup Southern Africa
which the design of each system compo- At the outset of the project an ‘operational kollan.pillay@arup.com
nent responds to the operational concepts concept’ was agreed with the client and

Co-author
Rogers Kisambira
Civil Engineer
Ministry of Works and Transport
Uganda

Figure 1: System components impacting on the business case

Civil Engineering September 2014 35


other stakeholders. In summary, this con- vehicles (Figure 3). exclusive BRT lanes will be used by BRT
cept incorporates the following: ■ Quality stations: The BRT stations will and designated vehicles such as emer-
■ Reliable and fast journey times: Full be comfortable, well-equipped, safe and gency vehicles. The hours of operation
segregation of BRT movements from secure, with level boarding access to the of BRT lanes will be 24-hours in order
general traffic along the whole corridor vehicles, located 800 m apart. Stations to maximise the perception of the BRT
length will result in journey speeds of will have capacity to accommodate two route as a ‘fi xed’ link, to avoid driver
over 20 km per hour, with guaranteed BRT vehicles and will thus be 40 m in confusion, and to emphasise compli-
journey times for travellers. length. ance.
■ Frequency: The BRT will operate at ■ Off-vehicle ticketing: All tickets for
60 buses per hour in peak periods (op- the BRT system will be purchased be- KEY PRINCIPLES FOR
erating in platoons of two vehicles per fore entering the station platform, thus INFRASTRUCTURE DESIGN
two minutes to correspond with junc- speeding up the boarding process. After the establishment of an operational
tion signal timings). ■ Short dwell times: As a result of off- concept, a design philosophy was devel-
■ Enforcement: It is essential for the board ticketing, and vehicles with mul- oped in order to clarify and guide design
smooth and efficient operation of the tiple doors, boarding and alighting will choices. The Terms of Reference for the
network that no parking, loading/un- be efficient, with short dwell times of 20 project emphasised the need to put in place
loading or unauthorised use of the BRT seconds, minimising the journey time. a high-quality public transport system as
lanes will be allowed during operational ■ Lane priority: BRT priority measures a pre-requisite of effectively addressing
hours. may reduce road capacity for general the current and future travel needs of
■ Distinctive branding: The Kampala traffic and may impose increased delays Kampala. It further indicated that “… the
BRT system will have its own distinc- on non-public transport modes. Priority Kampala Metropolitan Area was moving
tive brand identity, which will be dis- for BRT over general traffic is part of rapidly towards total gridlock. Concerted,
played in the vehicle livery, the design the ‘trade-off ’ of providing an enhanced rapid and effective measures are needed to
of stations and in all marketing material public transport system that is designed avoid this. Scarce urban transport space
(Figure 2). to achieve desired and sustainable must be used most effectively to enhance
■ Attractive vehicles: The BRT buses mode share targets. The BRT priority mobility of people (not autos) by providing
will be articulated 18 m long high- measures are thus based on a whole- space for pedestrians, bicycles and mass
passenger capacity, modern low-floor length corridor approach. The on-street transit.” (Photo 1)
A key principle of the approach taken
was to ensure that the BRT system can be
implemented over the short term, which
in particular led to an approach where
significant impacts on private land will
be avoided, and where there is no reliance
on implementation of other transport
projects (such as road-building or road-
widening schemes). Thus, the general
principles in respect of developing an
initial preliminary design were:
■ BRT infrastructure will generally be
within the road reserve.
■ Existing buildings with an apparent
legal status will generally be preserved.
Figure 2: Distinctive branding incorporated in BRT stations; also note cycle lane ■ Illegal encroachment of the road re-
serve and illegal constructions will not
be considered as a constraint.

TRANSPORT CORRIDOR FOR ALL


ROAD USERS
The design approach sought to provide an
improved quality and level of service for
all road users, i.e. to provide more than
just ‘priority BRT lanes’. Thus, insertion of
BRT lanes and stations would be accom-
panied and supported by the following
elements:
■ Clearly demarcated and well surfaced
general traffic lanes
Figure 3: BRT buses will be articulated low-floor vehicles, and the stations ■ Protected parking places (in laybys)
will be safe and secure, with level boarding access ■ Sidewalks on both sides of the corridor

36 September 2014 Civil Engineering


■ Pedestrian crossing islands ■ Existing on-street parking provision BRT STATION PLACEMENT
■ Kerbed entrances will be maintained where practicable There are 25 stations along the route,
■ Cycle lanes on the BRT corridor where or relocated to an alternative location. approximately 800 m apart. Station plat-
space exists and where impacts on legal Access to parking will not, however, forms will be side platforms, that is, lo-
or illegal buildings are minimised. obstruct the operation of BRT services. cated on the left-hand side of the bus such
■ Cycle parking facilities provided at BRT The general principle for placement of that the bus passenger doors will be in
stops along the corridor. BRT lanes in Kampala is: the conventional position. Since the BRT
Provision for the above elements would ■ Central lanes, located in the centre lane will generally be located centrally
create a step-change for road users in of the carriageway with general traffic within the road carriageway, the station
Kampala, especially for pedestrians, since lanes located adjacent to the edge of the platforms will be constructed as ‘islands’
there are presently limited sidewalks and road reserve (Figure 4). between the central BRT lanes and the
pedestrian crossings. ■ One-way mixed traffic adjacent to mixed traffic lanes on the edge of the
two-way BRT lanes, for specific loca- road (Figure 4).
BRT LANE DESIGN tions where traffic management or For Kampala, investigations of sta-
The existing road conditions and traffic station placement dictates; and where tion platform arrangements identified
management are poor, with illegal and central running is not suitable, a two- a number of advantages of central-side
unruly parking resulting in inefficient way BRT lane is located on one side of platforms in this case, namely:
use of traffic lanes. Vehicles often stop the road, with mixed traffic located on ■ Segregation: The central-side station
in traffic lanes to pick up or drop off, the other side of the road (and gener- creates a clear physical and visual seg-
while pedestrians interact with traffic, ally operating as a one-way lane). It is regation between BRT and traffic lanes.
and parking on the road verge worsens important in this case that pedestrians ■ Width: Traffic signal poles are located
the situation. understand the lane configuration with on the station islands and thus do not
Major modification to the existing signage and/or surface treatment. need additional space (width). The
road space allocation to provide ef-
fective priority for BRT services (over
general traffic) is essential to deliver
speed and journey time reliability. The
philosophy of establishing a running
way for BRT in Kampala acknowledges
that BRT priority measures will limit
road capacity for general traffic and will
generally give priority to BRT so as to
minimise delays to BRT movement over
non-public transport modes. The key
characteristics for the design of BRT
lanes in Kampala are:
■ Provision of BRT lanes is generally
based on a whole-length corridor ap-
proach (i.e. not intermittent, except at
intersections).
■ BRT lanes consist of on-street exclu-
sive lanes.
■ BRT lane width is 3.5 m, except at ‘in-
stantaneous’ pinch points where widths Photo 1: The Kampala metropolitan area is moving rapidly towards total gridlock
of 3.0 m are acceptable, provided that the
vehicle path can be accommodated safely.
■ BRT lanes will generally be discontin-
uous across major intersections to allow
for turning traffic.
■ Introduction of the BRT lanes will
not impede traffic from legal accesses.
However, for certain movements, ac-
cessing a minor side road, or other
accesses, may require a different route
choice for entry and/or exit journeys.
■ Priority measures will be designed to be
self-enforcing as far as possible – such
that drivers are able to easily compre-
hend the legality, or not, of turning Figure 4: Typical BRT station placement, with lane configurations for
manoeuvres. central BRT lanes, pedestrian crossings and cycle-securing facilities

38 September 2014 Civil Engineering


ability to offset stations also provides at all stations, pedestrian crossings
flexibility to minimise impact on adja- at all signal-controlled intersections,
cent land. dropped kerbs at pedestrian crossings,
■ Pedestrian crossing safety: The access ramps at stations, and new street
layout provides high-quality pedestrian lighting. Typically a 2 m wide sidewalk
crossing facilities for passengers and will be provided. Adjacent to stations
pedestrians (Figure 4). and at busy crossings a wider sidewalk
■ Bus costs: The BRT system will be will be provided.
operated with conventional buses with For the provision of cycling facilities,
doors on one side and hence does not the following key principles will apply:
require higher cost bespoke buses with ■ Cycle parking facilities will be provided
doors on both sides. at all BRT stations. Pedestrian/walking facilities
■ Seating capacity: Buses with doors on ■ On-road kerbside cycle lanes have been will be included at all locations
one side have significantly more seats provided along the BRT corridor along
than those with doors on both sides. a significant proportion of the scheme, on the corridor, comprising
■ Capability of buses to travel beyond and will represent a step change from kerbed sidewalks along the
infrastructure: Conventional buses the current situation where there are no
are able to travel beyond the BRT cycling facilities. road edge, pedestrian crossings
infrastructure (e.g. to the airport), Access for people with physical disabili-
at all stations, pedestrian
with no special kerbing needed at ad- ties follows established international
ditional stops. best practice design. Facilities include crossings at all signal-controlled
dropped kerbs at road crossings, tactile
intersections, dropped kerbs at
NON-MOTORISED TRANSPORT paving at road crossings, access ramps
Pedestrian/walking facilities will be to stations and wheelchair access pedestrian crossings, access
included at all locations on the corridor, through station turnstiles. Low-floor
ramps at stations, and new
comprising kerbed sidewalks along platforms and buses provide convenient
the road edge, pedestrian crossings access for wheelchairs. street lighting.
Civil Engineering September 2014 39
T03000

We don’t talk logistics solutions, we walk it


Being able to deliver high-quality logistic
and supply chain solutions requires
having more than just a one-size-fits-all
approach. At Cargo Carriers we pride
ourselves on being customer centric
and while vertical specific we are always
looking for challenges and opportunities
in new industries and regions. We strive
for the highest levels of reliability in
all that we move. With each customer
comes an individual set of safety, health,
environmental and quality requirements,
and our innovative and service orientated
offering means that we are consistently
able to provide for your specific needs.

Call us. We go the extra mile

Innovative supply chain solutions


INTERSECTION DESIGN APPROACH ■ Maximising and controlling the pri-
ority given to the BRT system
Major intersections ■ Avoiding the possibility of gridlock on
The principles of operating BRT at major the roundabout gyratory.
intersections are as follows (Figure 5):
■ BRT lanes should be signal-controlled Minor intersections and entrances
through all main intersections on the For minor intersections and private ac-
BRT Route. cesses, the arrangements for BRT traffic is
■ BRT vehicle movements through as follows:
signalised intersections should have ■ All minor intersections and accesses
dedicated phases. will operate as left-in / left-out accesses.
■ The BRT lanes should extend to the ■ Vehicular traffic movement across BRT
stop line at signalised intersections. lanes will not be allowed.
■ Signalised intersections should have a
dedicated pedestrian crossing phase. STATION DESIGN APPROACH
■ Signalised intersection should be
Figure 5: Typical intersection designed to operate with detection General design principles
arrangement with BRT
priority for BRT vehicles, and should The station and platform designs were
provide green time extension. assessed on a location-by-location basis,
addressing pedestrian accessibility, im-
Roundabouts pact on intersections and accesses for up-
The principle adopted for roundabouts stream or downstream platforms, journey
on the BRT route is to modify the junc- time, passenger demand, etc. Approaches
tion to a conventional signalised inter- to stations were designed to allow for ac-
section with the BRT travelling through curate vehicle/platform docking.
the centre of the junction without the
need to traverse the roundabout lanes Station operation
(Figure 6). Th is principle is important in The station will be surrounded by a fence
respect of: or barrier. Turnstiles will be located at
■ Passenger comfort through the junction both ends of the station. Passenger access
Figure 6: Roundabout converted to ■ Providing a tram-like level of service to/from BRT vehicles will be via gaps in
signalised BRT intersection and image the surrounding fence or barrier.

Figure 7: BRT stations will be surrounded by a barrier, turnstiles will be located at both ends, and passenger access to/from BRT
vehicles will be via gaps in the surrounding barrier

40 September 2014 Civil Engineering


Station locations FINANCIAL SUSTAINABILITY AND
Stations are located at approximately BRT PRIORITY
800 m intervals along the BRT route, A key requirement of the BRT operation is
although distances vary locally ac- that it should be, as far as possible, finan-
cording to specific needs and con- cially self-sustainable, i.e. the operating
straints, such as proximity to key cost should be paid from income gene-
passenger demand generators and the rated by fares.
availability of space. The level of priority given to move-
The BRT stations have level ment of BRT vehicles along the road cor-
boarding access for low-floor BRT ridor, and especially at intersections, is a
buses, and thus kerb heights will be key determinant of whether the BRT op-
approximately 300 mm. Stations have eration is financially self-sustainable. The Stations are located at
the capacity to accommodate two ar- resulting commercial speed of the BRT
ticulated BRT vehicles (approximately vehicles has a direct relationship with the approximately 800 m
18 m in length) and thus platforms are BRT operating costs and income, that is: intervals along the BRT
40 m in length. Station platforms will ■ The higher the speed the lesser the
have a 5 m width (kerb-to-kerb). The number of vehicles needed to operate route, although distances
resulting effective platform area will be the required frequency.
vary locally according
approximately 1 m less than the station ■ The higher the journey speed the
island to accommodate fencing and bus greater the attractiveness of the service to specific needs and
shelter panels. Stations will also com- to passengers.
constraints, such as
prise 5 m to 10 m long approach ramps
with ticketing turnstiles at the begin- PROGRAMME FOR IMPLEMENTATION proximity to key passenger
ning of the platform. The whole station The detailed design for the infrastructure
demand generators and
island is therefore approximately 60 m is currently being finalised, and operation
in length (Figure 7). is planned to start by 2018. the availability of space.

Civil Engineering September 2014 41

FASTEST
pcbs.co.za

TO MARKET.
IT’S WHAT
WE ARE
ALL ABOUT.
PCBS are the premier guarantee specialist in Africa. We specialise in guarantees and alternative
risk transfer. Our business has grown to become one of the largest guarantee specialists in Africa
through building meaningful partnerships with our clients and by delivering expedient results.
We are underwritten by Guardrisk.

For further information contact us on 011 482 2592 or info@pcbs.co.za

An Authorised Financial Services Provider - FSP19867


CTC - 1250
Copyright of Journal of the South African Institution of Civil Engineering is the property of
South African Institution of Civil Engineering (SAICE) and its content may not be copied or
emailed to multiple sites or posted to a listserv without the copyright holder's express written
permission. However, users may print, download, or email articles for individual use.

You might also like