Professional Documents
Culture Documents
Preparing To Synchronize A Generator To The Grid
Preparing To Synchronize A Generator To The Grid
CONDITIONS
In order to synchronize a generator to the grid, four conditions must be met:
Phase Sequence
Voltage Magnitude
Frequency
Phase Angle
PHASE SEQUENCE
The phase sequence (or phase rotation) of the three phases of the generator must be the same as the
phase sequence of the three phases of the electrical system (Grid).
The only time that the phase sequence could be wrong is at initial installation or after
maintenance. There are two possible problem sources.
The generator or transformer power leads could actually be interchanged during maintenance orthe
potential transformer leads could be interchanged during maintenance .
VOLTAGE MAGNITUDE
The magnitude of the sinusoidal voltage produced by the generator must be equal to the magnitude of
the sinusoidal voltage of the grid.
If all other conditions are met but the two voltages are not the same, that is there is a voltage
differential, closing of the AC generator output breaker will cause a potentially large MVAR flow.
Recall that before a generator is synchronized to the grid, there is no current flow, no armature reaction
and therefore the internal voltage of the generator is the same as the terminal voltage of the generator.
If the generator voltage is higher than the grid voltage, this means that the internal voltage of the
generator is higher than the grid voltage. When it is connected to the grid the generator will be
overexcited and it will put out MVAR.
If the generator voltage is less than the grid voltage, this means that the internal voltage of the generator is lower
than the grid voltage. When it is connected to the grid the generator will be under-excited and it will absorb
MVAR.
FREQUENCY
The frequency of the sinusoidal voltage produced by the generator must be equal to the frequency of
the sinusoidal voltage produced by the grid.
In doing so, the rotor and stator would be slipping poles and damage (possibly destroy) the generator as
described previously. The same problem would occur if the generator were faster than the grid.
The grid would try to slow it down, again resulting in slipping of poles.
However, if you notice in 2 with the grid and a phase angle exists between them. This would appear as a
non-rotating synchroscope (both generator and grid at same frequency), where the pointer would
appear stuck at about 9:00 o’clock (generator lagging grid).
If the generator breaker were to be closed at this time, the grid would pull the generator into step.
However, this again would cause a large current in-rush to the generator and high stresses on the
rotor/stator with subsequent damage to the generator. If the generator were leading the grid, it would
try to immediately push power into the grid with the same destructive forces as mentioned.
Hence the generator must be brought to a point where the grid voltage waveform exactly matches what
it is producing.
PHASE ANGLE
As previously mentioned, the phase angle between the voltage produced by the generator and the
voltage produced by the grid must be zero.
The phase angle (0 to 360°) can be readily observed by comparing the simultaneous occurrence of the
peaks or zero crossings of the sinusoidal waveforms.
If the generator breaker is closed when they match exactly, the connection will appear smooth and
seamless.
At that instance (Figure 4 below), the pointer on the synchroscope would indicate 12:00 oíclock.
The worst case occurs if the generator is exactly out-of phase, with a phase angle of 180° and the
synchroscope pointing at 6:00 o’clock.