Download as pdf or txt
Download as pdf or txt
You are on page 1of 135

MIDDLESEX UNIVERSITY LONDON

SCHOOL OF SCIENCE AND TECHNOLOGY

THESIS

ALIGNMENT FRAMEWORK BETWEEN BUILDING INFORMATION MODELING


PROCESSES AND THE PMBOK® GUIDE CONSTRUCTION EXTENSION PROCESSES IN
CONSTRUCTION PROJECTS

By

Saad Al-Jabri

Submitted in partial fulfilment of the

Requirements for the degree of

Master of Science

May 2017

Approved by

Dr Noha Saleeb
Alignment Framework between BIM and PMBOK® Processes 1

Abstract

A concern that project managers share is that despite the management protocols,
processes, and tools contained in the Project Management Body of Knowledge® (PMBOK®),
considerable resources are still spent every year correcting and adding to non-standard data
needed by any or all stakeholders, team members, designers, and project owners. As well,
facility and project history must be maintained A number of new tools and standards around
Building Information Modelling (BIM), common data environments (CDE) and Integrated
Project Delivery (IPD) were just beginning to see wider use and acceptance in the Project
Management community as the Fifth Edition PMBOK® was issued, thus guidance on these
topics was not necessarily included explicitly. This study queried the project management
community for input and probed thoughts around various external BIM guidance to develop a
preliminary process to integrate Information Management (IM) tools into each of the
Knowledge areas and propose to develop an Information Management Framework into the
PMBOK® and its Construction Extension (CE) as a new Knowledge Area, or KA.

An online survey, paper questionnaire, and formatted interview sheet were prepared
with focused questions and deployed to assess the degree of insight around several broad PM
topics concerning Information Management (IM) and IM formatting compatibility. As well,
respondents were asked to share any information they cared to, about what guidance or
procedures they used, anecdotes on what worked well or didn’t work in practice, thoughts on
BIM, CDE, and their exposure to any or all. In addition, respondents’ familiarity with existing
guidance details in the PMBOK® and CE were probed and used to gauge what future work
might be required to reach the end goal of adding robust support and guidance for BIM, IM,
and CDE.

Data suggested the respondents felt that more IM guidance was needed and could be
added to the PMBOK® and CE that a separate KA addressing process, procedure, tools, and
collaborative procedures could be included and raised the possibility of modifying and updating
information in existing KAs to integrate IM more explicitly. All suggested IM needed to be
robustly managed from facility cradle-to-grave. Some indicated support for more inclusion of
process for explicit collaboration support. As well, perceived lacks in the PMBOK® and CE
with respect to Communications and records-keeping were highlighted, along with the
recognition of digital tools, workspaces, and procedures as primary project criteria to keep in
mind as contracts are initiated, negotiated, and executed. Finally, respondents offered anecdotes
illustrating experiences on previous projects, speaking to familiarity with or to limited to the
routine use of BIM, Common Data Environments (CDE), and Intellectual Property Rights (IPR)
management. Some respondents suggested that inclusion of real-world examples of the process
might be particularly useful, as well.

The study contributes to the body of knowledge by providing enough information to


build a skeleton outline of best practices in digital data management, which may be used to
construct a digital data management knowledge area for inclusion in the PMBOK® and its
construction extension, and build a foundation for collection of examples, case studies, and
process around the larger area of Information Management.
Alignment Framework between BIM and PMBOK® Processes 2

Table of Contents

Abstract ....................................................................................................... 1

List of Figures ............................................................................................. 5

List of Tables .............................................................................................. 7

Chapter 1 Introduction to the Research ............................................. 8


1.1 Rationale ........................................................................................ 11
1.2 The main research question ........................................................... 14
1.2.1 Quick Summary ................................................................................... 14
1.2.2 Contribution(s) to knowledge .............................................................. 15
1.3 Benefits and beneficiaries .............................................................. 15
1.4 Proposed methods .......................................................................... 16
Chapter 2 Literature Review ........................................................... 17
2.1 Theoretical Background ................................................................. 17
2.2 Candidates for Incorporation into PMBOK® Guide ..................... 19
2.2.1 PAS 1192-2:2013 (BSI 2013) .............................................................. 19
2.2.2 Building Information Model (BIM) Protocol CIC/BIM pro
(Construction Industry Council, 2013) ................................................ 24
2.2.3 BS 1192:2007 (BSI 2007).................................................................... 25
2.2.4 BS 1192-4:2014 ................................................................................... 26
2.2.5 Employer’s Information Requirements (EIR) Guidance ..................... 27
2.2.6 AEC (UK) BIM Technology Protocol (Core of the BIM) ................... 28
2.2.7 Building Information Modelling Execution Planning Guide ............... 29
2.2.8 Using BIM as a Project Management Tool:......................................... 29
2.2.9 Building Information Model (BIM) Standards Manual by DASNY ... 30
2.2.10 The VA BIM Guide ............................................................................. 30
2.3 Summary: list of procedures and guideline candidates.................. 31
Chapter 3 Research Methods ........................................................... 32
3.1 Research Question Restatement ..................................................... 32
3.2 Research Strategy........................................................................... 32
3.2.1 Justification of Method ........................................................................ 33
3.2.2 Choosing a Sample Size....................................................................... 33
3.2.3 Designing the questionnaire and Forum Questions ............................. 35
Alignment Framework between BIM and PMBOK® Processes 3

3.3 Next Steps: Project Description and Data Collection .................... 36


Chapter 4 Chapter 4 Project Description......................................... 37
4.1 Business Drivers and Significance................................................. 37
4.2 Benefits and Costs.......................................................................... 37
4.3 Implementation Method ................................................................. 38
4.3.1 Timeline ............................................................................................... 38
4.3.2 The Survey Questions .......................................................................... 38
4.4 Focus Group ................................................................................... 44
Chapter 5 Data Analysis .................................................................. 46
5.1 Survey Responses .......................................................................... 47
5.1.1 PMBOK®/Construction Extension Surveys ........................................ 51
5.1.2 Guidance Integration into the PMBOK® Guide/Construction Extension
............................................................................................................. 53
5.1.3 PMBOK®/Construction Extension Open-ended Questions ................ 53
5.1.4 Focus Group Interview: MOHAP ........................................................ 53

Chapter 6 Survey Results ................................................................ 56


6.1 Discussion structure ....................................................................... 56
6.2 AllCounted dot Com Survey.......................................................... 57
6.3 Research Focus Group ................................................................... 71
6.4 Data Summary ............................................................................... 75
Chapter 7 Conclusion and Future Work .......................................... 76
7.1 Proposed Information Management Knowledge Area (KA) ......... 78
7.2 Future Work ................................................................................... 79
References................................................................................................. 82

Online Survey Questions ............................................. 90

RESEARCH INTERVIEW FORM ............................. 97

Raw Responses to Group Interview Survey .............. 101

AllCounted dot com Survey Data .............................. 102

a. Raw and Collated Online Survey Data ............................................. 103

b. Focus Group Interviews, organised by question number .................. 117

DATA APPENDICES ............................................... 133


Alignment Framework between BIM and PMBOK® Processes 4

............................................................................................ 134

a. Appendix E2.pdf................................................................................ 134

b. Focus Group Instructions: App_E3_Krueger-Focus.pdf .................. 134

c. Group Interviews PDF....................................................................... 134


Alignment Framework between BIM and PMBOK® Processes 5

List of Figures

Figure 1 - The information delivery cycle ............................................................................... 21

Figure 2 - The relationships between the contract and the associated documents ................... 23

Figure 3 Document and data Management repository (BSI 2007) ............................

Figure 4 Are you or have you been a project Manager? ............................................

Figure 5 Licensed or Certified? What kind? ..............................................................

Figure 6 Years in Project Management?....................................................................

Figure 7 Type of projects worked on? .......................................................................

Figure 8 Question 7 responses: Should more ‘best practices’ IM guidance be

added to the PMBOK®? ......................................................................................................

Figure 9 What kinds of electronic workspaces have you used (multiple selections

possible)

Figure 10 Communications flow issues (question 11)............................................. 64

Figure 11 Quality of communication flow (question 12) ........................................ 65

Figure 12 Might it be useful to add a separate Information Management KA to the

PMBOK® and/or its construction extension? (Question 13)........................................... 65

Figure 13 Table, question 16, regarding alternative guidances specific to

information management process. As indicated at the top of the figure, only 11 of 21

respondents filled out this table. ...................................................................................... 67

Figure 14 Question 24: Do you find adequate guidance in the PMBOK and C.E.

regarding intellectual property rights? ............................................................................. 69

Figure 15 Years managing projects ......................................................................... 71

Figure 16 years managing projects .......................................................................... 71

Figure 17 Certifications? ......................................................................................... 72

Figure 18 Certifications? ......................................................................................... 72

Figure 19 Types of projects worked on .................................................................. 73

Figure 20 Types of projects worked on ................................................................... 73


Alignment Framework between BIM and PMBOK® Processes 6

Figure 21 What Electronic workspaces have you used or are familiar with? .......... 75
Alignment Framework between BIM and PMBOK® Processes 7

List of Tables

Table 1 Minimum Sample Size by Confidence Level ....................................................... 34

Table 2 Non-PMBOK® Documents which contain Information Management or BIM

Guidance .......................................................................................................................... 41

Table 3 Calculated margin of error for a given sample size. ............................................. 47


Alignment Framework between BIM and PMBOK® Processes 8

Chapter 1 Introduction to the Research

The UK government promulgated the “Construction Strategy” cost-saving measure in

May 2011, with recent updates published March 2015. The target goal was to reduce waste and

losses in construction projects and to improve management and costs associated with public

projects (Cabinet Office, 2016). Budgetary concerns and increased need for trackable organised

reporting, as well as the need to minimise waste and costs under an on-going LEAN initiative,

led to the development of construction guidelines and protocols to address these concerns and

to establish collaborative relationships with the construction industry. The guidelines have

stated a purpose which seeks “… to improve the delivery, efficiency and performance of

economic and social infrastructure projects in public, private and regulated sectors”. The

construction strategy has goals ‘…for smarter procurement, fairer payment, improving digital

skills, reducing carbon emissions, and increasing client capability.

Project management as a concept may go back as far as the building of the Great Wall

of China (Brewer, 2012) but developed into a discipline in the 20th century. Project

management, as a discipline, still has a great many areas, which can be researched and

improved: one of these is data management and information sharing. Throughout a project life

cycle, significant amounts of data and information are collected, analysed, transformed, and

then distributed in various formats to project team members and other stakeholders. Project

data, collected because of various Executing Processes (EP), are shared within the project team,

analysed in context and aggregated, then transformed to become project information during

different Controlling Processes (CP). The information may then be communicated verbally or

stored and reported or distributed in various formats. (PMBOK® Guide 2013). Project data are

continuously collected and analysed during the dynamic context of the project execution.

However, problems can arise during that phase. For example, the terms ‘data’ and ‘information’

are often used interchangeably, and the indiscriminate use of these terms can lead to confusion

and misunderstandings by the various project stakeholders. (PMBOK® Guide, 2013).


Alignment Framework between BIM and PMBOK® Processes 9

The Project Management Body of Knowledge (PMBOK®) guide represents, to many,

the standard for contemporary project management practice. For example, its publisher, Project

Management Institute (PMI), has been endorsed by the American National Standards Institute

(ANSI) as a primary standards developer. However, the PMBOK® is not yet accepted

universally. It is sometimes criticised for being too ‘linear’ in approach for applying a ‘one size

fits all’ or mechanistic approach to project management that sometimes fails because it does

not take enough account of the human element (Brewer 2012, Cervone 2014). Still, the

PMBOK® provides a good support framework for sound practice, because it is process-based.

It is the ‘go-to’ document for developing an understanding of key concepts, understanding what

goes into proper management of the project body of knowledge, as well as the ethics and

standards the project manager should – and must – meet. Critical amongst these pieces are the

concepts of collaboration and trust.

Collaboration between the participants in construction projects is essential for the

efficient delivery of facilities. In ongoing efforts to maintain better tracking of costs and benefits

of the finished project or facility, organisations are working more and more in new collaborative

environments, based in significant degree on digital tools. Projects now come with diverse

stakeholders who must be kept informed: tools and process to manage the collaborative

environment allows the project management team to achieve higher standards of quality and

greater re-use and retention of existing knowledge and experience. A major feature of the

collaborative environment is the ability to communicate, re-use and share data efficiently

without loss, contradiction or misinterpretation. (BS 1192:2007). As well, the ability to manage

information in the collaborative environment can have the side benefit of reducing waste of

resources, time, and materials.

The PMBOK® Guide defines a project as “a temporary endeavour undertaken to create

a unique product, service, or result”, which further implies that the project has a well-defined

beginning and end (2013). This ‘endeavour’ can be an enhancement, a construction or

renovation of a facility, a service or capability for a service, a document, a projection or trend


Alignment Framework between BIM and PMBOK® Processes 10

analysis, or improvements, for example. A concern that project managers share, despite the

management protocols, processes, and tools in the PMBOK, is that each year considerable

resources are spent on making corrections to non-standard data. They must ensure that all data

are included in the central database, that new personnel are trained in approved data creation

techniques, that the efforts of the designer, the subcontractor teams, and management team are

coordinated, and that problem-solving related to data reproduction are addressed either via

standardisation of formats or standard conversion protocols. (BS 1192:2007).

Building Information Modelling (BIM), in contrast, is a process, which generates and

manages the digital representations of physical and functional characteristics of physical

buildings, infrastructure, etc. The PAS 1192-2:2013 states that a “BIM generates information

models and their associated information that are used throughout the lifecycle of

building/infrastructure facilities or assets” (BSI 2013). In other words, this process can manage

tasks like making corrections to non-standard data, ensuring that all data are included in the

central database, that the inputs from the designer, the subcontractor teams, and management

teams are coordinated without costly mistakes and revision. This is accomplished via a virtual

model of the project, which can be modified, cost estimated, and visualised with respect to

construction, by all teams concerned, including owners and other non-construction or

engineering stakeholders (BSI 2013).

BIM is accomplished using computer software and architecture to manage files

containing a wealth of information about a project, which can be used to support planning, as

well as construction and decision-making associated with the project. Thus, BIM focuses more

on design and execution, whereas PMBOK® is more of a global standard for managing the

project. In BIM, the focus is on information management also: the design is treated as a

combination of objects where the project can evolve and change as it progresses, and is

available to pass information from the designer, to the contractor, to the owner and back again,

as the project is executed and changes are made. For example, at the inception of the project,

BIM workspace contains project records, can visualise the facility at any phase from concept
Alignment Framework between BIM and PMBOK® Processes 11

through project completion tracking mods, and organise and track input from all parties

involved, as well. Once the construction phase is completed, the function of the BIM may

evolve from project-focused to records-focused – these phases are maintained in separate

workspaces but are heavily cross-referenced due to built-in features of the software. Once

documents/keys/operating manuals have been handed over, the BIM may transition into an

O&M-focused mode. It can maintain a variety of records over the facility lifetime beyond the

project phase, such as Environmental, Safety, Security, and Health (ESSH) records, repairs,

repurposing, etc. (Gelder, 2013). BIM services the whole facility life cycle while project

management services the asset lifecycle during the construction until completion. At this point

where the project manager’s involvement ceases or becomes minimal, BIM can potentially

bridge the gaps in the PMBOK® process, and hopes were high that it might. However, per the

“Government Construction Strategy Report” of 2016, procedures are not yet in place

everywhere for employing BIM. As well, process standards involving computer management

do not yet exist in recognised final form.

1.1 Rationale

Research investigation identifies that there is no inclusion of standards or processes for

dealing with or facilitating project information integration in the current iteration of the

PMBOK® guide (2013) or its Construction Extension (2007). Why does it matter what the

PMBOK® Guide or the Construction Extension say? Recall that the PMBOK, Project

Management Body of Knowledge (PMBOK) is described as ‘the standard for contemporary

project management practice’. In its introduction, the PMBOK® states that it “… identifies that

subset of the project management body of knowledge that is generally recognized as good

practice. “Generally recognized” means the knowledge and practices described apply to most

projects most of the time, and there is a consensus about their value and usefulness” (2013).

The Construction Extension to the PMBOK® Guide contains Knowledge Areas specific to

construction projects, for each of the PMBOK® Guide Knowledge Areas, as well as guidance

on project resources, health, safety, security, and environmental management, and financial
Alignment Framework between BIM and PMBOK® Processes 12

management and claims management in construction (2016). The PMBOK® Guide and

Construction Extension say this regarding information integration:

 project data may be shared within the project team, and with other stakeholders,

 collected data may be communicated verbally or stored and distributed in various


formats.

Both do acknowledge that during the active phase of project execution, the terms data

and information are used interchangeably, which can often lead to confusion and

misunderstanding between various project stakeholders. The PMBOK® Guide attempts to

address this by defining and explaining three preferred terms for data, information, and reports

(PMBOK® Guide, 2013):

 Work performance data: raw observations and measurements made during

project work activities.

 Work performance information: performance data collected from various

controlling processes contextually analysed and relationally integrated across

areas.

 Work performance reports: physical or electronic work performance information

compiled in project documents.

Malik (2016) pointed out that the PMBOK® Guide contains a Knowledge Area dealing

with Information Management titled, ‘Communication Management (section 10.2)’. It states

that “Project Communications Management includes the processes that are required to ensure

timely and appropriate planning, collection, creation, distribution, storage, retrieval,

management, control, monitoring, and the ultimate disposition of project information." It

provides a process flow for accomplishing the flow but suggests no tools for doing so, leaving

another gap in communications, which is dependent upon the diligence of the project manager

as well as each of the team members and stakeholders.


Alignment Framework between BIM and PMBOK® Processes 13

A second attempt to provide guidance on communications by PMI resulted in a new

Executing process for managing knowledge being added in the PMBOK® Guide 6th Edition.

Probably as Malik said, communication management in PMBOK® is gaining more focus than

the other Knowledge Areas. This is appropriate, as it is identified by almost everyone as an area

where project information management can fail (Cervone 2014, Carvalho 2008, and Brewer

2012). For example, Brewer addresses communication lapses in the context of trust issues

between the project manager, the project team, and stakeholders (2012). Cervone attempts to

assess where, and to what extent the fault lies, and concludes that communications management

while critical to project success, is seldom practised, in part, because of assumptions and

misunderstandings about who needs to know what, or how much background information a

given individual may already have (2014). In this study, more focus will be directed towards

Information Management Frameworks and their integration into existing guidance, such as the

PMBOK® Guide and Construction Extension. The researcher intends to show how integrating

BIM processes and standards can benefit the PMBOK® Guide construction extension.

This is a desirable area of study because

 the PMBOK® Guide Construction Extension does not yet focus on using new

technologies, such as Building Information Management (BIM) in projects,

 the current PMBOK® Guide Construction Extension, Second Edition offers

practically no guidance on how to manage information and data (2007).

 A Third edition has become available recently, and while it claims to address

concerns with data management more directly, the guidance is more focused on the

process flow, rather than specifics.

Many BIM standards and procedures have been introduced in the construction field by

governments such as The Building Information Modelling (BIM) Task Group a UK

Government-funded group, Dubai Municipality, AEC and consultant organisations such as


Alignment Framework between BIM and PMBOK® Processes 14

ARUP, developers’ companies such as Autodesk, Bentley and other BIM experts all working

together to develop tools and process. It is worth studying them more closely and investigating

what aspects may be added to the PMBOK® Guide Construction Extension.

1.2 The main research question

 What BIM and other information management processes and procedures can be added

to the Construction Extension to the PMBOK® Guide to increase its value in the field,

and how would they impact the current guide’s methods and techniques?

o How can the Construction Extension to the PMBOK® Guide benefit from BIM

standards in managing information?

 What are the main information processes discussed in current literature?

 What BIM Standards and Procedures exist?

o How do these compare with information processes in PMBOK?

o How do BIM information exchange procedures and terminology differ from

those in PMBOK®?

o How does BIM ensure interoperability and data standards?

1.2.1 Quick Summary

The researcher has reviewed different research/literature on information management,

PMBOK® processes, and BIM, to define where the gap lies between information and data

management within the project management framework provided by the PMBOK® Guide and

the Construction Extension. In general, there has been a little evaluation of the gaps or attempts

to bridge them using more rigorous Information Management, from the Project Management

point of view. Previous studies and research have focused on different issues than the

researcher’s proposed research area as follows:

 The PMBOK® Guide explains project information terminology only and divides it into

three categories: Work performance data, Work performance information, and Work

performance reports without providing detail or more specific guidance (PMI, 2013).
Alignment Framework between BIM and PMBOK® Processes 15

 Lawson et al. (2010) stated that “BIM requires the implementation and execution of a

new model of project management.”

 More recent literature (Brewer 2012, Alp 2014, and Belsky 2016) attempts to define

and implement BIM in new ways, but offer no concerted effort to integrate it more fully

into the PMBOK® and the Construction Extension Knowledge Areas.

o There are no indications of any specific process and methodology for

integrating BIM into PMBOK® processes; only general information is

available.

 Alin (2013) focused on Australian sample case studies and whether the high level of

information content offered by BIM and the potential for sharing that information

among contracting parties means that the information asymmetry can be alleviated

using BIM.

 Retana (2016) discussed the history of information management, specifically how

information has moved from paper-based transactions to the new digital forms. He

described information flow from one source to another within the project team and its

effect on construction project members. Next, Retana outlined the different project

phases and how information is treated within each. Finally, he addresses the role of

Information and Communications Technology (ICT) in the management of

construction information.

1.2.2 Contribution(s) to knowledge

This study’s results will result in a proposal for adding an Information Management

Framework in the Construction Extension to the PMBOK® Guide as a new Knowledge Area,

or KA, from the finding in BIM standards. Thus, a preliminary process, which integrates BIM

into each of the Knowledge areas, will be proposed.

1.3 Benefits and beneficiaries

There are no specific processes, procedures or recommendations on how to integrate

BIM into the Construction Extension KAs or into the PMBOK® Guide KAs. On the other hand,
Alignment Framework between BIM and PMBOK® Processes 16

several BIM standards and references offer Project Managers guidance on Information

Management during the Execution of the project. However, it can be difficult for project

managers who do not already have experience with BIM to benefit from them. This researcher

proposes an information management framework for BIM structured to allow project managers

to utilise these procedures even if they do not have experience in BIM. Those who might benefit

are:

 Projects managers

 PMI and its community

 BIM consultancy firms

 Project team contributors

1.4 Proposed methods

The researcher will use empirical research (Cotterell, 2014) to develop evidence to

support or refute a hypothesis:

“Should consider adding a Data and Information Management knowledge

area into its Construction Extension to the PMBOK® Guide?”

To answer this, The researcher will use Qualitative Content Analysis Methodology to

probe the hypothesis, then use findings to suggest where and how the proposed Data and

Information Management KA can fit into the Construction Extension. The researcher may use

a secondary methodology, such as interviews and a focus group to probe working project

managers’ opinions of this study’s findings and determine whether they agree that the proposed

KA should be added to the Construction Extension to the PMBOK® Guide.”


Alignment Framework between BIM and PMBOK® Processes 17

Chapter 2 Literature Review

2.1 Theoretical Background

Before addressing theory and previous research on the communication of information

and data, it might be appropriate to address the origins of the Project Management Body of

Knowledge Guide and its Construction Extension (PMI 2013, PMI 2007). Both are published

and updated by the Project Management Institute, a non-profit corporation formed in 1969.

Project management as a concept probably dates back thousands of years, but no formal

teachings were available for the professional until the twentieth century. One need only

consider the planning, communication, coordination, and execution that must have gone into

assuring the durability of structures like Great Wall of China, the pyramids of Egypt and the

Americas, or the Moai on Rapa Nui, to understand that project management planning is an old

science that has been little formalised until recent times. In the 1960s, the discipline began to

be used widely in the aerospace, construction, and defence industries and is when formal

processes and procedures began to develop. In 1969, five individuals: Ned Engman (McDonnel

Douglas Automation), James Snyder and Susan Gallagher (SmithKline & French Laboratories),

Eric Jenett (Brown & Root) and J Gordon Davis (Georgia Institute of Technology) formed the

Project Management Institute (PMI) at the Georgia Institute of Technology as a nonprofit

organisation. They incorporated it in the Commonwealth of Pennsylvania that same year (PMI

2016). Some years later, PMI described its major objectives:

 to foster recognition of the need for professionalism in project management;

 to provide a forum for the free exchange of project management problems,

solutions and applications;

 to coordinate industrial and academic research efforts;

 to develop common terminology and techniques to improve communication

between various groups involved in project management,

 to provide interfaces between users and hardware/software suppliers, and


Alignment Framework between BIM and PMBOK® Processes 18

 to provide project management instruction and career development guidelines.

As the institute grew, it gathered information from professionals in the field on

practices, procedures, and approaches, and began to promote standardisation of them. Because

of their efforts, PMI put together and published the first PMBOK ® Guide in 1996. The

PMBOK® guide is available in several translations and can be purchased at their website,

www.pmi.org. The Guide is also available in the US as American National Standard Institute

(ANSI) document BSR/PMI 99-001-2013. ANSI, while not directly involved in the

development of the PMBOK® and the Construction Extension performs several functions that

have contributed to the PMBOK® being recognised as the de facto standard for project

management. It:

 accredits standards that developed by representatives of other standards

organisations, government agencies, consumer groups, companies, and others

 ensures the characteristics and performance of products based on those

standards are consistent

 ensures that people use the same definitions and terms across the discipline,

and

 ensures that products are vetted the same way, against the same verified

standards.

The PMI chose to produce guidelines that work for most projects, as series of processes

organised into thirteen Knowledge Areas, including one (Section 10) called Project

Communications Management. The Project Communications Management section has been

subdivided further into Communications Management subsections 10.1-10.3: “Plan

Communications Management”, “Manage Communications”, and “Control Communications”

(planning communications management, executing the plan, and verifying the plan worked).

All three depend on the information needs of stakeholders and each member of the team, as

well as how, and in what format, that information is presented (raw data, calculated quantities,

reports, advisories, summaries, etc.). Unfortunately, this is the area where most projects suffer
Alignment Framework between BIM and PMBOK® Processes 19

problems. Guidance exists which attempts to address communications gaps and mistakes;

however, one must consult several documents in order to bridge the gaps. It might be useful to

examine some of these and suggest how they might be integrated with the PMBOK® Guide.

Not all information on a project will be originated, exchanged or managed in each BIM

format. Just as there are diverse team members and stakeholders involved in complex and/or

large construction projects, data and information generated, processed and disseminated to team

members will also be diverse. This information will be managed in a consistent and structured

way throughout the project lifecycle in order to ensure efficient and accurate information

exchange. Even where a BIM tools and procedures are being used, problems can arise due to

lack of interoperability and lack of precision in definitions (Belsky, 2015). Belsky states: there

are “significant difficulties remain in exchanging information between Building Information

Modelling (BIM) tools.” To probe the differences between BIM tool communications, native

format and storage schemes, would require another research project, and will not be addressed

here.

2.2 Candidates for Incorporation into PMBOK® Guide

The processes incorporated into the PMBOK® Guide do not specifically include

sections dealing with data management and dissemination that are explicit or detailed. There

are several guidance or contract documents that do provide support and guidance specifically

for Building Information Models, as well as how to incorporate that capability into a contract

(BSI 2013, CIC/BSI 2013, BSI 2007). These will be discussed briefly.

2.2.1 PAS 1192-2:2013 (BSI 2013)

“Process and Specification for Information Management for the Capital/Delivery

Phase of Construction Projects using Building Information Modelling (BIM)”

The Publically Available Specification (PAS) 1192-2:2013, published by the British

Standards Institution, provides specific guidance for information management associated with

projects delivered using BIM (BSI, 2013). The guidance contained in PAS 1192-2:2013
Alignment Framework between BIM and PMBOK® Processes 20

developed out of the need to meet mandates set out in the Construction Strategy of 2011

(Cabinet, 2011). The stated goals were to reduce the costs of public sector assets by 20% or so

by 2016, and to set a strategic objective “to achieve maturity Level 2 building information

modeling (BIM) on all public sector asset procurement, with equal applicability to private

sector building, infrastructure, refurbishment and new-build projects” (BSI 2013). The hope

was that imposing the mandate might improve information consistency across the lifetime of a

project, but this has not yet been realised.

The PAS, in fact, only addresses information exchanges specific to BIM, however, it

is possible that it attempts to address the lack of interoperability between BIM tools by stating,

“… all project information, whether in BIM environments or in conventional data formats

should be shared using a single collaborative data environment (CDE).” It is assumed that, for

this study, non-BIM information exchanges between a principal supplier and employer and

within the supply chain will be managed using other, similar information management

standards, decided on in advance, by all stakeholders.

The PAS 1192-2:2013 is organised into sections:


Introduction 6 Information delivery – Procurement
1 Scope 7 Information delivery – Post contract-
award
2 Normative References 8 Information delivery – Mobilisation
3 Terms and definitions 9 Information delivery – Production
4 Overview of documents referenced 10 Information Delivery – Asset
from this specification information model (AIM) maintenance
5 Information delivery – Assessment Annexes
and need
Bibliography

Points to be considered as follows: PAS 1192-2 provides specific guidance for the

information management requirements associated with projects delivered using BIM. Figure 1

shows the information delivery cycle for new projects and for projects that are part of a larger
Alignment Framework between BIM and PMBOK® Processes 21

portfolio, or for projects working on existing buildings and structures. Sections in BLUE outline

the general process to follow for identifying a project need, procuring and awarding a contract,

mobilising a supplier, then generating production information and asset information relevant to

the need. This cycle could be included in the Project Management Plan in the PMBOK® Guide

to demonstrate how the information may be gathered, shared, monitored, and controlled, side

by side with the other Project Management Processes. It integrates and consolidates all the

subsidiary plans and baselines from the planning processes in a simple schematic. The PAS

1192-2:2013 document has an underlying driver, which focuses specifically on data

management, reports, and documents on project delivery, which is known as the Project

Information Model (PIM).

Figure 1 - The information delivery cycle


It is possible that the PIM integrated into the Project Information System (PMIS) or the

Enterprise Environmental Factors (EEF) portions of the PMBOK® Guide, which are discussed

in sections three and four.


Alignment Framework between BIM and PMBOK® Processes 22

The PAS 1182-2:2013 introduces a new term: Building Information Modelling

Execution Plan (BEP). It is not exactly a new concept, but it is new in that it is being added to

the formal project management guidelines for BIM: some companies have been including a

BEP in contracts in the last couple of years in order to protect against lawsuits around

miscommunicated information or mishandled models, poor conceptual drawings or mistakes in

plan execution, for example (Alp, 2014). The BEP sets out how communications will be

handled. It is prepared by the suppliers and the stakeholders, to explain how the information

modelling aspects of a project will be conducted. Contractors in the industry are currently

experiencing some uncertainty about how BIM works, and adding this to guidance documents

could drive its universal adoption. There are few guidelines, case law, or guidelines guiding

adoption of BIM for information management (Alp, 2014), and guidance contained in PAS

1192-2:2013 could serve as a starting point to integrate the concept into the Procurement

Statement of Work section in the PMBOK® and expanded to include other information within

the project plan. For example, statements of work may include, but are not limited to:

Specifications,

Quantity desired,

Quality levels,

Performance data,

Period of performance,

Work location,

Building Information Modelling Execution Plan (BEP), and

Other requirements.
Alignment Framework between BIM and PMBOK® Processes 23

The concept of the BEP is listed as one of the steps in the statement of work and relies

on the project participants and stakeholders to ensure that what is laid out there in meets

everyone’s needs before work commences.

One advantage of the PAS is that it may be used with all contract forms. The PMBOK®

Guide may be less clear than the PAS in showing the relationships between the contract and

associated documents, whereas the PAS includes figures, such as figure 2, below, which

demonstrate it clearly. Figure 2 or a similar flow chart or diagram might be used in the Plan

Procurement Management section to illustrate this relationship more clearly. Here, input from

the community which uses both the PMBOK® and the BIM would be critical to determining

the diagram’s utility, as well as where, exactly, it might best fit within the PMBOK® guidance.

Figure 2 - The relationships between the contract and the associated


documents
Currently, the client is obliged to appoint an information manager (sometimes called

the BIM manager) at all project stages, specifically to manage information in through the BIM

system. It is that manager’s responsibility and task to ensure that the proper information is

communicated at a level and in as much detail as is required by each stakeholder along the way.
Alignment Framework between BIM and PMBOK® Processes 24

This is not, at present, something that the project manager takes responsibility for: s/he may not

have the right skill set or experience with the system being used. We suggest that if the project

is small, the project manager could, in theory, handle this responsibility in tandem with the

other project duties as outlined in the PMBOK® with training. This could be promoted within

the PMBOK®, section 1.7 (PMI 2013).

2.2.2 Building Information Model (BIM) Protocol CIC/BIM pro (Construction

Industry Council, 2013)

The CIC/BIM Pro document, titled “Building Information Model (BIM) Protocol, is

another document which discusses a UK protocol for projects using BIM. It identifies the

Building Information Model (BIM) objects to be produced by project team members and puts

into place specific obligations, liabilities and associated limitations on the use of the

Information Model. It states that it was designed expressly for inclusion in direct contracts, may

be used to facility information flow without infringing on intellectual property IP rights, is

binding on all team members, and at the same time, is meant to ensure intellectual property

rights are maintained and well-defined as the project changes towards completion. The

document sets out general categories, with detailed descriptions of what rights and

responsibilities should be assigned amongst the team, which impact Intellectual Property Rights

IPR, who is responsible for what part of document management and ensuring integrity, as well

as how the document binds responsible individuals.

This language could be modified, linked, and incorporated into the PMBOK® Guide

procurement management knowledge area (KA) (2013) as well as the claim management in the

Construction Extension to the PMBOK® Guide (2007). The outlined protocol adopts many of

the core principles used in the preparation of the consultant appointment contract and schedules

of service (which can also be linked to the time management KA). The language could provide

a good deal of clarification on tasks and responsibility related to information management,

which may benefit all project team members and stakeholders by removing ambiguity. Project

teams perform better and can maintain better cross-team and team-stakeholder communications
Alignment Framework between BIM and PMBOK® Processes 25

when there are clear responsibility and definition for communication, as well as for the action

and deliverables (scope management). To consider specific sections to incorporate into the

PMBOK® GUIDE, by a section of the BIM protocol (CIC/BIM 2013):

3.2 Incorporation into contracts,

3.3 Permitted Purposes, and

3.4 Treatment of Intellectual Property

All those could be added to the contract.

Appendix 1: Levels of Detail and the Model Production and Deliver Table

Appendix 2: Information Requirements

2.2.3 BS 1192:2007 (BSI 2007)

The Collaborative production of architectural, engineering and construction

information – UK Code of Practice standard applies to all construction project documentation.

The principles are guiding information sharing, and common modelling may be equally applied

to building and civil projects. The set of project documents and each document within it are

viewed as a hierarchy of named ‘containers’. The BS 1192:2007 makes recommendations on

naming conventions: suggesting structured names to convey information (meta-data) about the

containers, which is required for effective information management and exchange. This

standard establishes the methodology for managing the production, distribution and quality of

construction information, including that generated by CAD systems, using a disciplined process

for collaboration and a specified naming policy: specifically, it recommends a common data

environment, then provides guidance on how it should operate.

The document contains a diagram suggesting the structure and architecture of the CDE.

It is reproduced here as figure 3, below. It features a Work in Progress (WiP) area. A Share

Point, an area for management of published documentation and information, and an archive.
Alignment Framework between BIM and PMBOK® Processes 26

Data are validated at each step to ensure continuity, suitability for residence if moved from the

WiP into the Share or incorporated in Documentation area. These functions could be integrated

into the PMBOK® as well, under the communications guidance in section 10. Both may require

reorganisation as part of the integration.

Figure 3 Document and data Management repository (BSI 2007)

2.2.4 BS 1192-4:2014

This document is titled: “Collaborative Production of Information”. BS 1192‑ 4:2014

defines the UK usage of COBie, an internationally agreed-upon information exchange schema

for exchanging facility information between the employer and the supply chain. COBie

(Construction Operations Building information exchange) provides guidance on a common

structure for exchange of information about new and existing Facilities, including both

buildings and infrastructure. COBie holds information about the spatial locations and the

equipment and components that make up the Facility. As COBie is strictly a guidance and not

a specification or procedure, its direct incorporation into the Construction Extension to the
Alignment Framework between BIM and PMBOK® Processes 27

PMBOK® Guide could be recommended. Further research on current practice, gained through

interview or questioners could be done to find out where it might fit.

2.2.5 Employer’s Information Requirements (EIR) Guidance

The EIR is a UK document guide designed to be included in the tender documents for

the procurement process (BITG 2016). The EIR is a key document with regards providing

guidance and procedures for communicating information as well as establishing information

management requirements. This guide has a lot of managing process related to PMBOK ®

Guide, informally, such as:

 Roles and responsibilities

 Planning the work

 Coordination process

 Collaboration process

 Health and safety management (Construction Extension)

 Systems performance

 Compliance plan

 Delivery strategy for Asset Information

The EIR may be integrated into the Contract Change Control System (PMBOK®

Guide) and the Records Management System (PMBOK® Guide). The EIR section on

Management is further divided into several sections dealing with:

 Standards: This could be added to 5.2 Collect Requirements process under scope

management in the PMBOK® Guide to be BIM standards requirements.

 Roles and Responsibilities: this section could be added to the tools and techniques of

9.1.2 Plan Human Resource Management


Alignment Framework between BIM and PMBOK® Processes 28

 Planning the work and data segregation: this could be added to 5.2 Collect

Requirements process under scope management in the PMBOK® Guide.

 Security: Neither the PMBOK® Guide nor the construction extensions include security

requirements for data because they do not deal explicitly with information

management. Security should be added to the PMBOK® and its Construction

Extension. Where and how this could be done may be determined by probing current

industry practice via a focus group, questionnaires, or forum questions and interviews.

 Health and Safety/Construction Design Management: This could be added to 13.1.3

Safety Management Plan to the construction extension to the PMBOK® Guide as a

subsidiary.

 Compliance Plan: This section includes: information on Quality assurance/control

procedures, associated software, and level of assurance. Those documents could be

included in the 8.1.3.1 Quality Management Plan in the PMBOK® Guide.

2.2.6 AEC (UK) BIM Technology Protocol (Core of the BIM)

The AEC (UK) Initiative was formed to improve the process of design information

production, management and exchange. One objective of the AEC BIM technology protocol is

to define best practices that ensure delivery of high-quality information and uniform

information exchange across an entire project. The section on Implementation Planning

could be incorporated into the PMBOK®. It is divided into subtopics including:

Roles and Responsibilities: Strategic, Management, and Production. The research will

focus on the second point management because it is the project-focused role. It brings up topics

such as Ownership of the Project BIM Execution Plan, the need to perform regular audits of

the project information, representation of the team at interdisciplinary model coordination

meetings, and management and quality control of the content creation and dissemination

process. These things may be integrated into the PMBOK® Guide, with input from the working

community to determine where and how to integrate them.


Alignment Framework between BIM and PMBOK® Processes 29

2.2.7 Building Information Modelling Execution Planning Guide

This USA guide explains what information may be included in a BIM Project

Execution Plan. This information can include:

1. Plan Overview Information

2. Project Information

3. Key Project Contacts

4. Project Goals / BIM Objectives

5. Organisational Roles and Staffing

6. BIM Process Design

7. BIM Information Exchanges

8. Collaboration Procedures

9. Model Quality Control Procedures

10. Model Structure

11. Project Deliverables

12. Delivery Strategy / Contracts

Some of these task-oriented project steps are available in the PMBOK® Guide; others

are not. Perhaps information contained in the Building Information Modelling Execution

Planning Guide could be added to the PMBOK® Guide construction extension.

2.2.8 Using BIM as a Project Management Tool:

“How can BIM improve the delivery of Complex Construction Projects?”

Broquetas (2010) suggests finding new ways information handling by moving from the

document paradigm to the Project Integrated Database paradigm. The information analysed

suggested that BIM might be the tool that promotes better integration of teams and information.

All the above references provide Project managers guidance on managing information

by utilising BIM. It can be difficult for project managers who do not have experience with BIM
Alignment Framework between BIM and PMBOK® Processes 30

to benefit from these processes. The researcher aims to come up with a formulation of necessary

actions around information management from BIM in a way that allows project managers to

utilise these procedures even if they do not have experience in BIM.

2.2.9 Building Information Model (BIM) Standards Manual by DASNY

The Dormitory Authority of the State of New York (DASNY), Building Information

Model (BIM) Standards Manual, describes the processes, procedures, and requirements that

should be followed for the preparation and submission of BIM on all projects. The DASNY

BIM Standards Manual guidelines were formulated to ensure Design Professionals produce,

release, and receive data in a consistent format, for multiple building types and customers. It

includes strong, specific compliance measures. Similar language could integrate into the quality

Audits section as part of the process. The DASNY BIM Standards Manual also includes BIM

Project Workflow guidance; its language and concepts might also be added to the Construction

Extension as a new Knowledge Area (KA) called Information Management.

2.2.10 The VA BIM Guide

The U.S. Department of Veterans Affairs (VA) Office of Construction & Facilities

Management (CFM) provides design, major construction, and lease project management

guidance, as well as design and construction standards, environmental, and historic preservation

services and expertise to the Department of Veterans Affairs. It may also offer language and

concepts, which might be incorporated into the Construction extension, with input from

professionals performing project management. It would need to be reviewed carefully against

the PMBOK® Construction Extension to develop similarity comparisons. In a brief

examination, one key point that the VA BIM Guide makes is that a BIM Management Plan

(BMP) should be developed as a master information/data management plan, which can be used

to assign roles and responsibilities for model creation and data integration activities at project

initiation. Its processes are designed to ensure team members, and VA project management

agrees on how, when, why, to what level, and for which project outcomes BIM will be used.

This level of detail fits neatly into a new Information Management KA proposed to be added
Alignment Framework between BIM and PMBOK® Processes 31

the Construction Extension of the PMBOK® Guide. This is an additional idea to be explored

amongst working project managers through a focus group format, as well as interviews and

forum questions.

BIM Roles and Responsibilities, as defined in the VA guidance, could be added to the

Roles and Responsibilities under the Human Resource Management Plan. However, more

investigation is needed. Guidance and suggested procedures to manage “Files, Security,

Waivers”, “Project Folder Structures”, “Data Security”, and ”Waivers” could potentially be

integrated into the PMIS as part of the Enterprise Environmental Factors.

2.3 Summary: list of procedures and guideline candidates

Numerous guidance documents, outside of the PMBOK® and its Construction

Extension, and have been discussed briefly. These various guidance manuals and may be used

to serve as templates and provide structure for a proposed Information Management Knowledge

Area (KA) and/or incorporation in existing KAs, according to expressed opinion. These have

been used as guidance in preparing questions for a questionnaire and survey for this study. The

research method, strategy, and project description, including how the external guidance

documents informed the question pool, will be discussed in the next chapter.
Alignment Framework between BIM and PMBOK® Processes 32

Chapter 3 Research Methods

3.1 Research Question Restatement

What BIM and other Information Management processes and procedures can be added

to the Construction Extension to the PMBOK® Guide and the PMBOK® Guide, to increase its

value in the field? How would the added processes and procedures affect the guide’s current

methods and techniques? To assess both how BIM is being used in practice as well as how

strongly working project managers feel about formalizing best practices around Information

Management in both the PMBOK® guide and its Construction Extension, the target audience

will be surveyed and asked to share their thoughts on what can be integrated from existing

guidance documents which are NOT currently part of the body of knowledge.

3.2 Research Strategy

This study is deductive. The author has done some preliminary surveying of working

professionals (as previously mentioned) to determine the knowledge gap in the PMBOK ® and

its Construction Extension, around using BIM and other Information Management processes in

their work (as described in section 3.1). He gained some a bit of insight into the direction the

research might take next, as well as a small sample of current thinking on the research question.

The sample is very small but can offer guidance on the direction the questions might take.

The approach to gather data to explore the research question will be to (1) conduct

interviews using prepared questionnaires. (2) Survey individuals were chosen from the first

survey to probe some details within the working project management community (expanded

questionnaire), and (3) lead or moderate a discussion in an online forum or web forum. The

target audience will be practising project managers from a wide variety of areas across the

private, government, academic, and military sectors (if consenting).


Alignment Framework between BIM and PMBOK® Processes 33

3.2.1 Justification of Method

This study will use questionnaires, and discussions within a forum setting or focus

group for the following reasons: this work proposes to add to the ‘best practices body of

knowledge, consolidating and collecting in the two most widely used and most reliable sources

of process and procedure available to project managers. The PMBOK ® Guide and the

Construction Extension to the PMBOK® Guide. Persons are working in the field either are now

using the BIM in their work, starting to use it, or exploring it. As stated previously in section

1.1, none of the knowledge areas (KAs) in the PMBOK® or its Construction Extension

explicitly addresses Information Management now. Project managers with experience in the

field can provide guidance and on how they might like to see information management sections

placed, and offer their input into the sections which the researcher believes may be included, as

well on how to integrate it. Working project managers may have a better feel for where this

information might best be applied, especially for the Construction Extension. This is how the

PMBOK® best practices were originally determined, collected, and organised (PMI 2016,

Wikipedia 2016a).

3.2.2 Choosing a Sample Size

The project management demographic may be targeted in some ways: via existing

online forums like ProjectManagement.com or LinkedIn, using a survey software tool, package

or website to distribute the survey to professionals in the field, or by reaching out to professional

organisations to coordinate with the Membership Committee to request membership

participation. As well, the author will attempt first to determine what a statistically significant

population for the survey may be. Information that is needed is:

 An estimate of how many practising project managers or project managers-in-training

Possible sources:

o Professional societies such as the Association of Project Managers,

o the Project Management Institute (exposure to a global audience),


Alignment Framework between BIM and PMBOK® Processes 34

o Recruiters’ blogs, such as “How to Manage a Camel” blog (Thorpe, 2009). The

principal, John Thorpe compiled data in 2009 and has a census project to count

working project managers, which live right now.

o National Careers Service Website.

 -A good idea of what confidence interval will be used (±2, ±4, ±5 are all good

examples)

 The confidence level the researcher wishes to use (95% for example)

The PMI has determined that of the 800,060 professionals holding PMI certifications

as of 30 November 2016, 745,081 are PMP certified. It is possible to estimate a good survey

size using the following expression, based on standard normal distribution statistics (Gaussian

distribution; SurveyMonkey 2017, AllCounted 2017):

Equation 1
𝑁 ∗ 𝑧 2 ∗ (𝑝) ∗ (1 − 𝑝)
𝑆=
𝑐 2 𝑁 + 𝑧 2 ∗ (𝑝) ∗ (1 − 𝑝)

Where z = number of standard deviations or standard normal deviation at the chosen confidence

interval, p is the fraction or likelihood of gaining a response (0.5 on a scale from 0 to 1), N is

the sample population (800,000 worldwide), and c is the confidence level or margin of error.

Table 1, below, contains a list of sample sizes for various confidence levels.

Table 1 Minimum Sample Size by Confidence Level


C 95% 90% 85% 80%
z = 1.96 z = 1.65 z = 1.44 z = 1.28
± 0.05 384 272 207 164
± 0.10 96 68 52 41
± 0.15 43 30 23 18
± 0.20 24 17 13 10
± 0.25 15 11 8 7
Alignment Framework between BIM and PMBOK® Processes 35

For a large sample pool, c2N >> z2 * p * (1 – p), so the expression can be approximated:

Equation 2
𝑧 2 ∗ (𝑝) ∗ (1 − 𝑝)
𝑆≈
𝑐2

It is necessary to have a valid audience to question, so that the responses may have

meaning and provide support to the recommendations based upon it. For this study, the initial

sample size estimate of 384 was based on a confidence interval of 95% with a margin of error

of ± 5%.

 this study will need a robust method to evaluate responses and weight them, based

on statistics.

o There are several survey websites which can be accessed for free and will

statistically analyse responses as well. These may include a calculator

page, such as those found at Survey Monkey or Creative Research Systems

websites. The calculator at Survey Monkey was used to design the study.

o For this study, the researcher may also use Excel Statistics macros to

evaluate the data: the Student’s T-test may be appropriate for this target

audience, depending on sample size and distribution of demographic

information. This will be the first statistical method of choice. If changes

are made in statistical analysis, they will be noted in the Data Analysis.

3.2.3 Designing the questionnaire and Forum Questions

The author has posted a test question or two on an online project management forum

(projectmanagement.com), to test response time and quality, and develop a feel for current

thinking on whether an Information Management KA might be developed, collected, and added

to the PMBOK®. While the number of responses was low, the degree of engagement of

respondents was quite high, suggesting that this is a valid way to deliver targeted questions for

a response (Al Jabri, 2016). In Chapter 2, the research collected material from the BIM or other

procedural guides (named below) and made suggestions as to where they could be included. As
Alignment Framework between BIM and PMBOK® Processes 36

well, some explanation of what each might add was added. These suggestions will be

formulated into the first basic questions, along with points raised in the probe question

submitted to the forum on projectmanagement.com (Al Jabri, 2016). As well, questions probing

their favoured work practices and procedures for information management, observations on

what works well, what needs improvement, and what the level of engagement may be, will be

added.

3.3 Next Steps: Project Description and Data Collection

The next chapter will contain the draft questionnaires and proposed forum questions,

with sorted and categorised responses. Some respondents will be tracked; as well repeat

respondents will be monitored for inclusion in the forum or focus group discussions.
Alignment Framework between BIM and PMBOK® Processes 37

Chapter 4 Chapter 4 Project Description

4.1 Business Drivers and Significance

It has been shown that, in practice, good, consistent information management can

reduce construction costs, prevent communications errors, catch potentially catastrophic design

errors in the planning or modifications state, as well as provide a cradle-to-grave history of a

facility from concept through its useful life, until final disposition. Drivers include management

of all inputs, ability to incorporate, track, and include suggestions, modifications, project

changes, costs, forensic evaluation, as well as all record-keeping of issues that might arise,

tracking of health, safety, and environmental impacts, improvements, renovations, and new

construction associated with the facility. The significance of this task lies in its contribution to

the body of good practices Body of Knowledge. The PMBOK® is acknowledged by much of

the project management community as the source of good practices and processes for project

management.

The field of project management is young, dynamic, and experiencing rapid growth.

As well, the responsibilities the project manager takes on are becoming more complex. The

project manager may not have had the specialised skills required to develop the BIM from the

beginning: addition of an Information Management KA to the PMBOK ® Guide, as well as

procedures to the Construction Extension, can provide guidance the project manager can use to

support information management from the beginning. It could be used to combine Project and

BIM management functions as it matures.

4.2 Benefits and Costs

Benefits of conducting the project using questionnaires and surveys accrue from the

input of working project managers. The field is changing rapidly – adaptability and

standardisation are required to contain costs and minimise error, and in place by mutual consent.

The best way to ensure this is to obtain input and support from the working community.
Alignment Framework between BIM and PMBOK® Processes 38

Information gathered for this study will be the most recent and accurate input available. Costs

are minimal to develop this information: preparation of questions for use in questionnaires and

forums involves time costs for the researcher as well as the community.

4.3 Implementation Method

The researcher proposes to reach out to professional project manager organisations,

such as the Project Management Institute membership, as wel7l as project management forum

sites such as Project Management Central and Project Management Dot Com. A few test

questions were posted and responded to on the Project Management Dot Com

(projectmanagement.com). Response and participation in offering input were satisfactory. As

well, information which might not have been generally available in the PM community was

offered regarding possible improvements to come in the sixth edition of the PMBOK ® that

could have benefited from this KA development study. The first question posted in a forum by

the researcher was used as a test to gauge responses for number and types of answers, as well

as probe a small group of respondents for their thoughts (Malik, 2016). It received 12

independent responses. These responses have been evaluated to determine if the discussion

stayed on-topic (yes). The question: “Do you thing [sic] that PMI should add a new knowledge

set called: Information Management in the new PMBOK®?”, posted on the Project Management

Central Forum.

4.3.1 Timeline

Expected time to complete the study was estimated at approximately four to six weeks.

A rough statistical calculation (Chapter 3) suggested that a minimum statistically significant

number of responses is about 384. Any number of responses gathered over the 384 minimum

will serve to strengthen the statistical significance of the data gathered.

4.3.2 The Survey Questions

Draft questions presented below, use informal language to address each survey

participant. Questions which seem appropriate for use in a forum environment as well are
Alignment Framework between BIM and PMBOK® Processes 39

marked as such in the list. These open-ended questions were also present in the survey, either

as written or reformatted as multiple choice or Likert-type responses. These are presented in

this section, in no particular order, whilst the prepared (and answered) surveys will be discussed

in Chapters 5 and 6, and the survey itself, in final form, is included in Appendix A. The

questions in the survey are focused and grouped to first to gather demographic information on

the respondents, second, to find out what their understanding of Information Management and

key practices related to it are and what they know of BIM and electronic data management,

then, finally, probe their experiences around Project Information Management - what they

understand about its strengths, weaknesses, and purpose gather examples. The first group of

questions probed the respondents’ understanding of BIM and usage. Some questions were

reworded and asked twice, in both closed-ended questions at the beginning of the survey and

in open-ended format at the end, after various other guidance documents were mentioned, to

allow the respondent to freely share thoughts again, late in the survey. Some demographic data

was requested first, to determine if there is some bias related to a number of years of experience

or types of projects managed. The researcher did not seek gender or age information, as it is

not relevant to the information being gathered and probed.

Selected multiple-choice responses were qualified with an “explain” optional text box

where the responder could elaborate. Surveys and questionnaires have been posted on

“AllCounted” survey website. Survey responses are collected, collated, and analysed

statistically. Outputs include pie charts, bar graphs, trends, and lists of comments or information

on outliers. More in-depth analytical tools are available if needed; however, for this study, the

free analysis was adequate to characterise responses. Survey links went out by EMAIL,

containing an access code to maintain target population integrity and prevent one respondent

taking the survey multiple times. The survey was tested and modified before going ‘life’.

4.3.2.1 Question List

The question grouping is generic and focuses on probing the respondent’s

understanding around BIM or Information Management, whether the respondent has used some
Alignment Framework between BIM and PMBOK® Processes 40

of the formal tools (or is even aware of them), and what s/he considers to be ‘best practice’.

These may include questions like those listed below:

1. How do you manage data, information, and reporting between yourself and your

stakeholders on a project?

2. What do you consider ‘best practices’ in managing project information?

3. Do you use any electronic workspaces to share, categorise, organise, and archive

project information passed between your client, your project team and yourself?

a. How well do they work together?

4. Do you use Building Information Management (BIM) or work with a BIM manager

on your projects? Please share your thoughts.

5. Would it be helpful to you if the PMBOK®® and the Construction Extension (CE)

contained an Information Management KA in addition to the Communications

Management KA?

6. Do you consider developing a proposed Information Management KA for inclusion

in the PMBOK® Guide and Construction Extension a reasonable step in developing

and expanding best project management practices?

The next group of survey questions was taken in part from the questions listed below,

and partly from material in Chapter 2 on external guidance documents which contain process

which may serve as proposed additions to the PMBOK® Guide and the Construction Extension.

These provided the guidance and detail for questions addressing these other guidance

documents and the respondents’ knowledge of them. A test question was posted on the Project

Management Central Forum in September 2016 (Al Jabri, 2016) and has been asked again in

this more detailed grouping. It was: “Should the project management community actively work

to include more Information Management procedures and other process guidance into PMI’s

body of knowledge documents?” (Al Jabri, 2016). More generic questions on what ‘best

practices’ work best for the respondent, as well as a variant of the table below, with explanatory
Alignment Framework between BIM and PMBOK® Processes 41

text and ability to select multiple checkboxes, was included. The list of additional candidate

questions includes:

1. What specific BIM and other information management processes and procedures

do you think should integrate with the Construction Extension to the PMBOK®

Guide? A list of suggestions is included below. Please indicate which ones you

have used as well as which you would like to see included, and where (existing KA

or a new “Information Management” KA). You may check for ‘yes’. The last

column comment space is optional.

Table 2 Non-PMBOK® Documents which contain Information


Management or BIM Guidance
Familiar Use? Incorporate in Where? Comments (opt.)
with? PMBOK® Const.
Guide? Ext.?
PAS 1192-2:2013
Building Information
Model (BIM) Protocol,
CIC/BIM pro
BS 1192:2007
BS 1192-4:2014
AEC (UK) BIM
Technology Protocol
BIM Execution Planning
Guide
DASNY Building
Information Model
(BIM) Standards Manual
The VA BIM Guide
PAS 1192-2:2013 (BSI 2013) – specifies requirements for achieving building information
modelling (BIM) Level 2
Building Information Model (BIM) Protocol, CIC/BIM pro (Construction Industry Council,
2013) – identifies BIMs that must be produced by members of the Project Team and specifies
obligations, liabilities and associated limitations on the use of the models
BS 1192:2007 (BSI 2007) – guidance on the methodology for managing the production, distribution
and quality of construction information, including that generated by CAD systems
BS 1192-4:2014 – COBie guidance document: expectations for the exchange of information
throughout the lifecycle of a Facility
Employer’s Information Requirements (EIR) Guidance
AEC (UK) BIM Technology Protocol (Core of the BIM) – guidance on paying explicit attention
to design data management, display and quality
Alignment Framework between BIM and PMBOK® Processes 42

Building Information Modelling Execution Planning Guide - provides a structured procedure,


for creating and implementing a BIM Project Execution Plan (BEP)
Building Information Model (BIM) Standards Manual by DASNY – guidelines for ensuring
consistency in data and information generated from that data
The VA BIM Guide – guidance on using BIM to deliver maximum lifecycle building performance.

In the event, it becomes necessary to physically administer the questionnaire in a

physical forum or focus group; a modified paper questionnaire has been prepared with the same

core questions as the survey with focused follow-ups where appropriate, from questions listed

in this section. Results, statistics, and figures produced from the survey results will be

presented, in the next section.

The next group of questions in the survey focuses on obtaining the respondent’s

opinion of the perceived completeness or degree of lack of Information Management within the

Communications Management KA in the fifth edition of the PMBOK ® Guide. As well, the

respondents were asked about practical problems or successes they may have had on projects,

as well as what each respondent considered his or her best practices around Information

Management. Again, forum questions will be labelled as such, are designed primarily to gather

consensus on what working managers consider important, as well as answer questions the

researcher feels are critical. Questions were tested online, then reworked into the final format,

included in Appendix A.

1. Should the community actively work to include more Information

Management procedures and process into PMI’s body of knowledge

documents?

2. Responses to the first query on the project management forum indicated that

some people feel that PMBOK® was fine as it is and that relying on the

Communication Management KA provided enough support for project

managers to guide formal Information Management incorporation in project


Alignment Framework between BIM and PMBOK® Processes 43

procedures using BIM. Do you agree or disagree? Why? Please share your

thoughts.

3. In defining employer information requirements (EIR) per guidance in PAS

1192-2:2013. It is implied that one of the core functions of the EIR is to make

sure the project stakeholders gather and supply the information needed to

satisfy the client’s requirements for the solicitation of a contract proposal and

BIM Execution Plan (BEP) contract.

a. How do you organise information to fulfil that requirement?

b. Do you feel that more explicit guidance (process) needs to be added

explicitly to the PMBOK®?

c. Do you support the addition of this information, as well as procedures

for doing so be integrated into the construction extension as well?

4. Have you experienced communications and/or formatting issues between

stakeholder software and other project stakeholder software on a project? How

was this addressed?

5. Do you support actively supporting and incorporating the buildingSMART

(formerly known as International Alliance for Interoperability) efforts to

impose a standard, neutral non-proprietary data format (Industry Foundation

Classes) as a specification for standardising Information Management?

6. Do you use a BIM solution which supports (Industry Foundation Classes)

IFCs?

a. Do you know whether this support is robust or minimal?

b. Do you have a feel for what BIM solutions your clients favour?

c. Which ones do you favour? Why?

7. The buildingSMART consortium provides standards under the openBIM

name. Are you familiar with them?


Alignment Framework between BIM and PMBOK® Processes 44

a. What do you think about the movement to standardise Information

Management process and procedures in the same manner that best

practices for project management have been?

b. What do you see as the benefits of doing so?

8. How can the Construction Extension to the PMBOK® Guide benefit from

integrating BIM standards in information management?

9. Are you aware of vendor commitment to BIM standards integration in project

management solutions from companies like Autodesk?

10. How do these compare with information processes in PMBOK®?

11. Do BIM information exchange procedures and terminology differ from those

in PMBOK®?

Versions of the questions listed as samples, previously, were assembled into a three-

page long survey of thirty-two questions, built up and deployed on AllCounted dot com. The

researcher tested and edited the material for clarity, flow, and mechanics, then brought the

survey ‘live’. Questions were also distributed on paper in several ways to a target audience – a

focus group - to supplement the online responses. For the online survey, a group EMAIL was

sent, containing a request and web link to the online survey site, asking recipients to forward

the survey links and invitation to anyone they knew who might be interested, also. More surveys

were distributed, by posting to online forums and LinkedIn. The target audience has been

previously defined as the global PM community

4.4 Focus Group

The Merriam-Webster Dictionary defines ‘focus group’ as “a small group of people

whose response to something (such as a new product or a politician's image) is studied a small

group of people whose response to something (such as a new product or a politician's image) is

studied to determine the response that can be expected from a larger population” (2017). In

research, it provides a qualitative measure of where people’s thinking on a topic or subject lies,
Alignment Framework between BIM and PMBOK® Processes 45

wherein the group has time to think about the topic and discuss it with others in a safe space

that may help put them at ease, cause them to find, and express additional insight.

If insufficient online survey responses are obtained, the researcher will assemble a

focus group to obtain additional answers to the survey questions. The Likert-type closed end

questions will be converted to open-end questions to encourage the group to respond. The

prototype of the focus group survey is attached here, in Appendix C. Focus group forums will

be composed of a small group of people in each case. The researcher will be seeking input from

a minimum of three, but no more than five groups of 10-20 members. This is larger than the

recommended focus group size (Krueger, 2002), but the researcher can justify this because the

encounter will be conducted, beginning with a presentation and interview, followed by

requesting participants fill out the modified questionnaire. A number of construction and

engineering firms will be contacted in order to find participants, in order to address concerns

about a non-random sample (Krueger, 2002). The document sets out procedures and guidance

on how to set up and is attached here in Appendix D.


Alignment Framework between BIM and PMBOK® Processes 46

Chapter 5 Data Analysis

The scope of work for this study is to determine how to best develop an Information

Management Knowledge Area for integration into the PMBOK® and its Construction

Extension, based on Building Information Model Standards. As previously stated, the

researcher sought from the global project management community, input on common ‘best

practices’ around data, information, and reports of what the project management community is

using today. The working community provided the data used to gauge how Information

Management is practiced in their daily work, as well as what guidance and procedures they are

using; in addition, they shared both what is working as well as what they’d like to see improved

in the process of managing the project information for a facility.

The analysis of the responses presents a snapshot of Information Management current

practice, some information of what additional support and guidance they might find useful, and

some discussion of the respondents favoured methods and practices if any. The researcher

desired to obtain, at a minimum, 384 responses as calculated in Chapter 3, but the final tally of

responses was twenty-one (21) from the online survey, and 12 from the focus group.

Because the online survey return rate was low, the physical questionnaire was deployed

as well (Appendix B). In this version of the questionnaire, some closed-end questions were

converted to open-ended ones, to encourage free expression of opinions. An attempt was made

to set up an online forum or round-robin to work through the forum questions. Not enough

people to meet the statistical criterion were all available at the same time. The forum questions

were made available as a survey and deployed within a focus group. Those responses were

evaluated in combination with the online survey responses, and separately as well, because of

some contrasts in responses when compared to the online survey engine which suggests an

institutional bias towards procedures internal to the firm which employed the focus group.

Open-ended question responses have been collected and similar responses grouped

together for statistical evaluation. By ‘similar’, the researcher considered questions which said
Alignment Framework between BIM and PMBOK® Processes 47

the same thing (or could be interpreted as saying the same thing), but, perhaps, not in the same

words, as the same response. This involved some interpretation, aided by a dictionary and

thesaurus, and manual evaluation in Excel by the researcher. Responses provided insight, also,

into the main information processes that were considered most useful by the project managers

who responded. The responses shaped the form of the proposed Information Management KA

and drove the study towards a consensus on how the proposed KA could be integrated into the

PMBOK® Guide and its Construction Extension. How the details of the information gathered

will be discussed below.

5.1 Survey Responses

Survey responses were analysed for each question in real time, as they were answered,

at AllCounted dot com, using their proprietary algorithms. The researcher spot-checked

analysed and added to the overall statistics if required (AllCounted, 2017). As stated previously,

on average, the number of respondents totalled twenty-one (21) for the online survey responses

and 12 more from the focus group and forum. This did not meet the original estimate of desired

responses to support a minimum of a 95% confidence level in the data, so several additional

calculations were made, to determine a reasonable confidence interval and statistical error. The

governing equation for those calculations is included, below. To calculate confidence intervals

on the actual number of responses obtained after the study completed, the following equation,

based on standard normal distribution, was be applied (SurveyMonkey 2017, AllCounted

2017):

𝑁−𝑆
𝑐 = √( ) ∗ 𝑧 2 ∗ (𝑝) ∗ (1 − 𝑝)
𝑁𝑆

Table 3 contains those calculations of ‘c’ values for the focus group questions (12), the

online survey questions (21), and the combined dataset (33), for confidence intervals from 80%

to 95%:

Table 3 Calculated margin of error for a given sample size.


Alignment Framework between BIM and PMBOK® Processes 48

S 95% 90% 85% 80%


12 28 24 21 19
21 21 18 16 14
33 17 14 13 11

Where z = number of standard deviations or standard normal deviation at the chosen confidence

interval, p is the fraction or likelihood of gaining a response (0.5 on a scale from 0 to 1), N is

the sample population (800,000 worldwide), and c is the confidence level or margin of error.

If the 21 online responses are considered separately, they conform to an 85% confidence level

with a margin of error of 16%. When all responses are included, they conform to a 90%

confidence level at 14% margin of error. The results have utility as an indication of trends for

the sample size. The physical questionnaire, given in an interview format to a focus group

yielded other significant data which was evaluated, combined with the online survey data and

separately, to conclude the overall analysis.

As an example of how responses shaped the categories of answers, consider the first

survey. Question 5 in the survey and question 4 in the questionnaire represents the first non-

demographic question in the survey. It asks, “How do you, as a Project Manager, define

Information Management?” Responses for the question fell easily into categories. To illustrate

this, all 21 answers from the online survey and 12 responses from the focus group are listed,

below, as written, unless otherwise noted.

Online Responses 1-7 Online Responses 8-14 Online Responses 15-21


For me the Information management Sharing structured
is to have accurate information information
available at the time when it is
required. For example in design
management, I need to know the
information about utilities, right of
ways, access needs, environmental
issues, inter-governmental
a collaborative environment agreements and so on during
that contains project data for different stages of design process.
the whole project lifecycle, Similarly for construction
and managed by certain management, information about
stakeholders with a pre-setup availability of material, equipment
accessibility to it. and other resources must be timely.
Alignment Framework between BIM and PMBOK® Processes 49

generating, collecting, processing, The capture, storage,


analyzing, storing, communicating safeguarding, management ,
All documants that related to and ultimate disposition of project collaboration and reporting
all project aspects such as the data of project related
project contract, project information. This includes
charter, scope, master plane, planning and execution of
resk plan, schedule time, QT, handover of information to
drawing, change orders .. etc the employer.
information management is key The generation. processing,
element for the success of project storage, communication,
especially during design stages flow governance and
when different components are ultimate disposition of all
being designed like, project data
structure/arch/MEP/ID/SYSTEM
than proper integration is not
possible if appropriate information
system is not in place, also
communication with different
stakeholders on timely manner is
essential, the information
management system in a net shell
can be defined as what, when and
who will produce the
information/communication and
format is well defined to produce
the information. the information
management system is also play
vital role in execution/monitoring
All information and and control especially producing
documents related to the reports on earned values and status
project includes charter, and as well in close out to collect
contract, drawing, plans, and distribute the necessary
change orders, etc documents.
Application of management It is the definition of info The group of procedures to
techniques to collect requirements, info collection, info ensure the flow of
information, communicate analysis, info modelling and info information for all the
and process it to enable communication. concerned stakeholders
managers to make quicker
and better decisions.
Application of management It is very important tools the process of creating an
techniques to collect information management
information, communicate it plan that documents how
within and outside the the project information will
organization, and process it to be defined, validated and
enable managers to make controlled.
quicker and better decisions.
Collecting predefined data It's the system that simplify the The way for collecting
during execution of the communication and the distribution information to get the most
project then processing such of all information to those who need you can get
data according to predefined it on time.
rules in order to generate
predefined reports and
outputs used in decision
making while executing the
project.
a collaborative environment proper Collecting, analyzing & the way you control, store,
that contains project data for distribution of data through and share information flow
the whole project lifecycle, stakeholder over all project phases in your project
and managed by certain
Alignment Framework between BIM and PMBOK® Processes 50

stakeholders with a pre-setup


accessibility to it.
As something vital to achieve For me the Information management Sharing structured
greater efficiency and quality is to have accurate information information
in the construction of available at the time when it is
enterprises, in order to required. For example in design
achieve the goals and management, I need to know the
estimated profits (translated information about utilities, right of
from Portuguese) ways, access needs, environmental
issues, inter-governmental
agreements and so on during
different stages of design process.
Similarly for construction
management, information about
availability of material, equipment
and other resources must be timely.

Focus Group Responses 1 - 5 Focus Group Responses 6 - 10


It's meaning How to control and handle the Information management may be described as
information about the project such as the achival of information, document, historical
comunication and saving documents and recordes, and the ultimate disposition to all
contract. stakeholders. Also includes the when, the who,
the whow information will be transferred.
It is the Life project because the project consider It is the way you best organize the information
handling of data or information you have to keep to better use in the project.
& save it to lead the project to successful end.
The information management is the most Saving time and cost.
important issue in project management, to
manage the data, time, cost and stakeholders.
Documentation, formatting, and preservation of Information should be shared between all the
information. Recall the information when concerned parties/individuals in a timely and
needed. effective manner
the mangement that includes the process to Information manager containing but not limited
ensure that the project includes all the work to:
required and only the work required to complete 1 - recived all info. without any wastage from
the project successfully. stakeholders
2 - Recording it throug a list, sheet forms ... to
protect it from forgotten
3 - validating the info. and to make sure it
comply with the project (contrains, goals,
organsisation policies ...)

These were grouped into seven groups, initially, based on what keywords were

mentioned and often repeated in the responses, such as ‘data flow’, ‘data organisation’,

‘lifetime’, or ’time’, for example. The phrases considered as ‘commonly used’ were constrained

by limiting them to those contained in the formal description of information management, as

described in the literature. Most respondents recognised that data flow and communication were
Alignment Framework between BIM and PMBOK® Processes 51

important, that Information Management (IM) was needed to keep all stakeholders, team

members, and the project on-track, and that IM included managing drawings, plans, contracts,

communications, and modifications. Others saw IM in terms of efficiency, collaborative

projects, or simply, as a tool. Some respondents also mentioned electronic and paper

communications, drawings, plans, updates. Alternatively, may employ a records assistant to

organise and track information (own opinion).

Statistics to determine variance, standard deviations and other functions and plots

prepared using Microsoft Excel Spreadsheet statistical functions and graphics or calculated

automatically, online, as surveys were completed. The distribution of answers for the question

will be used to gain insight into current thinking in the working PM community.

The first question posted in a forum by the researcher was used as a test to gauge

responses for number and types of answers, as well as probe a small group of respondents for

their thoughts (Malik, 2016). It received 12 independent responses. These responses were

evaluated to determine if the discussion stayed on-topic (yes). The question: “Do you thing [sic]

that PMI should add a new knowledge set called: Information Management in the new

PMBOK®?”, Posted on Project Management Central Forum, “ProjectManagement Dot Com”.

Responses from this small group of professionals seemed to indicate a conformity of procedures

within it (12 responses, Al Jabri, 2016). This information was not lumped into the results of

assessment; rather, the question was recycled into one of the surveys so that a more

representative, statistically sound number of responses could be obtained. Results will be

presented, below.

5.1.1 PMBOK®/Construction Extension Surveys

This survey was presented as a preliminary probe of the Project Management

community to sample current thinking on Facilities Project Management (PM) tools and

guideline usage, as well to gather input on how well working project managers think

information management guidance 'best practices' are addressed in the PMBOK® and its
Alignment Framework between BIM and PMBOK® Processes 52

Construction Extension. The survey has thirty-two questions, four of which are background

questions. The rest are mostly multiple choice with an occasional option to comment in a text

box. More surveys were submitted with all questions answered than were not; if a question was

skipped it was usually a short answer, and in some cases, based on responses found later in the

same survey, the respondent often indicated that s/he was not familiar enough with the question

subject for the questions skipped. A deliberate decision was made not to collect a lot of

demographic data. In every case, the goal was to obtain as unbiased a response as possible, by

accepting the diversity of project manager types without probing too deeply into additional

disciplinary details in the target population surveyed.

The next few questions after the first four were designed to determine how the

respondent thinks of information management: whether an integral part of their practices or a

milestone to be hit, without truly leveraging its ability to facilitate project costs and risk

management. By question 6, questions began to turn to procedure and practice, as well as

introduce questions regarding knowledge and use of BIM.

In conclusion, the twenty-one online responses obtained, plus the additional focus

group questionnaire results (twelve total) suggested that BIM is not yet used routinely and

widely, but that PMs are aware and beginning to think about and address Information

Management (IM) and digital formats and tools, as they go about their work. Results regarding

whether this should be addressed more directly in the PMBOK® and the construction extension

were interesting (questions 6 and 13 in the written questionnaire, and questions 7, 8, 13, and

15, online survey). Those who answered online (21 responses) tended to support adding a new

KA and adding digital information management guidance dispersed throughout the PMBOK®

and construction extension, whereas, for the paper questionnaires and forum responses (12

responses), respondents appeared to be less supportive, or supportive with much more limited,

concrete suggestions on where and how this could be accomplished. Recall, some of the

questions were rather and generic, made so deliberately so that the respondent’s understanding
Alignment Framework between BIM and PMBOK® Processes 53

of the question guided the answer. These and the other responses will be discussed in more

detail in the next chapter.

5.1.2 Guidance Integration into the PMBOK® Guide/Construction Extension

Some of the questions were focused on examining respondent knowledge of guidance

documents other than the PMBOK® and the Construction Extension, to determine any

familiarity, and opinion of guidance provided if any. Earlier in this document (Chapter 2), the

researcher presented guidance documents which dealt with Information Management (IM) and

BIM usage and contracting and included links in the table within the survey, so that the

respondent could refresh themselves, or find out what a specific document contained. With some

explanation of each document and what it contains. In each case, the goal was to probe for

confirmation or contradiction from the PM community regarding whether the researcher’s

suggestions on whether to include, where to and include and what to include from these

documents.

5.1.3 PMBOK®/Construction Extension Open-ended Questions

There were seven open-ended questions posed at the end of the survey, which approach

some of the same questions and topics covered previously in closed-ended format. This was

designed to encourage the respondents to share opinions or anecdotes on their experiences after

presenting the external guidance documents and guiding them, hopefully, to review contents.

As well, it might be possible to determine if a respondent’s opinion was modified, or changed

between the beginning and the end of the survey. This worked out well some anecdotes were

gathered that provided more insight. The goal was to try to start a series of online discussions,

as well, to gather consensus then compare focus group responses against those from the online

surveys.

5.1.4 Focus Group Interview: MOHAP

The researcher conducted a group interview to obtain the paper responses. The

respondents work for a contracting company called “Modern Horizon Advanced Projects
Alignment Framework between BIM and PMBOK® Processes 54

(MOHAP)”. The focus group was limited to this firm, because, of all the firms contacted, they

were the only ones willing to talk with the researcher face to face. Several others indicated that

personnel at the firm would fill out the online survey, but all failed to do so except one set of

responses was collected from a respondent who was employed by Saudi Makeen Co. In total,

the questionnaire was submitted to consisted of 15 participants: all engineers from different

disciplines. Information on the different disciplines represented was not gathered, as it was not

felt to be relevant to the responses; rather, inquiries regarding project management experience,

as well as kind of projects each had managed, was obtained. The researcher introduced himself,

outlined the purpose of the study, gave a small introduction about and description of BIM and

possible advantages, and then distributed the questionnaire forms to the participants. Two of

the fifteen participants withdrew from filling out the questionnaire because they felt that they

did not have enough experience in project management standards to answer the questions.

One of the fifteen participants missed the first page of the survey, so that survey was

not included in the analysis. Thus, the final count of surveys gathered from the focus group

interview was twelve. The data were transcribed (in one case from Arabic), converted to digital

format, collated, and evaluated. The researcher noted that some of the participants might not

have understood the first question properly; they replied ‘Other’ with additional comment,

mentioning having attended a PMP workshop, but not indicating whether they had been

licensed/ PMP workshop attendance does not confer either a certification or a license. That said,

responses from the group interview provide a different point of view in that institutional

preferences, rather than personal ones seemed to dominate the answers. In other words,

responses seemed less random when compared with those obtained from the online survey:

these contrasts and features will be discussed in detail in the next chapter. As mentioned

previously, one participant answered in Arabic, so the researcher translated his answers to

English (designated in red colour - Appendix C). Participants who did not choose any option

for question one were eliminated as not certified or licensed. Wherever possible, quantitative

or Likert-type responses were entered into a spreadsheet for further evaluation such as plotting
Alignment Framework between BIM and PMBOK® Processes 55

and statistical evaluation. Statistics were assumed to follow a standard normal distribution, as

before (Gaussian), both separated and in combination with those obtained from the online

survey
Alignment Framework between BIM and PMBOK® Processes 56

Chapter 6 Survey Results

To sample the opinions of the working community on the amount of guidance around

the use of Digital Information Management tools such as BIM, and Project Information

Management (IM) in general, an online survey questionnaire and paper-based questionnaire

were prepared and submitted for respondents to fill out. In total, thirty-three responses were

obtained. The researcher recalculated answer statistical significance based on the small sample

size, and determined that the minimum number of total responses which could be considered

as representing the 90% confidence level for a sample size of thirty-three, is thirty, for twenty-

one responses (online survey) is 85%, for a sample size of twenty-one responses, and 85% for

the group interview responses, all with a margin of error of ±15% Those questions which the

researcher considers being critical to gauging community opinion were answered by all

respondents, and allow some conclusions to be drawn. The working community provided the

data used to gauge how Information Management is practised in their daily work, as well as

what guidance and procedures they are using. As the researcher hoped, they were quite willing

to share both what was working for them, as well as specifics on what improvements and

additions they would like to see incorporated, if they agreed that more guidance was needed.

6.1 Discussion structure

There are some interesting differences between responses gathered on AllCounted dot

com and those from the questions obtained on paper, so the two sets of data will be discussed

separately. One set of answers in the online survey were submitted in Portuguese; the researcher

could obtain translations to incorporate that data into the results, they were quite helpful. Data

from the AllCounted dot com surveys is included in collated form, in Appendix D. Data from

the online surveys, in both raw and collated form are attached in Appendix E.
Alignment Framework between BIM and PMBOK® Processes 57

6.2 AllCounted dot Com Survey

The online survey, consisting of thirty-two questions over three pages, required about

30 minutes to complete. Figures 4, 5, 6, and 7 illustrate the demographic information for the

online survey.

Figure 4 Are you or have you been a project Manager?


Alignment Framework between BIM and PMBOK® Processes 58

Figure 5 Licensed or Certified? What kind?

Figure 6 Years in Project Management?


Alignment Framework between BIM and PMBOK® Processes 59

Figure 7 Type of projects worked on?

The demographic data generated online shows a wide spread of data: slightly over 80%

of the respondents (17) have project management experience as presented in figure 4, and most

have some type of certification or training (Figure 5). As well, the range of experience is well

distributed, with only one respondent having three years or less experience managing projects.

This suggests that responses to the questions would be obtained from respondents who have

worked as a PM long enough to have used a variety of tools, have been involved with variety

of projects, have encountered several different tools, and would have a good idea of what

processes and procedures that work for them, as well as strong thoughts about process and

procedures that they might like to see expanded or improved. The fourth question, regarding

the kinds of projects each respondent had/has worked on, permitted selection of multiple

answers by the respondents, and again, there is a wide range of project experiences represented.

Most respondents have direct construction experience, as well as other types of project

experiences.
Alignment Framework between BIM and PMBOK® Processes 60

Figure 8 Question 7 responses: Should more ‘best practices’


IM guidance be added to the PMBOK®?
The next set of questions, five through ten (5 – 10), were concerned with Information

and Data Management: with what the respondent understands that it is, with what tools and

techniques the respondents have used or know about, as well as what protocols and procedures

they may have used, and any information the respondents cared to share on how well they may

have worked in practice. The respondents all appeared to have agreed on key process and

practice that they felt constituted sound information management, or rather, how, in practice, a

project manager should proceed to manage communications, data, drawings, stakeholder

communications, etc. using his/her best practices with digital tools, BIM (if the respondent was

familiar with it, and collaborative work spaces. The data indicate that the respondents, no matter

the number of years of experience in project management, mentioned the same things as being

characteristic of ‘sound information management’. Many had some experience with or were
Alignment Framework between BIM and PMBOK® Processes 61

beginning to use digital tools like BIM and 3D CAD systems (most of which support Industry

Foundation Classes or IFC in BIM).

Figures 7 and 8, above, summarise the responses to questions 7 and 9, which ask the

respondent’s opinion on the need to add more guidance on information management, digital

tools, and workspaces, such as BIM, common data environments, and others, to the PMBOK®

and its construction extension. Questions 5, 6, 8, and 10 probed specifics and asked for a

detailed opinion, using open-ended questions.

In figure 8 (question 9), respondents indicated how many and which electronic

workspaces they may have used if any. Results seem to suggest nearly two-thirds of the

respondents are familiar with both BIM solutions and using Cloud services for information

management and communications. It is not known if these were third-party solutions or not.

However, a good number of respondents were familiar with MS SharePoint and common data

Figure 9 What kinds of electronic workspaces have you used


(multiple selections possible)
environment workspaces, as well as 3D CAD. Associated with these responses, questions 5, 6,

8, and 10 provided more detail and insights. For example, with question 5: it appears that all

respondents have the same or very similar understanding of the meaning of information
Alignment Framework between BIM and PMBOK® Processes 62

management (paraphrasing): Information Management may be described as the archival of

information, documents, historical records, drawings, and the ultimate disposition of

information, drawings, calculations, documentation, etc., related to the construction and facility

lifetime, to all stakeholders. It also includes when, who, how, and why information will be

transferred.

In a few cases, the respondent discussed IM in terms of facility life-cycle management,

where IM begins at project conception and continues throughout the life of the facility. Most

respondents also indicated an understanding of IM which includes managing all information

and communications, including drawings, project notes, change orders, renovations, etc., which

also implies an understanding of the need for cradle to grave management. Nearly a third of the

responses also emphasised the cost and time efficiencies which IM makes possible. Question 6

followed this up by asking respondents to explain what procedure the respondent might use to

handle IM in practice on projects. The responses spanned a broad spectrum: in some cases,

respondents listed tools, others shared their favoured procedures for team-building, developing

mutual trust with the stakeholders, and steps toward building an IM protocol tailored to their

project and client. There were only fourteen responses gathered online for this question, and of

these, just four respondents mentioned formalising protocols, process, and procedures in

writing explicitly or implicitly. Those who did not mention formalising, appeared to expect that

their IM solution (almost always electronic in each case), would cover all contingencies,

making their management duties easier, more efficient, and uniform. Questions 7 and 8

essentially asked the same question: the first offering a Likert-type scale of responses, and the

second requesting free expression from the respondent of his or her opinion and input. The

responses to question 7 indicated that about ninety percent of the respondents, nineteen of

twenty-one, thought that more guidance on information management and digital tools could be

added to both the PMBOK® and the Construction Extension (CE) as a new Knowledge Area

(KA), and incorporated in the other KAs as appropriate to support an IM KA. In question 8, the
Alignment Framework between BIM and PMBOK® Processes 63

responses contained both criticisms of the PMBOK and CE documents as well as suggestions

on where more guidance may be needed.

Those who felt more explicit IM guidance was needed, made a number of points

regarding what each perceived as lacks or weaknesses in the PMBOK documents. Several

pointed out the lack of any guidance for digital tools and workspaces, the lack of concrete, real

examples of the different process, and templates addressing new procedures. As well, one

respondent noted that the concept of ensuring systems interoperability had not been discussed

or included in the PMBOK® or the CE, and suggested those were sorely needed. Respondents

also suggested that more detailed guidance could promote and sustain a collaborative

environment between team and stakeholders, and in a few cases, advocated for adding examples

and templates to illustrate basic workflows and procedures. Others advocated for updates to

both documents which would include concrete, real-world examples of completed projects or

life-cycle monitoring, process and protocol templates, suggestions assistance with for digital

tools, and how-tos for IM and BIM. All but two of the respondents were at least familiar with

BIM: most were using it or testing it for deployment as a protocol in project management. Two

respondents did not feel an additional KA was needed but also suggested that existing

information in the Communications KA could be expanded and updated to include the latest

tools and field-tested protocols. This study concentrated on the fifth edition documents. One

respondent mentioned the latest update (sixth edition) as lacking robust best practices guidance

in electronic tools, information management process and protocols. In short, the majority of

online survey respondents felt the PMBOK and Construction Extension could be updated to

incorporate more information management guidance, noting that BIM, 3D CAD solutions,

Cloud server workspaces, and common data environment technology is growing more

sophisticated and commonplace as a protocol for efficient, thorough project management.

The next set of questions, eleven through fourteen, finishing the first page, concerned

communications amongst the PM, team, and stakeholders. Figures 10, 11, and 12 present the

responses to questions eleven, twelve, and thirteen (next page), which asked how well the
Alignment Framework between BIM and PMBOK® Processes 64

respondent feels communications generally go during a project, and, if issues have arisen at any

time, where s/he thinks they could have originated; in other words, what sticking points to

smooth communications and robust information management has the respondent experienced,

which impeded the flow of communications flow and information sharing. Question 13 asked

if the respondent would be supportive of an Information Management (IM) Knowledge Area

(KA)

Added to the best practices, that is independent of or is incorporated in addition to the

Communications KA in the PMBOK® and/or its Construction Extension. About 85% of

respondents agreed it could be useful to add an IM KA to the PMBOK® and its Construction

Extension, in addition to the Communications KA.

Figure 10 Communications flow issues (question 11)


Alignment Framework between BIM and PMBOK® Processes 65

Figure 11 Quality of communication flow (question 12)

Figure 12 Might it be useful to add a separate Information Management KA to the PMBOK®


and/or its construction extension? (Question 13)

The last questions in the survey ask about each respondent’s best practices:

responses included using ISO standards, shared digital workspaces, using BIM, selecting one

shared workspace or BIM solution and sticking to it, and having historical examples available

to use as templates for new/young PMs. Suggestions were offered about settling beforehand

what data distribution formats will be used, advice to integrate communications, drawings,

work plans, and contract items to ensure interoperability, and suggestions on when to take those

actions (in the beginning or during contract preparation, for example). As well, a few

respondents suggested reliance on documents like COBie for BIM guidance, BCF (project
Alignment Framework between BIM and PMBOK® Processes 66

management solution consultants), performing due diligence to ensure that there are no

interoperability issues between communications software, BIM, common data space, and data

management tools before the project begins, for example.

Page two of the survey contains a set of questions that asked the respondents about

what specific elements they feel could be incorporated into the PMI PMBOK® and the

Construction Extension, where, and about alternative guidance documents which might contain

similar information or information not currently included in the PMI documents. Two of the

questions were optional, depending upon the answer to a previous question. In 11 responses,

those who responded suggested adding detailed IM templates and examples to the

Communications KA or separately suggested developing basic protocols or ‘how-tos’ which

could be flexible enough to customise to fit a specific project, emphasising data and information

management aspects, or inclusion of BIM guidance from documents like COBie. One

respondent had offered a critique of the PMBOK’s ability to address complex projects,

especially with respect to management of digital information, project drawings,

communications, data, and reports, and offered suggestions on how to update the entire

document to provide more support, by incorporating more explicit guidance around the digital

tools and interoperability considerations.

Question 16 addressed alternative guidance in a table where the guidance was listed

(with a web link). Questions were asked regarding respondent familiarity with it, probing their

understanding of what specifics of project information management were addressed in each.

Finally, each respondent was asked to evaluate whether the alternative guidance might be used

to add to the PMBOK® and its Construction Extension. It is attached below, as Figure 13.

None of the respondents had been well-familiarized with all of the guidance documents

listed in question 16, but links were made available on each line so that they could look to the

documents up and give them enough of a review to answer the question. It appears that all did
Alignment Framework between BIM and PMBOK® Processes 67

that. Because of their lack of familiarity, they could not provide any additional insight on their

usefulness in practice, as requested in question 17.

Figure 13 Table, question 16, regarding alternative guidance’s specific to


information management process. As indicated at the top of the
figure, only 11 of 21 respondents filled out this table.
Alignment Framework between BIM and PMBOK® Processes 68

Questions 18 through posed a series of questions on information management and

standardisation processes associated with digital tools such as 3D CAD and Building

Information Models (BIM). What the researcher was attempting to learn, was whether the

respondents had ever encountered IM digital tool incompatibilities, how they attempted to

address them, if encountered, and whether they had heard of, or supported efforts to ensure

compatibilities between different project management software packages, now, and into the

future, which is thought to be essential to ensure cradle-to-grave, or lifetime facilities

management. The researcher also was seeking to determine whether any respondent wished to

see compatibility included as a ‘best practices’ for incorporation into the PMBOK® and

Construction Extension. Question 18 seemed to cause some confusion – it is not quite clear

how to interpret responses, other than the mention of the U.S. National CAD Standard. The

standard constitutes an attempt to impose a compatibility requirement for 3D CAD and BIM

solutions, such as those advocated by some BIM solution manufacturers and the scientific

community. Thus, it might better be omitted from the discussion.

In question 19, the survey asked directly if the respondent believes that adequate

guidance on the use of digital tools is contained in the current PMBOK® and Construction

Extension guidances. Ten of the surveys recorded no answer; however, of the eleven answers

given, seven responded, ‘no’. One of the seven ‘no’ answers was given because the respondent

assumed the PMBOK® was only relevant for construction projects. Therefore, while s/he

believed the guidance was not adequate, s/he also did not believe it SHOULD provide it. Of the

remaining responses, one subject responded, “I do not know”, one responded ‘yes’, and the

other two considered its guidance ‘fair’ or ‘relative’. A few additional insights were asked for,

and offered, in question 20. Of the eleven responses obtained, the emphasis was placed on

standardisation as essential to cost and time savings, and the need to increase the sense of

importance around IM and BIM usage as being critical to the smooth, cost-effective

management of projects in the future.


Alignment Framework between BIM and PMBOK® Processes 69

Questions 21 – 23 addressed Intellectual Property Rights (IPR) in project management.

There have been some concerns around IPR, especially where shared data spaces are used. The

researcher hoped to find out how respondents dealt with IPR, in the context of seeking guidance

from the PMBOK® and the C.E. Responses were consistent in stating, in various ways, that

they allowed their legal department to deal with it, and, if IPR were expected to become an

issue, some attempted to address it in the contract. One respondent gave an example of a project

in which the firm used BIM for the first time and experienced a great deal of fighting over who

owned what IP. Responses suggest that there may be a critical need to improve and add to IPR

guidance in both documents. This is supported by responses to question 24, which, asks if the

PMBOK® and C.E. contain sufficient support and guidance on how to approach IPR

management. Responses to question 24 are shown in figure 14, below. All responses indicate

that there are, at the very least, gaps in the guidance provided, and most responses suggest

adding IPR support to both PMI documents. One more IPR question, 25, asks if anyone is

familiar with or has experience with IPR management in relation to BIM. Few responses were

returned, and answers did not provide any specific insight. One could only conclude that, with

BIM still not quite being a standard PM tool, that the lack of long-term experience with it,

expressed earlier by respondents, prevented respondents from relating experiences.

Figure 14 Question 24: Do you find adequate guidance in the PMBOK and
C.E. regarding intellectual property rights?
Alignment Framework between BIM and PMBOK® Processes 70

COBie is a UK standard that provides a significant amount of detailed guidance on

BIM and 3D CAD solutions for information management, as well as standardisation, and

contains information not yet added to the PMBOK® and Construction Extension (CE).

Respondents were not familiar enough with it to provide enough responses to draw any

conclusions. The last group of questions, numbers 26-31, were open-ended questions designed

to revisit briefly, topics from earlier in the survey. This was performed, in part, to determine if

some opinions had changed or if the respondent had more to say, before closing the survey. The

key feature of those last questions is that the respondent was now free to say whatever s/he

wished. Question 26 was a yes-no question inquiring if the respondent had personally found

enough support for their PM activities in the PMI PMBOK® and CE. Most the responses were

affirmative, at 54.55%. The negative respondents suggested adding the BIM standards to the

guidances and polling the PM community in the construction arena who might be able to

contribute insights as people become more familiar and comfortable with using BIM for IM in

projects. Question 27 asked again about how PMI volunteers could go about formulating

updates including more digital tool guidance, but few responses were received. Most felt they

had no insight to offer. One last question about communications focused on interoperability

during project execution elicited responses which suggested the response group might like to

see more focus and progress on interoperability between the software tools and various

electronic workspace solutions. One respondent who had used COBie indicated it had helped

him/her a lot. Five offered insights into their personal favoured best practices as examples and

suggested that most of the five would support ensuring more interoperability in future. One

response could be used to infer that another issue to address might be to ensure that while

process and procedure is changing towards more use of digital tools, it might be well if efforts

were made to educate both owners and stakeholders more on shared workspace advantages to

avoid situations where a client holds on to paper and hard-copy communication processes when

the rest of the team is using digital tools, management, and shared workspaces.
Alignment Framework between BIM and PMBOK® Processes 71

6.3 Research Focus Group

The focus group interviews were obtained from personnel employed by MOHAP

(Modern Horizon Advanced Projects). As discussed in Chapter 5, of the 15 people who

participated, a total of 12 surveys were collected which were considered suitable for further

analysis. Plots of the demographic data are included below, as figures 15-20.

Figure 15 Years managing projects

Figure 16 years managing projects


Alignment Framework between BIM and PMBOK® Processes 72

Figure 17 Certifications?

Figure 18 Certifications?
Alignment Framework between BIM and PMBOK® Processes 73

Figure 19 Types of projects worked on

Figure 20 Types of projects worked on

The respondents constituted a diverse group with respect to experience, which was

similar to the group of respondents for the online survey. The responses regarding the

understanding of what Information Management (IM) is are quite similar to the group which

responded to the online survey. Points mentioned regarding what IM means to the respondents

included mention of a good understanding of the requirements around maintaining historical

records on the project and facility, as well as managing costs, information dissemination,
Alignment Framework between BIM and PMBOK® Processes 74

schedules, changes, and completions. Other points were raised around document control, and

use of the ISO tools, which appeared to be quite useful to the respondents. When asked if they

felt there could be a need to add IM guidance to the PMBOK and Construction Extension, 75%

of responses were affirmative. Those who disagreed felt there was more than enough

information in the two guidance’s to carry out the firm’s projects.

Figure 21 maps the responses regarding the electronic workspaces the respondents had

familiarity with or had used. A significant number of responses fell into the ‘other’ category.

Written notes on the responses indicate other tools used included the ISO standards, Oracle,

and Autodesk company solutions, such as Revit. There were no responses indicating

familiarity or use of BIM solutions. Respondents were not familiar with BIM solutions, when

asked directly, and could not offer opinions on usage, as a result. Nearly all respondents

indicated having experienced communications issues on projects, and did not feel that there

was an urgent need to add more IM guidance to the PMBOK and C. E. Further analysis of the

responses suggest that the firm had developed internal procedures, communications, and

protocols to handle communications and IM management conflicts, that they felt were working,

and had no need to look to the PMBOK® and Construction Extension to figure things out. The

respondents expressed a preference in allowing others to deal with intellectual property rights

(IPR) but did acknowledge some issues around ownership could potentially be problems. One

respondent mentioned an external organisation, which provided suitable guidance on IPR when

needed. Some respondents indicated some issues with IPR, nonetheless, in practice, but

described them as minor. One respondent pointed out that there was a great deal of contention

at his firm the first time BIM was used, because of issues between the client and project team

about who owned what communications, which was address, going forward, in the contract

phase.

“Only that it is a challenge, as before you have one owner of IF of their

deliverables now we have a model that consist of many parts from several

companies who contributed. Ownership and responsibility become less clear.”


Alignment Framework between BIM and PMBOK® Processes 75

“If not stated in the contract, later during project fights will arise”.

In general, respondents are fine with the amount of guidance already in the PMBOK®

and the C. E. and provided a list of favoured practices, including EMAIL, GIS, meetings

between the team, PM, and stakeholders to set down the ground rules., as well as GIS and

AutoCAD Revit.

Figure 21 What Electronic workspaces have you used or are familiar with?

6.4 Data Summary

Once tested, the surveys were prepared online and administered in person in a group

interview. The online survey responses were obtained randomly, whereas the group interview

was conducted with personnel from the same firm. Despite this, for most questions, they

appeared to be in good agreement. When it came to adding IM and IPR guidance to the PMBOK

and the C.E., the two groups diverged. This may have been because the group interview

respondents worked for a firm with preferred protocols and procedures – they preferred the

tools they were using, even though most also mentioned communications and compatibility

issues they had experienced between themselves and their clients.


Alignment Framework between BIM and PMBOK® Processes 76

Chapter 7 Conclusion and Future Work

Project Management (PM) is a rapidly growing and developing discipline which is

continually evolving as projects become more complex and new standards become available.

The increasing complexity of the work is made easier when the PM can take advantage of the

guidance and protocols provided in the Project Management Body and Knowledge (PMBOK®

and its Construction Extension (CE) to assist in developing plans, procedures, and protocols for

execution of the project. As well, in these more complex projects, the PM, ideally, could turn

to the ‘best practices’ documents to find guidance on managing all data, information, and

correspondence around the design, construction, turnover, and use of a facility.

Although the PMBOK® is considered the gold standard in guidance, this ‘Best

Practices” Guide is sometimes subject to criticism for preferring a ‘one size fits all’ approach

to process, of seeming too linear in its processes, for not being flexible enough for customising

or adaptation to the increasingly complex projects that PMs are executing, or for not offering

guidance or, according to some, not even addressing in an overt fashion how to integrate digital

tools, digital collaborative data workspaces, ensure and support interoperability of formatting,

drawings, communications, and plan documents, or leverage and implement the potential for

efficient and holistic project management represented by Building Information Modeling

(BIM) solutions. These protocols and processes, when incorporated, could ensure smooth

project flow, and maintain a well-organised, robust facility history from the cradle to the grave.

Thus, project management community opinions on critical issues around robust

Information Management, or IM, BIM, and updating the PMBOK and CE to reflect more

explicit guidance and process were sought, to determine if a push to include a new KA in the

Guide would be warranted. The study proposed to survey technical people performing project

management to identify gaps in best practices guidance on Information Management,

employing BIM, and shared electronic workspaces, in construction and facilities lifetime

management. This was accomplished by preparing a group of focused questions to use in an


Alignment Framework between BIM and PMBOK® Processes 77

online survey and a physical questionnaire format, to gather the thoughts of a number of

individuals with a varied range of experiences, from entry level (0-3 years’ experience) to

greater than 15 years with project management, and seeking a diverse range of project types for

various kinds of facilities.

Recapping, the research questions which this study sought to answer were:

 What BIM and other information management processes and procedures can be
added to the Construction Extension to the PMBOK® Guide to increase its value in the
field, and how would they impact the current guide’s methods and techniques?
o How can the Construction Extension to the PMBOK® Guide benefit from BIM
standards in managing information?
 What are the main information processes discussed in current literature?
 What BIM Standards and Procedures exist?
o How do these compare with information processes in PMBOK?
o How do BIM information exchange procedures and terminology differ from
those in PMBOK®?
o How does BIM ensure interoperability and data standards?

The anticipated contribution to knowledge is to ensure that the rapidly developing

methods and technologies around Digital Information Management (IM), Building Information

Modelling (BIM), Common Digital Environments (CDE), and the parallel actions required to

manage Facility cradle-to-grave documentation within those areas, are directly incorporated

into the Project Management Book of Knowledge (PMBOK®) and its Construction Extension

(CE). While communications are addressed in one of the PMBOK® in several knowledge areas

(KAs) at present, the mention of digital tools or provision of guidance and protocols is not part

of the guidance. No procedures, process, or protocols are explicitly outlined or explained.

Interoperability of digital tools is the subject of active discussion and development,

also, but is not addressed in the PMBOK® currently, either. In order to find out what the project

management community might be thinking on these topics, and to find out what kinds of

methods and best practices working project managers might be using currently, the researcher

deployed a survey and collected results to determine if the community agreed that more explicit
Alignment Framework between BIM and PMBOK® Processes 78

guidance and best practices should be added to the PMBOK®, if interoperability should be

stressed to minimise communication issues between the PM, project team, and the client and

stakeholders, as well as what best practices the communication has developed, itself to deal

with digital IM, BIM, CDE use, and maintenance of facility history in a thorough and consistent

manner.

The results of the study indicated that the sample populations appear to agree that more

IM guidance could be included in the PMBOK® and its CE. Respondents suggested the

inclusion of a separate KA addressing process, tools, interoperability, and collaborative

procedures, as well as the possibility of modifying and updating information in existing KAs

to tie in these topic areas, where appropriate from the earliest stages through the transfer and

lifetime modelling of the finished facility. All stressed mutual trust and team building as critical

to team success and implied that this concept, as well, is something they would be supportive

of seeing integrated throughout the guides. A few respondents indicated they wished to see

collaborative support process integrated a bit more explicitly in the PMBOK documents. A

substantial number of respondents highlighted the same group of perceived lacks in the

PMBOK® and CE with respect to Communications and records-keeping as well, in addition to

the recognition that use of digital tools, workspaces, and procedures are becoming integral to a

project, even before the contracts are signed, and a project team identified. Respondents offered

anecdotes illustrating experiences on previous projects, suggesting that most were familiar with

BIM, Common Data Environments (CDE), and Intellectual Property Rights (IPR), if not

experienced, and suggest that inclusion of real-world examples of the process might be

particularly useful, as well.

7.1 Proposed Information Management Knowledge Area (KA)

Based on the responses, a draft Knowledge Area (KA) should be prepared as a proposed

Information Management (IM) KA for inclusion into the PMBOK® guidance. Portions of the

existing external documents, as outlined in the literature review section, 2.2 will be used to
Alignment Framework between BIM and PMBOK® Processes 79

formulate the section. For additions to the PMBOK®, the first section on IM, using Building

Information Modelling (BIM) and other digital tools, could be predicated on the document

described in section 2.2.1, the “Process and Specification for Information Management for the

Capital/Delivery Phase of Construction Projects using Building Information Modelling

(BIM)”, (PAS) 1192-2:2013. Recall, this document contains guidance on handling information

exchanges specific to BIM. Using resources provided by the buildingSmart Alliance, this can

be modified to codify guarantees to ensure digital tool interoperability and compatibility in

project communications. That means, that no matter what solutions the team, the stakeholders,

contractors, and subcontractors use, communications, drawings, models, data analysis, etc. will

be compatible with whatever digital information management, electronic workspaces, and other

data tools, choose to use.

Section 2.2.2 contains a description of the “Building Information Model (BIM)

Protocol CIC/BIM pro (Construction Industry Council, 2013)”, is specific to construction and

management of facilities, and suitable for the contracting phase. Specific to the U. K., protocols

contained in it could be directly incorporated into the Construction Extension.

COBie, Construction Operations Building information exchange, is guidance

contained in the “Collaborative Production of Information”. BS 1192‑ 4:2014 (section 2.2.4),

and impacts the construction process. This document, as well as the document described in

section 2.2.7, describing the Building Information Modelling Execution Planning Guide could

be used to develop the skeleton of the KA to be added to the construction extension. As stated,

the proposed KAs will be outlined and described in Appendix G

7.2 Future Work

Several potential areas of future work are suggested, based on the survey results. In the

approximately forty-five daylong survey period, about 33 total responses were gathered. While

results were encouraging and supportive of the researcher’s assessment of the need for the

suggested changes and additions to the PMBOK® and CE, the gathering of the estimated
Alignment Framework between BIM and PMBOK® Processes 80

statistically sound number of responses, and accompanying evaluation of those responses

would be useful. Some investigation of various options to distribute the survey and interviews

into wider audience were made. The Project Management Institute (PMI), the publisher of the

PMBOK® and its CE, and largest agency supporting project management professional

licencing indicated that an individual could, potentially, post surveys through PMI’s Survey

Links Program, as described below and at the URL: http://www.pmi.org/learning/academic-

research/surveys.aspx. One might, as well, as a member of a group of volunteers, apply for a

PMI grant specifically for this purpose in future work. Information detailing this possibility was

not available before this study was implemented and nearly complete, thus precluding the

researcher from locating a local chapter member of PMI that might be able to identify active

members who could have served as a research sponsor for this project; this route to access to

PMI membership was received a bit more than two weeks before the end of the survey period.

Other professional organisations in various engineering disciplines and architecture, offer

similar access to membership research and could be pursued.

However, for future studies, access to PMI’s research community support and

membership pool, which numbers close to one million people worldwide, would be a useful

group to gather input from, on a set of questions like the ones posed in this survey. This might

be accomplished over a longer period, with the data analysed, and organised into draft

protocols, KA, and updated sections, for submission. As well, more focused evaluation of some

of the non-PMBOK® guidance, such as those included in Chapter 2 of this work [e.i., COBie,

PAS 1192-2:2013, BS 1192:2007, or The VA BIM Guide], as well as consortiums such the

BuildingSmart Initiative which is developing the some of the base infrastructure being used by

BIM and 3D industrial providers to ensure interoperability, to build in the knowledge as it is

formalised (Belsky, 2016). As well, collaborative research opportunities to gather more

information to formulate a proposed IM KA could be found by contacting BuildingSmart and

locating Project Managers involved in smart facility projects.


Alignment Framework between BIM and PMBOK® Processes 81

As stated previously, the Sixth Edition of the PMBOK® will release at the end of 2017,

and according to comments made by some of the survey respondents, may not contain much

more support for protocols, process, and procedure around IM, BIM, CDE, and IPR than is

available in the Fifth Edition. This is something that will need to be verified in future work as

the release is not anticipated before the end of 2017. Thus, the proposed work is still very much

a project that a significant portion of the project management professional community would

support and welcome.


Alignment Framework between BIM and PMBOK® Processes 82

References

Alin, P., Maunula, A. O., Taylor, J. E. and Smeds, R. (2013), Aligning Misaligned Systemic

Innovations: Probing Inter‐ Firm Effects Development in Project Networks. Project

Management Journal, Vol. 44(1): pp. 77-93. Available online at

http://dx.doi.org/10.1002/pmj.21316

(2017). AllCounted.com Survey Engine. Available online at https://www.allcounted.com

Alp, N. and Manning, C. (2014), Creating a plan for building information modeling, in

Proceedings of PICMET '14 Conference: Portland International Center for

Management of Engineering and Technology; Infrastructure and Service Integration,

27-31 July 2014, pp. 2732-2734. Available online at

http://ieeexplore.ieee.org/document/6921318/

Belsky, M., Sacks, R. and Brilakis, I. (2016), Semantic Enrichment for Building Information

Modelling. Computer-Aided Civil and Infrastructure Engineering Vol 31(4): pp. 261-

274. Available online at http://dx.doi.org/10.1111/mice.12128 or at

https://www.repository.cam.ac.uk/handle/1810/246879.

Brewer, G., and Strahorn, S (2012). Trust and the Project Management Body of Knowledge.

Engineering, Construction and Architectural Management Vol 19(3): pp. 286-305.

Available online at http://dx.doi.org/10.1108/09699981211219616

British Standards Institution (BSI) (2013), PAS 1192-2:2013: Specification for Information

Management for the Capital/Delivery Phase of Construction Projects using Building

Information Modelling. Published by BSI Limited 2013. Available online at

http://shop.bsigroup.com/forms/PASs/PAS-1192-2/

British Standards Institution (BSI) (2007), BS 1192:2007: Collaborative Production of

Architectural, Engineering and Construction Information – Code of Practice.


Alignment Framework between BIM and PMBOK® Processes 83

Published by BSI Limited 2007. Available online at

http://shop.bsigroup.com/forms/PASs/BS-1192-2007/

British Standards Institution (BSI) (2014a), PAS 1192-3:2014: Specification for Information

Management for the Operational Phase of Assets using Building Information

Modelling (BIM). by BSI Limited 2014. Available online at

http://shop.bsigroup.com/upload/Construction_downloads/PAS1192-

3%20final%20bookmarked.pdf

British Standards Institution (BSI) (2014), BS 1192-4:2014: Collaborative Production of

Information Part 4: Fulfilling Employer’s Information Exchange Requirements Using

COBie – Code of Practice. Published by BSI Ltd. 2014. Available online at

http://shop.bsigroup.com/forms/PASs/BS-1192-4-2014/

Broquetas, M. (2011), Using BIM as a Project Management Tool. Published by HFT Stuttgart

University of Applied Sciences 2011) Master’s Thesis. Available online at

https://www.hft-stuttgart.de/Studienbereiche/ArchitekturGestaltung/International-

Project-Management/Programme/MasterThesis/KF_Broquetas_Marti/

Building Information Modelling (BIM) Task Group (2016). Employer’s Information

Requirements, contained in Commerical Resources web page. Available online at

http://www.bimtaskgroup.org/bim-eirs/

Cabinet Office for Infrastructure and Projects Authority, and the Construction Sector Unit of

the U. K. Department for Business Innovation and Skills (BIS) (2011), Government

Construction Strategy, Published by the Cabinet Office, May 2011. Available online

at https://www.gov.uk/government/publications/government-construction-strategy

Cabinet Office for Infrastructure and Projects Authority (2016), Government Construction

Strategy, Published by the Cabinet Office, May 2016. Available online at


Alignment Framework between BIM and PMBOK® Processes 84

https://www.gov.uk/government/publications/government-construction-strategy-

2016-2020

Carvalho, M. M. (2008), Communication issues in projects management, PICMET '08 - 2008

Portland International Conference on Management of Engineering & Technology,

Cape Town, 2008, pp. 1280-1284. doi: 10.1109/PICMET.2008.4599739. Available

online at

http://ieeexplore.ieee.org/stamp/stamp.jsp?tp=&arnumber=4599739&isnumber=4599

598

Cervone, H. F. (2014) Effective communication for project success. OCLC Systems and

Services: International digital library perspectives Vol. 30(2):pp. 74-77. Available

online at http://dx.doi.org/10.1108/OCLC-02-2014-0014

Chen, Y., Dib, H. and Cox, R. F. (2014), A measurement model of building information

modelling maturity. Construction Innovation: Information, Process, Management,

Vol. 14(2): pp. 186-209. Available online at http://dx.doi.org/10.1108/CI-11-2012-

0060

Chou, J. S. and Ngo, N. T. (2014). Identifying critical project management techniques and skills

for construction professionals to achieving project success, 2014 IEEE International

Conference on Industrial Engineering and Engineering Management, Bandar Sunway

Ed., pp. 1204-1208. Available online at http://dx/doi/org/10.1109/IEEM.2014.7058829

Construction Industry Council (CIC)/British Standards Institution (BSI) (2013). Building

Information Model (BIM) Protocol: Standard Protocol for use in projects using

Building Information Models. Published by CIC/BIM Pro 2013 (1st Edition). Available

online at http://cic.org.uk/download.php?f=the-bim-protocol.pdf

Cottrell, S., (2014), Dissertations and Project Reports A Step by Step Guide. s.l.:Palgrave

Macmillan, Houndmills, Basingstoke, Hampshire.


Alignment Framework between BIM and PMBOK® Processes 85

N.d. (2016), Designing Buildings Wiki: the construction industry knowledge base; published

by Designing Buildings Limited [Online]. Available at

https://www.designingbuildings.co.uk/wiki/Home

Ehsan, N., Waheed, K. Z., Asghar, U., Nawaz, M. T., Mirza, E. and Sarwar, S. Z. (2010),

Effects of project manager's competency on project success, 2010 IEEE International

Conference on Management of Innovation & Technology, Singapore, pp. 107-112.

DOI: 10.1109/ICMIT.2010.5492830. Available online at

http://ieeexplore.ieee.org/stamp/stamp.jsp?tp=&arnumber=5492830&isnumber=5492

694

Gelder, J. (2013), Record and operational BIMs, Extended chapter, in BIM for the terrified a

guide for manufacturers, published by the Construction Products Association.

Available online at https://www.thenbs.com/knowledge/record-and-operational-bims

or original version at https://www.thenbs.com/knowledge/bim-for-the-terrified

Jung, Y., and Joo, M. (2011), Building information modelling (BIM) framework for practical

implementation. Automation in Construction, Vol. 20(2): pp. 126-133. Available

online at http://dx.doi.org/10.1016/j.autcon.2010.09.010

Krueger, R. A. (2005). “Designing and Conducting Focus Group Interviews”, published on

the University of Minnesota website. Available online at

https://www.researchgate.net/publication/241250641_Designing_and_Conducting_F

ocus_Group_Interviews

Lawson, M., Brgan, N., Caristia, J., Cavieses, I. and Secilmis, M. (2010) BIM Standardization.

Available at: https://issuu.com/mrl23njit/docs/bim_standardization_12.2010_final

(Accessed: 7 May 2016).

Liu, Y.-S., Li, H., Li, H., Pauwels, P., and Beetz, J. (2015). Recent Advances on Building

Information Modelling. The Scientific World Journal, Vol 2015: pp. 1-2. DOI:
Alignment Framework between BIM and PMBOK® Processes 86

10.1155/2015/786598. Available online at

https://www.hindawi.com/journals/tswj/2015/786598/

“focus group” (2017). Merriam-Webster.com. Merriam-Webster, retrieved on 17 May 2017,

from https://www.merriam-webster.com.

Malik, P. (2016, December 18). Do you thing that PMI should add a new knowledge set called:

Information Management in the new PMBOK? [Online forum comment] Message

posted to https://www.projectmanagement.com/discussion-topic/42544/Do-you-thing-

that-PMI-should-add-a-new-knowledge-set-called--Information-Management-in-the-

new-PMBOK-?sort=asc&pageNum=2

Morris, P. W. G. (2010), Research and the future of project management, International Journal

of Managing Projects in Business, Vol. 3(1): pp.139 - 146. Available online at

http://dx.doi.org/10.1108/17538371011014080

Project Management Institute (2013), A Guide to the Project Management Body of Knowledge

(PMBOK® Guide)—Fifth Edition. Project Management Institute (PMI) Global

Standard, published by PMI, Pennsylvania. Available online at

http://www.pmi.org/pmbok-guide-standards/foundational/pmbok.

Project Management Institute (2007) Construction Extension to the PMBOK® Guide Second

Edition. Published by PMI, Pennsylvania 2007: 196 pages. Available online at

http://marketplace.pmi.org/Pages/ProductDetail.aspx?GMProduct=00101595601

Project Management Institute (2016) Construction Extension to the PMBOK® Guide Third

Edition. Published by PMI, Pennsylvania 2016: 216 pages. Available online at

http://marketplace.pmi.org/Pages/ProductDetail.aspx?GMProduct=00101595601

Retana, R. (2016) Implementation Feasibility of a Digital Nervous System (DNS) for the

Construction Industry: For Efficient and Effective Information Management Across

the Project Lifecycle. Research gate. Available at:


Alignment Framework between BIM and PMBOK® Processes 87

https://www.researchgate.net/publication/304093010_Implementation_Feasibility_of

_a_Digital_Nervous_System_DNS_for_the_Construction_Industry_For_Efficient_an

d_Effective_Information_Management_Across_the_Project_Lifecycle (Accessed: 1

October 2016).

Rogers, J., Chong, H.-Y., and Preece, C. (2015). Adoption of Building Information Modelling

technology (BIM) Engineering, Construction and Architectural Management vol.

22(4): pp. 424-445. Available online at http://dx.doi.org/10.1108/ECAM-05-2014-

0067

Rooij, S. W. van (2009), Scaffolding project-based learning with the project management body

of knowledge (PMBOK ® ). Computers & Education, Vol 52(1): pp. 210-219.

Available online at http://dx.doi.org/10.1016/j.compedu.2008.07.012

(2017). “Sample Size Calculator”, SurveyMonkey Survey Platform. Available online at

https://www.surveymonkey.com/mp/sample-size-calculator/

Turk, Žiga (2016), Ten questions concerning building information modelling. Building and

Environment, Vol 107: pp. 274-284. Available online at

http://dx.doi.org/10.1016/j.buildenv.2016.08.001

U. S. Department of Veteran’s Affairs (2016), Office of Construction & Facilities

Management, main webpage. Available online at http://www.cfm.va.gov/

Wikipedia Contributors (2016) Building information modeling, in Wikipedia, The Free

Encyclopedia. 2016, December 28Available online from

https://en.wikipedia.org/w/index.php?title=Building_information_modeling&oldid=7

57021594

Wikipedia contributors (2016), 'Project Management Body of Knowledge', Wikipedia, The

Free Encyclopedia, Available online at


Alignment Framework between BIM and PMBOK® Processes 88

https://en.wikipedia.org/w/index.php?title=Project_Management_Body_of_Knowled

ge&oldid=753638366
Alignment Framework between BIM and PMBOK® Processes 89

APPENDICES
Alignment Framework between BIM and PMBOK® Processes 90

Online Survey Questions

MIDDLESEX UNIVERSITY LONDON

SCHOOL OF SCIENCE AND TECHNOLOGY

Research Survey

Alignment Framework between Building Information Modelling Processes and the

PMBOK® Guide Construction Extension Processes in Construction Projects

By

Saad Al Jabri

Estimated time to complete: 30 minutes

This research survey is designed to provide data to determine perceived gaps in

Information Management Guidance and process within the Project Management Body of

Knowledge (PMBOK®) Guide 5th Edition and its Construction Extension Guide. The

information gathered will be incorporated into the thesis Alignment Framework Between

Building Information Management Processes and the PMBOK® Construction Extension Guide

Processes in Construction Projects”, by Saad Al Jabri. The study will help identify perceptions

of any knowledge gaps around BIM and other Information Management processes, especially

digital solutions, within in the PMBOK® and its Construction Extension. The research seeks

to develop information to bridge perceived gaps by gathering additional best practices data as

well as familiarity with external guidance documents, which explicitly address Information

Management and opinion on whether they might also be incorporated.


Alignment Framework between BIM and PMBOK® Processes 91

PMBOK/Construction Extension Survey

1. Are you or have you been a project manager?

Yes No

{→ goes to ‘thank you very much, you do not qualify-type statement}

2. What project management licenses or certifications, if any, do you hold?

Not certified or CAPM PMP


licensed PgMP Other (please list)
PMI-ACP

3. How many years have you worked in project management (or managed projects)?

0-3 4-6 7-10 11-15 > 15

4. What kinds of projects do you specialise in (check all that apply)?

Construction Structural engineering Architecture


engineering Public facilities Private facilities
Commercial facilities Healthcare Facilities Military Facilities
Residential
Other (specify):

5. How do you, as a Project Manager, define Information management?

6. How do you manage data, information, and reporting between yourself and your
stakeholders? Comment on any process, procedure, or tool you employ.

7. Do you think there is a need to include more 'best practices' guidance on Information
Management in the PMBOK Guide and its Construction Extension?

Strongly agree Agree No opinion Disagree Strongly Disagree

8. Do you think there is a need for the Project Management Institute (PMI) to incorporate
additional guidance or a Knowledge Area on Information Management into the PMBOK®
and its Construction Extension? Please explain.
Alignment Framework between BIM and PMBOK® Processes 92

9. Have you considered using, or do you use any of these electronic workspaces? Check all that
apply.

Common data environment (CDE) 3D CAD


Digital workspace Relational Database Manager
Building Information Modelling Cloud services
MS SharePoint Other (list): _____________________

10. If you are aware of BIM, do you use it yourself or work with a BIM manager on your
projects? Please explain.

11. If you are using a different information management system (IMS), protocol, or solution than
your clients, contractors, or other stakeholders, how well do communications flow?

Poorly Don’t use an IMS


It can be complicated Adequately Well
Occasional incompatibility issues Very Well

12. Is there anything you would like to share, regarding reasons for your answer to the previous
question?

Poor written or oral communications Makes no difference


Culture differences Miscommunication of responsibilities
Reticent team members Failure to uphold responsibilities
Overlooked team members Lack of engagement
Gender bias Lack of accountability
Remote team/team members Poor or no set reporting schedule
Unrealistic expectations Critical information is forgotten or withheld
Schedule slippage Inequitable distribution of resources
Insufficient information sharing Something else
Information silos

13. How useful might it be to your work if an Information Management Knowledge Area (KA),
addressing digital tools like BIM, were incorporated into the PMBOK® and the Construction
Extension (CE), in addition to the existing Communications Management KA?

Very useful Not useful


Useful Not applicable

14. What are some of your best practices around Information Management?
Alignment Framework between BIM and PMBOK® Processes 93

This next set of questions probes project manager opinion of the perceived completeness within the
Communications Management Knowledge Area for Information Management and BIM use

15. What specific aspects of information management do you think might be elaborated on,
extended, or added to the PMBOK® and the Construction Extension? How might that be
accomplished?

16. A list of other guidance documents is included below. Please indicate which ones you are
familiar with and whether you think they could potentially fill a knowledge gap in the
PMBOK® and its Construction Extension.
Abbreviations:
AEC: Architecture, CIC: Construction Industry Council
Engineering, and DASNY: Dormitory Authority State of New York
Construction VA: Veteran’s Administration
BS: British Standard PAS: Publicly Available Standard
C. E.: Construction Extension

Document/ Familiar Sufficiently covered Incorporate into


Guidance with? PMBOK® C. E. PMBOK® C. E.
PAS 1192-2:2013

Building Information Model (BIM)


Protocol, CIC/BIM Pro

BS 1192:2007

BS 1192-4:2014

AEC (UK) BIM Technology


Protocol

BIM Execution Planning Guide

DASNY Building Information


Model (BIM) Standards Manual

The VA BIM Guide

PAS 1192-2:2013

Building Information Model (BIM)


Protocol, CIC/BIM Pro

17. For anything you selected above, on separate lines, please add any comments and preference for
placement within the PMBOK and C. E
Alignment Framework between BIM and PMBOK® Processes 94

18. Do you have any suggestions on other guidances or process from other sources, besides the ones
mentioned in the previous table, which could be used to fill gaps, improve or expand guidance in
the PMBOK® and Construction Extension? Please reply below and include the document title in
the box to the left of your comment.

Building Information Modelling and Information Management

This next section contains questions on information management and standardisation processes
associated with digital tools such as 3D CAD and Building Information Models (BIM).

19. Do you feel that the PMBOK® Guide and Construction Extension provides adequate guidance
and process on information management using digital tools? If not, please elaborate.

20. What benefits might accrue to the project management community from efforts to standardise the
Information Management process and procedures for digital tools, and do you feel it is something
that is supported or should be supported in the PMBOK® Guide and Construction Extension as
well?

21. Might you offer some insight into BIM approaches, guidance and process that could be
incorporated into a “Best Practices” Knowledge Area?

22. What do you know of, or how familiar are you with Intellectual Property Rights (IPR) impacts
related to BIM? Please explain.

23. Have you experienced any digital Intellectual property rights (IPR) issues in your work that you
can discuss?
Alignment Framework between BIM and PMBOK® Processes 95

24. What is your opinion on how the PMBOK® Guide and the Construction Extension support
management of intellectual property rights (IPR)?
There is sufficient guidance There is little guidance
There is some guidance There is no guidance
There are gaps in guidance Recommend adding Guidance

25. Are you familiar with and how would you use COBie guidance or similar processes in your work?

BS 1192-4:2014: COBie: Construction Operations Building information exchange at


http://shop.bsigroup.com/forms/PASs/BS-1192-4-2014/

Information Management in BS 1192:2007

In part I of this survey, question 9 listed a number of electronic workspaces that facilitate Information
Management: Common data environment (CDE), Digital workspace, Building Information Modelling,
MS SharePoint, 3D CAD, Relational Database Manager, Cloud Services, or something else you might
use.
26. Have you found sufficient process in the PMBOK® Guide and/or Construction Extension to
support Information Management activities?
Yes No

27. If 'no', how would you suggest it be addressed?

28. How should the Project Management Volunteers actively work to ensure inclusion of more
Information Management procedures and process into PMI’s body of knowledge documents?

29. As a project management professional, have you experienced communications and/or formatting
issues while sharing information between stakeholder software and another project software on a
project? How was this addressed?

30. In your project management work, have you identified specific processes and procedures to
manage data and information flow between your clients and the team that you would care to see
encoded as best practices? What are they?
Alignment Framework between BIM and PMBOK® Processes 96

31. Do you know about or are you willing to actively support the buildingSMART (formerly known
as International Alliance for Interoperability) efforts to establish neutral non-proprietary data
format Industry Foundation Classes (IFC) as a specification for Information Management in the
PMBOK® Guide and /or the Construction extension?

32. Do you have a feel for what kinds of information processes and procedures your clients favour?
Which ones do you favour? Please share your thoughts.
Alignment Framework between BIM and PMBOK® Processes 97

RESEARCH INTERVIEW FORM

Alignment Framework between Building Information Modelling Processes and the

PMBOK® Guide Construction Extension Processes in Construction Projects

By

Saad Al-Jabri

General Information

Name: Interview date:

Position: Company:

Part 1: PMBOK / Construction Extension

1. What project management licenses or certifications, if any, do you hold?

PMP PgMP PfMP CAPM PMI-PBA


PMI-ACP PMI-RMP PMI-SP Not certified or Other (please
licensed specify)
Other (please specify):

2. How many years have you worked in project management?

0-3 4-6 7-10 11-15 < 15


Alignment Framework between BIM and PMBOK® Processes 98

3. What kinds of projects do you specialise in?

Buildings Buildings Infrastructure Defence Oil & Gas /


Residential Commercial / Civils Petro Chemical
Institutional
Healthcare Public facilities Other (specify):
Facilities

4. How do you, as a Project Manager, define Information management?

5. How do you manage data, information, and reporting between yourself and your
stakeholders? Comment on any process, procedure or tool you employ.

6. Do you think there is a need to include more 'best practices' guidance on Information
Management in the PMBOK Guide and its Construction Extension?

Strongly Agree Agree No Opinion Disagree Strongly


Disagree

7. Do you think there is a need for the Project Management Institute (PMI) to
incorporate additional guidance or even a Knowledge Area on Information
Management into the new PMBOK® and its Construction Extension? Please explain.

8. Have you considered using, or do you use any of these electronic workspaces?

Common data environment Digital workspace Building Information


(CDE) Modelling (BIM)
MS SharePoint Relational Database Cloud services
Manager
3D CAD Other (specify):

9. If you are aware of BIM, do you use it yourself or work with a BIM manager on your
projects? Please explain.
Alignment Framework between BIM and PMBOK® Processes 99

10. If you are using a different Information Management system, protocol, or solution
than your clients, contractors, or other stakeholders, how well do communications
flow?

Poorly It can be Occasional Don't use Adequately Well Very


complicated incompatibility an IM Well
issues system

11. How useful might it be to your work if an Information Management Knowledge Area
(KA), addressing digital tools like BIM, were incorporated into the PMBOK® and the
Construction Extension (CE), in addition to the existing Communications Management
KA?

Very Useful Useful Makes no Not useful Not applicable


difference

12. What are some of your favoured best practices around Information Management?

13. What specific aspects of Information Management do you think might elaborated on,
extended, or added to the PMBOK® and the Construction Extension? How might that
be accomplished?

14. Do you feel that the PMBOK® Guide and Construction Extension provides adequate
guidance and process on Information Management using digital tools? If not, please
elaborate.

15. What benefits might accrue to the project management community from efforts to
standardise the Information Management process and procedures for digital tools,
and do you feel it is something that is supported or should be supported in the
PMBOK® Guide and Construction Extension as well?

16. Might you offer some insight into BIM approaches, guidance and process that could
be incorporated into a “Best Practices” Knowledge Area?
Alignment Framework between BIM and PMBOK® Processes 100

17. What do you know of, or how familiar are you with Intellectual Property Rights (IPRs)
impacts related to BIM? Please explain.

18. Have you experienced any digital Intellectual property rights (IPR) issues in your work
that you can discuss?

19. Have you found sufficient process in the PMBOK® Guide and/or Construction
Extension to support Information Management activities?

Yes No

If 'no', how would you suggest it be addressed?

PMBOK/Construction Extension Discussion Questions

20. How should the Project Management Volunteers actively work to ensure inclusion of
more Information Management procedures and process into PMI’s body of
knowledge documents?

21. As a project management professional, have you experienced communications


and/or formatting issues while sharing information between stakeholder software
and another project software on a project? How was this addressed?

22. In your project management work, have you identified specific processes and
procedures to manage data and information flow between your clients and the team
that you would care to see encoded as best practices? What are they?

23. Do you have a feel for what kinds of information processes and procedures your
clients favour? Which ones do you favour? Please share your thoughts.
Alignment Framework between BIM and PMBOK® Processes 101

Raw Responses to Group Interview Survey

Research group interview report

The researcher has conducted a group interview, for a contracting company called

“Modern Horizon Advanced Projects (MOHAP)”.

The group were 15 participants, all engineers but from a different discipline. The

researcher first introduces himself, and his study purpose then gave a small introduction about

BIM then distribute the research interview forms to the participants.

Two out of the fifteen participants withdraw because they felt that they do not have

enough experience to answer the questions.

One out of the fifteen participants missed the first page, so this participant will not be

counted.

The researcher fills that most of the participants did not understand the first question

properly, they reply under Other with the comments PMP workshop which is not a certification

neither a license.

One participant answered in the Arabic language, so the researcher translated his

answers to English (red colour).

Participants who do not choose any option in question one are considered not certified

or licensed.
Alignment Framework between BIM and PMBOK® Processes 102

AllCounted dot com Survey Data

FILE: Q01-32_Data1.pdf
Alignment Framework between BIM and PMBOK® Processes 103

a. Raw and Collated Online Survey Data

Focus Group Interview Question Responses: M_S

Question

4 It's meaning How to control and handle the information about the
project such as comunication and saving documents and contract.

5 by official document submital if it's required or by email for minor


thing (if I understand the question in proper way)

6 D: no need for more details and area for PMBOK

8 yes I heard about it from projacs consultant and I can say that is a
program show you the life cycle of project by showing it step by step

9 No

11 I think that what is available now is enough

15 No
Alignment Framework between BIM and PMBOK® Processes 104

Focus Group Interview Question Responses: A_E

Question

5 Arrange ideas and information with someone responsible for them,


but varies from person to person as required

6 SA

8 First time I hear about it

9 No

10 Depends on their input information according to the ability to learn.

11 I do not know

20 No
Alignment Framework between BIM and PMBOK® Processes 105

Focus Group Interview Question Responses: E_A

Question

4 It is the Life project because the project consider Hautlond of data or


information you have tokeep & save it to lead the project to successful end.

5 I must have document control in the project so he can keep all


information and data so when need it we can get

6 A

8 No, I just study PMP but I think it must be in all project because it is
perfect to control project

9 No because normaly we didn't use it in the region or area

10 Weekly meeting

18 No

19 Always I follow consultant form which is different from one project


to another

20 No
Alignment Framework between BIM and PMBOK® Processes 106

Focus Group Interview Question Responses: A_T

Question

4 The information management is the most important issue in project


management, to manage the data, time, cost and stakeholders.

5 To mange data, information and reporting between me and the


stakeholders, we must trust each other and every thing must be registered &
recorded, and the following is very important to keep stakeholders with
follow also.

6 (D) WHy: I think no need for this, because the knowledg areas it's
more than enough to manage all types of projects.

8 Its a great system which will save contractor, consultant & owner
from any loss and you can control all your departments (MEP-Civil-Arc-
procurment-QS-QA). It's very important.

9 Actually, I didn't use it before, but I heered about it.

10 Poorly, and we will fall in a lot of problems.

11 Project Modeling and Cordinating Mangement.

12 Brain Storming.
Alignment Framework between BIM and PMBOK® Processes 107

Focus Group Interview Question Responses: K_G/SMCo

Question

Documentation, formatting, and preservation of information. Recall


4
the information when needed.

According to the client needs, other colleagues. I use letters, emails,


5
social media such aus Whats up (not official).

5 We have process and procedures but are not written.

6 D: Because it is available in the PMIS

It is a model or system to manage and format information and called


8
in when we need it.

At present, the company is in developing procedures stage, and there


9
is no plan shortly to use BIM. Probably in the future.

Communication flow well in general and things are clear between


10
stakeholders.

11 it is hard tosay because I did not use it.

ISO systems because it does not force a certain solution on us and it


12
allo us to monitor and follow what we say we are doing

I think PMBOK include these aspects in a suitable manner. There are


13 many points and examples regarding dealing with information. I believe PMI
has covered the subject in a right way.

I do not think that using one standard is adequate. However, putting


14 general frameworks suitable for each community and regains is better,
because each country or place may have their different needs.

There are some well know organization are responsible for


registering property rights. All contract clearly specify that. An example for
15
these organisations is Tala Abu Gazala Establishment. They have an important
intellectual property rights system.

16 No.
Alignment Framework between BIM and PMBOK® Processes 108

Focus Group Interview Question Responses: K_G/SMCo

First, perform experiments on specific systems then perform statistic


17
surveys to know if users understand and accept them.

Yes, we faced some simple issues, some consultant forces us to use


18 systems with some minors default. That is why these systems need to be
developed.

Perform daiy reports to know the progress of each then combine


19
these reports in a weekly report.

We have developed several systems and benefited from ISO system


20
and FIDIC contracts too.

Focus Group Interview Question ResponsesL A_D

Question

5 1 - Time Schedule

5 2 - Budget

5 3 - Cost

6 A: To know more experiances in different types of projects

8 BIM should be commenly used in future to save money, time, and


maintence and oepration in future

9 NO

11 GIS

12 I used before GIS in storing data and then analyzes to used in a


different facility projects
Alignment Framework between BIM and PMBOK® Processes 109

18 Yes, when importing a different version of software, then by phone


call discussed to export in different version.

19 Yes, at the beganing of any projects, some rules are difine like, one
contact person (document controller), on project Email, and a strict passes of
any documents transmital

20 GIS, BIM, Revit


Alignment Framework between BIM and PMBOK® Processes 110

Focus Group Interview Question Responses: A_Z

Question

4 the mangement that includes the process to ensure that the project
includes all the work required and only the work required to complete the
project successfully.

5 by following the iso, and by reporting small and big details of the
project.

6 A: to fully control the project.

6 by controling the scope of work, the time, the cost, the qulaity, the
human resourse, and etc ...

8 BIM is how to involve the generation and mangement of digital


representation of physical and funcational.

9 By coordination with all the employ in charge and to be fully known


which version to use.

10 have to follow the clients or the client follow me.

12 Risk Management

18 No.

19 by follow the client report if he has it not

20 Time and cost


Alignment Framework between BIM and PMBOK® Processes 111

Focus Group Interview Question Responses: I_H

Question

4 Information management may be described as the achival of


information, document, historical recordes, and the ultimate disposition to
all stakeholders. Also includes the when, the who, the whow information will
be transferred.

5 In the planning phase of each project the communication


management plan will be developed before the project management plan is
developed. This communication plan will have all what is needed to manage
the communication methods and models.

6 N/A

7 Autocad 2D

8 Building information model. it facilitates building a complete model


of the project & eases construction & project success.

9 No, I never interacted with any BIM holder.

10 Poorly, I believe a lot of conflicts might happen.

11 It would be very useful to add some real life programs that would be
helpful & endulge your experiance like primavera.

12 Historical records.

13 I think more examples, real life examples must be added to each


broad topic to ease up understating & and to remember it easily.

17 By sharing their experience to others.

18 No.

20 In my field, I didn't face any kind of this procedures.


Alignment Framework between BIM and PMBOK® Processes 112

Focus Group Interview Question Responses: M_K

Question

4 It is the way you best organzie the information to better use in the
project.

5 By using or utilizing the "Expedition" like program

6 SA

8 Great tool to efficiently control every aspect of the project

9 No

10 Not at this point (In S.A)

16 No
Alignment Framework between BIM and PMBOK® Processes 113

Focus Group Interview Question Responses: M_A-K

Question

4 Saving time and cost.

5 Emails and site report.

6 A: Any modeling can be done will add value to the fild & to the
personal experince

8 its a way of putting information in a table that will lead to enhance


the know how of doing things- to everyone in the best & shortest way

9 No

10 Poorly

11 I don't know

13 I don't know

16 No.

17 I have no idea.

18 only throu emails. & I see that its good in a way or another to spread
the information.

19 I don't pass throw this before.

20 Throw Emails as of Q17 answered


Alignment Framework between BIM and PMBOK® Processes 114

Focus Group Interview Question Responses: M_R

Question

4 Information should be shared between all the concerned


parties/individuals in a timely and effective manner

5 Through official document submittals. we als employ oracle database


system to manage data & information.

6 A

7 Oracle

10 Adequate

14 it should be supported & worked towards. Benefits would include


office dessimation of information as well as timely flow of the same.

17 By actively recording & sharing their knowledge & experience.


Alignment Framework between BIM and PMBOK® Processes 115

Focus Group Interview Question Responses: M_S_Y

Question

4 Information manager containing but not limited to:

1 - recived all info. without any wastage from stakeholders

2 - Recording it throug a list, sheet forms ... to protect it from


forgotten

3 - validating the info. and to make sure it comply with the project
(contrains, goals, organsisation policies ...)

5 1 - meeting records

2 - of formal directions/letters

3 - signed sketches/drawing

4 - approacals on physical samples

5 - response from stakeholders on the sumitted excution forms like


(request for information, materials, submittas)

6 A: Should add some new knowledge area related to coordinations


between organzation disciplinies
increase the examples related to actualy excution projects & and
more detailed for stakeholders changes cross project life cycle
facilitate the process of chagese in scope

8 BIM is used to reach to the project deliverables in (less cost, more


benifit, more stakeholder satisification less time

9 No I hope that in near future

10 poorly and difficult

11 I propose to include a (K.A.)related to information management


softwear to coordinate with the old classic way

12 to involve all related staeholders in the informations by emails and


ensure that by calls or face to face verbally recived
Alignment Framework between BIM and PMBOK® Processes 116

Focus Group Interview Question Responses: M_S_Y

13 how to be sure that any conflict between the infos. will happen
the infos should be clear for all related team member
its easy to access to all need infos

14 the benefits: more accurate in excution, less time and cost waste.

15 Yes, I know that the (IPRs) may make some problems specially in big
projects, or when the owner need to use the BIM in another project without
approval/permission from BIM designer

16 No.

17 Survey, researches, symposiums, seminars specially practical


application on the actual field and transfer the results to PMI

18 Yes. I solved this issues by one or more of the following:


1 - insure that the information are validated
2 - to know from where this isseue come
3 - to be sure this issue will not appear again in the future

19 Yes. to make scan for all documents/informations


make log/register fro the formal information
I used the feature from Outlook that when I send an email to anyone
then automatifally I'll recieved a notification that the email is delivered and
read (if occurs)

20 I favour the minute of meeting between the related


clients/stakeholders/
for the client he favour the verally information/directions
Alignment Framework between BIM and PMBOK® Processes 117

b. Focus Group Interviews, organised by question number

Question 1 Responses

Q1
1 2 3 4 5 6
4- 7- 11-
0-3 6 10 15 >15 N/A
3 1 3 3 1 1
25% 8% 25% 25% 8% 8%

Question 2 Responses

Q2
PM PgM PfM CAP PMI PMI PMI PMI No Othe
P P P M -PBA -ACP -RMP -SP Cert r
4 4 4
33
33% % 33%
Alignment Framework between BIM and PMBOK® Processes 118

Question 3 Responses

Q3
Constru Struc Archite Comm Pu Pri Resid Healt Mil O Infrastru
ction engineering tural engineering cture ercial facilities blic facilities vate facilities ential hcare Facilities itary Facilities ther cture

9 8 11 1 3
67 8
75% % 92% % 25%

Number of different projects per respondent

1 2 3 4

3 2 4 3

25% 17% 33% 25%

Q7
Common data Digital MS Relational Cloud 3D
environment (CDE) workspace BIM SharePoint Database Manager services CAD Other
0 1 0 0 3 3 7 5
0.0% 8.3% 0.0% 0.0% 25.0% 25.0% 58.3% 41.7%
Number of different projects per respondent
1 2 3 4
7 2 1 1
58% 17% 8% 8%

Q6
Strongly Strongly
Agree Agree NA Disagree Disagree
Alignment Framework between BIM and PMBOK® Processes 119

2 6 1 3 0
17% 50% 8% 25% 0%

Question 4 Responses
1. It's meaning How to control and handle the information about the project such as comunication and saving documents and contract.
2. It is the Life project because the project consider handling of data or information you have to keep & save it to lead the project to successful
end.
3. The information management is the most important issue in project management, to manage the data, time, cost and stakeholders.
4. Documentation, formatting, and preservation of information. Recall the information when needed.
5. the mangement that includes the process to ensure that the project includes all the work required and only the work required to complete
the project successfully.
6. Information management may be described as the achival of information, document, historical recordes, and the ultimate disposition to all
stakeholders. Also includes the when, the who, the whow information will be transferred.
7. It is the way you best organize the information to better use in the project.
8. Saving time and cost.
9. Information should be shared between all the concerned parties/individuals in a timely and effective manner
10. Information manager containing but not limited to:
1 - recived all info. without any wastage from stakeholders
2 - Recording it throug a list, sheet forms ... to protect it from forgotten
Alignment Framework between BIM and PMBOK® Processes 120

Question 4 Responses
3 - validating the info. and to make sure it comply with the project (contrains, goals, organsisation policies ...)

Question 5 Responses
1. by official document submital if it's required or by email for minor thing (if I understand the question in proper way)
2. Arrange ideas and information with someone responsible for them, but varies from person to person as required
3. I must have document control in the project so he can keep all information and data so when need it we can get
4. To mange data, information and reporting between me and the stakeholders, we must trust each other and every thing must be registered
& recorded, and the following is very important to keep stakeholders with follow also.
5. According to the client needs, other colleagues. I use letters, emails, social media such aus Whats up (not official).
6. We have process and procedures but are not written.
1 - Time Schedule
2 - Budget
3 - Cost
7. by following the iso, and by reporting small and big details of the project.
8. In the planning phase of each project the communication management plan will be developed before the project management plan is
developed. This communication plan will have all what is needed to manage the communication methods and models.
Alignment Framework between BIM and PMBOK® Processes 121

Question 5 Responses
9. By using or utilizing the "Expedition" like program
10. Emails and site report.
11. Through official document submittals. we als employ oracle database system to manage data & information.
1 - meeting records
2 - of formal directions/letters
3 - signed sketches/drawing
4 - approacals on physical samples
5 - response from stakeholders on the sumitted excution forms like (request for information, materials, submittas)
Alignment Framework between BIM and PMBOK® Processes 122

Question 6 Responses
1. D: no need for more details and area for PMBOK
2. SA
3. A
4. (D) WHy: I think no need for this, because the knowledg areas it's more than enough to manage all types of projects.
5. D: Because it is available in the PMIS
6. A: To know more experiances in different types of projects
7. A: to fully control the project.
8. by controling the scope of work, the time, the cost, the qulaity, the human resourse, and etc ...
9. SA
10. A: Any modeling can be done will add value to the fild & to the personal experince
11. A
12. A: Should add some new knowledge area related to coordinations between organzation disciplinies
increase the examples related to actualy excution projects &
facilitate the process of chagese in scope
Alignment Framework between BIM and PMBOK® Processes 123

Question 7 Responses
1. Autocad 2D
2. Oracle

Question 8 Responses
1. yes I heard about it from projacs consultant and I can say that is a program show you the life cycle of project by showing it step by step
2. First time I hear about it
3. No, I just study PMP but I think it must be in all project because it is perfect to control project
4. Its a great system which will save contractor, consultant & owner from any loss and you can control all your departments (MEP-Civil-Arc-
procurment-QS-QA). It's very important.
5. It is a model or system to manage and format information and called in when we need it.
6. BIM should be commenly used in future to save money, time, and maintence and oepration in future
7. BIM is how to involve the generation and mangement of digital representation of physical and funcational.
8. Building information model. it facilitates building a complete model of the project & eases construction & project success.
9. Great tool to efficiently control every aspect of the project
10. its a way of putting information in a table that will lead to enhance the know how of doing things to everyone in the best & shortest way
11. BIM is used to reach to the project deliverables in (less cost, more benifit, more stakeholder satisification less time
Alignment Framework between BIM and PMBOK® Processes 124

Question 9 Responses
1. No
2. No
3. No because normaly we didn't use it in the region or area
4. Actually, I didn't use it before, but I heered about it.
5. At present, the company is in developing procedures stage, and there is no plan shortly to use BIM. Probably in the future.
6. NO
7. By coordination with all the employ in charge and to be fully known which version to use.
8. No, I never interacted with any BIM holder.
9. No
10. No
11. No I hope that in near future
Alignment Framework between BIM and PMBOK® Processes 125

Question 10 Responses
1. Depends on their input information according to the ability to learn.
2. Weekly meeting
3. Poorly, and we will fall in a lot of problems.
4. Communication flow well in general and things are clear between stakeholders.
5. have to follow the clients or the client follow me.
6. Poorly, I believe a lot of conflicts might happen.
7. Not at this point (In S.A)
8. Poorly
9. Adequate
10. poorly and difficult
Alignment Framework between BIM and PMBOK® Processes 126

Question 11 Responses
1. I think that what is available now is enough
2. I do not know
3. Project Modeling and Cordinating Mangement.
4. it is hard tosay because I did not use it.
5. GIS
6. It would be very useful to add some real life programs that would be helpful & endulge your experiance like primavera.
7. I don't know
8. I propose to include a (K.A.)related to information management softwear to coordinate with the old classic way
Alignment Framework between BIM and PMBOK® Processes 127

Question 12 Responses
1. Brain Storming.
2. ISO systems because it does not force a certain solution on us and it allo us to monitor and follow what we say we are doing
3. I used before GIS in storing data and then analyzes to used in a different facility projects
4. Risk Management
5. Historical records.
6. to involve all related stakeholders in the informations by emails and ensure that by calls or face to face verbally recived

Question 13 Responses
1. I think PMBOK include these aspects in a suitable manner. There are many points and examples regarding dealing with information. I believe
PMI has covered the subject in a right way.
2. I think more examples, real life examples must be added to each broad topic to ease up understating & and to remember it easily.
3. I don't know
4. how to be sure that any conflict between the infos. will happen
5. the infos should be clear for all related team member
6. its easy to access to all need infos
Alignment Framework between BIM and PMBOK® Processes 128

Question 14 Responses
1. I do not think that using one standard is adequate. However, putting general frameworks suitable for each community and regains is better,
because each country or place may have their different needs.
2. it should be supported & worked towards. Benefits would include office dessimation of information as well as timely flow of the same.
3. the benefits: more accurate in excution, less time and cost waste.

Question 15 Responses
1. No
2. There are some well know organization are responsible for registering property rights. All contract clearly specify that. An example for these
organisations is Tala Abu Gazala Establishment. They have an important intellectual property rights system.
3. Yes, I know that the (IPRs) may make some problems specially in big projects, or when the owner need to use the BIM in another project
without approval/permission from BIM designer
Alignment Framework between BIM and PMBOK® Processes 129

Question 16 Responses
1. No.
2. No
3. No.
4. No.

Question 17 Responses
1. First, perform experiments on specific systems then perform statistic surveys to know if users understand and accept them.
2. By sharing their experience to others.
3. I have no idea.
4. By actively recording & sharing their knowledge & experience.
5. Survey, researches, symposiums, seminars specially practical application on the actual field and transfer the results to PMI
Alignment Framework between BIM and PMBOK® Processes 130

Question 18 Responses
1. No
2. Yes, we faced some simple issues, some consultant forces us to use systems with some minors default. That is why these systems need to
be developed.
3. Yes, when importing a different version of software, then by phone call discussed to export in different version.
4. No.
5. No.
6. only throu emails. & I see that its good in a way or another to spread the information.
7. Yes. I solved this issues by one or more of the following:
1 - insure that the information are validated
2 - to know from where this isseue come
3 - to be sure this issue will not appear again in the future
Alignment Framework between BIM and PMBOK® Processes 131

Question 19 Responses
1. Always I follow consultant form which is different from one project to another
2. Perform daiy reports to know the progress of each then combine these reports in a weekly report.
3. Yes, at the beganing of any projects, some rules are difine like, one contact person (document controller), on project Email, and a strict
passes of any documents transmital
4. by follow the client report if he has it not
5. I don't pass throw this before.
6. Yes. to make scan for all documents/informations
7. make log/register fro the formal information
8. I used the feature from Outlook that when I send an email to anyone then automatifally I'll recieved a notification that the email is delivered
and read (if occurs)
Alignment Framework between BIM and PMBOK® Processes 132

Question 20 Responses
1. No
2. No
3. We have developed several systems and benefited from ISO system and FIDIC contracts too.
4. GIS, BIM, Revit
5. Time and cost
6. In my field, I didn't face any kind of this procedures.
7. Throw Emails as of Q17 answered
8. I favour the minute of meeting between the related clients/stakeholders/ for the client he favour the verbally information/directions
Alignment Framework between BIM and PMBOK® Processes 133

DATA APPENDICES
Alignment Framework between BIM and PMBOK® Processes 134

a. Appendix E2.pdf

b. Focus Group Instructions: App_E3_Krueger-Focus.pdf

c. Group Interviews PDF

You might also like