Professional Documents
Culture Documents
Full Main Body
Full Main Body
INTRODUCTION
1.1 GENERAL
The world's first flyover was constructed and started in 1843 by the London and
Croydon Railway at Norwood Junction railway station to carry its atmospheric
railway vehicles over the Brighton Main Line. The first flyover in India was allowed
access on 14 April 1965 at Kemps Corner in Mumbai. The 48-foot-long bridge was
constructed in about seven months by Shirish Patel at a cost of ₹17.5 lakh.
The flyover consists of number of spans with columns (piers), deck, and foundation
etc. In order to construct a flyover all these elements are to be analysis and designed
properly. For large construction this process of designing and analysing become
complicated when done manually time taking and sometimes lead to errors so in order
to meet these problems software's are used. The computer software's are the ones
which can perform this action of analysis and designing with minimum errors with in
short
1
SVEC/CE/2017-20
period of time such that the designing of complex flyover become easier while using
software's. Some of the famous software's which are generally used for analysis and
designing of structure are ETABS, ROBOT STRUCTUREL ANALYSIS,
STAADPRO.
This project deals with analysis and design of flyover components i.e. Deck Slab,
Pier, Pedestals, Abutment, and Pile Foundation that includes pile cap.The details of
the project are assumptions that are taken as average from flyovers that we studies
around Tirupati Smart City.
Deck slab is modelled and analysed using STAAD.Pro software and Designed in
Manual Method. Remaining components are analysed and designed using Limit State
Method of Design.
1.3. FLYOVER
A flyover has three main elements. First the substructure i. e foundation transfers the
loaded weight of the bridge to the ground. It consists of components such as columns
(Also called piers) and abutments. An abutment is the connection between the end of
the bridge and the road carried by the earth; it provides support for the end sections of
the flyover. Second, the superstructure of the flyover is the horizontal platform that
spans the space between columns. Finally, the deck of the bridge.
1. Railway crossing
2. Road crossing
a. Super structure
b. Sub structure
a) Super structure:
2
SVEC/CE/2017-20
The superstructure consists of the components that actually span the obstacle the
bridge is intended to cross and includes the following
1. Bridge deck
2. Structural members
3. Parapets (bridge railings), hand rails, side walk, lighting and some drainage
features.
b) SUB STRUCTURE:
The sub structure consists of all of the parts that are mentioned above that support the
super structure. The main components are abutments, Piers, footings and piling.
The approach slab provides a transition between roadway pavement and the flyover.
The approach slab behaves as an intermediate flyover to span the portion of
embankment directly behind the abutment/back wall which was excavated to
construct the abutment/back wall
deck is the surface of a flyover sometimes the deck is covered a railroad bed and
track, asphalt concrete, or other form of pavement for ease of vehicle crossing. A
concrete deck may be an integral part of the flyover structure (T-beam or double tee
structure) or it may be supported with I-beams or steel girders.
1.6.3. KERB:
1.6.4. HANDRAILS:
3
SVEC/CE/2017-20
in order to prevent injurious falls. Handrails supported by posts or mounted directly to
walls.
A girder bridge uses girders for supporting the girder. Because of the properties of
inertia, the height of a girder is the most significant factor to affect its load capacity.
the bridge deck. Bearing is provided to control movement and thereby reduce the
stresses involved.
1.6.7. ABUTMENTS:
In engineering, abutment refers to the substructure at the ends of a bridge span or dam
whereon the structure's superstructure rests or contacts.
1.6.8. PIERS:
6.FOUNDATION:
Foundation is the load transmitting members. The loads from the columns and the
walls to be transmitted to the solid ground through foundation.
Here, we adopted Pile foundation.
2. Beam deck
4. Cellular deck
4
SVEC/CE/2017-20
1.7.1. SOLID SLAB DECK:
This type of bridge deck is the most cost efficient for shorter span less than20 meters.
Bridge deck can be built with or without cantilever Bridge deck with cantilever has
less weight with less reduction on second moment of area. Solid deck can be simply
constructed in-situ concrete and pre-cast concrete form.
Determination of worst combination of loads that may occur at one throughout the life
of structure. The standard codes of practice give guidelines for this. All the loads are
not expected at the same time for example, IS-875, wind and seismic force need not
be considered as acting simultaneously. The earthquake is a rare phenomenon. It is
therefore very unlikely that the maximum earthquake coincides with maximum of
other occasional forces like wind, flood etc., therefore for the design purpose these are
assumed not to occur simultaneously.
a. Dead load,
b. Live load,
d. Other loads
a.DEADLOAD:
Dead loads are the load due to self weight of structure or structural members. Dead
loads and static loads remain reasonably constant throughout the life of a structure.
5
SVEC/CE/2017-20
The unit weight of different materials may be taken from IRC:21-2000 code of
practice for design loads for the buildings and structures part 1 dead loads.
b.LIVELOAD:
Live loads are loads which are not steady unlike the dead loads they can change their
magnitudes. Live loads are comprehensively described in tables 1 and 2 IRC:21-2000
part 2 imposes loads. IRC:6-2014 code gives information about the live load positions
and magnitude of live loads on bridge structure.
c.IMPACTLOAD:
Impact load are the loads caused by the vibration of live loads.
6
SVEC/CE/2017-20
CHAPTER 2
LITERATRURE REVIEW
Dzolev et al, This paper presents the analysis of reinforced concrete Girder Bridge
designed according to EN 1998-2, with the determination of the achieved ductility in
plastic hinges at the target displacement for the designed seismic action, for confined
and unconfined concrete cross sections, with and without the effects of geometric
nonlinearity. . In this paper, analyses were conducted for RC Girder Bridge with
confined and unconfined concrete cross sections [1, 2] with and without the effects of
geometric nonlinearity. Based on the pushover curves, it can be concluded that, for
the same level of horizontal displacement, lower values of baseshear are obtained if P-
Δ effects are applied. Obtained target displacement and achieved local ductility also
differwhether concrete is modelled as confined or unconfined, giving higher values in
favour of confined concrete. Results are presented only for the shorter column.
Rajeev Sharma (2015),This paper deals with theevaluation studies for the existing,
RC bridge using non-linear static analysis. For the seismic assessment of the bridge a
3 span bridge is selected which is located on the hindon river at Ghaziabad (Uttar
Pradesh).this area is highly vulnerable to the seismic activity because it is lie in the
Zone – 4 .so , the high magnitude earthquake may be occurs in this region(may be
greater than 7 magnitude). . For doing the seismic evaluation of the bridge at the time
of earthquake open sees software is used. The open sees model is used to describe the
various performances of the bridge.
T. Pramod Kumar et al, This paper deals with the analysis and design of super
structure of road cum railway bridge across Krishna river proposed ondownstream
side of existing bridge between Mahanadu road of Sithanagaram and P.N.Bus station,
Vijayawada.The bridge is made of through type steel truss which carries two railway
tracks at lower level and a roadway ofthree lane carriage way in the upper level. The
span length matches with that of existing nearby railway bridge.Analyses of top floor
members, truss members and bottom floor members are done usingSTAAD.Pro.
Thedesign of structural members of the truss, top floor and bottom floor members is
done as per Indian railwaystandard code and Indian roads congress code. In which
7
SVEC/CE/2017-20
they concluded that Road cum railway bridge reduce the construction cost by
providing single bridge for both railway traffic road traffic instead of providing two
separate bridges.It meets the increased railway and road traffic needs across the river
Krishna.It reduces the land acquisition problem by providing single bridge.
Karthiga et al, This paper presents a linear analysis of the substructure of rail over
bridge by consideringIRS 25t railway loading and road over bridge by considering
IRC class-A loading.Road over bridges are bridges over which the roadway can be
operated. On the otherhand, in rail over bridges, the rail track can be operated over the
bridge. The aim ofthis paper is to determine the various types of loads acting on the
structure andanalyze the substructure of road over bridge and rail over bridge using
STAAD Pro.The moment is obtained from STAAD Pro for road over bridge and rail
over bridgeand compared for the critical pier section. The loads and load
combinations areconsidered with respect to IRS and IRC codes.
R.Monteiro et al, This paper intends to readdress that issue from the modeling type
point of view. Currently, most of the structural seismic analyses are carried out
considering either fiber-based or plastic hinge structural models. Depending on the
choice, distinct ways of considering the non-linear behavior of the elements are
regarded and different parameters and calibration procedures need to be set. With the
purpose of investigating the accuracy of both modeling possibilities, a parametric
study is conducted on different bridge configurations, comparing pushover curves as
well as NSP results which make use of those pushover curves. Application issues,
such as advantages and/or limitations.
Skew bridges analysis using grillage analogy., Vikash Khatri et., at (2012) In this
paper describes Grillage analysis is the most common method used in the bridge
analysis. In this method the deck is represented by an equivalent grillage of beams.
8
SVEC/CE/2017-20
The finer grillage mesh, provide more accurate results. It was found that the results
obtained from grillage analysis compared with experiments and more rigorous
methods are accurate enough for design purpose. The finite element method is a well-
known tool for the solution of complicated structural engineering problems, as it is
capable ofaccommodating many complexities in the solution. In this method, the
actual continuum is replaced by an equivalent idealized structure composed of
discrete elements, referred to as finite element, connected together at a number of
nodes.
Behaviour of a skew bridge., Dr. Maher Qaqish et., al. (2008) This method is
usually used for analysis of bridges based on the consideration of the bridge deck as
an elastic continuum in the form of an orthogonally anisotropic plate. Using the
stiffness method of structural analysis, it became possible to analyse the bridge deck
structure as an assembly of elastic structural members connected together at discrete
nodes. There are four distinct techniques which have been found useful by bridge
engineers: grillage and space frame analysis, folded plate method, finite element
method and finite strip method .The grillage analogy method involves a plane grillage
of discrete interconnected beams.
9
SVEC/CE/2017-20
CHAPTER 3
METHODOLOGY
Sub structure that is below deck slab is concluded that using limit state method of
design, the economy is achieved due to reduction in both reinforcing steel and
concrete volume due to reduction in sectional size. Also the limit state of deflection,
shear and bending stress are found to be safe as per IRC:112-2011 which is the latest
code of practice for designing reinforced and prestressed concrete bridges. The whole
structure is found to be stable against sliding and overturning.
10
SVEC/CE/2017-20
CHAPTER 4
ANALYSIS AND DESIGN OF BRIDGE COMPONENTS
12.000
3.000 1.500
11
SVEC/CE/2017-20
(Table no:6.5 (IRC:112-2011))
Charactristic strength of steel (fy) 500 MPa
Table no:18.1 (IRC:112-2011)
Tensile strength of concrete (fctm) 3 MPa
Table no:6.5 (IRC:112-2011)
348 MPa
Design yield strength of shear Page 86 IRC-112-2011
reinforcement fywd = 0
Partial material safety factor for 1.5
concrete (γm) Basic Page 49: (IRC:112-2011)
Partial material safety factor for Steel 1.15
(γs) Basic Page 30: (IRC:112-2011)
This loading is to be normally adopted on all roads on which permanent bridges and
culverts are constructed. Bridges designed for Class 70R Loading should be checked
12
SVEC/CE/2017-20
for Class A Loading also as under certain conditions, heavier stresses may occur
under Class A Loading.
13
SVEC/CE/2017-20
Fig.4.3. Class A Vehicle (IRC-6 2014)
14
SVEC/CE/2017-20
4.3.2. LOAD CALCULATION :
15
SVEC/CE/2017-20
Weight of RCC Kerb + Steel railing = 7.29 KN/m
Weight of RCC Kerb Weight of RCC Kerb Steel railing + Steel railing = 14 58 .
KN/m
The Live Loads are applied on the model as per IRC-6 2014 Table-2, Page16 ,
Analysis is done
by using STAAD.Pro Software.
STAAD PLANE
START JOB INFORMATION
ENGINEER DATE 19-Mar-20
END JOB INFORMATION
INPUT WIDTH 79
UNIT METER KN
JOINT COORDINATES
1 0 0 0; 2 24.3 0 0; 3 0 0 12.5; 4 24.3 0 12.5; 5 0 0 0.5; 6 24.3 0 0.5;
7 0 0 12; 8 24.3 0 12; 9 0 0 2; 10 24.3 0 2; 11 0 0 2.5; 12 24.3 0 2.5;
13 0 0 2.15; 14 24.3 0 2.15; 15 0 0 4.9; 16 24.3 0 4.9; 17 0 0 7.65;
18 24.3 0 7.65; 19 0 0 10.4; 20 24.3 0 10.4; 21 0.75 0 0; 22 0.75 0 12.5;
23 0.75 0 0.5; 24 0.75 0 12; 25 0.75 0 2; 26 0.75 0 2.5; 27 0.75 0 2.15;
28 0.75 0 4.9; 29 0.75 0 7.65; 30 0.75 0 10.4; 31 0.15 0 0; 32 0.15 0 12.5;
33 0.15 0 0.5; 34 0.15 0 12; 35 0.15 0 2; 36 0.15 0 2.5; 37 0.15 0 2.15;
38 0.15 0 4.9; 39 0.15 0 7.65; 40 0.15 0 10.4; 41 24.15 0 0; 42 24.15 0 12.5;
3 24.15 0 0.5; 44 24.15 0 12; 45 24.15 0 2; 46 24.15 0 2.5; 47 24.15 0 2.15;
48 24.15 0 4.9; 49 24.15 0 7.65; 50 24.15 0 10.4; 51 23.55 0 0;
52 23.55 0 12.5; 53 23.55 0 0.5; 54 23.55 0 12; 55 23.55 0 2; 56 23.55 0 2.5;
57 23.55 0 2.15; 58 23.55 0 4.9; 59 23.55 0 7.65; 60 23.55 0 10.4; 61 4.86 0 0;
62 4.86 0 0.416667; 63 0 0 0.416667; 64 9.72 0 0; 65 9.72 0 0.416667;
66 14.58 0 0; 67 14.58 0 0.416667; 68 19.44 0 0; 69 19.44 0 0.416667;
70 24.3 0 0.416667; 71 4.86 0 0.833333; 72 0 0 0.833333; 73 9.72 0 0.833333;
74 14.58 0 0.833333; 75 19.44 0 0.833333; 76 24.3 0 0.833333; 77 4.86 0 1.25;
78 0 0 1.25; 79 9.72 0 1.25; 80 14.58 0 1.25; 81 19.44 0 1.25; 82 24.3 0 1.25;
16
SVEC/CE/2017-20
83 4.86 0 1.66667; 84 0 0 1.66667; 85 9.72 0 1.66667; 86 14.58 0 1.66667;
87 19.44 0 1.66667; 88 24.3 0 1.66667; 89 4.86 0 2.08333; 90 0 0 2.08333;
91 9.72 0 2.08333; 92 14.58 0 2.08333; 93 19.44 0 2.08333; 94 24.3 0 2.08333;
95 4.86 0 2.5; 96 9.72 0 2.5; 97 14.58 0 2.5; 98 19.44 0 2.5;
99 4.86 0 2.91667; 100 0 0 2.91667; 101 9.72 0 2.91667; 102 14.58 0 2.91667;
103 19.44 0 2.91667; 104 24.3 0 2.91667; 105 4.86 0 3.33333; 106 0 0 3.33333;
107 9.72 0 3.33333; 108 14.58 0 3.33333; 109 19.44 0 3.33333;
110 24.3 0 3.33333; 111 4.86 0 3.75; 112 0 0 3.75; 113 9.72 0 3.75;
114 14.58 0 3.75; 115 19.44 0 3.75; 116 24.3 0 3.75; 117 4.86 0 4.16667;
118 0 0 4.16667; 119 9.72 0 4.16667; 120 14.58 0 4.16667; 121 19.44 0 4.16667;
122 24.3 0 4.16667; 123 4.86 0 4.58333; 124 0 0 4.58333; 125 9.72 0 4.58333;
126 14.58 0 4.58333; 127 19.44 0 4.58333; 128 24.3 0 4.58333; 129 4.86 0 5;
130 0 0 5; 131 9.72 0 5; 132 14.58 0 5; 133 19.44 0 5; 134 24.3 0 5;
135 4.86 0 5.41667; 136 0 0 5.41667; 137 9.72 0 5.41667; 138 14.58 0 5.41667;
139 19.44 0 5.41667; 140 24.3 0 5.41667; 141 4.86 0 5.83333; 142 0 0 5.83333;
143 9.72 0 5.83333; 144 14.58 0 5.83333; 145 19.44 0 5.83333;
146 24.3 0 5.83333; 147 4.86 0 6.25; 148 0 0 6.25; 149 9.72 0 6.25;
150 14.58 0 6.25; 151 19.44 0 6.25; 152 24.3 0 6.25; 153 4.86 0 6.66667;
154 0 0 6.66667; 155 9.72 0 6.66667; 156 14.58 0 6.66667; 157 19.44 0 6.66667;
158 24.3 0 6.66667; 159 4.86 0 7.08333; 160 0 0 7.08333; 161 9.72 0 7.08333;
162 14.58 0 7.08333; 163 19.44 0 7.08333; 164 24.3 0 7.08333; 165 4.86 0 7.5;
166 0 0 7.5; 167 9.72 0 7.5; 168 14.58 0 7.5; 169 19.44 0 7.5; 170 24.3 0 7.5;
171 4.86 0 7.91667; 172 0 0 7.91667; 173 9.72 0 7.91667; 174 14.58 0 7.91667;
175 19.44 0 7.91667; 176 24.3 0 7.91667; 177 4.86 0 8.33333; 178 0 0 8.33333;
179 9.72 0 8.33333; 180 14.58 0 8.33333; 181 19.44 0 8.33333;
182 24.3 0 8.33333; 183 4.86 0 8.75; 184 0 0 8.75; 185 9.72 0 8.75;
186 14.58 0 8.75; 187 19.44 0 8.75; 188 24.3 0 8.75; 189 4.86 0 9.16667;
190 0 0 9.16667; 191 9.72 0 9.16667; 192 14.58 0 9.16667; 193 19.44 0 9.16667;
194 24.3 0 9.16667; 195 4.86 0 9.58334; 196 0 0 9.58334; 197 9.72 0 9.58334;
198 14.58 0 9.58334; 199 19.44 0 9.58334; 200 24.3 0 9.58334; 201 4.86 0 10;
202 0 0 10; 203 9.72 0 10; 204 14.58 0 10; 205 19.44 0 10; 206 24.3 0 10;
207 4.86 0 10.4167; 208 0 0 10.4167; 209 9.72 0 10.4167; 210 14.58 0 10.4167;
211 19.44 0 10.4167; 212 24.3 0 10.4167; 213 4.86 0 10.8333; 214 0 0 10.8333;
215 9.72 0 10.8333; 216 14.58 0 10.8333; 217 19.44 0 10.8333;
17
SVEC/CE/2017-20
218 24.3 0 10.8333; 219 4.86 0 11.25; 220 0 0 11.25; 221 9.72 0 11.25;
222 14.58 0 11.25; 223 19.44 0 11.25; 224 24.3 0 11.25; 225 4.86 0 11.6667;
226 0 0 11.6667; 227 9.72 0 11.6667; 228 14.58 0 11.6667; 229 19.44 0 11.6667;
230 24.3 0 11.6667; 231 4.86 0 12.0833; 232 0 0 12.0833; 233 9.72 0 12.0833;
234 14.58 0 12.0833; 235 19.44 0 12.0833; 236 24.3 0 12.0833; 237 4.86 0 12.5;
238 9.72 0 12.5; 239 14.58 0 12.5; 240 19.44 0 12.5;
MEMBER INCIDENCES
1 1 31; 2 2 70; 3 4 42; 4 3 232; 5 5 63; 6 6 76; 7 5 33; 8 7 226; 9 8 236;
10 8 44; 11 9 84; 12 10 94; 13 9 35; 14 11 13; 15 12 104; 16 11 36; 17 13 90;
18 14 12; 19 13 37; 20 15 124; 21 16 134; 22 15 38; 23 17 166; 24 18 176;
25 17 39; 26 19 202; 27 20 212; 28 19 40; 29 21 61; 30 22 32; 31 23 53;
32 24 34; 33 25 55; 34 26 95; 35 27 57; 36 28 58; 37 29 59; 38 30 60; 39 22 24;
40 23 21; 41 24 30; 42 25 23; 43 26 27; 44 27 25; 45 28 26; 46 29 28; 47 30 29;
48 31 21; 49 32 3; 50 33 23; 51 34 7; 52 35 25; 53 36 26; 54 37 27; 55 38 28;
56 39 29; 57 40 30; 58 32 34; 59 33 31; 60 34 40; 61 35 33; 62 36 37; 63 37 35;
64 38 36; 65 39 38; 66 40 39; 67 41 2; 68 42 52; 69 43 6; 70 44 54; 71 45 10;
72 46 12; 73 47 14; 74 48 16; 75 49 18; 76 50 20; 77 41 43; 78 43 45; 79 44 42;
80 45 47; 81 46 48; 82 47 46; 83 48 49; 84 49 50; 85 50 44; 86 51 41;
87 52 240; 88 53 43; 89 54 24; 90 55 45; 91 56 46; 92 57 47; 93 58 48;
94 59 49; 95 60 50; 96 51 53; 97 53 55; 98 54 52; 99 55 57; 100 56 58;
101 57 56; 102 58 59; 103 59 60; 104 60 54; 106 61 64; 107 63 1; 109 64 66;
111 66 68; 113 68 51; 115 70 6; 117 72 5; 122 76 82; 124 78 72; 129 82 88;
131 84 78; 136 88 10; 138 90 9; 143 94 14; 145 95 96; 147 96 97; 149 97 98;
151 98 56; 154 100 11; 159 104 110; 161 106 100; 166 110 116; 168 112 106;
173 116 122; 175 118 112; 180 122 128; 182 124 118; 187 128 16; 189 130 15;
194 134 140; 196 136 130; 201 140 146; 203 142 136; 208 146 152; 210 148 142;
215 152 158; 217 154 148; 222 158 164; 224 160 154; 229 164 170; 231 166 160;
236 170 18; 238 172 17; 243 176 182; 245 178 172; 250 182 188; 252 184 178;
257 188 194; 259 190 184; 264 194 200; 266 196 190; 271 200 206; 273 202 196;
278 206 20; 280 208 19; 285 212 218; 287 214 208; 292 218 224; 294 220 214;
299 224 230; 301 226 220; 306 230 8; 308 232 7; 313 236 4; 315 237 22;
317 238 237; 319 239 238; 321 240 239;
ELEMENT INCIDENCES SHELL
108 1 61 62 63; 110 61 64 65 62; 112 64 66 67 65; 114 66 68 69 67;
18
SVEC/CE/2017-20
116 68 2 70 69; 118 63 62 71 72; 119 62 65 73 71; 120 65 67 74 73;
121 67 69 75 74; 123 69 70 76 75; 125 72 71 77 78; 126 71 73 79 77;
127 73 74 80 79; 128 74 75 81 80; 130 75 76 82 81; 132 78 77 83 84;
133 77 79 85 83; 134 79 80 86 85; 135 80 81 87 86; 137 81 82 88 87;
139 84 83 89 90; 140 83 85 91 89; 141 85 86 92 91; 142 86 87 93 92;
144 87 88 94 93; 146 90 89 95 11; 148 89 91 96 95; 150 91 92 97 96;
152 92 93 98 97; 153 93 94 12 98; 155 11 95 99 100; 156 95 96 101 99;
157 96 97 102 101; 158 97 98 103 102; 160 98 12 104 103; 162 100 99 105 106;
163 99 101 107 105; 164 101 102 108 107; 165 102 103 109 108;
167 103 104 110 109; 169 106 105 111 112; 170 105 107 113 111;
171 107 108 114 113; 172 108 109 115 114; 174 109 110 116 115;
176 112 111 117 118; 177 111 113 119 117; 178 113 114 120 119;
179 114 115 121 120; 181 115 116 122 121; 183 118 117 123 124;
184 117 119 125 123; 185 119 120 126 125; 186 120 121 127 126;
188 121 122 128 127; 190 124 123 129 130; 191 123 125 131 129;
192 125 126 132 131; 193 126 127 133 132; 195 127 128 134 133;
197 130 129 135 136; 198 129 131 137 135; 199 131 132 138 137;
200 132 133 139 138; 202 133 134 140 139; 204 136 135 141 142;
205 135 137 143 141; 206 137 138 144 143; 207 138 139 145 144;
209 139 140 146 145; 211 142 141 147 148; 212 141 143 149 147;
213 143 144 150 149; 214 144 145 151 150; 216 145 146 152 151;
218 148 147 153 154; 219 147 149 155 153; 220 149 150 156 155;
221 150 151 157 156; 223 151 152 158 157; 225 154 153 159 160;
226 153 155 161 159; 227 155 156 162 161; 228 156 157 163 162;
230 157 158 164 163; 232 160 159 165 166; 233 159 161 167 165;
234 161 162 168 167; 235 162 163 169 168; 237 163 164 170 169;
239 166 165 171 172; 240 165 167 173 171; 241 167 168 174 173;
242 168 169 175 174; 244 169 170 176 175; 246 172 171 177 178;
247 171 173 179 177; 248 173 174 180 179; 249 174 175 181 180;
251 175 176 182 181; 253 178 177 183 184; 254 177 179 185 183;
255 179 180 186 185; 256 180 181 187 186; 258 181 182 188 187;
260 184 183 189 190; 261 183 185 191 189; 262 185 186 192 191;
263 186 187 193 192; 265 187 188 194 193; 267 190 189 195 196;
268 189 191 197 195; 269 191 192 198 197; 270 192 193 199 198;
19
SVEC/CE/2017-20
272 193 194 200 199; 274 196 195 201 202; 275 195 197 203 201;
276 197 198 204 203; 277 198 199 205 204; 279 199 200 206 205;
281 202 201 207 208; 282 201 203 209 207; 283 203 204 210 209;
284 204 205 211 210; 286 205 206 212 211; 288 208 207 213 214;
289 207 209 215 213; 290 209 210 216 215; 291 210 211 217 216;
293 211 212 218 217; 295 214 213 219 220; 296 213 215 221 219;
297 215 216 222 221; 298 216 217 223 222; 300 217 218 224 223;
302 220 219 225 226; 303 219 221 227 225; 304 221 222 228 227;
305 222 223 229 228; 307 223 224 230 229; 309 226 225 231 232;
310 225 227 233 231; 311 227 228 234 233; 312 228 229 235 234;
314 229 230 236 235; 316 232 231 237 3; 318 231 233 238 237;
320 233 234 239 238; 322 234 235 240 239; 323 235 236 4 240;
START GROUP DEFINITION
MEMBER
_BEAMGIRDER 35 TO 38
_DIAPHRAGAM 45 TO 47 100 102 103
JOINT
END GROUP DEFINITION
ELEMENT PROPERTY
108 110 112 114 116 118 TO 121 123 125 TO 128 130 132 TO 135 137 139 TO 142
-
144 146 148 150 152 153 155 TO 158 160 162 TO 165 167 169 TO 172 174 176 -
177 TO 179 181 183 TO 186 188 190 TO 193 195 197 TO 200 202 204 TO 207 209 -
211 TO 214 216 218 TO 221 223 225 TO 228 230 232 TO 235 237 239 TO 242 244 -
246 TO 249 251 253 TO 256 258 260 TO 263 265 267 TO 270 272 274 TO 277 279 -
281 TO 284 286 288 TO 291 293 295 TO 298 300 302 TO 305 307 309 TO 312 314 -
316 318 320 322 323 THICKNESS 0.25
DEFINE MATERIAL START
ISOTROPIC CONCRETE
E 3.17185e+007
POISSON 0.17
DENSITY 25
ALPHA 1e-005
DAMP 0.05
20
SVEC/CE/2017-20
TYPE CONCRETE
STRENGTH FCU 40000
END DEFINE MATERIAL
MEMBER PROPERTY AMERICAN
1 TO 34 39 TO 44 48 TO 99 101 104 106 107 109 111 113 115 117 122 124 129 -
131 136 138 143 145 147 149 151 154 159 161 166 168 173 175 180 182 187 189 -
194 196 201 203 208 210 215 217 222 224 229 231 236 238 243 245 250 252 257 -
259 264 266 271 273 278 280 285 287 292 294 299 301 306 308 313 315 317 319 -
321 PRIS YD 0.25 ZD 0.25
MEMBER PROPERTY AMERICAN
45 TO 47 100 102 103 PRIS AX 2.3375 IY 1.47311 IZ 1.40737 YD 0.425 ZD 1.375
35 TO 38 PRIS AX 0.8625 IY 0.234 IZ 0.288171 YD 0.9
CONSTANTS
MATERIAL CONCRETE ALL
SUPPORTS
27 TO 30 57 TO 60 PINNED
DEFINE MOVING LOAD
TYPE 1 LOAD 40 60 60 85 85 85 85
DIST 3.96 1.52 2.13 1.37 3.05 1.37 WID 1.93
TYPE 2 LOAD 13.5 13.5 50.7 50.7 34 34 34 34 13.5 13.5
DIST 1.1 3.2 1.2 4.3 3 3 3 20 1.4 WID 1.84
LOAD 1 LOADTYPE Dead TITLE LOAD CASE 1
MEMBER LOAD
35 TO 38 UNI GY -21.56
LOAD 2 LOADTYPE Dead TITLE LOAD CASE 2
MEMBER LOAD
1 TO 104 106 107 109 111 113 115 117 122 124 129 131 136 138 143 145 147 149 -
151 154 159 161 166 168 173 175 180 182 187 189 194 196 201 203 208 210 215 -
217 222 224 229 231 236 238 243 245 250 252 257 259 264 266 271 273 278 280 -
285 287 292 294 299 301 306 308 313 315 317 319 321 UNI GY -17.19
1 TO 104 106 107 109 111 113 115 117 122 124 129 131 136 138 143 145 147 149 -
151 154 159 161 166 168 173 175 180 182 187 189 194 196 201 203 208 210 215 -
217 222 224 229 231 236 238 243 245 250 252 257 259 264 266 271 273 278 280 -
285 287 292 294 299 301 306 308 313 315 317 319 321 UNI GY -10.07
21
SVEC/CE/2017-20
LOAD GENERATION 1 ADD LOAD 1
TYPE 1 0 0 3.7 XINC 0.25 ZINC 0.25
TYPE 2 0 0 3.15 XINC 0.25 ZINC 0.25
LOAD GENERATION 1 ADD LOAD 2
TYPE 2 0 0 6.8 XINC 0.25 ZINC 0.25
PERFORM ANALYSIS PRINT ALL
PERFORM ANALYSIS PRINT ALL
FINISH
22
SVEC/CE/2017-20
Fig 4.7. Deck slab model rendered view
4.4.1. FINAL DESIGN MOMENT FROM STAAD ANALYSIS FOR
DECK SLAB :
SLS-RARE SLS‐ QPC ULS SLS
ULS BM BM BM 0.3 BM 0.3 BM
KN/m.m KN/m.m KN.m/m KN.m/m KN.m/m
Span moments 55 40 7.5 16.5 12.0
Intermediate supports 49.5 24 3.0 14.85 7.20
moments at face of web
Intermediate supports 27.0 20 2.50 8.10 6.00
moments at face of flange
End supports moments at 71.00 61.50 23.00 21.30 18.45
face of web
End supports moments at 65.00 57.00 22.00 19.50 17.10
face of flange
Cantilever moments at face 47.50 33.00 11.00 14.25 9.90
of Flange
Cantilever moments at face 57.50 39.00 12.00 17.25 11.70
of web
4.4.2. REINFORCEMENT SCHEDULE FOR DECK SLAB
23
SVEC/CE/2017-20
Cantilever
1 slab
a) At face of
flange b1 12 200 565.49
b) At face of
web b1 12 200 565.49
a)Span
moments a1 12 200 565.49 958.19 279 OK 5625 OK
b) Intermediate b
12 200 565.49
Supports at
face of
web b2 958.19 396 OK 5625 OK
10 200 392.70
b) Intermediate b
12 200 565.49
Supports at
face of
flange b2 10 200 392.70 958.19 279 OK 5625 OK
c)End supports
at b1 12 200 565.49
c)End supports
at b1 12 200 565.49
Cantilever
1 slab 10 200 392.70 392.70 279 OK
a)Span
moments 10 200 392.70 392.70 279 OK
24
SVEC/CE/2017-20
supports
Effective
Ast Pro Depth of Depth Check for
BM MOR
Sr. No. Type t.m/m t.m/m
(mm2) NA (mm) d (mm) MOR
Cantilever
1 slab
a) At face of 1130.9
flange 5.09 7 34.16 179.00 8.13 OK
b) At face of 1130.9
web 6.16 7 34.16 254.00 11.82 OK
8.13
c)End supports at face 1130.9
of flange 6.96 7 34.16 179.00 OK
Cantilever
1 slab 1.85 392.70 11.86 179.00 2.98 OK
25
SVEC/CE/2017-20
2 Mid span slab
a)Span
moments 1.77 392.70 11.86 179.00 2.98 OK
b) Intermediate
supports 1.59 392.70 11.86 179.00 2.98 OK
Effective
Ast Pro Depth of Depth Check for
BM
Sr. No. Type t.m/m MOR
NA
t.m/m
(mm2) (mm) d (mm) MOR
1 Cantilever slab
a) At face of
flange 5.09 1130.97 34.16 179.00 8.13 OK
b) At face of
web 6.16 1130.97 34.16 254.00 11.82 OK
10.11
6.98
8.13
c)End supports at face of
flange 6.96 1130.97 34.16 179.00 OK
26
SVEC/CE/2017-20
2 Mid span slab
b) Intermediate
supports 1.59 392.70 11.86 179.00 2.98 OK
Stress in steel
BM
Sr. No. Type t.m/m concrete concrete for steel
(Mpa)
1 Cantilever slab
a) At face of
flange 1.18 2.74 OK 70.3 OK
b) At face of
web 1.29 1.31 OK 51.18 OK
Sr. No. Type Equi.dia 5*(C+ф/2 ρρ.eff Ac eff Max. crack σsc (εsm-εcm) Crack Check for
me ) width
27
SVEC/CE/2017-20
ter фeq spacing Srmax
Crack
mm mm2 (Mpa) Wk (mm) width
(mm) (mm)
1 Cantilever slab
a) At face of
flange 12.00 230 0.0101 112500 338.92 70.3 0.00021 0.073 OK
b) At face of
web 12.00 230 0.0098 115000 343.43 51.18 0.00072 0.247 OK
a)Span moments 11.09 228 0.0085 112500 357.37 55.02 0.00013 0.048 OK
b) Intermediate
Supports at face
of
b) Intermediate
Supports at face
of
c)End supports
at
face of web 12.00 230 0.0098 115000 343.43 98.1 0.00068 0.234 OK
c)End supports
at
face of flange 12.00 230 0.0101 112500 338.92 140.61 0.00025 0.085 OK
• Height = 6m
28
SVEC/CE/2017-20
Dead load from three girders:
49 18.33 3 = 2694.51kN 2695 kN
Cross beams at end:
10.5 24.2 = 88.2 kN
Intermediate cross beam:
10.5 3 4.2 = 132.3 kN
ey = 2.5 m
29
SVEC/CE/2017-20
Total ht. of pier=6m
So DL of pier cap=9x1.4.0.25x25=78.75KN.
DL of 6 pedestals=6x(0.45x0.45x0.45x0.25)=13.67KN
DL of pier=6x1x9x25+2(π/8x0.52x6x25)=1350+29.45≈1380KN
Total DL =1473+2916=4389kN
Factored DL=4389x1.5=6584kN
Max.=1050/9+(1705x6)/1x92
=116.67+129.3
=245.97KN/m2=2.246N/mm2
Min.=1050/9-1705/1x92/6
= 116.67-129.30= -12.63KN/m2
= -0.0126N/mm2
Stress in YY dinn
30
SVEC/CE/2017-20
Max.=Pyy/A+M/Z
=Pyy/A+Muy/Z
=682/9+394x 6/9
=75.77+262.667
=338.45KN/m2=0.338N/mm2
Min.=Pyy/A-M/z
=-186.897KN/m2=-0.187n/mm2
i)Due to breaking
i.e. 0.2x700=140KN.
Factored moment=140x1.5x6.6=1386kN/m
Z= bd2/6=9x12/6=1.5m3
So M/Z=140x1.5x6.6/1.5=924KN/m2 =0.924N/mm2
31
SVEC/CE/2017-20
According to AASHTO LRFD code for elastomeric bearing coefficient of resistance
lies between 0.02 to 0.04
Dl + LL =4374+1050=5424KN
Resistance of bearing=0.04x5424+=217KN
Z=9x1/6=1.5m3
K1=1.08(referring to T1)
K3=1(topographic factor)
={(18.33x0.25)+(18.33x1)+18.33x(1.4+0.15)}
=57.234m2
LA=6+(0.45+0.05+1.4+0.95+0.25/2) =7.15m
Moment=89.82x7.15=642.213KN/m=643kNm
32
SVEC/CE/2017-20
According to code lead combination IS: 456:200
a)1.5(DL+LL)=1.5(4389+700)=7633.5KN
b)1.5(DL+WL)=1.5(4389+107.89)=6746KN
c)1.2(DL+LL+WL)=1.2(4389+107.89)=5396.27KN
6.Water current:
V=3m/s
P=52KV2=o.52x0.66x32=3.1KN/m2
P=3.1x1.4=4.34KN/m2
Area of obstruction=1x5.5=5.5m2
It acts at h/3 distance from base ABC is the pressure distribution after water current
max. at top & min. at bottom
So moment = (23.87x5.5)/3=87.53/2≈88/2=44KNm
=4.07x5.5x1=22.39KN
33
SVEC/CE/2017-20
=1.48x9x5.5=73.26KN
M=73.26x5.5/3=268.62/2 kNm=270/2=135KNm
Z=9x12/6=1.5m3
thus = M/Z=268.62/2/1.5=179.08Kn/m2=(0.179N/4)N/mm2
At pier base
3)eccentric
loading due to LL
4)longitudinal Forces
5) Water current
34
SVEC/CE/2017-20
------------------------------------------------------------------------------------------
DL of pier=9x1x4x25+2(π/8x0.5x0.5x4x25)≈920KN
So total DL=2916+920+78.67+13.67=3929KN
Factored DL stress=3929/9=436.56KN/m2=.436N/mm2
3)eccentric loading
Due to LL
4)longitudunaltenus
_____________________________________________________
35
SVEC/CE/2017-20
2.38 -1.074 2.414
-1.22
3)eccentric loading
due to LL
4)longitudinalForces
___________________________________________________
1.759 -0.55
1.793 0.78
Or (1000x9000)mm
Pu (factored) =6584+1050=7634kN
36
SVEC/CE/2017-20
Mux = 682x2.5=1705kNm
Muy=1050x0.375=394kNm
Iy=13x9/12=0.75mm4
z=1x93/12=60.75mm4
breq=iy√12=0.75√12=2.59
hreq=iz√12=60.75√12=210.44
iy 0.75
y=eff.length/Ky;Ky=
√ √A
=
91
= 0.288
So y =1.3x6/0.288=27.02
ix 60.75
z=eff. Length/Kz; Kz=
√ √A
=
91
= 2.59
So z = 1.36/2.59 = 3.00; zz = xx
Condition I
z/y=1/9=0.111<2
ey=1.475m
ez or ex =0.375m
Condition – II
37
SVEC/CE/2017-20
(ey/heq)/(ez/beq) 0.2 or (ez/beq)/(ey/heq)0.2
(ez/beq)/(ey/heq)=(0.375/2.59)/(1.475/210.44)=20.65>0.2
Assuming p=1.5
P/fck=1.5/35=0.042857=0.043
dI=45+20/2+10=65mm
dl/D=65/9000=0.00722
takingdI/D=0.05
Pu/fckbD=7634x103/35x1000x9000=0.0248=0.025
Muy=1050x0.375=394kNm
+ 1386kNm(breaking)
+ 1433kNm (resistance)
+ 135kNm(water current)
So Muy=3349kNm
Mux=1705kNm
d’/D=0.05and Pu/fckbD=0.072
=>Muy1=0.072x35x1000x90002=204120KNm
dl/D]y axis=65/1000=0.065=0.1
38
SVEC/CE/2017-20
P/fck=0.043,d1/D=0.1,Pu/fckbD =0.025
Muy1/fck bD2=0.0672
=>Muy1=fck bD20.0672
=>Muy1=0.0672x35x9000x10002=21168KN
Referring to chart 63 of SP-16 and following the values of P=1.5 Fe=415 m=3
Puz/Ag=21
Puz=21x9000x1000=189000KN
Pu/Puz=7634/189000=0.041
Muy/Muy1=3349/21168=10.1
Mux/Mux1=1705/204120=0.0084
Mux/Mux1=0.85
P/fck =0.8/35=0.0228
Pu/fckbD=7634x103/35x1000x9000=0.0248=0.025
P/fck=0.0228 Pu/fckbD=7634000/3510009000=0.025
We get Mux1=0.48x35x1000x90002=136080KNm
Muy1/fck bD2=0.04
=>Muy1=0.04x35x9000x10002
39
SVEC/CE/2017-20
=12600KNm
Puz/Ag=18.2
Puz=18.2x9000x1000=163800KN
Pu/Puz=7634/163800=0.0467
Mux/Mux1=1705/136080=0.0126
Spacing=18000/102=176.47c/c
Astp=18000x(π/4)x302/170=74844mm2
Since 1/4th of the main reinforcing bars i.e. 30mm # is 8.5 mm, that’s why we have
chosen 10mm # bars as lateral and transverse reinforcement.
4.5.2 PEDESTAL DESIGN:
40
SVEC/CE/2017-20
Pedestal on pier and abutment
1442 103
11.77 N / mm 2
Pressure or rubber paid 400 400
A1
A2
Pressure on loaded area and permissible bearing stress
A1
15.75 2 31.5 N / mm 2 9.013
A2
Permissible bearing stress (ok)
41
SVEC/CE/2017-20
L
15.75 9.92
400
= 229
0.15
450 450 303.75 mm
min reinforcement 100
405
3bans
162
Providing 16mm bans 4
400
250mm c / c
Providing 3 bans in spacing 2
Ast p 122 4 452.389 405 mm 2
4 (ok)
400
133mm 130 mm.c / c
Spacing 3
1 1 1
Pc Pe P
42
SVEC/CE/2017-20
2 EI 31.5 1
2
Pe
e 2 2 10492623.18kN
e
v2 (are end is ticked and other end is hinged)
2
450 450 4503
e I 3417187500mm 4
2 and 12
1 1
2.3698 107 kN 1
Pe Pc
P 0.4 f ck A n f ck A SC
Pu 0.4 t ck A C 0.67 t y ASC 0.4 35 202047 0.67 415 453 2828658 140996.25
1 1 1 1
3.36 107 kN 1
Pu Pu Pc Pe
; (ok)
Preliminary dimensions
43
SVEC/CE/2017-20
thickness = 1.5m (base slab)
ht. of stem = 6m
cos
2
1
ka
cos 2 cos sin sin
1 cos cos
350
00
2 / 3 22.50
2 35 22.5
3
23.336 22.5
So 23.336
k a 0.243
2
cos
2
1
kp
cos 2 cos sin sin
1
cos cos
= 9.547
44
SVEC/CE/2017-20
a) STABILITY ANALYSIS:
Earth pressure:
1 1
PA k a H 2 0.246 19 9.952 231.37 232 kN / m
2 2
N
Providing abutment cap 9.3 1.5 25 0.25 87.185 93kN 10k m
350
92.2 k N
Surcharge due to LL 0.85 2 0.08 3.6 2 0.08 m
185
ht 9.736 1.2m
So virtual 19 (acc to IRC-6:2014)
Horizontal force due to approach slab 0.3 25 0.243 9.95 = 18.15 kN/m
9.95
m
The above 2 forces act at a distance act at a distance 2 from base.
49 3
73.5kN / m
DL from super structure 2
45
SVEC/CE/2017-20
Total DL from super structure = 73.5 + 26.25 = 99.75 kN/m.
V H Mv
MH
1 DL from 99.75 ---- 2.075 208 ----
superstructure
2 Active Earth ---- 232 4.179 ----
pressure 960
3 Horizontal force
due to LL ---- 74.15 ---- 369
surcharge & 9.95/2
approach slab
4 Vertical load due to
LL surcharge & 151.5 ---- 5.5 833.25
approach slab -----
5 Self wt (1) 180 ---- 2.4 432
-----
6 Self wt (2) 22.5 ---- 1.833 41.2425
-----
7 Self wt (3) 300 ---- 4 1200
-----
8 Self wt (4) 25.3125 ---- 70.24
2.775 -----
9 Self wt (5) 802.75 ---- 5.5 4416
-----
Total 1581.8125 306.15 7200.7325 -----
m v −m H
x́ =
v
7200.7325−1329
= =3.712 m
1581.8125
b
e 3.71 0.2800 b 8 1.33
2 6 6 (ok or safe)
46
SVEC/CE/2017-20
Stabilizing moment 7200.7325
5.418 1.5 ok
Overturning moment 1329
9.95
It acts 2 from base of abutment.
V H Mv MH
47
SVEC/CE/2017-20
LL surcharge & 37.5 ---- 5.5 207 -----
approach slab
5 Self wt (1) 180 ---- 2.4 432 -----
6575 1050.3
x 3.53m
1565
8
e 4 3.53 0.47 1.33
3
6575
6.26 1.5
FOS against over turning 1050.5 (ok)
0.9 1565
2.53 1.5
FOS against sliding 280.5 (ok)
Comparing the two condition we get the worst case as traffic load surcharge and earth
surcharge.
b) DESIGN OF STEM :
Design is done by considering surcharge i.e. both traffic surcharge and earth
surcharges.
48
SVEC/CE/2017-20
1
P 5.544 6 27.72 6
2 33.264 81.66 114.924 120 kN
1 6
M v 5.544 6 6 / 2 27.22 6
2 3 99.792 163.32 263.112 kN m 270kN m
1000
613mm c / c
800 /( / 4 252 )
Spacing d = 1500 – 70 = 1430 mm c/c,
1000 20 2
4 392.69 mm c / c
Spacing 800
1000 162
4 255.327 cc
Spacing 800 = 200 mm c/c.
49
SVEC/CE/2017-20
1000 162
4 1006 mm 2
Astp 200
This rf. to be provided for one face only i.e. in the back fill side.
Assuming the rectangular portion or stem should carry all the loads than acc. to
10, 000
5000 mm 2
So rf. to be provided 2 (each side)
1000
123.15mmc / c
5000
Spacing / 4 282
1000 282
4 5132 mm 2
Astp = 120
5132
8.33 NOS 9 nos
282
No. of bars 4
9 282 5542 mm 2
Astp= 4 (in one face)
5542 2
100 0.93% 0.8%
% ofAstp 1000 1200 (ok)
50
SVEC/CE/2017-20
vu 180 103
v 0.159 N / mm 2
bd 1000 1130
A st
100 0.93
bd
τ cp =0.6476 n/mm2
200 200
k 1 1 1.38 2.0 ok
d 1430
ASL 5542 2
L 0.0077 0.2 ok
b d 1430 1000
cp 0.2 f cd
(max. value)
0.67 35
f cd 15.633
1.5
1347.255 110.25
N Ed 1460 103
1.021 3.1267
A C 1430 1000
51
SVEC/CE/2017-20
Vmin 0.031 1.383/ 2 35 0.2973
VED 180kN
VRd,C 872.809 kN
VEd VRd,C
(so safe) (No. shear ref. reqd).
Loads:
LL in yy = 682 kN.
e x 0.375m
e y 2.5 m
52
SVEC/CE/2017-20
(Plan of top of Abutment Stem)
e x 0.325 m
e y 2.5m
1.23 9
iy 1.296 mm 4
12
93 1.2
ix 72.9 mm 4
12
beq i y 12 4.49
h eq i z 12 252.53
iy 4.49
ky 0.645
A 9 1.2
ix 72.9
kz 2.598
A 9 1.2
1.3 6 1.3 6
z 3.002
kz 2.198
y 12.1
4.036 2
z 3.002
z 1
0.2481 2
y 4.036
y z
and
As the z y
both should be less than 2 so we have to design as biaxial bending.
53
SVEC/CE/2017-20
M uy 394 1407 150 821.25
= 2772.25 kNm 2800 kNm.
load) [2.25 0.45 6 25 228 kN] (dirt wall) + 93kN (pile cap)
Design checking for abutment whether the design reinforcement to be provided will
take the load or no additional reinforcement required. Solved referring to SP - 16.
P = 1.5%
P 1.5
0.043
f ck 3.5
d1 70
0.00777 0.05
D 9000
Pu 5188 103
0.014
f ck bD 35 1200 9000
referring to chart-43
M ux1
0.072
f ck bD 2
For YY
d1 70
0.06 0.1
D 1200
Pu
0.014 P 0.043
f ck bD t ck
,
referring to chart - 44
54
SVEC/CE/2017-20
M uy1
0.065
f ck bD 2
P = 1.5%, Fe-415, M - 35
Puz
20.5
Ag
Pu 5188
0.023
Puz 221400
M uy 2800
0.137
M uy1 20475
M ux 1705
0.0069 0.007
M ux1 244944
Pu M uy
0.023 0.137
Puz M uy1
and
M ux
0.87
M ux1
We get chart
M ux M
ux
M ux1 M ux1
chart from analysis
P 0.8
0.0228
f ck 35
Pu 5188 103
0.014
f ck bD 35 1200 9000
d1 70
0.0077
D 9000
55
SVEC/CE/2017-20
referring the chart - 43.
M ux1
0.042
f ck bD 2
d1 70
0.06 0.1
D 1200
M uy1
0.039
f ck bD 2
Puz
18.2
Ag
Pu 5188
0.027
Puz 196560
M uy 2800
0.158
M uy1 17691
M ux 1705
0.012
M ux1 142884
Pu M uy
0.027 0.158
Puz
and M uy 1
M ux
0.85
M ux1 chart
We get
M ux M
ux
M ux1 M ux1
chart from analysis
56
SVEC/CE/2017-20
So providing min. reinforcement as 0.8% of Ag
Astreqd=0.8/100(1000× 9000)
=72000mm2
0.8
1000 9000 72000 mm 2
Ast required 100
18000
181.69 180 mm c / c
61000 /( / 4 282 )
Spacing
( 282 ) 18000
Ast p 4 99851.70mm 2
111
99851.70 5644 2
So % of steel 1200 900 = 1.03%
p 1.03
0.0294
f ck 35
Spacing =
Pu 5188 103
0.014
f ck bD 35 1200 9000
M ux1
0.058
f ck bD 2
M uy1
0.055
f ck bD 2
57
SVEC/CE/2017-20
M uy1 0.055 35 9000 1200 2
= 24948 kNm
from chart - 64
Puz
18.8
Ag
Pu 5188 M uy 2800
0.0255 0.158
Puz 203040 M uy1 17691
,
M ux 1705
0.012
M ux1 142884
M ux M
085 ux
M ux1 M ux1 analytic
from chart - 64. chart
M ux
085 0.012
M ux1
chart
Pu = 5188 kN
So Pu<Puz
So taking n 1
n n
M ux M uy
M 0.012 (0.158)1 0.17 1
1
M ux1 uy1 (ok)
58
SVEC/CE/2017-20
Providing 30 mm # bars with 114 mm c/c spacing throughout the
18m.i.e., through both side of long section. Side face reinforcement.
e) DESIGN OF HEEL SLAB:
P = 1582 kN
e = 0.325 mm
1 82
z 10.667 m3
6
A 8 1 8m
Q 231.5 kN / m 2
Net pressure
1
171.5 5 5 60 857.5 150 1007.5kN 1008kN
Shear 2
d 1500 70 1430mm
59
SVEC/CE/2017-20
Factored M u 2400 1.5 3600kN
0.5 f ck 4.6 M u
Ast 1 1 bd
fy f ck bd 2
Providing 30 mm ∅ bars,
1000 30 2
4 95.07 mm
Astreqd 7435
1000 302
Ast p 4 7854 mm 2
90
Vu 1008 kN
v u 1512 1000
v 1.057 N / mm 2
bd 1000 1430
Ast 7854
100 100 0.56
bd 1000 1430
cp 0.53 N / mm 2 v
(so shear reinforcement(rf.) required)
60
SVEC/CE/2017-20
0.87f y Asv d
Vus
Sv
0.87 415 4 102 1430
753610 4
SV Sv 215.25mm
ASv 0.4
bSv 0.87 f y
314.16 0.4
1000Sv 0.87 415
Providing 4 legged – 10 stirrups with spacing 200 mm c/c throughout the heel
slabs. Provide 0.12% of Ag as distribution reinforcement.
1000 16 2
4 111mm c / c
.12
1000 1500
100
61
SVEC/CE/2017-20
(Net Pressure Diagram)
1
Vu 190.5 1.5 208.5 190.5 1.5
2 285.75 13.5 299.25 300 kN
1.5
A 285.75 13.5 1.5
Mu about 2 3 214.3125 6.75 221.0625 222 kNm
= 650 mm2
min. steel
vu 300 103
v 0.21N / mm 2
bd 1000 1430
Ast 2930
100 100 0.21
bd 1000 1430
62
SVEC/CE/2017-20
Increasing the half reinforcement from stem and heel slab to the intersection
portion of heel slab and stem.
1000 30 2
4 241.24 mm
Spacing of bars 2930
h) DISTRIBUTION REINFORCEMENT:
The base slab thickness is increased upto 4.5m as that the abutment can be designed
as shallow foundation and stress at heel & toe will be safe.
Wind force and live load cannot be considered at a time as per IRC:6-2014
Mux=1747kN-m
Muy=3348 kN-m
∑ V ∑ Mux dy ∑ Muy dx
P= ± ±
n ∑ dy 2 ∑dx 2
∑dx 2=3׿=30.375m 2
∑dy 2=2׿=81m 2
= 1811.2-97.056+248=1962.144kN
63
SVEC/CE/2017-20
F3= 1811.2+248 = 2060kN
F5= 1811.2+248+97.056=2157kN
F6 = 1811.2+97.056-248 = 1660.256kN
F1+F3+F5 = 6180 kN
F5 + F6= 3818 kN
Mux=3818× 4.5=17181 kN −m
4.5
Muy=6180× =13905 kN−m
2
17181 ×106
(dreq)=
√ 3
0.36× 35 ×0.48 ×6.2 ×10 ×(1−0.416 × 0.48)
=756.64mm
dprovided=1800-200(pile+ P.C.C)-55-15=1530mm
0.5× 3.5
(Ast req.)y-direction¿ × ¿)=32548.206mm2
415
0.5 ×35
(Ast req.)x-direction = ׿ ]
415
=26194.87mm2
(Ast)prov x-dir=26507.18mm2 ;
After considering the shear criteria (explained in next article), revised reinforcement
is given by, (Ast prov.)revised = 30mm-∅ @110mm c /c=¿67472.8422mm2
64
SVEC/CE/2017-20
Shear will be checked at a distance d/2 fromface of column as per IS-2911-part 3
Xx =1.75m, Xy =0 m
So the full reaction of the piles will be considered as the shear force to be resisted by
the cap.
VEd = Vu =6180-361.25= 5820kN-m
As per IRC:112-2011,
Vmin =0.2925
A sc
Ρ1= =0.00165<0.02
bw d
(Ast prov.)x-direction=97472.8422mm2
Ρ1 =0.0042
c) ANCHORAGE LENGTH:
αa=1,ℓb=k∅=30 × 30=900mm
(Astreq./Astprov.)x-direction = 0.388
65
SVEC/CE/2017-20
(Astreq./Astprov.)y-direction = 0.989
Hence calculated ℓbnet. will be smaller than ℓ b. But let’s continue the bars of base up to
top of the cap having 60 mm cover at top.
Scour depth=3.72m
Pile cap=1.8m
Фpile¿ 1.2 m
Lpile =11.7m
8.19
leff/d¿ =6.825 ( short column ) .
1.2
n
π π
Qu= ( Du2 – D2 ) [0.5 DunN + Nq∑ d r]+ D2 (0.5DN + dfNq)
4 r=1 4
+(0.5 πDK tanδ) (d12 + df2 – dn2) [for sandy soil] (Cl-5.2.3 of IS:2911-part3)
Du =3m,D=1.2m.
66
SVEC/CE/2017-20
d1= 6m, dn=10.5m
(Qu)2ud =39438.41+4602.503+1849.34=45890.253 kN
Qu
(Qu)compression =9601.462 kN =
2.5
Qu
(Qu)uplift = = 8001.218 kN
3
Due to group action, 10% strength will be reduced of each pile as per IS:2911-3-
1980(CL-5.2.8.1)
(Qu)uplift=7201.09kN=7200kN
Though middlepiles will be having lesser load, let us take it as same as that of corner
piles.
As per IS2911-3-1980,appendix-c,
EI EI
T=5
√ K1
, R=4
K2√
Using table- 2 of appendix-c.IS:2911-3-1980,since all the layers are impervious
&66%(approx.) of soil is sand/gravel group with in 13.50m, let us chose
Un-confined compression=2Cu
67
SVEC/CE/2017-20
Up to 4.5 m below the ground level ,unconfined compression is varying from 0.50-
0.64 in bore hole -1 up to 4,5 m below ground level of in all other case it is zero let us
take
π
I= × d 4 =1.017876× 1011 mm4
64
T=777.556 m
R=249.32m
Using flexible piles will be those for which embedded length is ≥ 4 R∨4 T
K=1.25, V =3m/sec
(Fu)short face=1.4×64.012=89.63 kN
&¿ 54.857 kN
68
SVEC/CE/2017-20
(Hence safe against lateral force)
Also safe load in uplift resistance is given by (using extrapolation),
As per appendix –B -1-11 of IS:2911-3-1980, the loads lesser than above extrapolated
loads need not be designed separately. Since in our case it is lesser, that’s why no
need of separate design for horizontal forces.
Using Brom’s chart (page -274of Foundation Engineering, PHI - publication by P.C.
Varghese),
e 1.92 L 9,78
= =0.1963=0.2 and = =8.15
L 9.78 b 1.2
From chart;
So Hu = 301.7282.518.87 = 2445.552 kN
For safe design, taking factor of safety 2.5, Hs = 978.2208 kN >> Fushort face and
Fulongface(Safe)
So our piles will be designed as short axially loaded columns with axial force
=Pu=2157 kN
Or 264.05 A st=(-)1.367×10 7
69
SVEC/CE/2017-20
That means minimum reinforcement will be provided. Since the design is based on
IS456:2000,minimum reinforcement is 0.8% of Ag as against 0.4% of Ag as per IS:
2911 (3)
0.8
Ast = ׿
100
9048
=12.80=13 numbers
Providing 30mm∅ bars, no. of bars= π 2 .
× 30
4
70
SVEC/CE/2017-20
CHAPTER 5
CONCLUSION
This project concludes the planning, analysis and design of fly over structures.
This project gives a model to understand how the flyover components
designed.
This structure reduces the traffic control and enhances the safe driving.
The structure is designed as per IRC class A loading and IRC 70R loading.
This project helps to improve the urbanization of rural areas
Also facilitate the connection of various system of road such as village road,
State highway, National highway etc.,
71
SVEC/CE/2017-20
CHAPTER 6
REFERNCES
72
SVEC/CE/2017-20