The document provides a checklist for reviewing isometric drawings. It lists 21 items to check, including verifying that north orientation matches other drawings, flow areas and component tags are shown, pipe sizes and support match other documents, dimensions are clearly indicated, and special items like high/low points and slopes are included. Ensuring isometrics contain all necessary information and match other engineering drawings is the focus of the checklist.
The document provides a checklist for reviewing isometric drawings. It lists 21 items to check, including verifying that north orientation matches other drawings, flow areas and component tags are shown, pipe sizes and support match other documents, dimensions are clearly indicated, and special items like high/low points and slopes are included. Ensuring isometrics contain all necessary information and match other engineering drawings is the focus of the checklist.
The document provides a checklist for reviewing isometric drawings. It lists 21 items to check, including verifying that north orientation matches other drawings, flow areas and component tags are shown, pipe sizes and support match other documents, dimensions are clearly indicated, and special items like high/low points and slopes are included. Ensuring isometrics contain all necessary information and match other engineering drawings is the focus of the checklist.
Construction North mark-up should be shown in Isometrics 1 and that also should match the Layout or 3D model. 2 Flow Area should be shown in Isometrics & its components. Tag Number of components,instruments or any other 3 special items should be shown in Isometrics as per P&ID. 4 MTO should be checked with part no. & also with PMS.
5 Isometric should be checked with P&ID to confirm that
there is no miss out of any component. Length,sizes & class of control valve or special component 6 should be checked in Isometrics with datasheet & G.A. 7 Start ,intermediate & end point connection detail should be shown along with its elevation at that point in Isometrics. Upstream and Downstream of flow meters or components 8 should be as per datasheet. For Eccentric reducers need to show (Flat side up) FSU OR 9 (Flat side up) FSD. 10 Floor crossing symbol with dimension shown be shown in Isometrics. Instruments standup piece should be match with hook up 11 or vendor requirement. Site weld & field weld symbol should be shown as per 12 requirement. 13 Inch dia. & Inch Meter should be shown in Isometrics. Spec change & scope change should be highlighted in 14 Isometrics. Support numbers should be shown in Isometrics & for 15 critical lines support numbers should be checked with stress report. 16 Fouling of lines should be checked with 3D Model. 17 Slope should be shown in Isometrics. 18 Legends of Symbols should be shown in Isometrics. High point vent & low point drain should be should in 19 Isometrics as per requirement. Proper notes need to be shown For eg. Either dimensions 20 are in mm or inch & dimension are from center line or outer line etc. 21 All dimension should be shown properly in Isometrics.