Professional Documents
Culture Documents
Date Activities: Graduate Trainee Monthly Report Summary Michael Mwonga ASAT31 OCTOBER 2019
Date Activities: Graduate Trainee Monthly Report Summary Michael Mwonga ASAT31 OCTOBER 2019
MICHAEL MWONGA
Environmental
Appendices
Appendix I: Daily Inspection Template
Appendix II: Drainage box 15+170 quantities
Table 1: Formwork quantities
FORM WORK COST
AREA
REQUIRE AREA ACTUAL
SECTION D COMPLETED C.P.U TOTAL COST COST
Blinding sides 18.19 18.19 2,108.40 38,351.80 38,351.80
Bottom slab sides 61.20 61.20 2,108.40 129,034.08 129,034.08
Walls(inside) 272.00 13.60 1,757.00 477,904.00 23,895.20
Walls(outside) 272.00 13.60 2,108.40 573,484.80 28,674.24
Headwall face & sides 3.76 0.00 1,757.00 6,606.32 0.00
Top Slab 197.20 0.00 2,108.40 415,776.48 0.00
Wing walls sides & Face 77.39 9.44 1,757.00 135,974.23 16,586.08
TOTAL 901.74 116.03 1,777,131.71 236,541.40
Formwork completion% 13.31%
Table 2: Earthworks
Quantities
EARTHWORKS COST
TOTAL COMPLETED ACTUAL
ITEM VOL VOL C.P.U TOTAL COST COST
Excavation 293.86 293.86 351.40 103,262.40 103,262.40
Rockfill 59.75 293.86 3,162.60 188,956.96 929,361.64
Backfill 0.00 0.00 1,405.60 0.00 0.00
Geotextile 0.00 0.00 175.70 0.00 0.00
TOTAL 292,219.37 1,032,624.04
Completion % 353.37%
Table 3: Concrete
Quantities
CONCRETE COST
VOLUME
REQUIRE VOL ACTUAL
SECTION D COMPLETED C.P.U TOTAL COST COST
Blinding C15 29.39 29.39 13,650.00 401,118.90 401,118.90
Top and Bottom slab 172.34 86.17 14,700.00 2,533,373.01 1,266,699.00
Walls 118.85 13.21 14,700.00 1,747,153.80 194,128.20
Wingwalls + Headwalls 13.99 0.00 14,700.00 205,711.74 0.00
Apron + Toe 14.37 14.37 14,700.00 211,297.80 211,297.80
TOTAL 348.95 143.14 5,098,655.25 2,073,243.90
Concrete completion% 40.66%
Fig. 3 Concreting & inspection of reinforcement