AMAIA Sucat Land Dev - COA Review and Comments

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

(1) COA set folder

Separate the COA for the Following:

• Civil Works (Per area and/or scope)


> Pavement
> Curbs & Gutter
> Side Walks
• MEPFS System
> Waterline System
> Fire Protection Line
> Sewer Line
> Drainage System

Attachment of the aforementioned per COA should have the following:

• Accomplished T&C results :


> Pre-functional Checklist
> Pre-functional Test
> Final Performance test & Commissioning
• Punchlist Close out forms
• A4 Size as-built plan with highlight of the area proposing to be accepted
• A3 Size complete set as-built plans
• Calibration Certificate (Water meter's and etc)
• Contractor's warranty to MDC
• Warranty certificate of MDC to SBU
• Operation Instruction & Maintenance (OIM)
• Contact information of Supplier
• Other documents:
> Listings and Certificate of installed underground valves (if applicable)
> Listings and Certificate of installed Fire hydrants (if applicable)
> Compact certificate

(2) COA front page (to be signed by)

• Replace the "Approved by" to "Noted by" on APMC Signatories


• Follow the below format and position of the following APMC signatories

Rodel M. Serion Michael F. Magpusao


Account Manager Chief Engineer
APMC TSG APMC Chief Operating Officer