> Pavement > Curbs & Gutter > Side Walks • MEPFS System > Waterline System > Fire Protection Line > Sewer Line > Drainage System
Attachment of the aforementioned per COA should have the following:
• Accomplished T&C results :
> Pre-functional Checklist > Pre-functional Test > Final Performance test & Commissioning • Punchlist Close out forms • A4 Size as-built plan with highlight of the area proposing to be accepted • A3 Size complete set as-built plans • Calibration Certificate (Water meter's and etc) • Contractor's warranty to MDC • Warranty certificate of MDC to SBU • Operation Instruction & Maintenance (OIM) • Contact information of Supplier • Other documents: > Listings and Certificate of installed underground valves (if applicable) > Listings and Certificate of installed Fire hydrants (if applicable) > Compact certificate
(2) COA front page (to be signed by)
• Replace the "Approved by" to "Noted by" on APMC Signatories
• Follow the below format and position of the following APMC signatories