Professional Documents
Culture Documents
G7M-1131-00 - OFF-LINE MAINTENANCE PROCEDURE FOR MORE THAN 1kV CIRCUIT BREAKERS
G7M-1131-00 - OFF-LINE MAINTENANCE PROCEDURE FOR MORE THAN 1kV CIRCUIT BREAKERS
ELECTRICAL G7M-1131-00
GLOBAL 19-MAR-2007
Page 1 of 9
i ii
OFF-LINE MAINTENANCE PROCEDURE FOR < 1kV CIRCUIT BREAKERS
iii
Equipment Type: E115A = Air Magnetic Circuit Breakers: < 1kV
Scope This procedure defines the requirements and methods for Acceptance
Testing (ACCTST) and off-line Predictive/ Preventive Maintenance
(OVHAUL) for < 1kV Circuit Breakers. The intent is to maximize the
reliability of this equipment at minimum cost through the combination of
testing equipment upon installation and employment of a regularly
scheduled off-line maintenance with the ultimate objective of eliminating all
unexpected failures.
PICK-UP POINT: RMS current level at which the circuit breaker tripping
function is indicated.
used for initial acceptance testing. Routine off-line PPM tests are not as
stringent and items marked as supplemental are only to be performed
when there is a suspected problem with the equipment. For example: If
breaker trips without a protective relay flag indication, a MEGGER
inspection may be used to troubleshoot the problem. For this example
case, an MOC is not required for performing the supplemental tests.
However, performing additional tests just for the sake of testing or just
because the tests have been traditionally done at a particular site is not
supported by the Electrical Discipline or Global Maintenance Leadership.
An approved MOC from the Switchgear TRL is required before such
supplemental testing is initiated.
Safety Safety is an integral part of all jobs. As such, all applicable Electrical Safe
Work Standards and Isolation of Energy Sources (IOES) criteria shall be
rigidly applied in the execution of the work described in this PPM
specification.
Equipment Needed The following table list the test equipment and other equipment needed to
perform this procedure.
P/PM Schedule The required frequency for P/PM inspections for < 1kV Circuit Breakers is
established via the Condition Based Electrical PPM web site.
Preparation Follow the steps below before starting the tests and inspections on the
equipment.
OVHAUL
Step Service Action P/PM ACCTST
offline
Visual and Follow the steps below to perform a visual and mechanical inspection of the equipment.
Mechanical
Inspection
blocks.
Electrical Tests Follow the steps below to perform electrical tests on the equipment.
Functional Tests Follow the steps below to perform functional tests on the equipment.
Calibration Tests Follow the steps below to perform protective device calibration tests
(overcurrent, undervoltage, etc. settings) on breakers equipped with these
devices.
Return to Operation Follow the steps below to return the equipment to operation.
i
19-MAR-2007; MOC 2007_04416; By: Paul Gabba; Supersedes Issue Date 08-DEC-
2004; Reviewed. Updates throughout as a result of the Plaquemine Poly A Arc
Flash Incident.
ii
18-AUG-2003, MOC2003.1100.110, By: Paul Gabba, Supercedes Issue Date 06-
MAY-2003, Complete rewrite for the Condition Based PPM program.
iii
08-DEC-2004, MOC 2004_02277, By: Paul Gabba, Supercedes Issue Date 18-AUG-
2003, Corrected Equipment Type
iv
08-DEC-2004, MOC 2004_02277, By: Paul Gabba, Supercedes Issue Date 18-AUG-
2003, Added STEPS 7 and 8 at FUNCTIONAL TEST.