Design Consideration For Tank Farm

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 5

Design Consideration for Tank Farm

Chapter IX
Design Consideration for Tank Farm

Learning Objectives

The tank farm area layout is important as a lot of risk is involved in the storage of different
flammable and hazardous fluids which are required to be stored in huge capacities. ‘Safety’
is involved in the storage and handling of these fluids which is governed by the statutory
body. This chapter will give detailed consideration to all aspects of the layout of the tank
farm.

Contents
9.1 Tank Foundations
9.2 Base Plate Laying
9.3 Base Plate Welding
9.4 Shell Erection
9.5 Vacuum Box Test and Radiography
9.6 Roof Structure and Roof Plate Erection
9.7 Tank Appurtenances
9.8 Tank Cleaning
9.9 Tank Testing
9.10 Storage of Petroleum Products
Summing Up
Self-assessment

9.1 Tank Foundations

Foundations made by others shall be checked for uniform slope and levels for
our acceptance. Reference of North and East markings or 00 orientation marking
on the foundation has to be furnished by the client.

Sump pit on the foundation must be given prior to the commence-ment of


the Bottom laying.

9.2 Base Plate Laying

The annular plates will be laid first and then the sketch plates and full plates
will be laid with sequences mentioned in the drawing; minimum lap for any
two plates will be 30mm. temporar y tack welding will be done during the
time of laying.

9.3 Base Plate Welding

The annular butt joints will be welded first. Subsequently every alternate short
seam will be fitted and welded and at the same time nearest short seams will
be freed from tack welds. The same procedure will be repeated for long seam
welding. Temporary erection cleats and jigs/fixtures will be used for laying
and avoiding distortion during the time of welding.

89/MITSDE
Layout Engineering

9.4 Shell Erection

After grinding off the weld reinforcement on the top the of annular joints where
the shell will rest and the vacuum box testing of this portion, erection of shell
will commence subsequent to marking the circle to tank inner radius on the
tank base.First shell course plates will be rested on the mark-ings by providing
small cleats on both sides of the shell plates on the tank base. For maintaining
the gap for the ver-tical joints, spacers will be inserted in between the two
plate edges. After tack welding the vertical joints, plumbing and gauging will
be done prior to the welding of vertical joints. Temporary strong backs will be
provided during the time of welding in order to check peaking of joints.

After completing the vertical welding from one side, the shell will be back
chipped before weld is deposited from the other side. Second shell course
erection will then be done, and the second shell plates will be rested on the
first shell course with the help of spacers and wedges. Minimum two numbers
of erection channels will be wedged per plate erected, with lower course of
plate, for stability and safety.

For the second course vertical joints, fitting and welding will be done as said
for the first course. After completing the ver-tical welding, horizontal joint
set up and plumbing will be done prior to welding the same. Sequence of
welding for the horizon-tal joints will be same as vertical welding.

For outside welding on the shell, welder’s trolley will be used and for inside,
scaffolding will be provided for erection and welding purpose.

In the same manner, subsequent shell courses will be erected and welded. To
safeguard erected tank plates, guy wire supports will be provided from plates
to the channels anchored in ground.

After welding the last horizontal joint, the curb angle will be fitted and welded.
Shell to bottom joint can be fitted before or after fitting the curb angle. After
welding the curb angle, final plumb check will be done in accordance with the
design code and also peaking and banding check for the shell joints will be
done. Identification marks for welder and weld joints shall be marked on the
tank by using paint or metallic marker simultaneously during fit up and welding.

9.5 Vacuum Box Test and Radiography

After all welding work on the tank base and shell vertical/horizontal joints,
shell to bottom and curb angle to shell joints are welded, the tank base butt/
lap joints will be vacuum box tested. Radiography of vertical/horizontal welds
will proceed as erection and welding work progresses.

9.6 Roof Structure and Roof Plate Erection

The roof structures will then be erected and welded. After inspection of the
same, the roof plates will be laid maintaining a minimum lap of 25mm . The
sequence of welding of short and long seams for the roof plates will be the
same as base plates. After all seams are welded, the roof peripheral joint with
the curb angle will be set up and welded

90/MITSDE
Design Consideration for Tank Farm

9.7 Tank Appurtenances

Installation and welding of tank fittings (on shell and root) and stairway will
then be taken up as per orientation given in the drawings. The compensating
pads given for openings shall be air tested for leakage as per design code.

9.8 Tank Cleaning

After all erection and welding work is over, the tank interior shall be cleaned
by removing and grinding off all tacks and other fixtures. The tank shell
openings shall then be blanked off preparatory to hydro-test.

9.9 Tank Testing

Prior to hydro-test, foundation levels will be taken by the customer with


reference to the benchmark. After inspection of the tank and getting approval
from the customer, water filling into the tank will commence. 24-hour inter val
shall be given after filling the water to ¼ full; ½ full and ¾ full and comparing
of foundation levels will be done at the above-mentioned intervals.

After filling the tank shell up to the top, the tank will be allowed to settle for
48 hours. Prior to draining the water, final levels will be taken. The roof test
will be done in accordance with the code prior to draining the water. During
the time of filling and draining water, all roof openings will be kept open to
avoid damage to the tank.

9.10 Storage of Petroleum Products

Why it so important?
General statutor y approval of plan and installation for any petroleum/chemical
plant.
1. Chief Controller of Explosive (CCOE)
2. Chief Inspector of Boiler
3. Chief Inspector of Factories.

CCOE is the enforcing agency for


A. Petroleum act 1934, petroleum rules 1976.
B. Gas cylinders rules 1981 & static and mobile pressure vessels (SMPV)
(Unfired) Rules 1981.

When license register form CCOE :


A. Under petroleum act : License register to storage/Transport petroleum
of :

Class A Flash PT. < 230C Storage cap > 30 Lit.


Expectation IC Engine > 100 Lit.

Class B 230C ≤ Flash Point < 65 0C Storage capacity > 2.5 M3


Or Individual storage > 1.0 M3

Class C 65 0C Flash Point < 93 0C Storage Capacity > 45 M3


If capacity > 5 M3 then prior
reporting to CCOE is adequate.

91/MITSDE
Layout Engineering

B. Under Gas Cylinder rules :

B1. 1. LPG 100 Kg at a time


2. Flammable but non toxic gas Number of cylinders > 15 or
Qty. 125 Kg.
3. Non Flammable and non Toxic > 50 cylinders
4. Toxic Gas > 5 cylinders
5. Acetylene gas > 15 Cylinders.

B 2. Under Compress

Compress Gas > 1.0 M3 water capacity


Definition of Compressed gas : Any permanent gas , liquefiable gas or gas
dissolved in liquid under pressure the gas mixture which in a closed pressure
vessel excurses process.

• 1.5 atm. g @ 15 0 c
• or > 2.0 atm g @ 50 0c
• or both

How license granted for storage of petroleum :

Following are required under petroleum act :


a) Letter indicating purpose of storage of petroleum product & nature of
business
b) Piping cum equipment layout plans to scale
c) Plot plan indicating premises to be licensed with boundary indicated red
and indicating area within 100M from edge of storage tank / unloading
station.
d) Fire protection system/hydrant.
e) Equipment specification
f) Scrutiny fee.

Above ‘b’ Points to be Indicated :


i) Distance between storage tank and storage tank to fencing.
ii) Dyked area and volume of each dyked area minimum Dyked HT. Class c=
1.o M.
iii) Tank fitted with vent pipe to Atm. fitted with non corrodible wire goal.
iv) Protected area is surrounded by walls.
v) Electrical insulation on cables and motor data sheet for pumps.

Process design of Petroleum storage facility


1) Kg/hr required and hrs/day.
2) Find availability data for storage capacity.
3) Total storage tank capacity to be finalised

As example
Furnace oil required for boiler firing
Boiler 100 TPH 10 Kg /cm2 g Sat.
Q 100 x 1000 x 600 Kcal/hr

Oil Required =

92/MITSDE
Design Consideration for Tank Farm

Say 15 days storage

15 × 24 × 6300
Cap= = 2520m 3
900
Provide total volume = 3000 m3

Say tank 1500 m3 each.


One for unloading, one for transfer.

4) Choose L/D — fix nt. Dia.

5) Unloading pumps

Each tanker 10 m3
= 17 tankers required / day.

8 hrs unloading time, say actual 4 hrs. ( 50% time for fixing, measuring )
Say 2 unloading stations as capacity 1 + 1
170m 3
So each capacity pump = ≅ 22m3 / nv
4hrs × 2 Nos.

Provide 2w + 1s 22m3 /nv ~ 30mcc pumps.

6) Transfer pumps :
24 × 6300
≅ 170m3 / day required
pumps , head based on final user.
900

Summing Up

Careful handling and storage of petroleum products and hazardous fluids is


very important. As the rules of the statutory body are very stringent, these
considerations have to be taken into account and are explained. The piping
engineer will get guidelines to prepare the layout of the tank farm.

Self-assessment

1. What is CCOE?

2. What is Flash Point of class A petroleum product?

3. What is storage capacity?

4. State three class of petroleum product?

5. State the act and rules in force by CCOE?


1…………….. 2 ……………..

6. What is SMPV?

93/MITSDE

You might also like