3) M&E Works:
Item Description Action by Block Status 2-8/5 9-15/5 16-22/5 20-26/6 Remarks
a) Balance of Works
1 Meeting room mic system FRM/AE Pentadbiran all material delivered
Installation not started yet
2 CO2 System (Chiller/MSB) AE/FRM Hospitaliti No Progress FRM will bare the cost for installation
of the unit. Waiting their proposal
5 MDF & PABX System LRSB/AE HEP Waiting for Line Setting
11 ELV system(PA system) LRSB/AE HEP already installed, but wrong Location
14 Others matters
a. Testing for sewerage pipeline. LRSB/AE External - Not started yet
b) Additional Works
3 Meter panel at car porch FRM/AE Quarters C Received FRM attach the TNB circular
to follow (will not be adjusted)
4 Telephone panel at car porch FRM/AE Quarters C Received receive the proposal on 13/5/10
5 Fix study lamp FRM/AE AP & AL Ledang Raya will talk to JKR (no progress) K.I.V
3) Defects List
1 Expose sanitary, cool & hot water JSB BH JSB to make box-up to conceal the
pipes near partition areas. services.
- Pilings - -
- Buildings - -
2
- Drainage - -
- Sewerage AE General
- Landscape NA General
Item Description Action by Block Status 2-8/5 9-15/5 16-22/5 20-26/6 Remarks
- Air cond FRM/AE Related
3
b) road crossing LRSB/JSB Walkway Material arrive on 10/7/10 Pn. Cheong verbally agreed
2 Roof cover at living sliding door NA/JSB Quarters C KIV until official comment from JKR
5 Shrubs at car porch NA/JSB HEP in progress target complete 10/7/10 Pn. Cheong verbally agreed
6 Bus parking cover LRSB/NA/ Cover bus in progress target complete 10/7/10 Pn. Cheong verbally agreed
JSB
7 Covering for meter panel NA/JSB Quarters D pending JSB to proceed the works
LRSB submit to JKR CKBA
8 Doors to be change from sliding JSB BH LRSB & NA decide to KIV until
type to open type due to swithes receive comment from JKR
locations (8 rooms ).
2) C&S Works:
Item Description Action by Block Status 2-8/5 9-15/5 16-22/5 23-29/5 30/5-5/6 6-12/6 13-19/6 20-26/6 Remarks
a) Balance of Works
1 Bus layby & bus stop LRSB/JSB External MPK approval received on 6/7/10, bus
stop and rubber wall completed pending
bus layby only.
3) M&E Works:
Item Description Action by Block Status 2-8/5 9-15/5 16-22/5 23-29/5 30/5-5/6 6-12/6 13-19/6 20-26/6 Remarks
a) Balance of Works
1 Meeting room mic system FRM/AE Pentadbiran FRM submit mic calculation by this all material delivered
Wednesday. Installation not started yet
3 Power point & water tap FRM/AE Tpt Cuci Only receive for power point tap (water tap not receive yet)
Kenderaan requires external water reticulation dwg Pending until to date
11 ELV system(PA system) LRSB/AE HEP - fixings not start yet Equipment ready, but the location
is wrong must be at Bilik Kawalan
12 Installation of cylinder gas for LRSB/AE Hospitaliti 100% pipe installation
LPG System D. Makan - Cylinder gas not delivered yet
Cafeteria - LPG gas Pipe testing completed - LPG gas Pipe testing completed
13 CCTV & ELV system LRSB/AE Hospitaliti 100% Installation 100% Completed
14 Others matters
a. Testing for sewerage pipeline. LRSB/AE External - Not started yet
c. Testing for the Suction tank LRSB/AE External Started on 16/06/2010 the test is not satisfied by C.M
& Elevated water tanks and must re-do again.
6
b) Additional Works
1 Switch board at living FRM/AE Quarters C Received receive the proposal on 13/5/10
No progress work
2 Lightning Arrestor at 1st floor FRM/AE/ Quarters C Received receive the proposal on 13/5/10
JSB No progress work
3 Meter panel at car porch FRM/AE Quarters C Received FRM attach the TNB circular
to follow (will not be adjusted)
4 Telephone panel at car porch FRM/AE Quarters C Received receive the proposal on 13/5/10
5 Fix study lamp FRM/AE AP & AL Ledang Raya will talk to JKR (no progress) K.I.V
7 Additional Air-cond ducting FRM/AE Pentadbiran FRM to resubmit proposal Due on 22/06/10
8 Lighting at the store FRM/AE Quarters C completed receive the proposal on 13/5/10
9 Additional lighting at MSB and FRM/AE HEP completed receive the proposal on 13/5/10
Dewan Serbaguna corridor.
3) Defects List
1 Expose sanitary, cool & hot water JSB BH JSB to make box-up to conceal the
pipes near partition areas. services.
4) As-Built Drawing
Item Description Action by Block Status 2-8/5 9-15/5 16-22/5 23-29/5 30/5-5/6 6-12/6 13-19/6 20-26/6 Remarks
1 C&S As-built Drawings:
- Earth work - - Completed
- Pilings - - Completed
- Buildings - - Completed
- Drainage - - Completed
7
Item Description Action by Block Status 2-8/5 9-15/5 16-22/5 23-29/5 30/5-5/6 6-12/6 13-19/6 20-26/6 Remarks
- Air cond FRM/AE Related Completed
- Operation manuals & AE Related Only receive the list From Asia Euro
warranty certificates. 12th May 10
5) CF & Authority
Item Description Action by Block Status 2-8/5 9-15/5 16-22/5 23-29/5 30/5-5/6 6-12/6 13-19/6 20-26/6 Remarks
1 Bomba
- Borang C1, C2 & C3 - - Completed. NA to check whether
the bomba inspection need permanent
electric supply or not.
- Hydrants - - Completed
- Wet chemical Work not completed
- Fire Extenguisher Work not completed
5 Telekom
Item Description 2-8/5 9-15/5 16-22/5 23-29/5 30/5-5/6 6-12/6 13-19/6 20-26/6 Remarks
1 Balance Of Works
-Architect Works
-C & S Works
-M & E Works
2 Additional Works
-Architect Works
-C & S Works
-M & E Works
3 Defect Works
-Architect Works
-C & S Works
-M & E Works
4 As Built Drawing
-Architect Works
-C & S Works
-M & E Works
Item Description 2-8/5 9-15/5 16-22/5 23-29/5 30/5-5/6 6-12/6 13-19/6 20-26/6 Remarks
5 Testing & Commisioning
a) C & S
-Tank leakage test
-Sewerage pipeline test
-STP system test
b) Mechanical Works
-Air-cond system test
- Fire fighting system
- LPG gas system test
c) Electrical Works
-Lighting test
-CCTV test
-ELV test
-Sound system test
6 CF Inspection
-JPS ◄▬▬▬▬▬► Target submission by 12/5/10
-Perancang Terengganu ◄▬▬▬▬▬► Target submission by 12/5/10
-Alam Sekitar ◄▬▬▬▬▬► Target submission by 12/5/10
-Kesihatan/Keselamatan ◄▬▬▬▬▬► Target submission by 12/5/10
-IWK ◄▬▬▬▬▬▬▬▬▬► Target submission by 19/5/10
-SATU ◄▬▬▬▬▬▬▬▬▬► Target submission by 25/5/10
-TNB ◄▬▬▬▬▬▬▬▬▬► Target submission by 25/5/10
-Telekom ◄▬▬▬▬▬▬▬▬▬► Target submission by 25/5/10
-Bomba ◄▬▬▬▬▬▬▬▬▬► Target submission by 10/6/10
-JKR Kemaman ◄▬▬▬▬▬► Target submission by 15/6/10
-MPK ◄▬▬►Target submission by 23/6/10