Name : ……………………………………………………………

E.C. No. : ……………………………………………………………

QUESTION PAPER - Asstt Panel Offier – CPP – Electrical

Maximum Marks: 50 Time Allowed: 1 - Hour

Note: There are 50 Questions. Each question has ONE correct answer. One mark for
Each question. Please ( ) mark in the question paper for marking the correct answer
1. What is “Black Start” facility in case of GT ?

2. All 33 kV breakers at CPP can be opened from local and remote both when it is
selected to :-

a. Remote mode
b. Local mode
c. Off mode
b. Any mode

3. Important point to be kept in mind while shutdown of grid transformer is,

a. Islanding of 33 kV board
b. Load shedding
c. Adjustment of generation / load
d. All of above

4. Before charging a out going 33 kV feeder on 33 kV board at either of MRS at


CPP, clearance is to be taken from
a. From downstream side sub station where this feeder is
feeding the power
b. From Plant manager
c. From SE (steam generation & distribution)
d. None of these

5. Before actually 33 kV cable Tie is closed at CPP 33 kV board, it’s all required
parameters for synchronizing are checked by
a. A check-synchronizing relay mounted on cable tie breaker
automatically
b. The operating personnel through 7SJ600 relay mounted on
cable tiebreaker
c. SE (power generation & distribution) on EDMS
d. None of these

6. The principle of 220 V battery charger is to :-


a. Convert AC to DC
b. Convert HT to LT
c. Convert DC to AC
d. None of these three

De-Engg-2004-APO-CPP_Elect Confidential 1
7 Incase of failure of UPS-B at CPP UPS unit, all load will be transferred to,
a. UPS-A
b. Static bypass UPS-A
c. Static bypass UPS-B
d. Manual Bypass

8. In DC system battery bank is meant for :-


a. Feeding battery charger
b. Feeding load continuously
c. Feeding load whenever AC supply fails
d. Feeding load & battery charger both

9. On start command in case of GT # 4 at CPP, its diesel engine starting drive gets
DC power from :-
a. GT # 4 125 V service charger
b. GT # 4 rectifier unit
c. GT # 4 MCC
d. None of these

10. All GT and STG MCC at CPP are having following facility,
a. Manual paralleling
b. Auto change over
c. Both a and b
d. None

11. Under which condition FCB of GT-1 and GT-4 will not open at CPP ?
a. Generator differential operation
b. Over fluxing operation
c. Reverse power operation
d. None

12. GT-1 MCC control supply is,


a. 220 V DC
b. 125V DC
c. 230 V AC
d. 115V AC

13. Under normal operation of GT (M/C on load), what is the current drawn by its
AOP?
a. 60 Amp
b. 45 Amp
c. 30 Amp
d. Not applicable

14. The class of winding insulation of generators in CPP is :-


a. F
b. A
c. Y
d. E
15. Transformer core is laminated to reduce
a. Hysteresis loss
b. Eddy current loss
c. Copper loss
d. All of above
16. What is the current rating of LT side of GRID transformer at CPP ?
a. 800 Amp
b. 789 Amp
c. 289 Amp
d. 886 Amp

De-Engg-2004-APO-CPP_Elect Confidential 2
17. Reduction in oil level of transformer will give alarm through,
a. MOGL
b. OTI
c. WTI
d. Buchholz
18. Balloons in transformer conservator are provided for,
a. Saving transformer oil
b. isolating atmospheric air from oil
c. Pressure control
d. none of above

19. What is the function of Lightening Arrester ?

20. Bus current transformers in case of CPP 33 kV system is installed in:-


a. Bus coupler panel
b. In each incomer panel
c. In bus PT panel
d. None of these

21. Main earthing connection bar for CPP 33 kV boards :-


a. Entering through cable box
b. Entering through breaker panel
c. Externally going to the top of board
d. None of these

22. What is the normal operating air pressure of switch yard breakers & what is the cut in pressure of it’s
air compressor?

23. What is the fault level at CPP 132 kV Switch yard bus?
a. 25 kA
b. 40 kA
c. 50 kA
d. 60 kA

24. For connecting two 33 kV boards directly through cables, total number of cable Ties in CPP are: -
a. One
b. Two
c. Three
d. Four

De-Engg-2004-APO-CPP_Elect Confidential 3
25. Earth switch and isolators in CPP 132 kV switchyard are provided with,
a. Electrical Interlock
b. Mechanical Interlock
c. Soft interlock
d. all of above

26. In CPP we have following motor starters,


a. DOL
b. Star-delta
c. Auto transformer
d. All of above

27 All CPP HT motor feeders are rated for,


a 415 V
b 3300 V
c 6600 V
d 11000 V

28 Auto change over time of PCC at CPP is,


a. Greater than MCC
b. Less than MCC
c. Less than 6.6 kV bus coupler
d. Same as MCC

29. How many trip coils is used in CPP switchyard 132 kV circuit breaker?
a. One
b. Two
c. Three
d. Four

30. What are the protections provided for 33 kV feeder/incomer?

31. In case of earth fault on Bus bar, which protection will operate?
a. Generator E/F
b. Feeder E/F
c. Bus-bar differential Vend
d. none of the above

32. List out different protections provided in Generators?

33. Distance protection for transmission line connecting Reliance at CPP is thorugh :
De-Engg-2004-APO-CPP_Elect Confidential 4
a. RADHD
b. REL 100
c. RADSS
d. RAICA

34 What is full form of ELDMS?

35. Starting of each GT starting drive (HT drive) in CPP is possible from :
a. DCS
b. LCS place nearby respective drive
c. EDMS
d. None of above

36. Largest rated LT motor in CPP is :


a. CCW pump motor
b. LP process pump motor
c. NP Off-base fuel pump
d. Augment air fan of HRSG

37. Following motors does at CPP not have speed-control facility,


a. HRSG HP dosing pump
b. Aux boiler dosing pump
c. GT Hi-tech dosing pump
d. none of above

38. Which system among following at CPP while in operation do not need aux oil pump running? (GT,
STG, HP process pump, HHP BFW pump, TFD & IAC).

39. Write down the actions to be taken on GT-1 tripping?

40. Bus coupler closure at downstream plants are inhibited in case of Load shedding operation through
EDMS from CPP :
a. To help downstream for locating fault
1. To help CPP end for locating fault
2. To help EDMS panel engineer to note down affetced loads
3. None of above

41. What is the basic law which governs CPP 33 kV Bus differential protection?
De-Engg-2004-APO-CPP_Elect Confidential 5
42. Power load shedding priority on CPP EDMS are :
a. 5
b. 10
c. 12
d. none of above

43. How many different types of control supplies are used in CPP MCCs? List out all with location?

44. While synchronizing a grid transformer on 33 kV side locally (i.e. from 33 kV


breaker side), voltage and frequency of both sources are matched by changing: -
a. Voltage & frequency of grid transformer (to be synchronized)
from
it’s 33 kV breaker
b. Voltage & frequency of grid transformer (to be synchronized)
from
it’s 132 kV breaker
c. Voltage & frequency of machine in operation on that 33 kV
board
d. None of these

45. Both EDG sets will start in auto in case of total power failure by sensing :-
a. U/V ON 6.6 kV bus of S/S 961-10
b. U/V ON 6.6 kV bus of MRS-1
c. U/V ON 6.6 kV bus of MRS-2
d. U/V ON 33 kV bus of MRS-1

46. What is the rating of UPS installed in CPP CCR?


a. 60 KVA
b. 100 KVA
c. 50 KVA
d. 40 KVA

47. 125 V battery charger for GT # 1,2,3,5 & 8 has :-


a. One float & one boost charger
b. One float & two boost chargers
c. Two float & one boost charger
d. Two float & two boost chargers

De-Engg-2004-APO-CPP_Elect Confidential 6
48. 220 V DC system is for the control of :-
a. Steam Turbine controller (Turbolog)
b. Gas Turbine controller (Mk-V)
c. DCS system
d. HT / LT panels & some MCCs

49. For CPP UPS : Both UPS-B and Bypass mains are supplied from,
a. Miscellaneous MCC
b. Black start GT MCCs
c. Directly from PCC
d. Emergency LT system

50. Phase sequence of incoming AC source is important in case of 125 V battery


charger’ this statement is :-
a. True
b. False