CONSTRUCTION OF BUILDING INFRASTRUCTURE UNDER PESHWAR SUSTAIBALE BUS DEPOT RAPID TRANSIT CORRIDOR PROJECT

LOT 2: CHAMKANI BUS DEPOT, PARK & RIDE, TRANS PESHWAR OFFICE AND BRT CONTROL CENTER
DAILY PROGRESS REPORT
Date: 26 September 2018 Weather: Sunny 31◦ᴄ ҉ DPR Ref No: 04

TOTAL Executed up to Executed up to Executed up to Executed up to


Sr. No DESCRIPTION UNIT QTY June 31st 2018 July 30th 2018 Aug 30th 2018 Sep 30th 2018
% Achieved by 30th Sep 2018

1 BUS PARKING AREA


Total Area of Depot M2 55,384.00
1 Excavation M3 42,054.91 35,200.00 37,517.00 39,982.18 39,982.18 95.07%
2 Gravel Material M3 31,386.73 22,250.00 24,093.00 28,812.80 28,812.80 91.80%
3 Sub Base M3 15,611.22 5,400.00 11,035.00 12,368.85 13,617.07 87.23%
4 Agreegate Base M3 15,611.22 4,200.00 6,621.00 10,489.00 10,949.92 70.14%
5 Lean Concrete M3 5,206.34 291.00 1,325.00 1,954.00 2,895.68 55.62%
6 Rigid Pavement M3 15,619.02 - 24.00 1,448.00 5,410.00 34.64%

2 BOUNDARY WALL
Total Boundary Wall Length M 1,128.35
1 Excavation M3 680.30 486.00 615.00 666.00 666.00 97.90%
2 Gravel Material M3 184.45 143.65 175.00 180.00 180.00 97.59%
3 Common Filling M3 418.26 150.00 300.00 350.00 406.00 97.07%
4 PCC Footing M3 185.42 81.01 152.78 160.00 180.00 97.08%
5 RCC in Foundation, Class- A1 M3 99.76 60.66 98.53 99.76 99.76 100.00%
6 RCC in Super Structure, Class- A1 M3 292.32 92.00 149.23 167.23 280.00 95.79%
7 Reinforcement Ton 51.41 23.03 43.37 46.36 50.00 97.26%
8 Brick Work M3 594.89 43.00 470.00 485.00 579.00 97.33%

Page 1 of 51
CONSTRUCTION OF BUILDING INFRASTRUCTURE UNDER PESHWAR SUSTAIBALE BUS DEPOT RAPID TRANSIT CORRIDOR PROJECT
LOT 2: CHAMKANI BUS DEPOT, PARK & RIDE, TRANS PESHWAR OFFICE AND BRT CONTROL CENTER
DAILY PROGRESS REPORT
Date: 26 September 2018 Weather: Sunny 31◦ᴄ ҉ DPR Ref No: 04

TOTAL Executed up to Executed up to Executed up to Executed up to


Sr. No DESCRIPTION UNIT QTY June 31st 2018 July 30th 2018 Aug 30th 2018 Sep 30th 2018
% Achieved by 30th Sep 2018

9 Pointing M2 2,764.77 1,955.00 1,955.32 2,604.06 94.19%


10 Plastering M2 2,764.77 162.48 1,717.17 62.11%

3 WORKSHOP
Total Covered Area M2 4,369.15

1 Excavation M3 4,813.63 4,813.63 1,857.89 4,813.65 4,813.63 100.00%

2 Gravel Material M3 1,266.75 1,258.20 1,258.20 1,258.20 1,266.75 100.00%

3 Anti Termite M2 1,800.00 1,800.00 1,800.00 1,814.92 100.83%

4 PCC Footing M3 142.00 142.00 137.64 96.93%

5 RCC In Foundation M3 1,356.96 1,350.00 1,350.00 99.49%

6 RCC in Super Structure M3 1,837.55 7.02 0.38%


7 Reinforcement Ton 682.11 208.88 30.62%
8 Bitumen paint (Coverage 7 Kg / 10 Sqm) M2 3,402.10 2,374.85 69.81%
9 Sand Filling M3 3,796.13 1,980.19 52.16%
10 Brick masonary Ratio 1:4 (225mm thick) M3 874.38 0.00%

Page 2 of 51
CONSTRUCTION OF BUILDING INFRASTRUCTURE UNDER PESHWAR SUSTAIBALE BUS DEPOT RAPID TRANSIT CORRIDOR PROJECT
LOT 2: CHAMKANI BUS DEPOT, PARK & RIDE, TRANS PESHWAR OFFICE AND BRT CONTROL CENTER
DAILY PROGRESS REPORT
Date: 26 September 2018 Weather: Sunny 31◦ᴄ ҉ DPR Ref No: 04

TOTAL Executed up to Executed up to Executed up to Executed up to


Sr. No DESCRIPTION UNIT QTY June 31st 2018 July 30th 2018 Aug 30th 2018 Sep 30th 2018
% Achieved by 30th Sep 2018

4 PARK & RIDE


Total Covered Area M2 15,547.18
1 Excavation M3 15,302.72 3,150.00 3,150.00 3,150.00 20.58%

5 OFFICE BUILDING
Total Covered Area M2 5,210.43

1 Excavation M3 5,982.54 3,857.08 3,857.08 5,982.54 100.00%

2 Gravel Material M3 1,227.19 1,215.00 1,227.19 100.00%

3 PCC Footing M3 193.94 143.30 193.94 100.00%

4 RCC in Foundation M3 3,393.98 1,451.49 42.77%

5 RCC in Super Structure M3 1,812.83 0.00%


RCC in Super Structure Auditorium & Shear
6 M3 89.22 0.00%
walls
7 Reinforcement Ton 795.29 161.76 20.34%

8 Brick masonary Ratio 1:4 (225mm thick) M3 1,127.25 0.00%


9 Bitumen paint (Coverage 7 Kg / 10 Sqm) M2 2,387.00 0.00%

Page 3 of 51
CONSTRUCTION OF BUILDING INFRASTRUCTURE UNDER PESHWAR SUSTAIBALE BUS DEPOT RAPID TRANSIT CORRIDOR PROJECT
LOT 2: CHAMKANI BUS DEPOT, PARK & RIDE, TRANS PESHWAR OFFICE AND BRT CONTROL CENTER
DAILY PROGRESS REPORT
Date: 26 September 2018 Weather: Sunny 31◦ᴄ ҉ DPR Ref No: 04

TOTAL Executed up to Executed up to Executed up to Executed up to


Sr. No DESCRIPTION UNIT QTY June 31st 2018 July 30th 2018 Aug 30th 2018 Sep 30th 2018
% Achieved by 30th Sep 2018

6 DRAIN NO. 07
Total Length M 625.00

1 Excavation M3 734.28 173.00 200.00 734.28 100.00%

2 Gravel Material M3 321.07 294.00 294.00 91.57%

3 Lean Concrete M3 103.84 92.50 92.50 89.08%

4 RCC of Drain Bed, Walls & Slab M3 632.00 316.00 380.00 60.13%
5 Reinforcement Ton 60.77 36.00 37.28 61.35%
6 Water Stopper M 1,300.00 90.00 1,052.68 80.98%
7 Rest Area's (Male & Female)
Total Covered Area M2 1,230.00

1 Excavation M3 1,644.17 1,644.17 1,644.17 100.00%

2 Gravel Material M3 319.14 328.83 319.14 100.00%

3 PCC Footing M3 46.00 31.57 31.57 68.62%

4 RCC in Foundation M3 452.25 226.13 298.23 65.94%

5 RCC in Super Structure M3 585.94 4.25 0.73%


6 Reinforcement Ton 166.11 37.69 22.69%
8 Bitumen paint (Coverage 7 Kg / 10 Sqm) M2 558.48 272.40 48.78%
9 Sand Filling M3 1,245.89 1,245.89 100.00%

Contractor: Consultant:
ANHUI-CALSON JV MM PAKISTAN.

Page 4 of 51
CONSTRUCTION OF BUILDING INFRASTRUCTURE UNDER PESHWAR SUSTAIBALE BUS DEPOT RAPID TRANSIT CORRIDOR PROJECT
LOT 2: CHAMKANI BUS DEPOT, PARK & RIDE, TRANS PESHWAR OFFICE AND BRT CONTROL CENTER
DAILY PROGRESS REPORT
Date: January 2019 Weather: Sunny 31◦ᴄ ҉ DPR Ref No: 04

TOTAL Executed by
Sr. No DESCRIPTION UNIT QTY % Achieved
the end of Dec Executed In
2018 Jan 2019 Total Executed

1 BUS PARKING AREA


1 Excavation M3 42,054.91 42,055.00 - 42,055.00 100.00%
2 Gravel Material M3 31,386.73 30,502.00 298.00 30,800.00 98.13%
3 Sub Base M3 15,611.22 14,668.00 232.00 14,900.00 95.44%
4 Agreegate Base M3 15,611.22 14,266.00 634.00 14,900.00 95.44%
5 Lean Concrete M3 5,206.34 3,934.50 456.00 4,390.50 84.33%
6 Rigid Pavement M3 15,619.02 10,708.75 167.25 10,876.00 69.63%
7 Saw cut of Contraction Joint RM 10,406.00 3,201.00 1,151.00 4,352.00 41.82%
8 Saw cut of Construction Joint RM 14,233.00 1,958.00 6,366.00 8,324.00 58.48%
9 Filling of Contraction Joint RM 10,406.00 3,947.00 405.00 4,352.00 41.82%
10 Filling of Construction Joint RM 14,233.00 2,537.00 5,787.00 8,324.00 58.48%
11 Expansion Joint Treatment RM 1,180.00 - 726.00 726.00 61.53%

2 BOUNDARY WALL
Total Boundary Wall Length M 1,128.35
1 Excavation M3 680.30 666 - 680.30 100.00%
2 Gravel Material M3 184.45 180 - 184.45 100.00%
3 Common Filling M3 418.26 414 - 418.26 100.00%
4 PCC Footing M3 185.42 182 - 185.42 100.00%
5 RCC in Foundation, Class- A1 M3 99.76 99.76 - 99.76 100.00%
6 RCC in Super Structure, Class- A1 M3 292.32 285 - 292.3155 100.00%
7 Reinforcement Ton 51.41 50.5 - 51.41 100.00%
8 Brick Work M3 594.89 580.4 1.89 593.00 99.68%

Page 5 of 51
CONSTRUCTION OF BUILDING INFRASTRUCTURE UNDER PESHWAR SUSTAIBALE BUS DEPOT RAPID TRANSIT CORRIDOR PROJECT
LOT 2: CHAMKANI BUS DEPOT, PARK & RIDE, TRANS PESHWAR OFFICE AND BRT CONTROL CENTER
DAILY PROGRESS REPORT
Date: January 2019 Weather: Sunny 31◦ᴄ ҉ DPR Ref No: 04

TOTAL Executed by
Sr. No DESCRIPTION UNIT QTY % Achieved
the end of Dec Executed In
2018 Jan 2019 Total Executed
9 Pointing M2 2,764.77 2690.4 64.77 2,700.00 97.66%
10 Plastering M2 2,764.77 2552.42 64.77 2,700.00 97.66%

3 WORKSHOP
Total Covered Area M2 4,369.15

1 Excavation M3 4,813.63 100.00%

2 Gravel Material M3 1,266.75 100.00%

3 Anti Termite M2 1,800.00 100.83%

4 PCC Footing M3 142.00 96.93%

5 RCC In Foundation M3 1,356.96 99.49%

6 RCC in Super Structure M3 1,837.55 0.38%


7 Reinforcement Ton 682.11 30.62%
8 Bitumen paint (Coverage 7 Kg / 10 Sqm) M2 3,402.10 69.81%
9 Sand Filling M3 3,796.13 52.16%
10 Brick masonary Ratio 1:4 (225mm thick) M3 874.38 0.00%

Page 6 of 51
CONSTRUCTION OF BUILDING INFRASTRUCTURE UNDER PESHWAR SUSTAIBALE BUS DEPOT RAPID TRANSIT CORRIDOR PROJECT
LOT 2: CHAMKANI BUS DEPOT, PARK & RIDE, TRANS PESHWAR OFFICE AND BRT CONTROL CENTER
DAILY PROGRESS REPORT
Date: January 2019 Weather: Sunny 31◦ᴄ ҉ DPR Ref No: 04

TOTAL Executed by
Sr. No DESCRIPTION UNIT QTY % Achieved
the end of Dec Executed In
2018 Jan 2019 Total Executed

4 PARK & RIDE


Total Covered Area M2 15,547.18
1 Excavation M3 16,628.74 3,150 13,478.74 16,628.74 100.00%
Anti Termite M2 3,681.79 3,681.79 3,681.79 100.00%
Granular Material M3 2,472.33 2,472.33 2,472.33 100.00%
Lean Concrete M3 300.00 288.00 288.00 96.00%
Reinforcement Concrete In Foundation M3 3,000.00 2,200.00 2,200.00 73.33%
Reinforcement Steel Tonne 2,200.00 1,000.00 1,000.00 45.45%

5 OFFICE BUILDING
Total Covered Area M2 5,210.43

1 Excavation M3 5,982.54 100.00%

2 Gravel Material M3 1,227.19 100.00%

3 PCC Footing M3 193.94 100.00%

4 RCC in Foundation M3 3,393.98 42.77%

5 RCC in Super Structure M3 1,812.83 0.00%

6 RCC in Super Structure Auditorium & Shear M3 89.22 0.00%


walls
7 Reinforcement Ton 795.29 20.34%

8 Brick masonary Ratio 1:4 (225mm thick) M3 1,127.25 0.00%


9 Bitumen paint (Coverage 7 Kg / 10 Sqm) M2 2,387.00 0.00%

Page 7 of 51
CONSTRUCTION OF BUILDING INFRASTRUCTURE UNDER PESHWAR SUSTAIBALE BUS DEPOT RAPID TRANSIT CORRIDOR PROJECT
LOT 2: CHAMKANI BUS DEPOT, PARK & RIDE, TRANS PESHWAR OFFICE AND BRT CONTROL CENTER
DAILY PROGRESS REPORT
Date: January 2019 Weather: Sunny 31◦ᴄ ҉ DPR Ref No: 04

TOTAL Executed by
Sr. No DESCRIPTION UNIT QTY % Achieved
the end of Dec Executed In
2018 Jan 2019 Total Executed
6 DRAIN NO. 07
Total Length M 625.00

1 Excavation M3 734.28 100.00%

2 Gravel Material M3 321.07 91.57%

3 Lean Concrete M3 103.84 89.08%

4 RCC of Drain Bed, Walls & Slab M3 632.00 60.13%


5 Reinforcement Ton 60.77 61.35%
6 Water Stopper M 1,300.00 80.98%
6 Cable Trench
Total Length M

Excavation CM 5550.43 3150 2,350.00 5,500.00 99.09%

Gravel Material CM 630.22 620 - 620 98.38%

PCC Footing CM 272.43 234 - 234 85.89%

RCC of bed, Walls & Slab CM 1943.17 1386 32.00 1,418.00 72.97%

Reinforcement Ton 540 228 254.00 482.00 89.26%

Sand Filling CM 2200 376 1,325.63 1,701.63 77.35%

PVC Class D 150mm Dia Ducting RM 2555.01 490 560.00 1,050.00 41.10%

PVC Class D 100mm Dia Ducting RM 4304.84 392 588.00 980.00 22.77%

7 Rest Area's (Male & Female)


Total Covered Area M2 1,230.00

1 Excavation M3 1,644.17 100.00%

Page 8 of 51
CONSTRUCTION OF BUILDING INFRASTRUCTURE UNDER PESHWAR SUSTAIBALE BUS DEPOT RAPID TRANSIT CORRIDOR PROJECT
LOT 2: CHAMKANI BUS DEPOT, PARK & RIDE, TRANS PESHWAR OFFICE AND BRT CONTROL CENTER
DAILY PROGRESS REPORT
Date: January 2019 Weather: Sunny 31◦ᴄ ҉ DPR Ref No: 04

TOTAL Executed by
Sr. No DESCRIPTION UNIT QTY % Achieved
the end of Dec Executed In
2018 Jan 2019 Total Executed
2 Gravel Material M3 319.14 100.00%

3 PCC Footing M3 46.00 68.62%

4 RCC in Foundation M3 452.25 65.94%

5 RCC in Super Structure M3 585.94 0.73%


6 Reinforcement Ton 166.11 22.69%
8 Bitumen paint (Coverage 7 Kg / 10 Sqm) M2 558.48 48.78%
9 Sand Filling M3 1,245.89 100.00%

Contractor: Consultant:
ANHUI-CALSON JV MM PAKISTAN.

Page 9 of 51
CONSTRUCTION OF BUILDING INFRASTRUCTURE UNDER PESHWAR SUSTAIBALE BUS DEPOT RAPID TRANSIT CORRIDOR PROJECT
LOT 2: CHAMKANI BUS DEPOT, PARK & RIDE, TRANS PESHWAR OFFICE AND BRT CONTROL CENTER
DAILY PROGRESS REPORT
Date: Feb 2019 Weather: Sunny 31◦ᴄ ҉ DPR Ref No: 04

TOTAL Executed by
Sr. No DESCRIPTION UNIT QTY % Achieved
the end of Dec Executed In Executed In Executed In
2018 Jan 2019 Feb 2019 March 2019 Total Executed

1 BUS PARKING AREA


1 Excavation M3 42,054.91 42,055.00 - - - 42,055.00 100.00%
2 Gravel Material M3 31,386.73 30,502.00 298.00 260.00 300.00 31,060.00 98.96%
3 Sub Base M3 15,611.22 14,668.00 232.00 400.00 270.00 15,300.00 98.01%
4 Agreegate Base M3 15,611.22 14,266.00 634.00 400.00 260.00 15,300.00 98.01%
5 Lean Concrete M3 5,206.34 3,934.50 456.00 100.00 300.00 4,490.50 86.25%
6 Rigid Pavement M3 15,619.02 10,708.75 167.25 1,000.00 1,200.00 11,876.00 76.04%
7 Saw cut of Contraction Joint RM 10,406.00 3,201.00 1,151.00 600.00 500.00 4,952.00 47.59%
8 Saw cut of Construction Joint RM 14,233.00 1,958.00 6,366.00 500.00 500.00 8,824.00 62.00%
9 Filling of Contraction Joint RM 10,406.00 3,947.00 405.00 450.00 400.00 4,802.00 46.15%
10 Filling of Construction Joint RM 14,233.00 2,537.00 5,787.00 400.00 450.00 8,724.00 61.29%
11 Expansion Joint Treatment RM 1,180.00 - 726.00 100.00 100.00 826.00 70.00%

2 BOUNDARY WALL (Revised)


Total Boundary Wall Length M 1,898.35
1 Excavation M3 1,144.54 680.30 - 57.23 80.12 737.53 64.44%
2 Gravel Material M3 310.31 184.45 - 15.52 21.72 199.97 64.44%
3 Common Filling M3 703.68 418.26 - 35.18 49.26 453.44 64.44%
4 PCC Footing M3 311.95 185.42 - 15.60 21.84 201.02 64.44%
5 RCC in Foundation, Class- A1 M3 167.84 99.76 - 8.39 11.75 108.15 64.44%
6 RCC in Super Structure, Class- A1 M3 491.80 292.31 - 24.59 34.43 316.90 64.44%
7 Reinforcement Ton 86.49 51.41 - 4.32 6.05 55.73 64.44%
8 Brick Work M3 1,000.85 593.00 - 50.04 70.06 643.04 64.25%

Page 10 of 51
CONSTRUCTION OF BUILDING INFRASTRUCTURE UNDER PESHWAR SUSTAIBALE BUS DEPOT RAPID TRANSIT CORRIDOR PROJECT
LOT 2: CHAMKANI BUS DEPOT, PARK & RIDE, TRANS PESHWAR OFFICE AND BRT CONTROL CENTER
DAILY PROGRESS REPORT
Date: Feb 2019 Weather: Sunny 31◦ᴄ ҉ DPR Ref No: 04

TOTAL Executed by
Sr. No DESCRIPTION UNIT QTY % Achieved
the end of Dec Executed In Executed In Executed In
2018 Jan 2019 Feb 2019 March 2019 Total Executed
9 Pointing M2 4,651.48 2,700.00 - 64.77 2,764.77 59.44%
10 Plastering M2 4,651.48 2,700.00 - 64.77 2,764.77 59.44%

3 WORKSHOP
Total Covered Area M2 4,369.15

1 Excavation M3 4,814.00 4,814.00 - - 4,814.00 100.00%

2 Gravel Material M3 1,266.75 1,266.75 - - 1,266.75 100.00%

3 Anti Termite M2 3,698.00 3,698.00 - - 3,698.00 100.00%

4 PCC Footing M3 427.00 289.00 138.00 - 427.00 100.00%

5 RCC In Foundation M3 1,356.96 1,356.00 0.96 - 1,356.96 100.00%

6 RCC in Super Structure M3 1,837.55 1,125.22 536.00 86.09 28.70 1,747.31 95.09%
7 Reinforcement Ton 682.11 439.00 156.00 11.25 3.75 606.25 88.88%
8 Bitumen paint (Coverage 7 Kg / 10 Sqm) M2 3,402.10 3,402.00 - - - 3,402.00 100.00%
9 Sand Filling M3 3,796.13 3,616.00 180.00 - - 3,796.00 100.00%
10 Brick masonary Ratio 1:4 (225mm thick) M3 500.00 - 173.00 240.00 80.00 413.00 82.60%
10 Brick masonary Ratio 1:4 (112mm thick) M2 189.00 - 148.58 40.95 148.58 78.61%
Cement Plaster M2 5,580.00 2,790.00 2,511.00 2,790.00 50.00%

Page 11 of 51
CONSTRUCTION OF BUILDING INFRASTRUCTURE UNDER PESHWAR SUSTAIBALE BUS DEPOT RAPID TRANSIT CORRIDOR PROJECT
LOT 2: CHAMKANI BUS DEPOT, PARK & RIDE, TRANS PESHWAR OFFICE AND BRT CONTROL CENTER
DAILY PROGRESS REPORT
Date: Feb 2019 Weather: Sunny 31◦ᴄ ҉ DPR Ref No: 04

TOTAL Executed by
Sr. No DESCRIPTION UNIT QTY % Achieved
the end of Dec Executed In Executed In Executed In
2018 Jan 2019 Feb 2019 March 2019 Total Executed

4 PARK & RIDE

1 Excavation M3 16,756.14 3,150 13,478.74 127.40 - 16,756.14 100.00%


Anti Termite M2 3,716.87 3,681.79 35.08 - 3,716.87 100.00%
Granular Material M3 2,538.24 2,472.33 65.91 - 2,538.24 100.00%
Lean Concrete M3 320.06 288.00 4.30 2.37 292.30 91.33%
Reinforcement Concrete In Foundation M3 4,275.20 2,200.00 731.25 402.19 2,931.25 68.56%
Reinforcement Concrete In Super Structure M3 7,596.26 624.00 156.00 624.00 8.21%
Reinforcement Steel Tonne 1,917.42 1,000.00 149.60 37.40 1,149.60 59.96%

5 OFFICE BUILDING
Total Covered Area

1 Excavation M3 7,495.43 6,085.67 - - 6,085.67 81.19%

2 Gravel Material M3 2,304.34 1,215.00 33.00 - 1,248.00 54.16%

3 Sand Filling M3 4,041.00 3,907.00 134.00 - - 4,041.00 100.00%

4 PCC Footing M3 431.40 210.00 210.00 48.68%

5 RCC in Foundation M3 2,175.60 1,645.00 - - 1,645.00 75.61%

6 RCC in Super Structure M3 1,726.13 164.00 372.00 340.89 227.26 876.89 50.80%

7 PCC On Ground M3 375.38 - - - 0.00%

8 RCC in Super Structure Auditorium & Shear M3 143.50 28.20 18.80 28.20 19.65%
walls
9 Reinforcement Ton 1,000.00 314.00 8.00 134.40 89.60 456.40 45.64%

10 Brick masonary Ratio 1:4 (225mm thick) M3 1,785.00 294.60 196.40 294.60 16.50%

11 Brick masonary Ratio 1:4 (112mm thick) M2 478.00 74.40 49.60 74.40 15.56%

Page 12 of 51
CONSTRUCTION OF BUILDING INFRASTRUCTURE UNDER PESHWAR SUSTAIBALE BUS DEPOT RAPID TRANSIT CORRIDOR PROJECT
LOT 2: CHAMKANI BUS DEPOT, PARK & RIDE, TRANS PESHWAR OFFICE AND BRT CONTROL CENTER
DAILY PROGRESS REPORT
Date: Feb 2019 Weather: Sunny 31◦ᴄ ҉ DPR Ref No: 04

TOTAL Executed by
Sr. No DESCRIPTION UNIT QTY % Achieved
the end of Dec Executed In Executed In Executed In
2018 Jan 2019 Feb 2019 March 2019 Total Executed
12 Bitumen paint (Coverage 7 Kg / 10 Sqm) M2 4,642.00 2,993.00 1,649.00 - - 4,642.00 100.00%

Page 13 of 51
CONSTRUCTION OF BUILDING INFRASTRUCTURE UNDER PESHWAR SUSTAIBALE BUS DEPOT RAPID TRANSIT CORRIDOR PROJECT
LOT 2: CHAMKANI BUS DEPOT, PARK & RIDE, TRANS PESHWAR OFFICE AND BRT CONTROL CENTER
DAILY PROGRESS REPORT
Date: Feb 2019 Weather: Sunny 31◦ᴄ ҉ DPR Ref No: 04

TOTAL Executed by
Sr. No DESCRIPTION UNIT QTY % Achieved
the end of Dec Executed In Executed In Executed In
2018 Jan 2019 Feb 2019 March 2019 Total Executed
6 DRAIN NO. 07
Total Length

1 Excavation M3 350.00 350.00 - - - 350.00 100.00%

2 Gravel Material M3 321.00 315.00 - - - 315.00 98.13%

3 Lean Concrete M3 104.00 101.00 - - - 101.00 97.12%

4 RCC of Drain Bed, Walls & Slab M3 698.00 689.45 - - - 689.45 98.78%
5 Reinforcement Ton 69.00 68.67 - - - 68.67 99.52%
6 Water Stopper M 1,300.00 1,274.00 6.00 - - 1,280.00 98.46%
7 Rest Area's (Male & Female)
Total Covered Area M2

1 Excavation M3 1,886.00 1,886.00 - - - 1,886.00 100.00%

2 Gravel Material M3 377.00 377.00 - - - 377.00 100.00%

3 PCC Footing M3 144.00 90.00 54.00 - - 144.00 100.00%

4 RCC in Foundation M3 452.00 452.00 - - - 452.00 100.00%

5 RCC in Super Structure M3 586.00 376.00 136.00 48.00 - 560.00 95.56%


6 Reinforcement Ton 166.00 144.00 8.00 - - 152.00 91.57%
7 Bitumen paint (Coverage 7 Kg / 10 Sqm) M2 558.00 558.00 - - - 558.00 100.00%
8 Sand Filling M3 880.00 880.00 - - - 880.00 100.00%
6 Cable Trench
Total Length M

Excavation CM 5,550.43 3,150.00 2,350.00 - - 5,500 99.09%

Gravel Material CM 630.22 620.00 - - - 620 98.38%

Page 14 of 51
CONSTRUCTION OF BUILDING INFRASTRUCTURE UNDER PESHWAR SUSTAIBALE BUS DEPOT RAPID TRANSIT CORRIDOR PROJECT
LOT 2: CHAMKANI BUS DEPOT, PARK & RIDE, TRANS PESHWAR OFFICE AND BRT CONTROL CENTER
DAILY PROGRESS REPORT
Date: Feb 2019 Weather: Sunny 31◦ᴄ ҉ DPR Ref No: 04

TOTAL Executed by
Sr. No DESCRIPTION UNIT QTY % Achieved
the end of Dec Executed In Executed In Executed In
2018 Jan 2019 Feb 2019 March 2019 Total Executed
PCC Footing CM 272.43 234.00 - - - 234 85.89%

RCC of bed, Walls & Slab CM 1,943.17 1,386.00 32.00 - - 1,418 72.97%

Reinforcement Ton 540.00 228.00 254.00 - - 482 89.26%

Sand Filling CM 2,200.00 376.00 1,325.63 498.00 - 2,200 99.98%

PVC Class D 150mm Dia Ducting RM 2,555.01 490.00 560.00 766.50 720.00 1,817 71.10%

PVC Class D 100mm Dia Ducting RM 4,304.84 392.00 588.00 1,291.45 2,000.00 2,271 52.77%
Manhole Covers Each 35.00 - - - - - 0.00%
7 Inspection Area
1 Excavation CM 56.00 56.00 - - - 56.00 100.00%

2 Gravel Material CM 30.00 30.00 - - - 30.00 100.00%

3 PCC Footing CM 5.48 5.48 - - - 5.48 100.00%

4 RCC of Pit, Bed & Wall CM 73.00 23.00 50.00 - - 73.00 100.00%

5 Reinforcement of Pit Ton 6.20 3.20 3.00 - - 6.20 100.00%


7 Tube Well (Boring)
1 Boring RFT 400.00 400.00 - 400.00 100.00%

2 Pipe Casing 8'' Internal Dia (UPVC Class 'D' RFT 400.00 400.00 - 400.00 100.00%

3 Gravel Material CM 4.83 4.83 - 4.83 100.00%

4 Lean Concrete CM 1.15 1.15 - 1.15 100.00%


7 Fuel Station/Tank
1 Excavation CM 1,954.00 1,679.00 186.00 89.00 - 1,954.00 100.00%

2 Gravel Material CM 256.00 54.44 12.00 189.56 - 256.00 100.00%

Page 15 of 51
CONSTRUCTION OF BUILDING INFRASTRUCTURE UNDER PESHWAR SUSTAIBALE BUS DEPOT RAPID TRANSIT CORRIDOR PROJECT
LOT 2: CHAMKANI BUS DEPOT, PARK & RIDE, TRANS PESHWAR OFFICE AND BRT CONTROL CENTER
DAILY PROGRESS REPORT
Date: Feb 2019 Weather: Sunny 31◦ᴄ ҉ DPR Ref No: 04

TOTAL Executed by
Sr. No DESCRIPTION UNIT QTY % Achieved
the end of Dec Executed In Executed In Executed In
2018 Jan 2019 Feb 2019 March 2019 Total Executed
3 Lean Concrete CM 34.00 17.33 11.00 5.50 - 33.83 99.50%

4 Reinforcement of Bed, Wall & Column TON 27.00 7.07 15.00 4.20 - 26.27 97.30%

5 RCC Bed, Wall & Column CM 288.00 32.52 153.00 98.00 - 283.52 98.44%
7 UGWT & OHWT
1 Excavation CM 558.69 446.00 - 446.00 79.83%

2 Gravel Material CM 157.00 157.00 - 157.00 100.00%

3 Lean Concrete CM 11.76 11.76 11.76 100.00%

4 Reinforcement Concrete UGWT CM 411.67 411.67 61.75 65.87 473.42 115.00%

5 Steel UGWT & OHWT Ton 85.00 55.00 12.75 13.60 67.75 79.71%

Contractor: Consultant:
ANHUI-CALSON JV MM PAKISTAN.

Page 16 of 51
CONSTRUCTION OF BUILDING INFRASTRUCTURE UNDER PESHWAR SUSTAIBALE BUS DEPOT RAPID TRANSIT CORRIDOR PROJECT
LOT 2: CHAMKANI BUS DEPOT, PARK & RIDE, TRANS PESHWAR OFFICE AND BRT CONTROL CENTER
DAILY PROGRESS REPORT
Date: March 2019 Weather: Sunny 31◦ᴄ ҉ DPR Ref No: 04

TOTAL Executed by
Sr. No DESCRIPTION UNIT QTY % Achieved
the end of Dec Executed In Executed In Executed In
2018 Jan 2019 Feb 2019 March 2019 Total Executed

1 BUS PARKING AREA


1 Excavation M3 42,054.91 42,055.00 - - - 42,055.00 100.00%
2 Gravel Material M3 31,386.73 30,502.00 298.00 260.00 300.00 31,360.00 99.91%
3 Sub Base M3 15,611.22 14,668.00 232.00 400.00 270.00 15,570.00 99.74%
4 Agreegate Base M3 15,611.22 14,266.00 634.00 400.00 260.00 15,560.00 99.67%
5 Lean Concrete M3 5,206.34 3,934.50 456.00 100.00 300.00 4,790.50 92.01%
6 Rigid Pavement M3 15,619.02 10,708.75 167.25 1,000.00 1,200.00 13,076.00 83.72%
7 Saw cut of Contraction Joint RM 10,406.00 3,201.00 1,151.00 600.00 500.00 5,452.00 52.39%
8 Saw cut of Construction Joint RM 14,233.00 1,958.00 6,366.00 500.00 500.00 9,324.00 65.51%
9 Filling of Contraction Joint RM 10,406.00 3,947.00 405.00 450.00 400.00 5,202.00 49.99%
10 Filling of Construction Joint RM 14,233.00 2,537.00 5,787.00 400.00 450.00 9,174.00 64.46%
11 Expansion Joint Treatment RM 1,180.00 - 726.00 100.00 100.00 926.00 78.47%

2 BOUNDARY WALL (Revised)


Total Boundary Wall Length M 1,898.35
1 Excavation M3 1,144.54 680.30 - 57.23 80.12 817.65 71.44%
2 Gravel Material M3 310.31 184.45 - 15.52 21.72 221.69 71.44%
3 Common Filling M3 703.68 418.26 - 35.18 49.26 502.70 71.44%
4 PCC Footing M3 311.95 185.42 - 15.60 21.84 222.85 71.44%
5 RCC in Foundation, Class- A1 M3 167.84 99.76 - 8.39 11.75 119.90 71.44%
6 RCC in Super Structure, Class- A1 M3 491.80 292.31 - 24.59 34.43 351.33 71.44%
7 Reinforcement Ton 86.49 51.41 - 4.32 6.05 61.79 71.44%
8 Brick Work M3 1,000.85 593.00 - 50.04 70.06 713.10 71.25%

Page 17 of 51
CONSTRUCTION OF BUILDING INFRASTRUCTURE UNDER PESHWAR SUSTAIBALE BUS DEPOT RAPID TRANSIT CORRIDOR PROJECT
LOT 2: CHAMKANI BUS DEPOT, PARK & RIDE, TRANS PESHWAR OFFICE AND BRT CONTROL CENTER
DAILY PROGRESS REPORT
Date: March 2019 Weather: Sunny 31◦ᴄ ҉ DPR Ref No: 04

TOTAL Executed by
Sr. No DESCRIPTION UNIT QTY % Achieved
the end of Dec Executed In Executed In Executed In
2018 Jan 2019 Feb 2019 March 2019 Total Executed
9 Pointing M2 4,651.48 2,700.00 - 64.77 35.00 2,799.77 60.19%
10 Plastering M2 4,651.48 2,700.00 - 64.77 35.00 2,799.77 60.19%

3 WORKSHOP
Total Covered Area M2 4,369.15

1 Excavation M3 4,814.00 4,814.00 - - 4,814.00 100.00%

2 Gravel Material M3 1,266.75 1,266.75 - - 1,266.75 100.00%

3 Anti Termite M2 3,698.00 3,698.00 - - 3,698.00 100.00%

4 PCC Footing M3 427.00 289.00 138.00 - 427.00 100.00%

5 RCC In Foundation M3 1,356.96 1,356.00 0.96 - 1,356.96 100.00%

6 RCC in Super Structure M3 1,837.55 1,125.22 536.00 86.09 28.70 1,776.00 96.65%
7 Reinforcement Ton 682.11 439.00 156.00 11.25 3.75 610.00 89.43%
8 Bitumen paint (Coverage 7 Kg / 10 Sqm) M2 3,402.10 3,402.00 - - - 3,402.00 100.00%
9 Sand Filling M3 3,796.13 3,616.00 180.00 - - 3,796.00 100.00%
10 Brick masonary Ratio 1:4 (225mm thick) M3 500.00 - 173.00 240.00 80.00 493.00 98.60%
10 Brick masonary Ratio 1:4 (112mm thick) M2 189.00 - 148.58 40.95 189.53 100.28%
Cement Plaster M2 5,580.00 2,790.00 2,511.00 5,301.00 95.00%

Page 18 of 51
CONSTRUCTION OF BUILDING INFRASTRUCTURE UNDER PESHWAR SUSTAIBALE BUS DEPOT RAPID TRANSIT CORRIDOR PROJECT
LOT 2: CHAMKANI BUS DEPOT, PARK & RIDE, TRANS PESHWAR OFFICE AND BRT CONTROL CENTER
DAILY PROGRESS REPORT
Date: March 2019 Weather: Sunny 31◦ᴄ ҉ DPR Ref No: 04

TOTAL Executed by
Sr. No DESCRIPTION UNIT QTY % Achieved
the end of Dec Executed In Executed In Executed In
2018 Jan 2019 Feb 2019 March 2019 Total Executed

4 PARK & RIDE

1 Excavation M3 16,756.14 3,150 13,478.74 127.40 - 16,756.14 100.00%


Anti Termite M2 3,716.87 3,681.79 35.08 - 3,716.87 100.00%
Granular Material M3 2,538.24 2,472.33 65.91 - 2,538.24 100.00%
Lean Concrete M3 320.06 288.00 4.30 2.37 294.67 92.07%
Reinforcement Concrete In Foundation M3 4,275.20 2,200.00 731.25 402.19 3,333.44 77.97%
Reinforcement Concrete In Super Structure M3 7,596.26 624.00 156.00 780.00 10.27%
Reinforcement Steel Tonne 1,917.42 1,000.00 149.60 37.40 1,187.00 61.91%

5 OFFICE BUILDING
Total Covered Area

1 Excavation M3 7,495.43 6,085.67 - - 6,085.67 81.19%

2 Gravel Material M3 2,304.34 1,215.00 33.00 - 1,248.00 54.16%

3 Sand Filling M3 4,041.00 3,907.00 134.00 - - 4,041.00 100.00%

4 PCC Footing M3 431.40 210.00 210.00 48.68%

5 RCC in Foundation M3 2,175.60 1,645.00 - - 1,645.00 75.61%

6 RCC in Super Structure M3 1,726.13 164.00 372.00 340.89 227.26 1,104.15 63.97%

7 PCC On Ground M3 375.38 - - - 0.00%

8 RCC in Super Structure Auditorium & Shear M3 143.50 28.20 18.80 47.00 32.75%
walls
9 Reinforcement Ton 1,000.00 314.00 8.00 134.40 89.60 546.00 54.60%

10 Brick masonary Ratio 1:4 (225mm thick) M3 1,785.00 294.60 196.40 491.00 27.51%

11 Brick masonary Ratio 1:4 (112mm thick) M2 478.00 74.40 49.60 124.00 25.94%

Page 19 of 51
CONSTRUCTION OF BUILDING INFRASTRUCTURE UNDER PESHWAR SUSTAIBALE BUS DEPOT RAPID TRANSIT CORRIDOR PROJECT
LOT 2: CHAMKANI BUS DEPOT, PARK & RIDE, TRANS PESHWAR OFFICE AND BRT CONTROL CENTER
DAILY PROGRESS REPORT
Date: March 2019 Weather: Sunny 31◦ᴄ ҉ DPR Ref No: 04

TOTAL Executed by
Sr. No DESCRIPTION UNIT QTY % Achieved
the end of Dec Executed In Executed In Executed In
2018 Jan 2019 Feb 2019 March 2019 Total Executed
12 Bitumen paint (Coverage 7 Kg / 10 Sqm) M2 4,642.00 2,993.00 1,649.00 - - 4,642.00 100.00%

Page 20 of 51
CONSTRUCTION OF BUILDING INFRASTRUCTURE UNDER PESHWAR SUSTAIBALE BUS DEPOT RAPID TRANSIT CORRIDOR PROJECT
LOT 2: CHAMKANI BUS DEPOT, PARK & RIDE, TRANS PESHWAR OFFICE AND BRT CONTROL CENTER
DAILY PROGRESS REPORT
Date: March 2019 Weather: Sunny 31◦ᴄ ҉ DPR Ref No: 04

TOTAL Executed by
Sr. No DESCRIPTION UNIT QTY % Achieved
the end of Dec Executed In Executed In Executed In
2018 Jan 2019 Feb 2019 March 2019 Total Executed
6 DRAIN NO. 07
Total Length

1 Excavation M3 350.00 350.00 - - - 350.00 100.00%

2 Gravel Material M3 321.00 315.00 - - - 315.00 98.13%

3 Lean Concrete M3 104.00 101.00 - - - 101.00 97.12%

4 RCC of Drain Bed, Walls & Slab M3 698.00 689.45 - - - 689.45 98.78%
5 Reinforcement Ton 69.00 68.67 - - - 68.67 99.52%
6 Water Stopper M 1,300.00 1,274.00 6.00 - - 1,280.00 98.46%
7 Rest Area's (Male & Female)
Total Covered Area M2

1 Excavation M3 1,886.00 1,886.00 - - - 1,886.00 100.00%

2 Gravel Material M3 377.00 377.00 - - - 377.00 100.00%

3 PCC Footing M3 144.00 90.00 54.00 - - 144.00 100.00%

4 RCC in Foundation M3 452.00 452.00 - - - 452.00 100.00%

5 RCC in Super Structure M3 586.00 376.00 136.00 48.00 - 560.00 95.56%


6 Reinforcement Ton 166.00 144.00 8.00 - - 152.00 91.57%
7 Bitumen paint (Coverage 7 Kg / 10 Sqm) M2 558.00 558.00 - - - 558.00 100.00%
8 Sand Filling M3 880.00 880.00 - - - 880.00 100.00%
9 Brick masonary Ratio 1:4 (225mm thick) M3 519.79 120.00 115.00 110.00 150.00 495.00 95.23%
10 Brick masonary Ratio 1:4 (112mm thick) M2 520.20 120.00 115.00 110.00 140.00 485.00 93.23%
11 Cement Plaster M2 1,031.00 200.00 150.00 300.00 300.00 950.00 92.14%
6 Cable Trench
Total Length M

Page 21 of 51
CONSTRUCTION OF BUILDING INFRASTRUCTURE UNDER PESHWAR SUSTAIBALE BUS DEPOT RAPID TRANSIT CORRIDOR PROJECT
LOT 2: CHAMKANI BUS DEPOT, PARK & RIDE, TRANS PESHWAR OFFICE AND BRT CONTROL CENTER
DAILY PROGRESS REPORT
Date: March 2019 Weather: Sunny 31◦ᴄ ҉ DPR Ref No: 04

TOTAL Executed by
Sr. No DESCRIPTION UNIT QTY % Achieved
the end of Dec Executed In Executed In Executed In
2018 Jan 2019 Feb 2019 March 2019 Total Executed
Excavation CM 5,550.43 3,150.00 2,350.00 - - 5,500.00 99.09%

Gravel Material CM 630.22 620.00 - - - 620.00 98.38%

PCC Footing CM 272.43 234.00 - - - 234.00 85.89%

RCC of bed, Walls & Slab CM 1,943.17 1,386.00 32.00 - - 1,418.00 72.97%

Reinforcement Ton 540.00 228.00 254.00 - - 482.00 89.26%

Sand Filling CM 2,200.00 376.00 1,325.63 498.00 - 2,199.63 99.98%

PVC Class D 150mm Dia Ducting RM 2,555.01 490.00 560.00 766.50 720.00 2,536.50 99.28%

PVC Class D 100mm Dia Ducting RM 4,304.84 392.00 588.00 1,291.45 2,000.00 4,271.45 99.22%
Manhole Covers Each 35.00 - - - - - 0.00%
7 Inspection Area
1 Excavation CM 56.00 56.00 - - - 56.00 100.00%

2 Gravel Material CM 30.00 30.00 - - - 30.00 100.00%

3 PCC Footing CM 5.48 5.48 - - - 5.48 100.00%

4 RCC of Pit, Bed & Wall CM 73.00 23.00 50.00 - - 73.00 100.00%

5 Reinforcement of Pit Ton 6.20 3.20 3.00 - - 6.20 100.00%


7 Tube Well (Boring)
1 Boring RFT 400.00 400.00 - 400.00 100.00%

2 Pipe Casing 8'' Internal Dia (UPVC Class 'D' RFT 400.00 400.00 - 400.00 100.00%

3 Gravel Material CM 4.83 4.83 - 4.83 100.00%

4 Lean Concrete CM 1.15 1.15 - 1.15 100.00%


7 Fuel Station/Tank

Page 22 of 51
CONSTRUCTION OF BUILDING INFRASTRUCTURE UNDER PESHWAR SUSTAIBALE BUS DEPOT RAPID TRANSIT CORRIDOR PROJECT
LOT 2: CHAMKANI BUS DEPOT, PARK & RIDE, TRANS PESHWAR OFFICE AND BRT CONTROL CENTER
DAILY PROGRESS REPORT
Date: March 2019 Weather: Sunny 31◦ᴄ ҉ DPR Ref No: 04

TOTAL Executed by
Sr. No DESCRIPTION UNIT QTY % Achieved
the end of Dec Executed In Executed In Executed In
2018 Jan 2019 Feb 2019 March 2019 Total Executed
1 Excavation CM 1,954.00 1,679.00 186.00 89.00 - 1,954.00 100.00%

2 Gravel Material CM 256.00 54.44 12.00 189.56 - 256.00 100.00%

3 Lean Concrete CM 34.00 17.33 11.00 5.50 - 33.83 99.50%

4 Reinforcement of Bed, Wall & Column TON 27.00 7.07 15.00 4.20 - 26.27 97.30%

5 RCC Bed, Wall & Column CM 288.00 32.52 153.00 98.00 - 283.52 98.44%
7 UGWT & OHWT
1 Excavation CM 558.69 446.00 - 446.00 79.83%

2 Gravel Material CM 157.00 157.00 - 157.00 100.00%

3 Lean Concrete CM 11.76 11.76 11.76 100.00%

4 Reinforcement Concrete UGWT CM 640.00 411.67 96.00 102.40 610.07 95.32%

5 Steel UGWT & OHWT Ton 85.00 55.00 12.75 13.60 81.35 95.71%

Contractor: Consultant:
ANHUI-CALSON JV MM PAKISTAN.

Page 23 of 51
CONSTRUCTION OF BUILDING INFRASTRUCTURE UNDER PESHWAR SUSTAIBALE BUS DEPOT RAPID TRANSIT CORRIDOR PROJECT
LOT 2: CHAMKANI BUS DEPOT, PARK & RIDE, TRANS PESHWAR OFFICE AND BRT CONTROL CENTER
DAILY PROGRESS REPORT
Date: April 2019 Weather: Sunny 31◦ᴄ ҉ DPR Ref No: 04

TOTAL Executed by
Sr. No DESCRIPTION UNIT QTY % Achieved
the end of Executed In
March 2019 April 2019 Total Executed

1 BUS PARKING AREA


1 Excavation M3 42,054.91 42,055.00 42,055.00 100.00%
2 Gravel Material M3 31,386.73 31,360.00 31,360.00 99.91%
3 Sub Base M3 15,611.22 15,570.00 15,570.00 99.74%
4 Agreegate Base M3 15,611.22 15,560.00 15,560.00 99.67%
5 Lean Concrete M3 5,206.34 4,790.50 4,790.50 92.01%
6 Rigid Pavement M3 15,619.02 13,076.00 240.00 13,316.00 85.26%
7 Saw cut of Contraction Joint RM 10,406.00 5,452.00 250.00 5,702.00 54.80%
8 Saw cut of Construction Joint RM 14,233.00 9,324.00 350.00 9,674.00 67.97%
9 Filling of Contraction Joint RM 10,406.00 5,202.00 250.00 5,452.00 52.39%
10 Filling of Construction Joint RM 14,233.00 9,174.00 350.00 9,524.00 66.91%
11 Expansion Joint Treatment RM 1,180.00 926.00 926.00 78.47%

2 BOUNDARY WALL (Revised)


Total Boundary Wall Length M 1,898.35
1 Excavation M3 1,144.54 817.65 137.35 954.99 83.44%
2 Gravel Material M3 310.31 221.69 37.24 258.93 83.44%
3 Common Filling M3 703.68 502.70 84.44 587.14 83.44%
4 PCC Footing M3 311.95 222.85 37.43 260.29 83.44%
5 RCC in Foundation, Class- A1 M3 167.84 119.90 20.14 140.04 83.44%
6 RCC in Super Structure, Class- A1 M3 491.80 351.33 59.02 410.34 83.44%
7 Reinforcement Ton 86.49 61.79 10.38 72.17 83.44%
8 Brick Work M3 1,000.85 713.10 120.10 833.21 83.25%

Page 24 of 51
CONSTRUCTION OF BUILDING INFRASTRUCTURE UNDER PESHWAR SUSTAIBALE BUS DEPOT RAPID TRANSIT CORRIDOR PROJECT
LOT 2: CHAMKANI BUS DEPOT, PARK & RIDE, TRANS PESHWAR OFFICE AND BRT CONTROL CENTER
DAILY PROGRESS REPORT
Date: April 2019 Weather: Sunny 31◦ᴄ ҉ DPR Ref No: 04

TOTAL Executed by
Sr. No DESCRIPTION UNIT QTY % Achieved
the end of Executed In
March 2019 April 2019 Total Executed
9 Pointing M2 4,651.48 2,799.77 558.18 3,357.95 72.19%
10 Plastering M2 4,651.48 2,799.77 558.18 3,357.95 72.19%

3 WORKSHOP
Total Covered Area M2 4,369.15

1 Excavation M3 4,814.00 4,814.00 4,814.00 100.00%

2 Gravel Material M3 1,266.75 1,266.75 1,266.75 100.00%

3 Anti Termite M2 3,698.00 3,698.00 3,698.00 100.00%

4 PCC Footing M3 427.00 427.00 427.00 100.00%

5 RCC In Foundation M3 1,356.96 1,356.96 1,356.96 100.00%

6 RCC in Super Structure M3 1,837.55 1,776.00 1,776.00 96.65%


7 Reinforcement Ton 682.11 610.00 610.00 89.43%
8 Bitumen paint (Coverage 7 Kg / 10 Sqm) M2 3,402.10 3,402.00 3,402.00 100.00%
9 Sand Filling M3 3,796.13 3,796.00 3,796.00 100.00%
10 Brick masonary Ratio 1:4 (225mm thick) M3 500.00 493.00 493.00 98.60%
10 Brick masonary Ratio 1:4 (112mm thick) M2 189.00 189.53 189.53 100.28%
Cement Plaster M2 5,580.00 5,301.00 5,301.00 95.00%
Tile floor 24"x24" Local Made M2 2,193.00 1,200.00 200.00 1,400.00 63.84%
Tile floor 16"x16" Local Made M2 154.00 80.00 20.00 100.00 64.94%
Aluminum door /window M2 620.27 250.00 76.00 326.00 52.56%

Page 25 of 51
CONSTRUCTION OF BUILDING INFRASTRUCTURE UNDER PESHWAR SUSTAIBALE BUS DEPOT RAPID TRANSIT CORRIDOR PROJECT
LOT 2: CHAMKANI BUS DEPOT, PARK & RIDE, TRANS PESHWAR OFFICE AND BRT CONTROL CENTER
DAILY PROGRESS REPORT
Date: April 2019 Weather: Sunny 31◦ᴄ ҉ DPR Ref No: 04

TOTAL Executed by
Sr. No DESCRIPTION UNIT QTY % Achieved
the end of Executed In
March 2019 April 2019 Total Executed

4 PARK & RIDE

1 Excavation M3 16,756.14 16,756 - 16,756.14 100.00%


Anti Termite M2 3,716.87 3,716.87 - 3,716.87 100.00%
Granular Material M3 2,538.24 2,538.24 - 2,538.24 100.00%
Lean Concrete M3 320.06 294.67 - 294.67 92.07%
Reinforcement Concrete In Foundation M3 4,275.20 3,333.44 941.76 4,275.20 100.00%
Reinforcement Concrete In Super Structure M3 7,596.26 780.00 250.00 1,030.00 13.56%
Reinforcement Steel Tonne 1,917.42 1,187.00 5.00 1,192.00 62.17%
8 Bitumen paint (Coverage 7 Kg / 10 Sqm) M2 1,651.00 1,651.00 - 1,651.00 100.00%

5 OFFICE BUILDING
Total Covered Area

1 Excavation M3 7,495.43 6,085.67 - 6,085.67 81.19%

2 Gravel Material M3 2,304.34 1,248.00 - 1,248.00 54.16%

3 Sand Filling M3 4,041.00 4,041.00 - 4,041.00 100.00%

4 PCC Footing M3 431.40 210.00 98.21 308.21 71.44%

5 RCC in Foundation M3 2,175.60 1,645.00 - 1,645.00 75.61%

6 RCC in Super Structure M3 1,726.13 1,104.15 - 1,104.15 63.97%

7 PCC On Ground M3 375.38 - - - 0.00%

8 RCC in Super Structure Auditorium & Shear M3 143.50 47.00 - 47.00 32.75%
walls
9 Reinforcement Ton 1,000.00 546.00 - 546.00 54.60%

10 Brick masonary Ratio 1:4 (225mm thick) M3 1,785.00 350.00 141.94 491.94 27.56%

Page 26 of 51
CONSTRUCTION OF BUILDING INFRASTRUCTURE UNDER PESHWAR SUSTAIBALE BUS DEPOT RAPID TRANSIT CORRIDOR PROJECT
LOT 2: CHAMKANI BUS DEPOT, PARK & RIDE, TRANS PESHWAR OFFICE AND BRT CONTROL CENTER
DAILY PROGRESS REPORT
Date: April 2019 Weather: Sunny 31◦ᴄ ҉ DPR Ref No: 04

TOTAL Executed by
Sr. No DESCRIPTION UNIT QTY % Achieved
the end of Executed In
March 2019 April 2019 Total Executed
11 Brick masonary Ratio 1:4 (112mm thick) M2 478.00 100.00 24.00 124.00 25.94%
12 Bitumen paint (Coverage 7 Kg / 10 Sqm) M2 4,642.00 4,642.00 4,642.00 100.00%

Page 27 of 51
CONSTRUCTION OF BUILDING INFRASTRUCTURE UNDER PESHWAR SUSTAIBALE BUS DEPOT RAPID TRANSIT CORRIDOR PROJECT
LOT 2: CHAMKANI BUS DEPOT, PARK & RIDE, TRANS PESHWAR OFFICE AND BRT CONTROL CENTER
DAILY PROGRESS REPORT
Date: April 2019 Weather: Sunny 31◦ᴄ ҉ DPR Ref No: 04

TOTAL Executed by
Sr. No DESCRIPTION UNIT QTY % Achieved
the end of Executed In
March 2019 April 2019 Total Executed
Cement Plaster M2 15,000.00 3,000.00 2,000.00 5,000.00 33.33%
6 DRAIN NO. 07
Total Length

1 Excavation M3 350.00 350.00 350.00 100.00%

2 Gravel Material M3 321.00 315.00 315.00 98.13%

3 Lean Concrete M3 104.00 101.00 101.00 97.12%

4 RCC of Drain Bed, Walls & Slab M3 698.00 689.45 689.45 98.78%
5 Reinforcement Ton 69.00 68.67 68.67 99.52%
6 Water Stopper M 1,300.00 1,280.00 1,280.00 98.46%
7 Rest Area's (Male & Female)
Total Covered Area M2

1 Excavation M3 1,886.00 1,886.00 1,886.00 100.00%

2 Gravel Material M3 377.00 377.00 377.00 100.00%

3 PCC Footing M3 144.00 144.00 144.00 100.00%

4 RCC in Foundation M3 452.00 452.00 452.00 100.00%

5 RCC in Super Structure M3 586.00 560.00 560.00 95.56%


6 Reinforcement Ton 166.00 152.00 152.00 91.57%
7 Bitumen paint (Coverage 7 Kg / 10 Sqm) M2 558.00 558.00 558.00 100.00%
8 Sand Filling M3 880.00 880.00 880.00 100.00%
9 Brick masonary Ratio 1:4 (225mm thick) M3 519.79 495.00 20.00 515.00 99.08%
10 Brick masonary Ratio 1:4 (112mm thick) M2 520.20 485.00 15.00 500.00 96.12%
11 Cement Plaster M2 3,150.00 950.00 950.00 1,900.00 60.32%
Tile floor 24"x24" Local Made M2 494.72 1,200.00 200.00 1,400.00 282.99%
Tile floor 16"x16" Local Made M2 156.30 80.00 20.00 100.00 63.98%
Page 28 of 51
CONSTRUCTION OF BUILDING INFRASTRUCTURE UNDER PESHWAR SUSTAIBALE BUS DEPOT RAPID TRANSIT CORRIDOR PROJECT
LOT 2: CHAMKANI BUS DEPOT, PARK & RIDE, TRANS PESHWAR OFFICE AND BRT CONTROL CENTER
DAILY PROGRESS REPORT
Date: April 2019 Weather: Sunny 31◦ᴄ ҉ DPR Ref No: 04

TOTAL Executed by
Sr. No DESCRIPTION UNIT QTY % Achieved
the end of Executed In
March 2019 April 2019 Total Executed
Aluminium door /window M2 216.00 70.00 60.00 130.00 60.19%
Marble on Stairs complete in all respects M² 52.00 - - - 0.00%

6 Cable Trench
Total Length M

Excavation CM 5,550.43 5,500.00 5,500.00 99.09%

Gravel Material CM 630.22 620.00 620.00 98.38%

PCC Footing CM 272.43 234.00 234.00 85.89%

RCC of bed, Walls & Slab CM 1,943.17 1,418.00 150.00 1,568.00 80.69%

Reinforcement Ton 540.00 482.00 20.00 502.00 92.96%

Sand Filling CM 2,200.00 2,199.63 2,199.63 99.98%

PVC Class D 150mm Dia Ducting RM 2,555.01 2,536.50 2,536.50 99.28%

PVC Class D 100mm Dia Ducting RM 4,304.84 4,271.45 4,271.45 99.22%


Manhole Covers Each 35.00 - - 0.00%
7 Inspection Area
1 Excavation CM 56.00 56.00 56.00 100.00%

2 Gravel Material CM 30.00 30.00 30.00 100.00%

3 PCC Footing CM 5.48 5.48 5.48 100.00%

4 RCC of Pit, Bed & Wall CM 73.00 73.00 73.00 100.00%

5 Reinforcement of Pit Ton 6.20 6.20 6.20 100.00%

Steel Conopy M2 432.00 - - - 0.00%


7 Tube Well (Boring)

Page 29 of 51
CONSTRUCTION OF BUILDING INFRASTRUCTURE UNDER PESHWAR SUSTAIBALE BUS DEPOT RAPID TRANSIT CORRIDOR PROJECT
LOT 2: CHAMKANI BUS DEPOT, PARK & RIDE, TRANS PESHWAR OFFICE AND BRT CONTROL CENTER
DAILY PROGRESS REPORT
Date: April 2019 Weather: Sunny 31◦ᴄ ҉ DPR Ref No: 04

TOTAL Executed by
Sr. No DESCRIPTION UNIT QTY % Achieved
the end of Executed In
March 2019 April 2019 Total Executed
1 Boring RFT 400.00 400.00 400.00 100.00%

2 Pipe Casing 8'' Internal Dia (UPVC Class 'D' RFT 400.00 400.00 400.00 100.00%

3 Gravel Material CM 4.83 4.83 4.83 100.00%

4 Lean Concrete CM 1.15 1.15 1.15 100.00%


7 Fuel Station/Tank
1 Excavation CM 1,954.00 1,954.00 1,954.00 100.00%

2 Gravel Material CM 256.00 256.00 256.00 100.00%

3 Lean Concrete CM 34.00 33.83 33.83 99.50%

4 Reinforcement of Bed, Wall & Column TON 27.00 26.27 26.27 97.30%

5 RCC Bed, Wall & Column CM 288.00 283.52 283.52 98.44%

Steel Conopy Fuel Station M2 400.00 350.00 - 350.00 87.50%


7 UGWT & OHWT
1 Excavation CM 558.69 558.69 - 558.69 100.00%

2 Gravel Material CM 157.00 157.00 157.00 100.00%

3 Lean Concrete CM 11.76 11.76 11.76 100.00%

4 Reinforcement Concrete UGWT CM 640.00 610.07 10.00 620.07 96.89%

5 Steel UGWT & OHWT Ton 85.00 81.35 2.00 83.35 98.06%
7 Internal Roads & BS 00
Internal Roads
Excavation of unsuitable Material CM 11,525.90 11,525.90 - 11,525.90 100.00%

Granular Filling (River Bed Material) M3 8,537.70 6,969 500.00 7,469.17 87.48%

Page 30 of 51
CONSTRUCTION OF BUILDING INFRASTRUCTURE UNDER PESHWAR SUSTAIBALE BUS DEPOT RAPID TRANSIT CORRIDOR PROJECT
LOT 2: CHAMKANI BUS DEPOT, PARK & RIDE, TRANS PESHWAR OFFICE AND BRT CONTROL CENTER
DAILY PROGRESS REPORT
Date: April 2019 Weather: Sunny 31◦ᴄ ҉ DPR Ref No: 04

TOTAL Executed by
Sr. No DESCRIPTION UNIT QTY % Achieved
the end of Executed In
March 2019 April 2019 Total Executed
Granular Sub-Base CM 4,268.85 2,512 900.00 3,411.77 79.92%

Aggregate Base Course CM 4,268.85 2,159 1,200.00 3,358.52 78.67%

Plain cement Concrete(Lean concrete) CM 1,311.83 721.00 350.00 1,071.00 81.64%

Rigid Pavement floor 1:2:4 CM 3,879.93 2,900.00 115.00 3,015.00 77.71%

Dowels with PVC Pipe Each 3,374.68 2,400.00 200.00 2,600.00 77.04%

Steel Welded Mesh in Rigid Pavement M2 12,933.10 10,098.16 90.00 10,188.16 78.78%

TUFF TILES M2 2,400.00 - - - 0.00%

Kerb stone (18''x6'') M 4,184.28 - - - 0.00%


Bus Station 00 & Rest/ Toilet Block
BS STRUCTURAL STEEL WORKS SM 2,500.00 1,600.00 250.00 1,850.00 74.00%

Contractor: Consultant:
ANHUI-CALSON JV MM PAKISTAN.

Page 31 of 51
CONSTRUCTION OF BUILDING INFRASTRUCTURE UNDER PESHWAR SUSTAIBALE BUS DEPOT RAPID TRANSIT CO
LOT 2: CHAMKANI BUS DEPOT, PARK & RIDE, TRANS PESHWAR OFFICE AND BRT CONT
%

MONTHLY PROGRESS REPORT


A
c
Date: May 2019 Weather: Sunny 31◦ᴄ ҉ h
i
DPR Ref No: 04 e
v
TOTAL e
Sr. No DESCRIPTION UNIT QTY d

U
p
1 BUS PARKING AREA t
o
1 Excavation M3 42,054.91###
M
2 Gravel Material M3 a
31,386.73###
y
3 Sub Base M3 15,611.22###
4 Agreegate Base M3 15,611.22###
5 Lean Concrete M3 5,206.34###
6 Rigid Pavement M3 15,619.02###
7 Saw cut of Contraction Joint RM 10,406.00###
8 Saw cut of Construction Joint RM 14,233.00###
9 Filling of Contraction Joint RM 10,406.00###
10 Filling of Construction Joint RM 14,233.00###
11 Expansion Joint Treatment RM 1,180.00###

2 BOUNDARY WALL (Revised)


Total Boundary Wall Length
1 Excavation M3 1,144.54###
2 Gravel Material M3 310.31###
3 Common Filling M3 703.68###
4 PCC Footing M3 311.95###
5 RCC in Foundation, Class- A1 M3 167.84###
6 RCC in Super Structure, Class- A1 M3 491.80###
7 Reinforcement Ton 86.49###

Page 32 of 51
CONSTRUCTION OF BUILDING INFRASTRUCTURE UNDER PESHWAR SUSTAIBALE BUS DEPOT RAPID TRANSIT CO
LOT 2: CHAMKANI BUS DEPOT, PARK & RIDE, TRANS PESHWAR OFFICE AND BRT CONT
%

MONTHLY PROGRESS REPORT


A
c
Date: May 2019 Weather: Sunny 31◦ᴄ ҉ h
i
DPR Ref No: 04 e
v
TOTAL e
Sr. No DESCRIPTION UNIT QTY d

U
8 Brick Work M3 p
1,000.85###
t
9 Pointing M2 o
4,651.48###
10 Plastering M2 M
4,651.48###
a
11 Barbed Wire Fence and Razor Wire M y
1,800.00###

3 WORKSHOP
Total Covered Area

1 Excavation M3 4,814.00###

2 Gravel Material M3 1,266.75###

3 Anti Termite M2 3,698.00###

4 PCC Footing M3 427.00###

5 RCC In Foundation M3 1,356.96###

6 RCC in Super Structure M3 1,837.55###


7 Reinforcement Ton 682.11###
8 Bitumen paint (Coverage 7 Kg / 10 Sqm) M2 3,402.10###
9 Sand Filling M3 3,796.13###
10 Brick masonary Ratio 1:4 (225mm thick) M3 500.00###
11 Brick masonary Ratio 1:4 (112mm thick) M2 255.00###
12 Cement Plaster M2 5,580.00###
13 Tile floor 24"x24" Local Made M2 2,096.00###
14 Tile floor 16"x16" Local Made M2 640.00###
15 Aluminum door /window M2 407.00###
16 UPVC Doors M2 54.00###
17 PCC 1:2:4 A2 On Roof Floor (Screeding) M3 99.32###
18 Marble on Stairs M2 87.00###

Page 33 of 51
CONSTRUCTION OF BUILDING INFRASTRUCTURE UNDER PESHWAR SUSTAIBALE BUS DEPOT RAPID TRANSIT CO
LOT 2: CHAMKANI BUS DEPOT, PARK & RIDE, TRANS PESHWAR OFFICE AND BRT CONT
%

MONTHLY PROGRESS REPORT


A
c
Date: May 2019 Weather: Sunny 31◦ᴄ ҉ h
i
DPR Ref No: 04 e
v
TOTAL e
Sr. No DESCRIPTION UNIT QTY d

U
19 SS Railing M2 p
85.96###
t
o

M
a
y

Page 34 of 51
CONSTRUCTION OF BUILDING INFRASTRUCTURE UNDER PESHWAR SUSTAIBALE BUS DEPOT RAPID TRANSIT CO
LOT 2: CHAMKANI BUS DEPOT, PARK & RIDE, TRANS PESHWAR OFFICE AND BRT CONT
%

MONTHLY PROGRESS REPORT


A
c
Date: May 2019 Weather: Sunny 31◦ᴄ ҉ h
i
DPR Ref No: 04 e
v
TOTAL e
Sr. No DESCRIPTION UNIT QTY d

U
20 Baskit Ball Courtyard Fence RM p
154.00###
t
21 Weather Shield M2 1,278.00###
o
22 Emulsion Paint M2 10,514.00###
M
4 PARK & RIDE a
y
1 Excavation M3 16,756.14###
2 Anti Termite M2 3,716.87###
3 Granular Material M3 2,538.24###
4 Lean Concrete M3 320.06###
5 Back Filling M3 2,700.00###
6 Reinforcement Concrete In Foundation M3 3,500.00###
7 Reinforcement Concrete In Super Structure M3 7,596.26###
8 Reinforcement Steel Tonne 2,200.00###
9 Bitumen paint (Coverage 7 Kg / 10 Sqm) M2 1,651.00###
10 Brick Masonary M3 1,600.00###

5 OFFICE BUILDING
Total Covered Area

1 Excavation M3 7,495.43###

2 Gravel Material M3 2,304.34###

3 Sand Filling M3 4,041.00###

4 PCC Footing M3 308.21 ###

5 RCC in Foundation M3 1,645.00###

6 RCC in Super Structure M3 1,726.13###

7 PCC On Ground M3 375.38###


Page 35 of 51
CONSTRUCTION OF BUILDING INFRASTRUCTURE UNDER PESHWAR SUSTAIBALE BUS DEPOT RAPID TRANSIT CO
LOT 2: CHAMKANI BUS DEPOT, PARK & RIDE, TRANS PESHWAR OFFICE AND BRT CONT
%

MONTHLY PROGRESS REPORT


A
c
Date: May 2019 Weather: Sunny 31◦ᴄ ҉ h
i
DPR Ref No: 04 e
v
TOTAL e
Sr. No DESCRIPTION UNIT QTY d

U
RCC in Super Structure Auditorium & Shear p
8 walls M3 143.50###
t
o
9 Reinforcement (Revised) Ton 700.00###
M
a
y

Page 36 of 51
CONSTRUCTION OF BUILDING INFRASTRUCTURE UNDER PESHWAR SUSTAIBALE BUS DEPOT RAPID TRANSIT CO
LOT 2: CHAMKANI BUS DEPOT, PARK & RIDE, TRANS PESHWAR OFFICE AND BRT CONT
%

MONTHLY PROGRESS REPORT


A
c
Date: May 2019 Weather: Sunny 31◦ᴄ ҉ h
i
DPR Ref No: 04 e
v
TOTAL e
Sr. No DESCRIPTION UNIT QTY d

U
p
10 Brick masonary Ratio 1:4 (225mm thick) M3 1,785.00###
t
o
11 Brick masonary Ratio 1:4 (112mm thick) M2 478.00###
M
12 Bitumen paint (Coverage 7 Kg / 10 Sqm) M2 4,642.00###
a
y
13 Cement Plaster M2 24,000.00###
14 Aluminium Doors Windows M2 850.00###
Granitto tile floor on Stairs M2 700.00###

Raised Flooring (HPL Finish)+ESD Flooring M2 349.00###


Sub Base M3 250.00###
Base Course M3 250.00###
Emulsion Paint M2 16,000.00###
SS Railing M2 140.00###
VRF System Job 1.00###
Fire Fighting System Job 1.00###

6 DRAIN NO. 07, 08 & 13


Total Length

1 Excavation M3 2,424.00###

2 Gravel Material M3 400.00###

3 Lean Concrete M3 250.00###

4 RCC of Drain Bed, Walls & Slab M3 1,800.00###


5 Reinforcement Ton 130.00###
6 Water Stopper M 1,690.00###
7 Rest Area's (Male & Female)

Page 37 of 51
CONSTRUCTION OF BUILDING INFRASTRUCTURE UNDER PESHWAR SUSTAIBALE BUS DEPOT RAPID TRANSIT CO
LOT 2: CHAMKANI BUS DEPOT, PARK & RIDE, TRANS PESHWAR OFFICE AND BRT CONT
%

MONTHLY PROGRESS REPORT


A
c
Date: May 2019 Weather: Sunny 31◦ᴄ ҉ h
i
DPR Ref No: 04 e
v
TOTAL e
Sr. No DESCRIPTION UNIT QTY d

U
p
Total Covered Area t
o
1 Excavation M3 1,886.00###
M
2 Gravel Material M3 a
377.00###
y
3 PCC Footing M3 144.00###

4 RCC in Foundation M3 452.00###

5 RCC in Super Structure M3 586.00###


6 Reinforcement Ton 166.00###
7 Bitumen paint (Coverage 7 Kg / 10 Sqm) M2 558.00###
8 Sand Filling M3 1,792.51###
9 Brick masonary Ratio 1:4 (225mm thick) M3 519.79###
10 Brick masonary Ratio 1:4 (112mm thick) M2 520.20###
11 Cement Plaster M2 1,031.26###
12 Tile floor 24"x24" Local Made M2 1,024.00###
13 Tile floor 16"x16" Local Made M2 781.00###
14 Aluminium door /window M2 240.00###
15 UPVC Doors M2 66.78###
16 Marble on Stairs and Window Cells M² 147.00###
17 Weather Shield M2 1,419.00###
18 Emulsion Paint M2 2,105.00###

6 Cable Trench
Total Length

1 Excavation CM 5,550.43###

2 Gravel Material CM 630.22###


Page 38 of 51
CONSTRUCTION OF BUILDING INFRASTRUCTURE UNDER PESHWAR SUSTAIBALE BUS DEPOT RAPID TRANSIT CO
LOT 2: CHAMKANI BUS DEPOT, PARK & RIDE, TRANS PESHWAR OFFICE AND BRT CONT
%

MONTHLY PROGRESS REPORT


A
c
Date: May 2019 Weather: Sunny 31◦ᴄ ҉ h
i
DPR Ref No: 04 e
v
TOTAL e
Sr. No DESCRIPTION UNIT QTY d

U
p
3 PCC Footing CM 272.43###
t
o
4 RCC of bed, Walls & Slab CM 1,943.17###
M
5 Reinforcement Ton a
540.00###
y
6 Sand Filling CM 2,200.00###

7 PVC Class D 150mm Dia Ducting RM 2,555.01###

8 PVC Class D 100mm Dia Ducting RM 4,304.84###


Manhole Covers Each 35.00###
7 Inspection Area
1 Excavation CM 407.54###

2 Gravel Material CM 103.33###

3 PCC Footing CM 9.80###

4 RCC of Pit, Bed & Wall CM 73.00###

5 Reinforcement of Pit Ton 6.20###

6 Steel Conopy M2 432.00###


7 Tube Well (Boring)
1 Boring RFT 400.00###

2 Pipe Casing 8'' Internal Dia (UPVC Class 'D' RFT 400.00###

3 Gravel Material CM 4.83###

4 Lean Concrete CM 1.15###


7 Fuel Station/Tank

Page 39 of 51
CONSTRUCTION OF BUILDING INFRASTRUCTURE UNDER PESHWAR SUSTAIBALE BUS DEPOT RAPID TRANSIT CO
LOT 2: CHAMKANI BUS DEPOT, PARK & RIDE, TRANS PESHWAR OFFICE AND BRT CONT
%

MONTHLY PROGRESS REPORT


A
c
Date: May 2019 Weather: Sunny 31◦ᴄ ҉ h
i
DPR Ref No: 04 e
v
TOTAL e
Sr. No DESCRIPTION UNIT QTY d

U
p
1 Excavation CM 1,954.00###
t
o
2 Gravel Material CM 256.00###
M
3 Lean Concrete CM a
35.26###
y
4 Reinforcement of Bed, Wall & Column TON 33.29###

5 RCC Bed, Wall & Column CM 350.00###

6 Steel Conopy Fuel Station M2 400.00###


7 UGWT & OHWT
1 Excavation CM 601.99###

2 Gravel Material CM 92.39###

3 Lean Concrete CM 13.22###

4 Reinforcement Concrete UGWT & OHWT CM 207.00###

5 Steel UGWT & OHWT Ton 80.00###


7 Internal Roads & BS 00
Internal Roads
Excavation of unsuitable Material CM 11,119.69###

Granular Filling (River Bed Material) M3 8,630.99###

Granular Sub-Base CM 4,076.48###

Aggregate Base Course CM 3,627.15###

Plain cement Concrete(Lean concrete) CM 1,660.00###

Rigid Pavement floor 1:2:4 CM 3,903.00###

Page 40 of 51
CONSTRUCTION OF BUILDING INFRASTRUCTURE UNDER PESHWAR SUSTAIBALE BUS DEPOT RAPID TRANSIT CO
LOT 2: CHAMKANI BUS DEPOT, PARK & RIDE, TRANS PESHWAR OFFICE AND BRT CONT
%

MONTHLY PROGRESS REPORT


A
c
Date: May 2019 Weather: Sunny 31◦ᴄ ҉ h
i
DPR Ref No: 04 e
v
TOTAL e
Sr. No DESCRIPTION UNIT QTY d

U
p
Dowels with PVC Pipe Each 3,374.68###
t
o
Steel Welded Mesh in Rigid Pavement M2 11,242.00###
M
TUFF TILES M2 a
2,400.00###
y
Kerb stone (18''x6'') M 4,184.28###
Bus Station 00 & Rest/ Toilet Block
BS STRUCTURAL STEEL WORKS SM 2,500.00###

Page 41 of 51
CONSTRUCTION OF BUILDING INFRASTRUCTURE UNDER PESHWAR SUSTAIBALE BUS DEPOT RAPID TRANSIT CORRIDOR PROJECT
LOT 2: CHAMKANI BUS DEPOT, PARK & RIDE, TRANS PESHWAR OFFICE AND BRT CONTROL CENTER

MONTHLY PROGRESS REPORT

Total Executed Upto Executed in April Total Executed Upto % Achieved Upto Feb
March 2020 2020 April 2020 2020

42,054.91 42,054.91 100.00%


31,386.73 31,386.73 100.00%
15,611.22 15,611.22 100.00%
15,611.22 15,611.22 100.00%
5,203.70 2.64 5,206.34 100.00%
15,591.52 27.50 15,619.02 100.00%
10,300.66 105.34 10,406.00 100.00%
14,187.62 45.38 14,233.00 100.00%
10,250.66 155.34 10,406.00 100.00%
14,102.62 130.38 14,233.00 100.00%
1,158.16 1,158.16 98.15%

1,144.54 1,144.54 100.00%


310.31 310.31 100.00%
703.68 703.68 100.00%
311.95 311.95 100.00%
167.84 167.84 100.00%
491.80 491.80 100.00%
86.49 86.49 100.00%

Page 42 of 51
CONSTRUCTION OF BUILDING INFRASTRUCTURE UNDER PESHWAR SUSTAIBALE BUS DEPOT RAPID TRANSIT CORRIDOR PROJECT
LOT 2: CHAMKANI BUS DEPOT, PARK & RIDE, TRANS PESHWAR OFFICE AND BRT CONTROL CENTER

MONTHLY PROGRESS REPORT

Total Executed Upto Executed in April Total Executed Upto % Achieved Upto Feb
March 2020 2020 April 2020 2020

1,000.85 1,000.85 100.00%


4,632.44 19.04 4,651.48 100.00%
4,618.50 32.98 4,651.48 100.00%
1,785.80 14.20 1,800.00 100.00%

4,814.00 4,814.00 100.00%

1,266.75 1,266.75 100.00%

3,698.00 3,698.00 100.00%

427.00 427.00 100.00%

1,356.96 1,356.96 100.00%

1,837.55 1,837.55 100.00%


682.11 682.11 100.00%
3,402.00 3,402.00 100.00%
3,796.00 3,796.00 100.00%
500.00 500.00 100.00%
255.00 255.00 100.00%
5,580.00 5,580.00 100.00%
2,096.00 2,096.00 100.00%
640.00 640.00 100.00%
407.00 407.00 100.00%
54.00 54.00 100.00%
99.32 99.32 100.00%
87.00 87.00 100.00%

Page 43 of 51
CONSTRUCTION OF BUILDING INFRASTRUCTURE UNDER PESHWAR SUSTAIBALE BUS DEPOT RAPID TRANSIT CORRIDOR PROJECT
LOT 2: CHAMKANI BUS DEPOT, PARK & RIDE, TRANS PESHWAR OFFICE AND BRT CONTROL CENTER

MONTHLY PROGRESS REPORT

Total Executed Upto Executed in April Total Executed Upto % Achieved Upto Feb
March 2020 2020 April 2020 2020

85.96 85.96 100.00%

Page 44 of 51
CONSTRUCTION OF BUILDING INFRASTRUCTURE UNDER PESHWAR SUSTAIBALE BUS DEPOT RAPID TRANSIT CORRIDOR PROJECT
LOT 2: CHAMKANI BUS DEPOT, PARK & RIDE, TRANS PESHWAR OFFICE AND BRT CONTROL CENTER

MONTHLY PROGRESS REPORT

Total Executed Upto Executed in April Total Executed Upto % Achieved Upto Feb
March 2020 2020 April 2020 2020

153.23 0.77 154.00 100.00%


1,277.45 0.55 1,278.00 100.00%
10,467.98 46.02 10,514.00 100.00%

16,756.14 16,756.14 100.00%


3,716.87 3,716.87 100.00%
2,538.24 2,538.24 100.00%
320.06 320.06 100.00%
2,696.21 3.79 2,700.00 100.00%
3,500.00 3,500.00 100.00%
6,582.73 151.93 6,734.65 88.66%
2,143.40 2,143.40 97.43%
1,651.00 1,651.00 100.00%
1,338.00 32.00 1,370.00 85.63%

7,495.43 7,495.43 100.00%

2,304.34 2,304.34 100.00%

4,041.00 4,041.00 100.00%

308.21 308.21 100.00%

1,645.00 1,645.00 100.00%

1,726.13 1,726.13 100.00%

375.38 375.38 100.00%


Page 45 of 51
CONSTRUCTION OF BUILDING INFRASTRUCTURE UNDER PESHWAR SUSTAIBALE BUS DEPOT RAPID TRANSIT CORRIDOR PROJECT
LOT 2: CHAMKANI BUS DEPOT, PARK & RIDE, TRANS PESHWAR OFFICE AND BRT CONTROL CENTER

MONTHLY PROGRESS REPORT

Total Executed Upto Executed in April Total Executed Upto % Achieved Upto Feb
March 2020 2020 April 2020 2020

143.50 143.50 100.00%

700.00 700.00 100.00%

Page 46 of 51
CONSTRUCTION OF BUILDING INFRASTRUCTURE UNDER PESHWAR SUSTAIBALE BUS DEPOT RAPID TRANSIT CORRIDOR PROJECT
LOT 2: CHAMKANI BUS DEPOT, PARK & RIDE, TRANS PESHWAR OFFICE AND BRT CONTROL CENTER

MONTHLY PROGRESS REPORT

Total Executed Upto Executed in April Total Executed Upto % Achieved Upto Feb
March 2020 2020 April 2020 2020

1,785.00 1,785.00 100.00%

478.00 478.00 100.00%


4,642.00 4,642.00 100.00%
24,000.00 24,000.00 100.00%
850.00 850.00 100.00%
700.00 700.00 100.00%

348.03 0.97 349.00 100.00%


250.00 250.00 100.00%
250.00 250.00 100.00%
16,000.00 16,000.00 100.00%
140.00 140.00 100.00%
0.50 0.20 0.70 70.00%
0.50 0.20 0.70 70.00%

2,424.00 - 2,424.00 100.00%

400.00 - 400.00 100.00%

250.00 - 250.00 100.00%

1,755.00 45.00 1,800.00 100.00%


128.80 1.20 130.00 100.00%
1,690.00 - 1,690.00 100.00%

Page 47 of 51
CONSTRUCTION OF BUILDING INFRASTRUCTURE UNDER PESHWAR SUSTAIBALE BUS DEPOT RAPID TRANSIT CORRIDOR PROJECT
LOT 2: CHAMKANI BUS DEPOT, PARK & RIDE, TRANS PESHWAR OFFICE AND BRT CONTROL CENTER

MONTHLY PROGRESS REPORT

Total Executed Upto Executed in April Total Executed Upto % Achieved Upto Feb
March 2020 2020 April 2020 2020

1,886.00 1,886.00 100.00%

377.00 377.00 100.00%

144.00 144.00 100.00%

452.00 452.00 100.00%

586.00 586.00 100.00%


166.00 166.00 100.00%
558.00 558.00 100.00%
1,792.51 1,792.51 100.00%
519.79 519.79 100.00%
520.20 520.20 100.00%
1,031.26 1,031.26 100.00%
1,024.00 1,024.00 100.00%
781.00 781.00 100.00%
240.00 240.00 100.00%
66.78 66.78 100.00%
146.36 146.36 99.57%
1,395.31 23.69 1,419.00 100.00%
2,070.40 34.60 2,105.00 100.00%

5,550.43 5,550.43 100.00%

630.22 630.22 100.00%


Page 48 of 51
CONSTRUCTION OF BUILDING INFRASTRUCTURE UNDER PESHWAR SUSTAIBALE BUS DEPOT RAPID TRANSIT CORRIDOR PROJECT
LOT 2: CHAMKANI BUS DEPOT, PARK & RIDE, TRANS PESHWAR OFFICE AND BRT CONTROL CENTER

MONTHLY PROGRESS REPORT

Total Executed Upto Executed in April Total Executed Upto % Achieved Upto Feb
March 2020 2020 April 2020 2020

272.43 272.43 100.00%

1,943.17 1,943.17 100.00%

540.00 540.00 100.00%

2,200.00 2,200.00 100.00%

2,555.01 2,555.01 100.00%

4,304.84 4,304.84 100.00%


- 8.00 8.00 22.86%

407.54 407.54 100.00%

103.33 103.33 100.00%

9.80 9.80 100.00%

73.00 73.00 100.00%

6.20 6.20 100.00%

246.24 30.24 276.48 64.00%

400.00 400.00 100.00%

400.00 400.00 100.00%

4.83 4.83 100.00%

1.15 1.15 100.00%

Page 49 of 51
CONSTRUCTION OF BUILDING INFRASTRUCTURE UNDER PESHWAR SUSTAIBALE BUS DEPOT RAPID TRANSIT CORRIDOR PROJECT
LOT 2: CHAMKANI BUS DEPOT, PARK & RIDE, TRANS PESHWAR OFFICE AND BRT CONTROL CENTER

MONTHLY PROGRESS REPORT

Total Executed Upto Executed in April Total Executed Upto % Achieved Upto Feb
March 2020 2020 April 2020 2020

1,954.00 1,954.00 100.00%

256.00 256.00 100.00%

35.26 35.26 100.00%

33.29 33.29 100.00%

350.00 350.00 100.00%

400.00 400.00 100.00%

601.99 601.99 100.00%

92.39 92.39 100.00%

13.22 13.22 100.00%

207.00 207.00 100.00%

80.00 80.00 100.00%

11,119.69 11,119.69 100.00%

8,630.99 8,630.99 100.00%

4,076.48 4,076.48 100.00%

3,627.15 3,627.15 100.00%

1,660.00 1,660.00 100.00%

3,874.32 11.71 3,886.03 99.57%

Page 50 of 51
CONSTRUCTION OF BUILDING INFRASTRUCTURE UNDER PESHWAR SUSTAIBALE BUS DEPOT RAPID TRANSIT CORRIDOR PROJECT
LOT 2: CHAMKANI BUS DEPOT, PARK & RIDE, TRANS PESHWAR OFFICE AND BRT CONTROL CENTER

MONTHLY PROGRESS REPORT

Total Executed Upto Executed in April Total Executed Upto % Achieved Upto Feb
March 2020 2020 April 2020 2020

3,350.15 10.12 3,360.28 99.57%

11,102.79 101.18 11,203.97 99.66%

2,306.00 36.00 2,342.00 97.58%

3,949.54 62.76 4,012.30 95.89%

2,496.25 2,496.25 99.85%

Page 51 of 51