APQP 3 - 1 Pan Brand Reporter V7c (586) Rev 19
APQP 3 - 1 Pan Brand Reporter V7c (586) Rev 19
APQP 3 - 1 Pan Brand Reporter V7c (586) Rev 19
Revision 1/23/2006
Supplier/Org: RICO AUTO INDUSTRIES LTD. Brand: Jaguar,(Lead = VCC) Part Name: Bracket Ac Servo AW 21
Location: GURGAON , INDIA Model Year / Vehicle: SI6-MY2006_20 Part Number: SI63071158630****
(ST)
(CP)
<SI>
<SC>
<PH>
<PA>
<PR>
<CC>
<LR>
<LS>
<J1>
<FS>
FPDS MILESTONE
( ) Denotes Key Element for
Milestone Responsibility Timing
Volvo Milestone G-1 G0 G1 G2 G5 G6 G7 G8 G10 Issue(s) for Red/Yellow Elements Corrective Action / Resolution Plan
Powertrain Milestone 9 8 7 6 5 4 3 2 1 -1 (summarize the concern & resulting risk) (e.g. revise timing, allocate resources)
5-Dec-02
19-Jun-03
18-Nov-03
18-Nov-03
13-Apr-04
1-Sep-04
1-Mar-05
11-Oct-05
3-Jan-06
3-Jan-06
16-May-06
1-Sep-06
Target
APQP ELEMENT Ford Supplier Open Close
Date
7. ESTA not followed as per Mr. Lars Eric 7,9. TA is not mandatory requirement for Volvo.
1 Sourcing Decision () () () R Y G G G G 9. TA not signed Conformed by Jonas, Volvo Corporation
Jonas Prashant 15-Oct-04 10-Oct-05
11. Run@rate of sub supplier has to be 11. Run@rate of sub supplier demonstrated and Mkj / anil
7 Subcontractor APQP Status () () () () (Y) (Y) (G) (G) G G esatablished established Sharma
15-Oct-04 30-Aug-05
Maninder
10 Prototype Build(s) () (Y) (G) G G G G Volvo to support for Proto Build Rico will support for Proto Build
Singh
15-Oct-04 30-Aug-05
MS / Anil
13 Manufacturing Process Flowchart () R (Y) G G G G SC / CC has to decide sc/cc finalised. CRT agreement signed Petrus
sharma
15-Oct-04 28-Aug-05
Copyright© 2001 Ford Motor Company Page 1 of 49 - APQP Status Report Printed: 05/08/2020
All Rights Reserved
Uncontrolled Copy
474860621.xls ( GYR ratings for elements were automatically copied from respective element worksheets)
Advanced Product Quality Planning Status Report (Pan Brand, Europe)
Revision 1/23/2006
Supplier/Org: RICO AUTO INDUSTRIES LTD. Brand: Jaguar,(Lead = VCC) Part Name: Bracket Ac Servo AW 21
Location: GURGAON , INDIA Model Year / Vehicle: SI6-MY2006_20 Part Number: SI63071158630****
(ST)
(CP)
<SI>
<SC>
<PH>
<PA>
<PR>
<CC>
<LR>
<LS>
<J1>
<FS>
FPDS MILESTONE
( ) Denotes Key Element for
Milestone Responsibility Timing
Volvo Milestone G-1 G0 G1 G2 G5 G6 G7 G8 G10 Issue(s) for Red/Yellow Elements Corrective Action / Resolution Plan
Powertrain Milestone 9 8 7 6 5 4 3 2 1 -1 (summarize the concern & resulting risk) (e.g. revise timing, allocate resources)
5-Dec-02
19-Jun-03
18-Nov-03
18-Nov-03
13-Apr-04
1-Sep-04
1-Mar-05
11-Oct-05
3-Jan-06
3-Jan-06
16-May-06
1-Sep-06
Target
APQP ELEMENT Ford Supplier Open Close
Date
MS / Anil
19 Production Trial Run Y (Y) (G) (G) (G) G 4. OEE analysis has to do . 4. PPAP planned on 23-Mar-06
sharma
15-Oct-04
8. Pp/Ppk study to be done for Additional 8. Pp/Ppk study done for Additional Manufacturing Mkj / Anil
21 Preliminary Process Capability Study Y (Y) (G) (G) G (G) Manufacturing Streem. Streem.
Petrus
Sharma
15-Oct-04 10-Oct-06
22 Production Validation Testing G (G) (G) (G) G G 12.Agreement of PV testing in under process Volvo has no data. Confirmed by Volvo Jonas Prashant 15-Oct-04 28-Aug-05
FORD STA / Maninder
23 Part Submission Warrant (PSW) G (G) (G) (G) (G) (G) () Phase 3 PPAP (PSW) to be sign off Phase 3 PPAP (PSW) demonstrated to Ford STA.
Petrus Singh
15-Oct-05 18-Oct-06
Copyright© 2001 Ford Motor Company Page 2 of 49 - APQP Status Report Printed: 05/08/2020
All Rights Reserved
Uncontrolled Copy
474860621.xls ( GYR ratings for elements were automatically copied from respective element worksheets)
Advanced Product Quality Planning - Builds
Supplier/Org: RICO AUTO INDUSTRIES LTD. Brand: Jaguar,(Lead = VCC) Part Name: Bracket Ac Servo AW 21
MILESTONE / BUILD EVENT INFORMATION
PROGRAM INFORMATION
Location: GURGAON , INDIA Model Year/ Vehicle: SI6-MY2006_20 Part Number: SI63071158630****
(dates will show up on linked APQP Status Report and
individual checklists) ###
Supplier Code: EBL8A FPDS Milestone: <J1> Notice Level: 0
FPDS MILESTONES (KO) <SI> <SC> <PH> <PA> (ST) <PR> (CP) <CC> HTFB <LR> 1PP FEU <LS> CB (J1) <FS> DPV
1 SI6____2006_20_AW _TORSLANDA 5-Dec-02 5-Dec-02 19-Jun-03 18-Nov-03 18-Nov-03 13-Apr-04 1-Sep-04 1-Mar-05 11-Oct-05 3-Jan-06 3-Jan-06 3-Jan-06 3-Jan-06 3-Jan-06 14-Mar-06 16-May-06 1-Sep-06
2 ________________
3 ________________
4 ________________
5 ________________
6 ________________
7 ________________
8 ________________
9 ________________
10 ________________
Vehicle QTY MRD QTY MRD QTY MRD QTY MRD QTY MRD QTY MRD QTY MRD QTY MRD QTY MRD QTY MRD
1 SI6____2006_20_AW _TORSLANDA
2 ________________
3 ________________
4 ________________
5 ________________
6 ________________
7 ________________
8 ________________
9 ________________
10 ________________
QTY MRD QTY MRD QTY MRD QTY MRD QTY MRD QTY MRD QTY MRD QTY MRD QTY MRD QTY MRD
1 SI6____2006_20_AW _TORSLANDA
2 ________________
3 ________________
4 ________________
5 ________________
6 ________________
7 ________________
8 ________________
9 ________________
10 ________________
Vehicle 1 2 3 4 5 6 7 8 9 10
MY2006_20
Part number PSW Date
Notice (change Phase 0 Capacity verification
PMST, Module or 1st OFF tool Run @ Rate Run
Part description Base PMT Comments release
"Chunk" date Phase 1
Prefix Or Complete Suffix number) Interim Phase 3
SI6-
(or Phase 2)
Volvo number Date QTY Date QTY
EXAMPLE
A widget 2S61 AAADF AA Y Y CHA Sub Frame LHD 5dr High series only
Warning Only Use letters and numbers.
If you need to use a seperator please use an underscore ( _ )
Bracket Ac Servo
1 SI6 30711586 30 Y 10-Mar-06 50 23-Mar-06 300 23-Mar-06 18-Oct-06
AW 21
10
11
12
13
14
15
16
17
18
19
20
TEAM INFORMATION
Team Members Company / Role Tel No. Fax No. Email Remarks
Supplier Exec Champion
Ford Exec Champion
IMDS contact
Supplier Exec Champion
Lars- Erik Lindqvist Purchasing - Buyer
Component Design Engineer (Bracket 298
Bjorn Jonsson
)
Vinod Kurup Ford India - STA kvinod@ford.com
Per Saltin Volvo - SQE psaltin@volvocars.com
Maninder Singh Rico / Manufacturing ( Project Leader ) +91-124-2824434 +91-124-2824200 manindersingh@ricoauto.com
Rico / Marketing ( Volvo Account
Prashant Gupta +91-124-2824328 +91-124-2824200 prashantgupta@ricoauto.com
Manager)
MK Jain Quality Assurance (Rico) +91-124-2824412 +91-124-2824200 mkjain@ricoauto.com
D.k. Manjhi Rico Material Planning & Logistics +91-124-2824423 +91-124-2824200 dkmanjhi@ricoauto.com
Rico / Process Engineering &
Rakesh Nagpal +91-124-2824523 +91-124-2824200 rakeshnagpal@ricoauto.com
Development .
Anil Sharma Rico / Development +91-124-2824412 +91-124-2824200 anilsharma@ricoauto.com
Slankar lal Rico / Quality +91-124-2824412 +91-124-2824200 shankarlal@ricoauto.com
Rajeev Gangwar Rico / Engineering- CAD CAM +91-124-2824463 +91-124-2824200 rajeevgangwar@ricoauto.com
SK Sen Rico/ Die Manufacturing +91-124-2824463 +91-124-2824200 sksen@ricoauto.com
Vivek hazari Rico/ volvo Champion +91-124-2824239 +91-124-2824200 vivekhazari@ricoauto.com
Karen Kuhlman Rico -Europe, Account Manager +91-124-2824200 karenkuhlmann03@aol.com
Berndt Johansson Buyer bjohan38@volvocars.com
Jonas Hallerstrom Buyer jhallers@volvocars.com
APQP Element Rating Checklist Sourcing Decision is a formal customer commitment to work with all Internal & External Part
Suppliers, Tooling Suppliers, and Facility Suppliers on the program. Suppliers, and their sub-
1 Sourcing Decision suppliers, should be engaged as early as possible (e.g. by SC) to understand program timing and
requirements. Sourcing Decision should be made with appropriate Quality History & Customer
Current Gate <J1> Input Data.
FPDS Timing Due Dates
<CC>
<SC>
<PH>
<PA>
<PR>
<LR>
<LS>
<FS>
<J1>
Program Supplier
<SI>
(CP)
(ST)
Item Start Target Expectations Issues / Comments / Risks Corrective Actions / Resolution Plan Ford Supplier Open Close
Timing Timing
16-May-06
18-Nov-03
18-Nov-03
19-Jun-03
13-Apr-04
11-Oct-05
5-Dec-02
1-Sep-04
1-Sep-06
1-Mar-05
3-Jan-06
3-Jan-06
APQP Element Rating Checklist Customer Input Requirements are the design criteria and the program requirements necessary to initiate the APQP process. They include Design Goals,
Reliability and Quality Goals, Program Timing, Affordable Cost Targets, Capacity Planning Volumes, Key Contact Personnel, and input requested from &
2 Customer Input Requirements supplied by the Manufacturing Facilities involved. This is done to assure that any current Manufacturing/Process issues are addressed appropriately by the new
Current Gate <J1> design and process, early in the Product Development cycle.
<CC>
<SC>
<PH>
<PA>
<PR>
<LR>
<LS>
<FS>
<J1>
Program Supplier
<SI>
(CP)
(ST)
Item Start Target Expectations Issues / Comments / Risks Corrective Actions / Resolution Plan Ford Supplier Open Close
Timing Timing
APQP Element Rating Checklist Customer Input Requirements are the design criteria and the program requirements necessary to initiate the APQP process. They include Design Goals,
Reliability and Quality Goals, Program Timing, Affordable Cost Targets, Capacity Planning Volumes, Key Contact Personnel, and input requested from &
2 Customer Input Requirements supplied by the Manufacturing Facilities involved. This is done to assure that any current Manufacturing/Process issues are addressed appropriately by the new
Current Gate <J1> design and process, early in the Product Development cycle.
<CC>
<SC>
<PH>
<PA>
<PR>
<LR>
<LS>
<FS>
<J1>
Program Supplier
<SI>
(CP)
(ST)
Item Start Target Expectations Issues / Comments / Risks Corrective Actions / Resolution Plan Ford Supplier Open Close
Timing Timing
Have you loaded 100% of the materials data for all supplied
components in to the international material data system
(IMDS) in accordance with the contractual requirements
agreed at Target Agreement.
Maninder
13. SC CP 1-Mar-05 30-May-05 (Note: This requirement should be fulfilled for components by Y Y G G G G IMDS to be updated by Supplier IMDS Updated 15-Oct-04 10-Jun-05
Singh
the <CP> phase (Volvo Gate5 (G5)) for all programs and
should be updated to reflect any engineering changes for the
life of the component.)
APQP Element Rating Checklist Customer Input Requirements are the design criteria and the program requirements necessary to initiate the APQP process. They include Design Goals,
Reliability and Quality Goals, Program Timing, Affordable Cost Targets, Capacity Planning Volumes, Key Contact Personnel, and input requested from &
2 Customer Input Requirements supplied by the Manufacturing Facilities involved. This is done to assure that any current Manufacturing/Process issues are addressed appropriately by the new
Current Gate <J1> design and process, early in the Product Development cycle.
<CC>
<SC>
<PH>
<PA>
<PR>
<LR>
<LS>
<FS>
<J1>
Program Supplier
<SI>
(CP)
(ST)
Item Start Target Expectations Issues / Comments / Risks Corrective Actions / Resolution Plan Ford Supplier Open Close
Timing Timing
16-May-06
18-Nov-03
18-Nov-03
19-Jun-03
13-Apr-04
11-Oct-05
5-Dec-02
1-Sep-04
1-Sep-06
1-Mar-05
3-Jan-06
3-Jan-06
<CC>
<SC>
<PH>
<PA>
<PR>
<LR>
<LS>
<FS>
<J1>
Program Supplier
<SI>
(CP)
(ST)
Item Start Target Expectations Issues / Comments / Risks Corrective Actions / Resolution Plan Ford Supplier Open Close
Timing Timing
There are NO major Craftsmanship issues/inhibitors, that will
1 KO J1 16-May-06 dd-mmm-yy create an uncontainable risk now or in the foreseeable future G G G G G N.A TO RICO
per preliminary assumptions/product letter.
<CC>
<SC>
<PH>
<PA>
<PR>
<LR>
<LS>
<FS>
<J1>
Program Supplier
<SI>
(CP)
(ST)
Item Start Target Expectations Issues / Comments / Risks Corrective Actions / Resolution Plan Ford Supplier Open Close
Timing Timing
Prepare and sign Engineering Statement of Work for SSL3
15 PH PA 18-Nov-03 dd-mmm-yy components, including Craftsmanship targets. Review the G G G G G N.A TO RICO
ESOW with Global Craftsmanship prior to signing.
Participate and/or support Global Craftsmanship Gateway
16 --- PA 18-Nov-03 dd-mmm-yy G G G G G N.A TO RICO
sign-off process.
Develop and finalize SRI (Surface Required Illustration) and/or
17 SI ST 13-Apr-04 dd-mmm-yy Fit & Finish requirements. SRI/F&F required at Hard Freeze G G G G G N.A TO RICO
per program VPP.
Electronic Math Surface Data (PDN 2) is complete and
18 PA ST 13-Apr-04 dd-mmm-yy G G G G G N.A TO RICO
resides in Metaphase.
Review information in ColorTrax for accuracy and
19 --- ST 13-Apr-04 dd-mmm-yy G G G G G N.A TO RICO
completeness.
Participate and/or support Global Craftsmanship Gateway
20 --- ST 13-Apr-04 dd-mmm-yy G G G G G N.A TO RICO
sign-off process.
Participate/support the implementation of the verification
21 PH PR 1-Sep-04 dd-mmm-yy G G G G G N.A TO RICO
strategy for surface prove-out.
Support the colour Harmony process with pictorials and
22 PA PR 1-Sep-04 dd-mmm-yy G G G G G N.A TO RICO
material/grain/gloss/colour information.
<CC>
<SC>
<PH>
<PA>
<PR>
<LR>
<LS>
<FS>
<J1>
Program Supplier
<SI>
(CP)
(ST)
Item Start Target Expectations Issues / Comments / Risks Corrective Actions / Resolution Plan Ford Supplier Open Close
Timing Timing
16-May-06
18-Nov-03
18-Nov-03
19-Jun-03
11-Oct-05
13-Apr-04
5-Dec-02
1-Sep-04
1-Sep-06
1-Mar-05
3-Jan-06
3-Jan-06
APQP Element Rating Checklist A Design or Concept FMEA is a systematic approach; used by a design responsible team, to
assure that potential design failure modes and their associated causes have been considered and
4 Design Failure Modes and Effects Analysis (DFMEA) addressed. DFMEA's are to be done concurrently with the design process to allow for the
Current Gate <J1> determined Recommended Actions to positively affect the design.
FPDS Timing Due Dates
<CC>
<SC>
<PH>
<PA>
<PR>
<LR>
<LS>
<FS>
<J1>
Program Supplier
<SI>
(CP)
(ST)
Item Start Target Expectations Issues / Comments / Risks Corrective Actions / Resolution Plan Ford Supplier Open Close
Timing Timing
There are NO major DFMEA issues/inhibitors, that will create DFMEA not available with Volvo,
1 SI CC 11-Oct-05 dd-mmm-yy Y G G G G G Volvo to share DFMEA with Rico ###
an uncontainable risk now or in the foreseeable future. Confirmed by Volvo.
APQP Element Rating Checklist A Design or Concept FMEA is a systematic approach; used by a design responsible team, to
assure that potential design failure modes and their associated causes have been considered and
4 Design Failure Modes and Effects Analysis (DFMEA) addressed. DFMEA's are to be done concurrently with the design process to allow for the
Current Gate <J1> determined Recommended Actions to positively affect the design.
FPDS Timing Due Dates
<CC>
<SC>
<PH>
<PA>
<PR>
<LR>
<LS>
<FS>
<J1>
Program Supplier
<SI>
(CP)
(ST)
Item Start Target Expectations Issues / Comments / Risks Corrective Actions / Resolution Plan Ford Supplier Open Close
Timing Timing
16-May-06
18-Nov-03
18-Nov-03
19-Jun-03
13-Apr-04
11-Oct-05
5-Dec-02
1-Sep-04
1-Sep-06
1-Mar-05
3-Jan-06
3-Jan-06
<CC>
<SC>
<PH>
<PA>
<PR>
<LR>
<LS>
<FS>
<J1>
Program Supplier
<SI>
(CP)
(ST)
Item Start Target Expectations Issues / Comments / Risks Corrective Actions / Resolution Plan Ford Supplier Open Close
Timing Timing
Ensure that the APQP Status for all internally supplied, and
ON External Suppliers Documents are under PFMEA, Control Plan , APQP status
4 SI 16-May-06 dd-mmm-yy externally supplied parts/systems is documented and G Y G G G G
GOING review reviewed as per Plan
discussed.
Evaluate all design, functional requirements, and the technical
ON
5 SI 16-May-06 dd-mmm-yy aspects of all other APQP elements (e.g. All other APQP Y Y G G G G O.K , Under Process ( Ongoing Process)
GOING
elements, as appropriate).
ON
6 SI 16-May-06 dd-mmm-yy Participate in appearance and clay reviews, as appropriate. N.A
GOING
Ensure that the Reviews contain data reviews of documents
ON including FMEA's, DVP&R, Government Regulations, Control Document review to be done jointly by
7 SI 16-May-06 dd-mmm-yy Y Y G G G G Review not done
GOING Plans, etc., with an emphasis on a Quality-Of-Event for each VOLVO / RICO --- Team
phase of the design and manufacturing process.
ON Ensure that Government Regulations (e.g. stop ships, recalls, Document review to be done jointly by
8 SI 16-May-06 dd-mmm-yy Y Y G G G G Review not done
GOING etc.) and Campaign issues are reviewed. VOLVO / RICO --- Team
ON Ensure that Serviceability and Repairability concerns are Document review to be done jointly by
9 SI 16-May-06 dd-mmm-yy Y Y G G G G Review not done
GOING reviewed. VOLVO / RICO --- Team
<CC>
<SC>
<PH>
<PA>
<PR>
<LR>
<LS>
<FS>
<J1>
Program Supplier
<SI>
(CP)
(ST)
Item Start Target Expectations Issues / Comments / Risks Corrective Actions / Resolution Plan Ford Supplier Open Close
Timing Timing
16-May-06
18-Nov-03
18-Nov-03
19-Jun-03
13-Apr-04
11-Oct-05
5-Dec-02
1-Sep-04
1-Sep-06
1-Mar-05
3-Jan-06
3-Jan-06
<CC>
<SC>
<PH>
<PA>
<PR>
<LR>
<LS>
<FS>
<J1>
Program Supplier
<SI>
(CP)
(ST)
Item Start Target Expectations Issues / Comments / Risks Corrective Actions / Resolution Plan Ford Supplier Open Close
Timing Timing
Software Statement of Work (SWSOW)
1 PA PA 18-Nov-03 dd-mmm-yy Has a SWSOW including compliance matrix been created &
approved?
Perform ISO/IEC TR 15504 (SPICE) SW process assessment
compliant to Supplier SW Quality Assurance Plan (SSQAP).
2 PA PA 18-Nov-03 dd-mmm-yy Has an assessment been carried out? Have
appropriate SW improvement actions been created and
approved?
Perform 4 different SW Joint Reviews. Have Joint Review 1,
3 PA CC 11-Oct-05 dd-mmm-yy 2, 3 and 4 been carried out? Have minuted actions been
carried out in a timely fashion?
Define project products, processes, schedules, resources, and
4 PH CP 1-Mar-05 dd-mmm-yy responsibilities. Has a SW Development Plan (SWDP) been
created/updated?
Has the SW Development Plan (SWDP) been reviewed and
5 PH CP 1-Mar-05 dd-mmm-yy
approved?
Define project overall SW quality program.
6 PH CP 1-Mar-05 dd-mmm-yy
Has a SW Quality Plan (SWQP) been created/updated?
Has the SW Quality Plan (SWQP) been reviewed and
7 PH CP 1-Mar-05 dd-mmm-yy
approved?
18-Nov-03
19-Jun-03
13-Apr-04
11-Oct-05
5-Dec-02
1-Sep-04
1-Sep-06
1-Mar-05
3-Jan-06
3-Jan-06
<CC>
<SC>
<PH>
<PA>
<PR>
<LR>
<LS>
<FS>
<J1>
Program Supplier
<SI>
(CP)
(ST)
Item Start Target Expectations Issues / Comments / Risks Corrective Actions / Resolution Plan Ford Supplier Open Close
Timing Timing
Define the design-responsible cross-functional team for the Discuss with VOLVO Team DVP&R
development of the DVP including engineering, suppliers, Tracking is being Done by VOLVO as per
2 SI SC 19-Jun-03 dd-mmm-yy G G G G G G
manufacturing, suppliers, etc., as applicable, and list the team plan & status is Green. RICO will be
members or appropriate contact names on the DVP. informed for DVP&R Review
<CC>
<SC>
<PH>
<PA>
<PR>
<LR>
<LS>
<FS>
<J1>
Program Supplier
<SI>
(CP)
(ST)
Item Start Target Expectations Issues / Comments / Risks Corrective Actions / Resolution Plan Ford Supplier Open Close
Timing Timing
16-May-06
18-Nov-03
18-Nov-03
19-Jun-03
13-Apr-04
11-Oct-05
5-Dec-02
1-Sep-04
1-Sep-06
1-Mar-05
3-Jan-06
3-Jan-06
APQP Element Rating Checklist The Subcontractor APQP Status identifies and reports on the condition of an External Supplier or
Subcontractor's APQP process. It is required that Internal suppliers (within Ford) & External
7 Sub-Contractor APQP Status suppliers cascade APQP requirements to their sub-suppliers or sub-contractors, and conduct
Current Gate <J1> APQP reviews as appropriate.
FPDS Timing Due Dates
<CC>
<SC>
<PH>
<PA>
<PR>
<LR>
<LS>
<FS>
<J1>
Program Supplier
<SI>
(CP)
(ST)
Item Start Target Expectations Issues / Comments / Risks Corrective Actions / Resolution Plan Ford Supplier Open Close
Timing Timing
There are NO major Sub-Contractor issues/inhibitors, that will Detailed timing plan on all the equipments Mkj / anil
1 SC LR 3-Jan-06 30-Aug-05 Y G G G G G Timing Plan has made , reviewed 15-Oct-04 30-Aug-05
create an uncontainable risk now or in the foreseeable future. and facilities needed. Sharma
Perform APQP reviews with sub-contractors on a regular Subcontractor APQP reviews done once /
APQP reviews to be documented as per Mkj / anil
7 PA LR 3-Jan-06 30-Aug-05 basis between Milestones, to ensure ongoing communication Y Y G G G G month & Issue Deck is generated with 15-Oct-04 30-Aug-05
plan Sharma
and progress towards completion. suppliers
Use APQP Checklists to assess Quality of Event and
APQP reviews done as per AIAG manual,
8 PA LR 3-Jan-06 dd-mmm-yy determine ratings for each of the APQP Elements identified in G G G G G G
its an ongoing process
the Status Report.
Monitor all sub-supplier PSW dates and report to the customer PSW dates & Report is monitored on the Mkj / anil
10 PR LR 3-Jan-06 30-Aug-05 Y Y G G G G Done 15-Oct-04 30-Aug-05
if any fail to meet the vehicle program timing requirements. monthly basis via detailed Timimg Plan Sharma
Verify that sub-supplier's run-at-rate will meet vehicle program Run@rate of sub supplier has to be Run@rate of sub supplier demonstrated Mkj / anil
11 CC LR 3-Jan-06 30-Aug-05 Y Y G G G G 15-Oct-04 30-Aug-05
requirements for launch, ramp-up and production. esatablished and established Sharma
11. Run@rate of sub supplier has to be 11. Run@rate of sub supplier Mkj / anil
Overall SC LR 3-Jan-06 30-Aug-05 Team's Overall Rating of this Element ( G/Y/R ) Y Y G G G G esatablished demonstrated and established Sharma
15-Oct-04 30-Aug-05
16-May-06
18-Nov-03
18-Nov-03
19-Jun-03
13-Apr-04
11-Oct-05
5-Dec-02
1-Sep-04
1-Sep-06
1-Mar-05
3-Jan-06
3-Jan-06
APQP Element Rating Checklist Facilities, tools, and gauges are those additional, new, refurbished, and relocated resources
required to produce the product at the customer specified quantity and quality levels. Expectations
8 Facilities / Tools / Gauges for this element include but are not limited to planning, statistical and acceptance criteria, lean
Current Gate <J1> manufacturing considerations, qualification of equipment, corrective actions, delivery and setup.
FPDS Timing Due Dates
<CC>
<SC>
<PH>
<PA>
<PR>
<LR>
<LS>
<FS>
<J1>
Program Supplier
<SI>
(CP)
(ST)
Item Start Target Expectations Issues / Comments / Risks Corrective Actions / Resolution Plan Ford Supplier Open Close
Timing Timing
There are NO major Facilities, Tooling, or Gauge
1 SI LR 3-Jan-06 30-Jun-05 issues/inhibitors, that will create an uncontainable risk now or Y G G G G G
in the foreseeable future.
Define the appropriate cross-functional team and process to Under Process Done
identify the Facility, Tooling, and Gauge requirements,
2 SI PA 18-Nov-03 dd-mmm-yy necessary to manufacture the customer specified product at Y Y G G G G
designated quantity and quality levels. (Ref. appropriate
AIAG manuals)
Identify Tooling and Equipment that will be required for the Under Process Done
3 SI PA 18-Nov-03 dd-mmm-yy process with particular emphasis on SC/CC's (e.g. torque, Y Y G G G G
welding, etc).
Identify Test Equipment and Checking Fixtures that will be Under Process Done
required for the process with particular emphasis on SC/CC's
4 SI PA 18-Nov-03 dd-mmm-yy (e.g. torque, welding, etc) and develop a timing plan to Y Y G G G G
support the vehicle program.
Ensure Tooling and Equipment design has provided for a Under Process Done
5 SI PA 18-Nov-03 dd-mmm-yy Flexible System, e.g. Cell Manufacturing, etc. Y Y G G G G
Ensure that Tooling and Equipment design has provided for Under Process Done
6 SI PA 18-Nov-03 dd-mmm-yy Synchronous Material Flow (SMF) and quick change over. Y Y G G G G
Ensure that Tooling and Equipment design has provided for Tooling and Equipment have been made to CPV requirement has to know from Volvo
7 SI PA 18-Nov-03 30-Jun-05 volume fluctuations. Y Y G G G G CPV requirements.
Ensure that Tooling and Equipment design incorporates the Tooling and Equipment design are being Done
MS / Anil
8 SI PA 18-Nov-03 30-Jul-05 recommend actions from the Process FMEA. Y Y G G G G studied to incorporate the reccommnede 15-Oct-04 15-Jul-05
actions from the PFMEA. sharma
Ensure that Tooling and Equipment design has provided for All proecss are being reviewed for Mistake Proofing done for sc/cc MS / Anil 30-Aug-05
9 SI PA 18-Nov-03 30-Jul-05 mistake proofing. Y Y G G G G mistakeproofing. 15-Oct-04
sharma
Obtain agreement of acceptance criteria for tooling and Agreement on the tooling and the Done
MS / Anil
10 SI PA 18-Nov-03 30-Jul-05 equipment between the customer and the supplier of the Y Y G G G G equipmentbetween the customer will be 15-Oct-04 15-Jul-05
equipment. taken from the Ford STA. sharma
Obtain agreement of acceptance criteria for test and checking Agreement on the tooling and the Done
MS / Anil
11 SI PA 18-Nov-03 30-Jun-05 equipment between the customer and the supplier of the Y Y G G G G equipmentbetween the customer will be 15-Oct-04 15-Jul-05
equipment. taken from the Ford STA. sharma
Establish gauge and test and checking equipment feasibility Gauge ,Test checking equipment feasibility Done 30-Aug-05
MS / Anil
12 SI PA 18-Nov-03 30-Jul-05 and accuracy. through Gauge R and R studies. Y G G G G G and accuracy notestablished through R&R . 15-Oct-04
sharma
Ensure that an FMEA has been conducted on all equipment FMEA on Tooling and Equipment not done. Tooling FMEA prepared
MS / Anil
13 SI CC 11-Oct-05 30-Jul-05 and tooling that is new to the process. (Ref. appropriate AIAG Y Y G G G G 15-Oct-04 15-Jul-05
manuals) sharma
Ensure capable gauges are available to run preliminary Gauge review will be conducted to ensure Gauge reviewed conducted to ensure that 30-Aug-05
MS / Anil
14 SI CC 11-Oct-05 30-Jul-05 Process Capability Studies at the tooling and equipment Y G G G G G that capable gauges are available to run capable gauges are available to run 15-Oct-04
supplier's facility. process capability trials. process capability trials. sharma
APQP Element Rating Checklist Facilities, tools, and gauges are those additional, new, refurbished, and relocated resources
required to produce the product at the customer specified quantity and quality levels. Expectations
8 Facilities / Tools / Gauges for this element include but are not limited to planning, statistical and acceptance criteria, lean
Current Gate <J1> manufacturing considerations, qualification of equipment, corrective actions, delivery and setup.
FPDS Timing Due Dates
<CC>
<SC>
<PH>
<PA>
<PR>
<LR>
<LS>
<FS>
<J1>
Program Supplier
<SI>
(CP)
(ST)
Item Start Target Expectations Issues / Comments / Risks Corrective Actions / Resolution Plan Ford Supplier Open Close
Timing Timing
Conduct an initial preliminary Process Capability Study at the Preliminary process capability at the Preliminary process capability done at the 30-Aug-05
tooling and equipment supplier's facility, prior to shipment to suppliers facility is not done .The same will suppliers facility. MS / Anil
15 SI CC 11-Oct-05 30-Jul-05 the customer. (Ref. appropriate AIAG manuals) Y Y G G G G be done at RICO.Timing to be established 15-Oct-04
sharma
Conduct Preliminary Capability Studies at the customer's Preliminary process capability trials will Preliminary process capability done at the MS / Anil 30-Aug-05
16 SI LR 3-Jan-06 30-Jul-05 manufacturing facility. Y Y G G G G beconducted at RICO.Timing plan not suppliers facility. 15-Oct-04
sharma
fixed.
Develop a training plan that ensures training has been Under Process Done
17 SI LR 3-Jan-06 dd-mmm-yy conducted on new/revised tooling and equipment. Y Y G G G G
Ensure setup instructions for new tooling and equipment are Under Process Done
19 SI LR 3-Jan-06 dd-mmm-yy complete and understandable to the user. Y Y G G G G
MS / Anil
9. All proecss are being reviewed for
9. Under Review , Mistake Proofing done sharma /
Overall SI LR 3-Jan-06 30-Jul-05 Team's Overall Rating of this Element ( G/Y/R ) Y Y G G G G mistakeproofing. Petrus 15-Oct-04 30-Aug-05
as per sc/cc Rajiv
Gangwar
16-May-06
18-Nov-03
18-Nov-03
19-Jun-03
13-Apr-04
11-Oct-05
5-Dec-02
1-Sep-04
1-Sep-06
1-Mar-05
3-Jan-06
3-Jan-06
<CC>
<SC>
<PH>
<PA>
<PR>
<LR>
<LS>
<FS>
<J1>
Program Supplier
<SI>
(CP)
(ST)
Item Start Target Expectations Issues / Comments / Risks Corrective Actions / Resolution Plan Ford Supplier Open Close
Timing Timing
Develop the Prototype Build Control Plan using the latest Ford
internal procedures, and/or Section 6 of the AIAG Advanced
3 SC PH 18-Nov-03 dd-mmm-yy Y G G G G G N.A
Product Quality Planning and Control Plan manual, or
Dynamic Control Planning as appropriate.
Review all product characteristics, identifying those required
4 SC ST 13-Apr-04 dd-mmm-yy for the Prototype Build Control Plan, and obtain design G G G G G G N.A
engineering input and concurrence.
16-May-06
18-Nov-03
18-Nov-03
19-Jun-03
13-Apr-04
11-Oct-05
5-Dec-02
1-Sep-04
1-Sep-06
1-Mar-05
3-Jan-06
3-Jan-06
APQP Element Rating Checklist The Prototype Builds element entails the manufacture or assembly of components, sub-systems,
10 Prototype Build systems, or assembled vehicles (e.g. Confirmation Prototype) that will be supplied to the customer
and built prior to the 1PP production trial run.
Current Gate <J1>
FPDS Timing Due Dates
<CC>
<SC>
<PH>
<PA>
<PR>
<LR>
<LS>
<FS>
<J1>
Program Supplier
<SI>
(CP)
(ST)
Item Start Target Expectations Issues / Comments / Risks Corrective Actions / Resolution Plan Ford Supplier Open Close
Timing Timing
16-May-06
18-Nov-03
18-Nov-03
19-Jun-03
13-Apr-04
11-Oct-05
5-Dec-02
1-Sep-04
1-Sep-06
1-Mar-05
3-Jan-06
3-Jan-06
Copyright© 2001 Ford Motor Company Page 24 of 49 - 10. Prototype Build Printed: 05/08/2020
All Rights Reserved Uncontrolled Copy
474860621.xls
Advanced Product Quality Planning - 11. Drawings Specifications
APQP Element Rating Checklist The Drawings & Specifications element is an evaluation of the development of Targets and
Specifications as they are defined to be input to the design process (e.g. VDS/SDS/CDS), and to
11 Drawings and Specifications: Design Information the Drawings (including all engineering drawings, CAD data, material specifications and
Current Gate <J1> engineering specifications.)
FPDS Timing Due Dates
<CC>
<SC>
<PH>
<PA>
<PR>
<LR>
<LS>
<FS>
<J1>
Program Supplier
<SI>
(CP)
(ST)
Item Start Target Expectations Issues / Comments / Risks Corrective Actions / Resolution Plan Ford Supplier Open Close
Timing Timing
There are NO major Drawings and Specification Design not freeze. Decision to be taken for PCR under review.
MS / Anil
1 SI PR 1-Sep-04 30-Jul-05 issues/inhibitors, that will create an uncontainable risk now or G Y G G G G PCR #5 and PCRs (#7 and #8) under VOLVO confirmed for non-availability of Petrus 15-Oct-04
sharma
in the foreseeable future. Discussion these data, Volvo's responsibility.
ENGINEERING DRAWINGS
3 SI PR 1-Sep-04 dd-mmm-yy Identify dimensions that affect fit, function, durability and G G G G G G
customer satisfaction.
MATERIAL SPECIFICATIONS
12 SI PR 1-Sep-04 dd-mmm-yy Identify special material characteristics, (e.g. affected by N.A
temperature, humidity, etc.)
16-May-06
18-Nov-03
18-Nov-03
19-Jun-03
13-Apr-04
11-Oct-05
5-Dec-02
1-Sep-04
1-Sep-06
1-Mar-05
3-Jan-06
3-Jan-06
Copyright© 2001 Ford Motor Company Page 25 of 49 - 11. Drawings & Specifications Printed: 05/08/2020
All Rights Reserved Uncontrolled Copy
474860621.xls
Advanced Product Quality Planning - 12. Team Feasibility Commitment
Team Feasibility determines whether the proposed design can be manufactured within the
APQP Element Rating Checklist guidelines and specifications. A cross-functional design/manufacturing review team is charged
12 Team Feasibility Commitment with assessing design feasibility. Once workability is established, the Program Organization
undertakes the responsibility for the design/manufacturing review process and reassessing
Current Gate <J1> feasibility for any design/part change that may occur.
FPDS Timing Due Dates
<CC>
<SC>
<PH>
<PA>
<PR>
<LR>
<LS>
<FS>
<J1>
Program Supplier
<SI>
(CP)
(ST)
Item Start Target Expectations Issues / Comments / Risks Corrective Actions / Resolution Plan Ford Supplier Open Close
Timing Timing
There are NO major Team Feasibility issues/inhibitors, that
1 SI CC 11-Oct-05 30-Jun-05 will create an uncontainable risk now or in the foreseeable G G G G G G
future.
Define the cross-functional team that will be responsible for
2 SI SC 19-Jun-03 dd-mmm-yy identifying the Feasibility Review Process, and the Program G G G G G G
Team Members that must Sign-Off on all Feasibility Issues.
Ensure that the design allows for the use of efficient material
8 SI PR 1-Sep-04 dd-mmm-yy G G G G G G
handling techniques.
Ensure that the design is considered for ergonomic
9 SI PR 1-Sep-04 dd-mmm-yy manufacturing techniques, and that all issues are resolved G G G G G G
before signoff.
Ensure there is adequate facilities/capability to produce
10 SI CC 11-Oct-05 dd-mmm-yy G G G G G G
product, and consider any potential product/volume changes.
11 SI CC 11-Oct-05 dd-mmm-yy Verify that all WERS concerns are accepted and approved. G G No WERS with RICO
Verify that all engineering actions, and quality/reliability targets Engineering actions , Quality & reliability Engineering actions , Quality & reliability MS / Anil
12 SI CC 11-Oct-05 30-Jun-05 G G G G G G Per saltin 15-Oct-04
have been met and signed off. Targets has not met Targets will be discussed with Volvo Team sharma
13 SI CC 11-Oct-05 dd-mmm-yy Ensure that all WERS concerns are closed. G G No WERS is applicable
Tolerance issues are being discussed in Tolerances will be discussed and finalised
the Issue deck. 12. Engineering actions , Quality & MS / Anil
Overall SI CC 11-Oct-05 30-Jun-05 Team's Overall Rating of this Element ( G/Y/R ) G G G G G G 12. Engineering actions , Quality & reliability Targets discussed with Volvo
Petrus
sharma
15-Oct-04 30-Aug-05
reliability Targets has not met Team
16-May-06
18-Nov-03
18-Nov-03
19-Jun-03
13-Apr-04
11-Oct-05
5-Dec-02
1-Sep-04
1-Sep-06
1-Mar-05
3-Jan-06
3-Jan-06
Copyright© 2001 Ford Motor Company Page 26 of 49 - 12. Team Feasibility Commitment Printed: 05/08/2020
All Rights Reserved Uncontrolled Copy
474860621.xls
Advanced Product Quality Planning - 13. Manufacturing Process Flow Chart
APQP Element Rating Checklist The Manufacturing Process Flow is a graphic representation of the current or proposed sequence
of manufacturing process. The Manufacturing flow chart can be either in the traditional flow chart
13 Manufacturing Process Flow Chart format, or depicted in Cycle Line Layouts, Tooling Line Layouts, Plant Layouts, or other
Current Gate <J1> appropriate types of layouts, providing all necessary information is included or attached.
FPDS Timing Due Dates
<CC>
<SC>
<PH>
<PA>
<PR>
<LR>
<LS>
<FS>
<J1>
Program Supplier
<SI>
(CP)
(ST)
Item Start Target Expectations Issues / Comments / Risks Corrective Actions / Resolution Plan Ford Supplier Open Close
Timing Timing
Develop the new part process flow, using surrogate part Process Flow using surrogate part process
4 SC PA 18-Nov-03 dd-mmm-yy G G G G G G to be send by VOLVO
process flow charts and existing process FMEAs. flow & process FMEA has to develop
Use the current part Design FMEA as an input to develop the Input from DFMEA has to put to develop
5 SC PA 18-Nov-03 dd-mmm-yy R Y G G G G DFMEA has to be send by VOLVO
process flow. the Process Flow
Describe how the product will move within the process (e.g.
7 SC CP 1-Mar-05 dd-mmm-yy Y Y G G G G Process movement has to be decided To be done by RICO as per Timing Plan
roller conveyer, slide, containers).
8 SC CP 1-Mar-05 dd-mmm-yy Create a key for symbols used in the flow chart. Y Y G G G G Flow chart symbols has to decide To be done by RICO as per Timing Plan
16-May-06
18-Nov-03
18-Nov-03
19-Jun-03
13-Apr-04
11-Oct-05
5-Dec-02
1-Sep-04
1-Sep-06
1-Mar-05
3-Jan-06
3-Jan-06
Copyright© 2001 Ford Motor Company Page 27 of 49 - 13. Mfg Process FlowChart Printed: 05/08/2020
All Rights Reserved Uncontrolled Copy
474860621.xls
Advanced Product Quality Planning - 14. Process Failure Mode and Effects Analysis
A Process FMEA is a systematic approach used by a mfg. responsible team to assure that
APQP Element Rating Checklist potential process related failure modes and their associated causes have been addressed and
14 Process Failure Mode and Effects Analysis (PFMEA) resolved.
The Mfg. Process Flow diagrams as well as the Potential SC/Cc's from the DFMEA are used to
Current Gate <J1> ensure that the process is analyzed in the appropriate sequence, with all failure modes addressed.
FPDS Timing Due Dates
<CC>
<SC>
<PH>
<PA>
<PR>
<LR>
<LS>
<FS>
<J1>
Program Supplier
<SI>
(CP)
(ST)
Item Start Target Expectations Issues / Comments / Risks Corrective Actions / Resolution Plan Ford Supplier Open Close
Timing Timing
Identify and list all operation numbers and descriptions from PFMEA includes all the Process operation PFMEA includes all the Process operation MS / Anil
6 SC ST 13-Apr-04 30-Jun-05 G Y G G G G 15-Oct-04 30-Jun-05
the Manufacturing Process Flow sequentially on the PFMEA. number & descriptions of flow number & descriptions of flow sharma
List and describe Failure Modes in physical, technical and all failure Modes are described in Physical all failure Modes will be described in MS / Anil
7 SC ST 13-Apr-04 30-Jun-05 G Y G G G G 15-Oct-04 30-Jun-05
measurable terms. & Technical , measurable terms Physical & Technical , measurable terms sharma
Address the impact of failures as applicable to each of the part, Subsequent operations, system part, Subsequent operations, system
following items: each part, subsequent operation, system, vehicle, customer wants , Government vehicle, customer wants , Government MS / Anil
8 SC ST 13-Apr-04 30-Jun-05 G Y G G G G 15-Oct-04 30-Jun-05
vehicle, customer wants, government regulations and operator Regulations & operator safety included in Regulations & operator safety included in sharma
safety. PFMEA PFMEA
Copyright© 2001 Ford Motor Company Page 28 of 49 - 14. Process FMEA Printed: 05/08/2020
All Rights Reserved Uncontrolled Copy
474860621.xls
Advanced Product Quality Planning - 14. Process Failure Mode and Effects Analysis
A Process FMEA is a systematic approach used by a mfg. responsible team to assure that
APQP Element Rating Checklist potential process related failure modes and their associated causes have been addressed and
14 Process Failure Mode and Effects Analysis (PFMEA) resolved.
The Mfg. Process Flow diagrams as well as the Potential SC/Cc's from the DFMEA are used to
Current Gate <J1> ensure that the process is analyzed in the appropriate sequence, with all failure modes addressed.
FPDS Timing Due Dates
<CC>
<SC>
<PH>
<PA>
<PR>
<LR>
<LS>
<FS>
<J1>
Program Supplier
<SI>
(CP)
(ST)
Item Start Target Expectations Issues / Comments / Risks Corrective Actions / Resolution Plan Ford Supplier Open Close
Timing Timing
For Volvo:
"Identify and list all operation numbers and descriptions from All Operations Numbers & Descriptions
16 SC ST 13-Apr-04 dd-mmm-yy the Manufacturing Process Flow sequentially on the PFMEA, G G G G G G from the Manufacturing Process Flow on will be completed using the philosophy
also including all rework operations as foreseen in the in the the PFMEA
final Process Flow."
12. SC/CC to be decided
12.SC,CC decided ,PFMEA completed. MS / Anil
Overall SC CP 1-Mar-05 30-Jul-05 Team's Overall Rating of this Element ( G/Y/R ) G Y G G G G 13. SC / CC has to include in Control Plans
13.sc/cc included in Control Plan sharma
15-Oct-04 30-Aug-05
16-May-06
18-Nov-03
18-Nov-03
19-Jun-03
13-Apr-04
11-Oct-05
5-Dec-02
1-Sep-04
1-Sep-06
1-Mar-05
3-Jan-06
3-Jan-06
Copyright© 2001 Ford Motor Company Page 29 of 49 - 14. Process FMEA Printed: 05/08/2020
All Rights Reserved Uncontrolled Copy
474860621.xls
Advanced Product Quality Planning - 15. Measurement System Evaluation
<CC>
<SC>
<PH>
<PA>
<PR>
<LR>
<LS>
<FS>
<J1>
Program Supplier
<SI>
(CP)
(ST)
Item Start Target Expectations Issues / Comments / Risks Corrective Actions / Resolution Plan Ford Supplier Open Close
Timing Timing
Check and verify gauges and test equipment for safety and Functionality & safety Check of equipment Functionality & safety Check of equipment Mkj / anil
7 SC CC 11-Oct-05 30-Jul-05 Y Y G G G G 15-Oct-04 30-Aug-05
functionality. & gauges has to be verified & gauges verified Sharma
Check and verify gauges and test equipment for accuracy and Accuracy & linearity of gauges & test Accuracy & linearity of gauges & test Mkj / anil
8 SC CC 11-Oct-05 30-Jul-05 Y Y G G G G 15-Oct-04 30-Aug-05
linearity with adequate discrimination. equipment has to be verified equipment verified Sharma
Check and verify gauges and test equipment for repeatability Repeatability & Reproducbility of gauges & Repeatability & Reproducbility of gauges & Mkj / anil
9 SC CC 11-Oct-05 30-Jul-05 Y Y G G G G 15-Oct-04 30-Aug-05
and reproducibility with adequate discrimination. test equipment has to be verified test equipment verified Sharma
Copyright© 2001 Ford Motor Company Page 30 of 49 - 15. Measurement Sys Evaluation Printed: 05/08/2020
All Rights Reserved Uncontrolled Copy
474860621.xls
Advanced Product Quality Planning - 15. Measurement System Evaluation
<CC>
<SC>
<PH>
<PA>
<PR>
<LR>
<LS>
<FS>
<J1>
Program Supplier
<SI>
(CP)
(ST)
Item Start Target Expectations Issues / Comments / Risks Corrective Actions / Resolution Plan Ford Supplier Open Close
Timing Timing
Perform correlation studies when duplicate gauges and test Correlation studies has to perform in case Mkj / anil
13 SC CC 11-Oct-05 30-Jul-05 Y Y G G G G Done 15-Oct-04 30-Aug-05
equipment exist. of duplicate gauges & tset equipment Sharma
16-May-06
18-Nov-03
18-Nov-03
19-Jun-03
13-Apr-04
11-Oct-05
15. Gauge Instructions & Visual aids
5-Dec-02
1-Sep-04
1-Sep-06
1-Mar-05
3-Jan-06
3-Jan-06
13. Correlation studies has to perform in
prepared to assure a fool proof Production
case of duplicate gauges & tset equipment
15. Gauge Instructions & Visual aids to
assure a fool proof Production
Copyright© 2001 Ford Motor Company Page 31 of 49 - 15. Measurement Sys Evaluation Printed: 05/08/2020
All Rights Reserved Uncontrolled Copy
474860621.xls
Advanced Product Quality Planning - 16. Pre-Launch Control Plan
APQP Element Rating Checklist The Pre-Launch Control Plan is a written description of the dimensional measurements and material and
functional tests (in-process checks) that will occur after the Prototype Builds and before the Production Builds.
16 Pre-Launch Control Plan This plan should include any additional necessary product/process controls until the production process is
validated. Its purpose is to contain potential non-conformances after prototype, but prior to full production (e.g.
Current Gate <J1> 1PP and FEU Builds).
<CC>
<SC>
<PH>
<PA>
<PR>
<LR>
<LS>
<FS>
<J1>
Program Supplier
<SI>
(CP)
(ST)
Item Start Target Expectations Issues / Comments / Risks Corrective Actions / Resolution Plan Ford Supplier Open Close
Timing Timing
Define inspection plans for all material and engineering Inspection Plan for all material &
7 PR CP 1-Mar-05 30-Jul-05 Y Y G G G G Done 30-Aug-05
specifications. Engineering specifications has to be made
Verify gages and test equipment are accurate, repeatable, Gauges & Test Equipement are to be
8 PR CP 1-Mar-05 30-Jul-05 and reproducible with adequate discrimination using the AIAG Y Y G G G G accurate , repetable as per AIAG MSA Done 30-Aug-05
Measurement Systems Analysis (MSA) Handbook. Hand book
Include appropriate inspection sample sizes and frequencies appropriate inspection sample sizes &
9 PR CC 11-Oct-05 30-Jul-05 Y Y G G G G Defined 30-Aug-05
on the Pre-Launch Control Plan. frequencies are included in Pre launch CP.
Give the customer the opportunity to review and approve the Pre launch CP has to send to Customer for MS / Anil
12 PR CC 11-Oct-05 30-Jul-05 Y Y G G G G 15-Oct-04 30-Aug-05
Pre-Launch Control Plan. approval sharma
Copyright© 2001 Ford Motor Company Page 32 of 49 - 16. PreLaunch Control Plan Printed: 05/08/2020
All Rights Reserved Uncontrolled Copy
474860621.xls
Advanced Product Quality Planning - 16. Pre-Launch Control Plan
APQP Element Rating Checklist The Pre-Launch Control Plan is a written description of the dimensional measurements and material and
functional tests (in-process checks) that will occur after the Prototype Builds and before the Production Builds.
16 Pre-Launch Control Plan This plan should include any additional necessary product/process controls until the production process is
validated. Its purpose is to contain potential non-conformances after prototype, but prior to full production (e.g.
Current Gate <J1> 1PP and FEU Builds).
<CC>
<SC>
<PH>
<PA>
<PR>
<LR>
<LS>
<FS>
<J1>
Program Supplier
<SI>
(CP)
(ST)
Item Start Target Expectations Issues / Comments / Risks Corrective Actions / Resolution Plan Ford Supplier Open Close
Timing Timing
Document Pre-Launch processes that are different from the Document Pre launch & Production Pre
13 PR CC 11-Oct-05 30-Jul-05 Y Y G G G G OK 30-Aug-05
intended production process on the Pre-Launch Control Plan. launch CP are different.
4. Review of KPC / KCC
4. Review of KPC / KCC - Done
5. Critical & Significant Characteristics MS / Anil
Overall PR CC 11-Oct-05 30-Jul-05 Team's Overall Rating of this Element ( G/Y/R ) Y Y G G G G parameters has to be defined .
5. Defined
sharma
15-Oct-04 30-Aug-05
6. SC / CC defined in FMEA
6. SC / CC will be defined in FMEA
16-May-06
18-Nov-03
18-Nov-03
19-Jun-03
13-Apr-04
11-Oct-05
5-Dec-02
1-Sep-04
1-Sep-06
1-Mar-05
3-Jan-06
3-Jan-06
Copyright© 2001 Ford Motor Company Page 33 of 49 - 16. PreLaunch Control Plan Printed: 05/08/2020
All Rights Reserved Uncontrolled Copy
474860621.xls
Advanced Product Quality Planning - 17. Operator Process Instructions
<CC>
<SC>
<PH>
<PA>
<PR>
<LR>
<LS>
<FS>
<J1>
Program Supplier
<SI>
(CP)
(ST)
Item Start Target Expectations Issues / Comments / Risks Corrective Actions / Resolution Plan Ford Supplier Open Close
Timing Timing
Include acceptance & rejection criteria for product and Acceptance & Rejection criteria has been MS / Anil
9 CP LR 3-Jan-06 30-Jul-05 G G G G Acceptance & Rejection criteria has made Petrus 15-Oct-04 15-Jul-05
process where appropriate. made sharma
Copyright© 2001 Ford Motor Company Page 34 of 49 - 17. Operator Proc Instructions Printed: 05/08/2020
All Rights Reserved Uncontrolled Copy
474860621.xls
Advanced Product Quality Planning - 17. Operator Process Instructions
<CC>
<SC>
<PH>
<PA>
<PR>
<LR>
<LS>
<FS>
<J1>
Program Supplier
<SI>
(CP)
(ST)
Item Start Target Expectations Issues / Comments / Risks Corrective Actions / Resolution Plan Ford Supplier Open Close
Timing Timing
Use the lessons learned from the 1PP & FEU builds to update
15 LR J1 16-May-06 dd-mmm-yy the process definitions/instructions, and prepare them for use
in production.
Demonstrate compliance to the training plan at each build
phase for the latest level of instructions, including execution of
16 LR J1 16-May-06 dd-mmm-yy
process, measurement equipment and gauges, SPC, etc
(Manufacturing facility responsible).
Ensure that process definitions/instructions are accessible and
17 LR J1+ 16-May-06 dd-mmm-yy visible in the work station area. (Manufacturing facility
responsible)
Ensure that visual aids (e.g. FMVSS, Emission labels etc.) are
18 LR J1+ 16-May-06 dd-mmm-yy visible and accessible in the work station area. (Manufacturing
facility responsible)
16-May-06
18-Nov-03
18-Nov-03
19-Jun-03
13-Apr-04
11-Oct-05
5-Dec-02
1-Sep-04
1-Sep-06
1-Mar-05
3-Jan-06
3-Jan-06
Copyright© 2001 Ford Motor Company Page 35 of 49 - 17. Operator Proc Instructions Printed: 05/08/2020
All Rights Reserved Uncontrolled Copy
474860621.xls
Advanced Product Quality Planning - 18. Packaging Specifications
APQP Element Rating Checklist The supplier of a product must ensure that individual packaging for shipment (including interior
18 Packaging Specifications partitions) is designed and developed. Customer packaging standards or generic packaging
requirements should be used when appropriate.
Current Gate <J1>
FPDS Timing Due Dates
<CC>
<SC>
<PH>
<PA>
<PR>
<LR>
<LS>
<FS>
<J1>
Program Supplier
<SI>
(CP)
(ST)
Item Start Target Expectations Issues / Comments / Risks Corrective Actions / Resolution Plan Ford Supplier Open Close
Timing Timing
Copyright© 2001 Ford Motor Company Page 36 of 49 - 18. Packaging Specifications Printed: 05/08/2020
All Rights Reserved Uncontrolled Copy
474860621.xls
Advanced Product Quality Planning - 18. Packaging Specifications
APQP Element Rating Checklist The supplier of a product must ensure that individual packaging for shipment (including interior
18 Packaging Specifications partitions) is designed and developed. Customer packaging standards or generic packaging
requirements should be used when appropriate.
Current Gate <J1>
FPDS Timing Due Dates
<CC>
<SC>
<PH>
<PA>
<PR>
<LR>
<LS>
<FS>
<J1>
Program Supplier
<SI>
(CP)
(ST)
Item Start Target Expectations Issues / Comments / Risks Corrective Actions / Resolution Plan Ford Supplier Open Close
Timing Timing
16-May-06
18-Nov-03
18-Nov-03
19-Jun-03
13-Apr-04
11-Oct-05
5-Dec-02
1-Sep-04
1-Sep-06
1-Mar-05
3-Jan-06
3-Jan-06
Volvo's responsibility.
Copyright© 2001 Ford Motor Company Page 37 of 49 - 18. Packaging Specifications Printed: 05/08/2020
All Rights Reserved Uncontrolled Copy
474860621.xls
Advanced Product Quality Planning - 18a. Logisitics (VCC Unique)
APQP Element Rating Checklist Logistics is the movement of material or parts from one location to another by the safest, quickest
18a Logistics - VCC and most reliable means available. The location may be internal or external, a building,
department or machine.
Current Gate <J1>
FPDS Timing Due Dates
<CC>
<SC>
<PH>
<PA>
<PR>
<LR>
<LS>
<FS>
<J1>
Program Supplier
<SI>
(CP)
(ST)
Item Start Target Expectations Issues / Comments / Risks Corrective Actions / Resolution Plan Ford Supplier Open Close
Timing Timing
D K Manjhi
There are NO major Logistics issues/inhibitors, that will create Rico to understand the requirements &
1 PA LS 3-Jan-06 30-Jul-05 Y Y Y G G G Rico to understand the Requirements Akinla / Prashant 15-Oct-04
an uncontainable risk now or in the foreseeable future. completed as per Timing Plan
Gupta
D K Manjhi
6 CP LR 3-Jan-06 30-Jul-05 Ensure that EDI is used for all deliveries including preseries. Y Y Y G G G Rico to ensure To be ensured Akinla / Prashant 15-Oct-04
Gupta
Copyright© 2001 Ford Motor Company Page 38 of 49 - 18a. VCC Unique Logistics Printed: 05/08/2020
All Rights Reserved Uncontrolled Copy
474860621.xls
Advanced Product Quality Planning - 18a. Logisitics (VCC Unique)
APQP Element Rating Checklist Logistics is the movement of material or parts from one location to another by the safest, quickest
18a Logistics - VCC and most reliable means available. The location may be internal or external, a building,
department or machine.
Current Gate <J1>
FPDS Timing Due Dates
<CC>
<SC>
<PH>
<PA>
<PR>
<LR>
<LS>
<FS>
<J1>
Program Supplier
<SI>
(CP)
(ST)
Item Start Target Expectations Issues / Comments / Risks Corrective Actions / Resolution Plan Ford Supplier Open Close
Timing Timing
D K Manjhi
Ensure that distribution of empty packaging have been set up,
25 CP LR 3-Jan-06 30-Jul-05 Y Y Y G G G To be ensured will be ensured by Rico as per Plan Akinla / Prashant 15-Oct-04
agreement (standard packaging), booking routines.
Gupta
D K Manjhi
Ensure capacity for loading and unloading and protected from
26 CP LR 3-Jan-06 30-Jul-05 Y Y Y G G G To be ensured will be ensured by Rico as per Plan Akinla / Prashant 15-Oct-04
wind and rain.
Gupta
D K Manjhi
Ensure that despatch frequency, despatch days and window
27 CP LR 3-Jan-06 30-Jul-05 Y Y Y G G G To be ensured will be ensured by Rico as per Plan Akinla / Prashant 15-Oct-04
are established with VCC.
Gupta
D K Manjhi
Verify that the DESADV is sent within one hour after transport
28 CP LR 3-Jan-06 30-Jul-05 Y Y Y G G G Verification of DESADV will be ensured by Rico as per Plan Akinla / Prashant 15-Oct-04
departure.
DK Gupta
Manjhi
29 CP LR 3-Jan-06 dd-mmm-yy Develop strategy for transportation of Dangerous goods G G G N.A. / Prashant
DK Gupta
Manjhi
Ensure the ability to handle daily despatches in accordance to
30 CP LR 3-Jan-06 30-Jul-05 Y Y Y G G G Time table has to be decided to be done Akinla / Prashant 15-Oct-04
a by VCC pre-set time table.
Gupta
D K Manjhi
Ensure that ordering routines at Lead Logistics Provider have
31 CP LR 3-Jan-06 30-Jul-05 Y Y Y G G G To be ensured will be ensured by Rico as per Plan Akinla / Prashant 15-Oct-04
been established.
Gupta
D K Manjhi
Ensure label position according to Odette standard and
32 CP LR 3-Jan-06 30-Jul-05 Y Y Y G G G To be ensured will be ensured by Rico as per Plan Akinla / Prashant 15-Oct-04
fixation of label without staples in the bar code.
Gupta
D K Manjhi
Ensure that normal transport and rush transport instruction
33 CP LR 3-Jan-06 30-Jul-05 Y Y Y G G G To be ensured will be ensured by Rico as per Plan Akinla / Prashant 15-Oct-04
have been confirmed.
Gupta
D K Manjhi
Ensure packaging set up. Packaging defined and verified. Unit
34 CP LR 3-Jan-06 30-Jul-05 Y Y Y G G G To be ensured will be ensured by Rico as per Plan Akinla / Prashant 15-Oct-04
load updated, packaging instruction produced and confirmed.
Gupta
D K Manjhi
Rico to understand the Volvo specific
Overall 3-Jan-06 30-Jul-05 Team's Overall Rating of this Element ( G/Y/R ) Y Y Y G G G Logistics Requirements
Rico will ensure it as per plan Akinla / Prashant 15-Oct-04
Gupta
16-May-06
18-Nov-03
18-Nov-03
19-Jun-03
13-Apr-04
11-Oct-05
5-Dec-02
1-Sep-04
1-Sep-06
1-Mar-05
3-Jan-06
3-Jan-06
Copyright© 2001 Ford Motor Company Page 39 of 49 - 18a. VCC Unique Logistics Printed: 05/08/2020
All Rights Reserved Uncontrolled Copy
474860621.xls
Advanced Product Quality Planning - 19. Production Trial Run (Internal and External Suppliers)
APQP Element Rating Checklist The Production Trial Run is a validation of the effectiveness of the manufacturing and assembly
process, using production tooling, equipment, environment (including production operators),
19 Production Trial Run - Internal & External Suppliers facilities and cycle times. Output of the Production Trial Run is used for Production Part Approval
Current Gate <J1> for the manufacturer.
FPDS Timing Due Dates
<CC>
<SC>
<PH>
<PA>
<PR>
<LR>
<LS>
<FS>
<J1>
Program Supplier
<SI>
(CP)
(ST)
Item Start Target Expectations Issues / Comments / Risks Corrective Actions / Resolution Plan Ford Supplier Open Close
Timing Timing
MS / Anil
7 CP LR 3-Jan-06 30-Jul-05 Conduct Production Trial Run using production packaging. Y G G G Production Packaging has to finalise Packaging Discussion under Process Akinla 15-Oct-04 28-Aug-05
sharma
Conduct Production Trial Run producing latest engineering
8 CP LR 3-Jan-06 dd-mmm-yy G G G G
level PSW-1 parts.
MS / Anil
Overall CP LS 3-Jan-06 30-Jul-05 Team's Overall Rating of this Element ( G/Y/R ) Y Y G G G G 4. OEE analysis has to do . 4. PPAP planned on 23-Mar-06
sharma
15-Oct-04
16-May-06
18-Nov-03
18-Nov-03
19-Jun-03
13-Apr-04
11-Oct-05
5-Dec-02
1-Sep-04
1-Sep-06
1-Mar-05
3-Jan-06
3-Jan-06
Copyright© 2001 Ford Motor Company Page 40 of 49 - 19. Prod'n Trial Run - Supplier Printed: 05/08/2020
All Rights Reserved Uncontrolled Copy
474860621.xls
Advanced Product Quality Planning - 19. Production Trial Run (Ford Assembly Plant)
APQP Element Rating Checklist The Production Trial Run is a validation of the effectiveness of the manufacturing and assembly
process, using production tooling, equipment, environment (including production operators),
19 Production Trial Run - Ford Assembly Plant facilities and cycle times. Output of the Production Trial Run is used for Production Part Approval
Current Gate <J1> for the manufacturer, and "Open-To-Go" review for Assembly.
FPDS Timing Due Dates
<CC>
<SC>
<PH>
<PA>
<PR>
<LR>
<LS>
<FS>
<J1>
Program Supplier
<SI>
(CP)
(ST)
Item Start Target Expectations Issues / Comments / Risks Corrective Actions / Resolution Plan Ford Supplier Open Close
Timing Timing
16-May-06
18-Nov-03
18-Nov-03
19-Jun-03
13-Apr-04
11-Oct-05
5-Dec-02
1-Sep-04
1-Sep-06
1-Mar-05
3-Jan-06
3-Jan-06
Copyright© 2001 Ford Motor Company Page 41 of 49 - 19. Prod'n Trial Run - Ford Printed: 05/08/2020
All Rights Reserved Uncontrolled Copy
474860621.xls
Advanced Product Quality Planning - 20. Production Control Plan (Internal and External Suppliers)
<CC>
<SC>
<PH>
<PA>
<PR>
<LR>
<LS>
<FS>
<J1>
Program Supplier
<SI>
(CP)
(ST)
Item Start Target Expectations Issues / Comments / Risks Corrective Actions / Resolution Plan Ford Supplier Open Close
Timing Timing
Copyright© 2001 Ford Motor Company Page 42 of 49 - 20. Prod'n Ctrl Plan - Supplier Printed: 05/08/2020
All Rights Reserved Uncontrolled Copy
474860621.xls
Advanced Product Quality Planning - 20. Production Control Plan (Internal and External Suppliers)
<CC>
<SC>
<PH>
<PA>
<PR>
<LR>
<LS>
<FS>
<J1>
Program Supplier
<SI>
(CP)
(ST)
Item Start Target Expectations Issues / Comments / Risks Corrective Actions / Resolution Plan Ford Supplier Open Close
Timing Timing
16-May-06
18-Nov-03
18-Nov-03
19-Jun-03
13-Apr-04
11-Oct-05
5-Dec-02
1-Sep-04
1-Sep-06
1-Mar-05
3-Jan-06
3-Jan-06
Copyright© 2001 Ford Motor Company Page 43 of 49 - 20. Prod'n Ctrl Plan - Supplier Printed: 05/08/2020
All Rights Reserved Uncontrolled Copy
474860621.xls
Advanced Product Quality Planning - 20. Production Control Plan (Ford Assembly Plant)
<CC>
<SC>
<PH>
<PA>
<PR>
<LR>
<LS>
<FS>
<J1>
Program Supplier
<SI>
(CP)
(ST)
Item Start Target Expectations Issues / Comments / Risks Corrective Actions / Resolution Plan Ford Supplier Open Close
Timing Timing
Copyright© 2001 Ford Motor Company Page 44 of 49 - 20. Prod'n Ctrl Plan - Ford Printed: 05/08/2020
All Rights Reserved Uncontrolled Copy
474860621.xls
Advanced Product Quality Planning - 20. Production Control Plan (Ford Assembly Plant)
<CC>
<SC>
<PH>
<PA>
<PR>
<LR>
<LS>
<FS>
<J1>
Program Supplier
<SI>
(CP)
(ST)
Item Start Target Expectations Issues / Comments / Risks Corrective Actions / Resolution Plan Ford Supplier Open Close
Timing Timing
16-May-06
18-Nov-03
18-Nov-03
19-Jun-03
13-Apr-04
11-Oct-05
5-Dec-02
1-Sep-04
1-Sep-06
1-Mar-05
3-Jan-06
3-Jan-06
Copyright© 2001 Ford Motor Company Page 45 of 49 - 20. Prod'n Ctrl Plan - Ford Printed: 05/08/2020
All Rights Reserved Uncontrolled Copy
474860621.xls
Advanced Product Quality Planning - 21. Preliminary Process Capability
APQP Element Rating Checklist The Preliminary Process Capability study is a statistical assessment of the ability of the process to
21 Preliminary Process Capability produce product within specification. Refer to the AIAG Production Part Approval Process (PPAP)
manual for more details concerning the Preliminary Process Capability Study.
Current Gate <J1>
FPDS Timing Due Dates
<CC>
<SC>
<PH>
<PA>
<PR>
<LR>
<LS>
<FS>
<J1>
Program Supplier
<SI>
(CP)
(ST)
Item Start Target Expectations Issues / Comments / Risks Corrective Actions / Resolution Plan Ford Supplier Open Close
Timing Timing
16-May-06
18-Nov-03
18-Nov-03
19-Jun-03
13-Apr-04
11-Oct-05
5-Dec-02
1-Sep-04
1-Sep-06
1-Mar-05
3-Jan-06
3-Jan-06
Copyright© 2001 Ford Motor Company Page 46 of 49 - 21. Prelim Process Capability Printed: 05/08/2020
All Rights Reserved Uncontrolled Copy
474860621.xls
Advanced Product Quality Planning - 22. Product Validation Testing (Internal and External Supplier)
APQP Element Rating Checklist Production Validation Testing refers to engineering testing which validates that products made from
production tools and processes meet engineering standards/specifications. All Internal and
22S Production Validation Testing - Internal & External Suppliers External Suppliers to Ford are to complete Production Validation Testing as a requirement of the
Current Gate <J1> Part Submission Warrant (PSW).
FPDS Timing Due Dates
<CC>
<SC>
<PH>
<PA>
<PR>
<LR>
<LS>
<FS>
<J1>
Program Supplier
<SI>
(CP)
(ST)
Item Start Target Expectations Issues / Comments / Risks Corrective Actions / Resolution Plan Ford Supplier Open Close
Timing Timing
16-May-06
18-Nov-03
18-Nov-03
19-Jun-03
13-Apr-04
11-Oct-05
5-Dec-02
1-Sep-04
1-Sep-06
1-Mar-05
3-Jan-06
3-Jan-06
Copyright© 2001 Ford Motor Company Page 47 of 49 - 22. PV Testing - Supplier Printed: 05/08/2020
All Rights Reserved Uncontrolled Copy
474860621.xls
Advanced Product Quality Planning - 22. Product Validation Testing (Ford Assembly Plant)
<CC>
<SC>
<PH>
<PA>
<PR>
<LR>
<LS>
<FS>
<J1>
Program Supplier
<SI>
(CP)
(ST)
Item Start Target Expectations Issues / Comments / Risks Corrective Actions / Resolution Plan Ford Supplier Open Close
Timing Timing
16-May-06
18-Nov-03
18-Nov-03
19-Jun-03
13-Apr-04
11-Oct-05
5-Dec-02
1-Sep-04
1-Sep-06
1-Mar-05
3-Jan-06
3-Jan-06
Copyright© 2001 Ford Motor Company Page 48 of 49 - 22. PV Testing - Ford Printed: 05/08/2020
All Rights Reserved Uncontrolled Copy
474860621.xls
Advanced Product Quality Planning - 23. Part Submission Warrant
Production Part Approval Process is the documented verification that the Internal or
APQP Element Rating Checklist External supplier meets all engineering design requirements and the process has the
23 Part Submission Warrant (PSW) capability to meet these requirements during an actual production run. The Part
Submission Warrant (PSW) is the final sign-off that the Production Part Approval Process
Current Gate <J1>
(PPAP) has been followed.
FPDS Timing Due Dates
<CC>
<SC>
<PH>
<PA>
<PR>
<LR>
<LS>
<FS>
<J1>
Program Supplier
<SI>
(CP)
(ST)
Item Start Target Expectations Issues / Comments / Risks Corrective Actions / Resolution Plan Ford Supplier Open Close
Timing Timing
16-May-06
18-Nov-03
18-Nov-03
19-Jun-03
13-Apr-04
11-Oct-05
5-Dec-02
1-Sep-04
1-Sep-06
1-Mar-05
3-Jan-06
3-Jan-06
Copyright© 2001 Ford Motor Company Page 49 of 49 - 23. Part Submission Warrant Printed: 05/08/2020