Bridge Part (A) : SL Item of Work Unit Qty Rate Amount Cl. No. of
Bridge Part (A) : SL Item of Work Unit Qty Rate Amount Cl. No. of
ESTIMATE (Based on SOR for RURAL ROADS FOR THE YEAR 2019-20)
1 2 3 4 5 6 7
Bridge Part(A)
1.17/13 Labour for dismantling all members of RM 72.00 1429.00 102887.86
the timber bridge (except piles) and
stacking them at suitable places as
directed (all members will be under
custody of the contractor till taken over
by the Department.) scarfing and
joining piles 25cm to 30cm dia d Dismantling Rs 102887.86
2./12.01 Earth work in excavation of foundation Cum 978.81 142.38 139363.10
of structures as per drawings &
technical specifications, including
setting
3./12.09 Well out, construction of shoring and
Foundation Each 2.00 165574.61 331149.21
bracing, removal ofProviding
stumps and
and other
constructing temporary
deleterious matter, Island 12
dressing of msides
diameter for
and bottomand construction of
andconstructing well
back fillingone
wit span
3A./12.09 Providing RM 50.00 4701.93 235096.50
foundation
service roadforto8reach
m diaisland
well.complete
location as
per clause 1200 of MORTH
from one pier location to another pier
specifications.
4./12.10 location
Providing and laying of cutting edge of MT 4.68 124303.39 581739.87
mild steel weighing 40 K.G. per meter
for Well foundation complete as perv
5./12.11 drawing and as perCement
Plain / Reinforced clause 1200 &1900
concrete, in 0.00
of MORTH specifications .
well foundationcomplete as perdrawing
and as per clause 1200 , 1500 & 1700
of
A. MORTH specifications.
Well Curb 10612.96
I)
RCC M - 25 grade Cum 69.54 737,973.66
Case - I : Using
B. Well steining 9728.17
concrete mixer. III) RCC M- 25
grade Cum 1,270.70 12,361,553.44
C.Case I : Using
Bottom Plug concrete mixer.
Concrete to be
placed using tremie pipe.
II) PCC grade M-20 Case - I : Cum 230.13 9,176.73 2,111,883.40
Using concrete mixer.
D. Intermediate plug
1645.28