CONSTRUCTION OF RCC BRIDGE NO 1/1 ON Balijuri to Salmara Road Under PMGSY for the year 2019-20

ESTIMATE (Based on SOR for RURAL ROADS FOR THE YEAR 2019-20)

Sl Item of work Cl. No. of Unit Qty Rate Amount

No. MORT & (in Rs.) (in Rs.)


H’s
specification

1 2 3 4 5 6 7
Bridge Part(A)
1.17/13 Labour for dismantling all members of RM 72.00 1429.00 102887.86
the timber bridge (except piles) and
stacking them at suitable places as
directed (all members will be under
custody of the contractor till taken over
by the Department.) scarfing and
joining piles 25cm to 30cm dia d Dismantling Rs 102887.86
2./12.01 Earth work in excavation of foundation Cum 978.81 142.38 139363.10
of structures as per drawings &
technical specifications, including
setting
3./12.09 Well out, construction of shoring and
Foundation Each 2.00 165574.61 331149.21
bracing, removal ofProviding
stumps and
and other
constructing temporary
deleterious matter, Island 12
dressing of msides
diameter for
and bottomand construction of
andconstructing well
back fillingone
wit span
3A./12.09 Providing RM 50.00 4701.93 235096.50
foundation
service roadforto8reach
m diaisland
well.complete
location as
per clause 1200 of MORTH
from one pier location to another pier
specifications.
4./12.10 location
Providing and laying of cutting edge of MT 4.68 124303.39 581739.87
mild steel weighing 40 K.G. per meter
for Well foundation complete as perv
5./12.11 drawing and as perCement
Plain / Reinforced clause 1200 &1900
concrete, in 0.00
of MORTH specifications .
well foundationcomplete as perdrawing
and as per clause 1200 , 1500 & 1700
of
A. MORTH specifications.
Well Curb 10612.96
I)
RCC M - 25 grade Cum 69.54 737,973.66
Case - I : Using
B. Well steining 9728.17
concrete mixer. III) RCC M- 25
grade Cum 1,270.70 12,361,553.44
C.Case I : Using
Bottom Plug concrete mixer.
Concrete to be
placed using tremie pipe.
II) PCC grade M-20 Case - I : Cum 230.13 9,176.73 2,111,883.40
Using concrete mixer.
D. Intermediate plug

II) PCC grade M - 25 Cum 0.00 9,117.97 0.00


E. Top plug Case - I :
using concrete mixer. III) PCC grade M-
15 Cum 34.88 7,363.08 256,835.94
F. Well CapCase - I : using concrete
mixer.
Cum 179.81 9,174.47 1,649,651.10
I) RCC M - 25 grade
6./12.12 Sinking of 6 m external diameter Well 0.00
throgh all types of soil ( other than
pneumatic method of sinking ) complete
as per Drawing
soil as per MORTH Section
A. Sandy 0.00
No. 1200 .
I) Depth below Bed level up to 3.0m 6238.73
Metre 6.00 37,432.38
II) Beyond 3.0 m upto 10.0 m 8976.72
Metre 14.00 125,674.08
III) Additional depth beyond 10 m up to 11855.96
20 m Metre 20.00 237,119.20
IV) Additional depth beyond 20 m up to 22238.40
30 m Metre 2.01 44,692.52
B. Clayey soil 0.00
I) Depth below Bed level up to 3.0m 0.00
Metre 0.00 0.00
II) Beyond 3.0 m upto 10.0 m 0.00
Metre 0.00 0.00
III) Additional depth beyond 10 m up to 0.00
20 m Metre 0.00 0.00
IV) Additional depth beyond 20 m up to 0.00
30 m Metre 0.00 0.00
7./12.13 Sinking of 7m external diameter Well 0.00
throgh all types of soil ( other than
pneumatic
A. Sandy soil method of sinking ) complete 0.00
as per Drawing as per MORTH Section
I)
No.Depth
1200below
. Bed level up to 3.0m Metre 6.00 9420.81 56,524.86
II) Beyond 3.0 m upto 10.0 m Metre 14.00 12893.30 180,506.20
III) Additional depth beyond 10 m up to Metre 20.00 17026.84 340,536.80
20 m
IV) Additional depth beyond 20 m up to Metre 6.01 31937.19 191,932.94
30 m
8./12.21 Sand Filling in Well complete as per 1641.89
drawing and as per Technical
Specification as per MORTH Section cum 1,330.17 2,183,998.17
No. 1207 .
9./12.40 Supplying, fitting and placing un- 76279.52
coated TMT bar reinforcement in
foundation complete as per drawing 1600 MT 64.68 4934120.75
and technical
10./12.41 Supplying, specification
fitting and placing uncoated 14175.85
(Refersteel
mild to reinforcement
quantity estimation)(TATA
in foundation
complete
MAKE TMT as per drawing and Technical
REBAR) MT 0.00 0.00
Specifications as per MORTH Section
No. 1600 Total for Foundadation Rs. 26,737,784.1
11./13.5 Plain/Reinforced Cement concrete, in 1500,170
Substructure complete as per Drawing 0,
and Technical Specifications 2200 Cum 232.90 9728.17 2265707.29
F. RCC Grade
12./13.6 Supplying, M 25
fitting and placing TMT bar Section
(p).Height up tocomplete
reinforcement 5.0 m to in
10M
substructure 1600 &
Case – I : as
complete Using
per Concrete
drawing Mixer
and technical 2200 MT 23.83 76436.59 1821619.90
13./13.6 specification
Supplying, fitting and placing uncoated
(Refer
mild to quantity
steel estimation)
reinforcement in Substructure
complete as per drawing and Technical MT 0.00 70675.85 0.00
14/.17.49 Specifications
Providing as perholes
weep MORTH
in Section
Brick
No. 1600
masonry/Plain/Reinforced concrete
abutment, wing wall/return wall with 100 Each 36.00 226.00 8136.00
mm dia AC pipe, extending through the full
23./13.14 Supplying, fitting with
width of the structure andslope
fixing in
of 1V :20H
towards
position drawing
true foce. Complete
to line and aslevel
per 2000,
drawing and Technical
elastomeric bearings conforming to 2200 Cucm 320760.00 4.31 1380968.03
IRC : 83 (Pt. II) Section IX and Clause
2005 of MoRT &H Specifications
complete including all accessories as
per drawing and Technical
Specifications.
21./13,09 Back filling behind Abutment , Wing 710.1.4 of
Wall and return wall complete as per IRC 78 &
drawing and Technical specification 2200 Cum 278.92 0.00 0.00
Granular material

278.92 1644.15 458586.32


Sandy material

1645.28

Total for substructure Rs. 5935017.54


14./14.1 Furnishing and placing reinforced / 1500,160
Prestressed cement concrete in 0
superstructure as per drawing and & 1700 Cum 343.50 11438.99 3929293.07
Technical Specifications.
15./14.2 Supplying, fitting and placing TMT bar
RCC Grade M 25, complete
reinforcement in
Case - I : Usingcomplete
superstructure ConcreteasMixer
per drawing MT 52.76 77484.10 4088254.83
II)
and T-beam &
technical slab
specification
16./14.3 High tensile steel wires/ strands
(a) Height
(Refer uptoacessories
to quantity
including all 5mestimation)
for stressing,
(Refer to quantity
stressing operations and grouting 1800 MT 0.00 134745.72 0.00
complete as per drawing
(Refer to quantity and Technical
estimation)
Specifications.
15604.17
17./14.04 Providing and laying cement concrete
wearing coat M 30 grade including
reinforcement complete as per drawing 2702 Cum 42.82 2387.69 102234.92
and TechnicalofSpecifications
18./14.07 Construction pre cast RCC railing of
(ReferGrade
M30 to quantity
in situestimation)
with 20 mm nominal
size aggregate, true to line and grade, RM 167.04 1692.74 282755.29
19 toleranceJoint
Burried of vertical
(ProvidingRCCand postlaying
not toa
exceed 1expansion
burried in 500 center to expansion
joint, center spacinggap
between
being 20mm,vertical
coveredpostwithnot12mm
to exceed
thick, 2604 Rm 0.00 4859.00 0.00
20 2000
200mm mm wide
Providing leaving adequat
and galvanised
fixing 2mm wieldable
thick
structural steel plate as
corrugated copper plate in expansion per IS:2062,
placed symmetrical
joint complete asto per
centredrawing
line of the
& 2605 Rm 0.00 410.19 0.00
21 join, resting freely
Technical Specification
Providing over the
and fixing 20mm thick
(Refer to quantity
compressible fibreestimation)
board in expansion
joint complete as per drawing & 2605 Rm 30.00 21192.02 635760.60
Technical Specification .
19./14.22 Providing and and laying of a strip seal
expansion joint catering to maximum
horizontal movement upto 70mm, RM 30.00 0.00 0.00
complete
27./12.37 Pile as per
load test approved
on single verticaldrawings
pile in
and standard
accordance specificatons to be
with IS:2911(Part-IV)
installed
a) by the
Initial and manufacturer
routine load test / supplier
or theirtoauthorised representative e 1100 MT 0.00 330.00 0.00
(Refer quantity estimation)
20./13.11 Supplying, fitting, and fixing in
position true to line and level cast steel
rocker bearing conforming to IRC:83
tonne 733.00 0.00
(Pt.-1) section IX and clause 2003 of
21./13.12 Supplying,
MoRTH fitting, and fixing
specifications completein
position
includingtrue to line andas level
all accessories forged
per drawing 2000,100
steel roller bearing
and Technical conforming to
Specifications. 0 & 2201 tonne 633.00 0.00
IRC:83 (Pt.-1) section IX and clause
22./14.9 Drainage
2003 of spouts MoRTH complete as per
specifications
approved drawings and
complete including all accessories as technical
specifications.
per drawing and Technical 2705 Each 32 8615.00 275680.00
(Refer to quantity estimation)
Specifications.
23./14.11 Reinforced cement concrete Approach 1500,
Slab including reinforcement and form 1600,
work complete as per drawing and 1700&
technical specification . 2704 Cum 13382.00 0.00
Total for Superstructure Rs 9313978.70
Sub Total of Bridge Part (A) = 42089668.20
Protection work:(B)
24./15.04 Providing and laying pitching on slopes
laid over prepared filter media
including boulder apron laid dry in 2504 Cum 611.68 4180.50 2557112.82
25./15.05 front of toe and
Providing of embankment complete
laying filter as
material
per drawing and technical
underneath pitching in slopes as per
specifications
drawing and technical specifications. 2504 Cum 305.84 4490.94 1373500.81
26./15.01 A. Stone/Boulder
(Qty
Providingas per
and statement of Protection
laying boulders with
(Qty ) as peron statement
work crates
wire of Protection
river bed for protection
work ) scour with stone boulders
against 2503 Cum 304.14 5114.90 1555635.54
weighing not less than 40 kg each Sub Total of Protection Work (B) =
complete as per drawing and Technical 5486249.16
specification . Grand Total (A+B) =
47575917.36
Say, Rs. 47575917.00

Asst. Executive Engineer , PWD Executive Engineer , PWD


Jagiroad State Road Sub Division Nawgaon State Road Division
Nawgaon Nawgaon