10 Maintenance in Steel Industry - Tomas Berglund Kelly Berg - Final
10 Maintenance in Steel Industry - Tomas Berglund Kelly Berg - Final
10 Maintenance in Steel Industry - Tomas Berglund Kelly Berg - Final
steel industry
Kelly Berg, Maintenance & Operations
Tomas Berglund, Key Account Manager Toolox
Oxelösund mill
►Employees: 2,100
►First ironworks in Oxelösund, built 1914–1917,
was for the manufacture of pig iron.
►Products: Hardox® wear plate, Strenx®
Performance steel, Armox® protection plate and
Toolox® engineering and tool steel
►Production: 900 ktons of slabs and 550 ktons of
rolled plate per year.
►Two of Sweden’s three blast furnaces are in
Oxelösund which produces more than 5,000
tons of pig iron per day.
Maintenance budget
►Yearly Maintenance budget
− Steel and wear parts are the largest part of the
maintenance budget
►Additional CAPEX budget for improvement
projects
►3 and 5 year maintenance plans
− Audit of the equipment/mill
− Large components will be replaced and become
investments due to scale of project
Maintenance department: >20 % of Oxelösund employees
440
1660
Roles and responsibilities of maintenance
organization
►8 strategic technicians responsible for:
− Budget
− Strategic and long term planning
− Production availability
− Maintenance improvements
►Plan spare part inventory (SAT) ►Perform maintenance ►Analyze wear part service life
►Set maintenance plan ►Perform inspection ►Generate improvements
− Job planning
− Spare parts
100 % of all
purchases are
done (2 months
before the stop)
− 80 tons of Toolox®
• Hot areas with wear e.g. coking plant
• When a lot of milling is required
• Form stability
− 50 tons of Hardox®
• Wear in areas <200°C
Hardox 600
15 mm 0.3–0.5 mm /
10,000 tons