Professional Documents
Culture Documents
Management of Interruptible Loads For Power System Security and Operation
Management of Interruptible Loads For Power System Security and Operation
Management of Interruptible Loads For Power System Security and Operation
net/publication/3973387
CITATIONS READS
21 138
6 authors, including:
Some of the authors of this publication are also working on these related projects:
All content following this page was uploaded by Dario Lucarella on 23 February 2014.
Abstract – The paper critically analyzes the state of the art Competition among market actors is likely to result in
of the procedures to ensure the security of power system more stressed power systems [6]. As security will still
operation with respect to the introduction of Interruptible be a top goal for power system operation and control,
Loads. A short overview of the existing international the system operator may use load as a resource in
approaches is presented. The potentiality of load curtailment
providing ancillary services thus increasing system
as an ancillary service is underlined. The benefits for the
power system in terms of increased exploitation of the reliability. Further possible applications of load control
network capability - with particular attention to the increase are related to congestion management and available
of Total Transfer Capacity (TTC) across network sections - transfer capacity. Load curtailment can be seen as an
are emphasized. alternative approach to generator rescheduling for
A new definition of security is discussed as a consequence of resolving or alleviating congestion [7].
the use of Interruptible Loads not only into emergency The concept of security also including dynamic aspects
conditions but also during normal and alert operation, in is a very important issue. Preventive or corrective
order to guarantee the N-1 criterion satisfaction. The
approaches can be adopted [8]. The corrective approach
consequences of the introduction of Interruptible Loads are
detailed and some preliminary hints for the specific
may be often associated with the identification of
situations of the Italian Power System are presented. The specific critical conditions such as those occurring in a
results of a research activity on the possibility to use the load predetermined set of transmission lines named “critical
curtailment approach to increase the TTC in the Italy- sections”. Once the specific event occurred, some
Europe section are reported. almost instantaneous action must follow. Load can
prove to be useful both in preventive and corrective
Keywords: Interruptible Loads, Dynamic Security approaches.
Assessment, Ancillary Services. The following sections deal with the possibility of load
to be used as an “ancillary service provider” for
maintaining system security in order to lead the power
system to a more secure state or to avoid its degradation
1. INTRODUCTION into an insecure or an emergency state.
The use of load for power system security and economy is 2. LOAD CURTAILMENT: EXISTING
not a new item in research agendas [1]. In the past, both APPROACHES
Demand Side Management (DSM) and Load Shedding
(LS) have been used to provide reliable power system 2.1 The International perspective
operation under normal and emergency conditions. DSM
There is great attention in considering load as a resource
was specifically devoted to peak demand shaving [2] and
for providing ancillary services [5], [9]. By considering
made use of particular tariff conditions. LS is still a world
that load is composed by relatively small components
wide used methodology for preventing power system
and that it is only required to partially contribute to
degradation to blackouts [3], [4].
service provision, one can reasonably expect load to
In the new context set up by the Electrical Energy Market,
provide an efficient service both in terms of speed of
the role of load is under revision. Controlling load may
response and reliable operation.
result in significant economical and security
The candidate ancillary services that can be associated
improvements. Abnormally high market clearing prices
to load curtailment are those related to the generation-
(“price spikes”) related to high demand and generation
load balance. Although definitions may vary from
shortage might have been avoided if sufficient load
country to country, the following list should be
elasticity had been available [5]. Another driving force for
comprehensible for everybody: Regulation, Load
incrementing load control is the necessity to enlarge the
Following, Spinning Reserve, Supplemental Reserve,
number of actors in the market in order to make it really
Back-up Supply. Figure 1 clearly identifies the required
competitive.
time span for each service.
It is reasonable to assume that loads respond more and is currently under test. The following table
rapidly to control center orders than large size summarizes the 2001 situation in Italy for what concerns
generators so that load can be used as an ancillary the role of Interruptible Loads [11].
service under contingency operation. The possible Table 1: Interruptible Loads: 2001 situation
aggregation of loads under some sort of “load Total curtailed
Interruptible Loads energy until
dispatcher” capable of cycling daily operation with
respect to some price signal and the intensive use of 31.08.2001
Total MW Real-Time (*) Notified Number of MWh
advanced communication facilities may open
(MW) (**) (MW) loads
unexpected perspectives to load curtailment even in 941 500 441 54 19240
normal operation.
(*) Intervention within 200 ms
(**) Notification specified by GRTN within 24 hours
It can be noticed that strategy (a) is more efficient than The paper has examined the actual situation for what
strategy (c), as could already be argued by the concerns the use of Interruptible Loads as contributors
description of Section 4.3. In fact the former can be to system security. The different approaches used in the
chosen in a more selective way with respect to the international context provided by the liberalised market
overloaded lines, and the total import reduction is have been recalled.
larger. Therefore the amount of load curtailment needed The actual capability of Interruptible Loads under test in
to remove a violation is smaller than that required by the Italian system has been presented.
strategy (c). The preliminary results of a research study oriented to
analyze some different strategies for Interruptible Loads
Table 7: Distribution of load curtailment with respect to each area for with respect to TTC are finally reported.
strategy (a) with limited (and unlimited) load curtailment The present work developed within the aims of an
Limited corrective control industry-university research activity has pointed out that
[Curtailed MW/winter]
some benefits can be obtained by the use of Interruptible
Curtailment area F CH A-SLO Bal-
anced Loads. A preliminary analysis has shown that the
Area 1 111 83 0 111 amount of load to be disconnected for achieving a
Area 2 658 1011 642 685 significant increment in the TTC of a real system may
Area 3 289 24 1280 226 be somewhat burdensome. Lower increments should be
Area 4 259 0 274 207 feasible at reasonable levels of disconnection.
Σ 1317 1118 2196 1229 The implications in the mutual control among different
Unlimited corrective control
[Curtailed MW/winter]
TSOs can cause some difficulties in the implementation
Curtailment area F CH A-SLO Bal- of at least some of the strategies proposed. There is
anced anyway a significant international interest in the role of
Area 1 860 0 0 627 Interruptible Loads both for security applications and
Area 2 131 1055 115 158 economic reasons that deserve more research effort.
Area 3 16 24 1933 226
Area 4 0 0 0 0 6. ACKNOWLEDGEMENTS
Σ 1007 1079 2048 1011
This paper is a synthesis of part of the work developed within the
research activity “Ricerca di Sistema”, Italian Ministry DM
Table 8: Distribution of load curtailment with respect to each area for 17/04/2001.
strategy (c) with limited (and unlimited) load curtailment Dr. F. Casamatta has been with CESI during the present activity.
Limited corrective control
[Curtailed MW/winter]
7. REFERENCES
Curtailment area F CH A-SLO Bal-
anced
Area 1 - 0 - - [1] J. Eto, J. Kueck, J. Dagle, F. Alvarado, C. Martinez, et alii, “An R&D
Area 2 - 1084 - - Agenda to Enhance Electricity System Reliability by increasing Customer
Participation in Emerging Competitive Markets”, IEEE 2001 Winter
Area 3 - 101 - - Meeting, Columbus, Ohio, USA, 28 January-1 February 2001
Area 4 - 450 - -
[2] NERC Document, “Demand-Side Management: the System Operator’s
Σ NF 1635 NF NF Perspective”, December 1993
Unlimited corrective control
[3] C. Concordia, L. H. Fink, G. Poullikkas, “Load shedding on an isolated
[Curtailed MW/winter] system”, IEEE Transactions on Power Systems, Vol. 10, No. 3, August
Curtailment area F CH A-SLO Bal- 1995, pp. 1467-1472
anced [4] B. Delfino, S. Massucco, A. Morini, P. Scalera, F. Silvestro,
Area 1 990 0 0 725 “Implementation and Comparison of Different Under Frequency Load-
Area 2 187 1090 0 223 Shedding Schemes”, IEEE Summer Meeting 2001, Vancouver (Canada),
15-19 July 2001
Area 3 40 61 2450 594
Area 4 0 440 2562 0 [5] B. Kirby, E. Hirst, “Load as a resource in providing Ancillary Services”,
ORNL, January 1999
Σ 1217 1591 5012 1542
[6] Proceedings of the IEEE, Special Issue on the Technology of Power
System Competition, Vol. 88, No. 2, February 2000
[7] C. D. Vournas, “Interruptible Load as a Competitor to Local Generation
for Preserving Voltage Security”, IEEE 2001 Winter Meeting, Columbus,
Ohio, USA, 28 January-1 February 2001
[8] M. Pavella, D. Ernst, D. Ruiz-Vega, “Transient Stability of Power
Systems: A Unified Approach to Assessment and Control”, Kluwer
Academic, Boston, 2000
[9] J. Cox, “Ancillary Services Demand-Side Provision, National Grid
Company (NGC), UK, 1997
[10] J. H. Douna, “Overview of California ISO Summer 2000 Demand
Response Programs”, IEEE 2001 Winter Meeting, Columbus, Ohio,
USA, 28 January-1 February 2001
[11] P. L. Parcu, “Electricity Transmission and Grid Access”, GRTN
presentation, Rome, June 7th, 2001 and “Rights and Duties for the
Eligible Customer”, II Forum of Electrical Energy, Villa d’Este,
Cernobbio, Italy, September 28th, 2001 (In Italian)
[12] G. Montanino, C. Sabelli, “Problems and Rules of Interconnections in
Italy: the Viewpoint of the System Operator”, AEI Annual Meeting &
CIGRE Workshop, Padova, Italy, October 5th, 2001
[13] ETSO (European Transmission System Operators), “Definitions of
Transfer Capacities in liberalised Electricity Markets”, Final Report, April
2001 and “Evaluation of congestion management methods for cross-
border transmission”, Florence Regulators Meeting, November 1999.
Web site www.etso-net.org
[14] P. Baratella, P. Scarpellini, R. Marconato, B. Cova, E. Gaglioti, R.
Zacheo, “A Power System Simulator Covering Different Time Scale
Phenomena: Models, Algorithms, MMI and Test Results”, Proc. IEEE
Stockholm Power Tech, Stockholm, June 1995, pp. 376-381
[15] OMASES - Open Market Access and Security Assessment System,
Contract No. ENK6-CT-2000-00064, EU - Framework V, December
2000