Demolition Work MS
Demolition Work MS
INDEX:
REVISION STATUS
1. PURPOSE
2. WORK LOCATION AND WORK HOURS
3. PROGRAMME
4. RESPONSIBILITIES
4.1 PROJRCT MANAGER
4.2 PROJECT ENGINEER
4.3 HSE OFFICER
4.4 FIRST AIDER
4.5 SITE SUPERVISOR
4.6 OPERATOR
4.7 BANKSMAN
5. MATERIALS
6. PLANT AND EQUIPMENT
7. HSE REQUIREMENT
8. METHODOLOGY
a) Local authority’s approval
b) Survey before Commencement
c) Record of unrestrained work and services / existing damages
d) Disconnection of Services
I. Disconnection of electrical cables
II. Disconnection of water service
LOYAL BUILDING CONTRACTING LLC
DEMOLITION WORK - METHOD STATEMENT, ITP AND RISK ASSESSMENT
9. SOFT STRIPPING
10.REMOVING OF ROOF SHEET
11.REMOVAL OF WALL CLADDING
12.DEMOLITION OF BLOCK WALL
13.REMOVAL OF STEEL STRUCTURE OFFICE AREA
14.REMOVAL OF STEEL WAREOUSE AREA
15.REMOVAL OF FLOOR SLAB
16.REMOVAL OF FOUNDATION
17.INSPECTION AND TEST PLAN
18.RISK ASSESSMENT
REVISION STATUS:
1. PURPOSE:
The method is prepared to ensure that construction of warehouse for the project shall comply on plans specifications
and all relevant standard and code requirements in the execution of different work activities to be performed in the
LOYAL BUILDING CONTRACTING LLC
DEMOLITION WORK - METHOD STATEMENT, ITP AND RISK ASSESSMENT
construction of warehouse and other relevant structures associated with the project. In addition this will serve as a tool to
guide all technical personnel and layman execute proper construction procedures complied with the quality and safety plan
for the projects.
3. PROGRAMME:
4. RESPONSIBILITIES:
4.1PROJECT MANAGETR:
LOYAL BUILDING CONTRACTING LLC
DEMOLITION WORK - METHOD STATEMENT, ITP AND RISK ASSESSMENT
Implementing the work program / tracking day-to-day Demolition Work and associated activities as per the
program scheduled.
Ensuring that personnel involved in demolition activity and associated works meets the minimum
qualifications for their assignment and are properly trained.
In-charge of maintaining the safety standards by all staff and ensuring that they have required HSE
Training.
4.2PROJECT ENGINEER:
Responsible for the entire activities of Demolition work and associated work complying with the safety
standard requirements.
To ensure that the team engineers and foreman are aware of the Method statement and all resource area
available to carry out the work as planned.
To liaise with the CMCS to ensure timely approval of WIR, Shop drawing etc.
Responsible for the supervision of the work activity and associated work as per approved method statement
and drawings.
To ensure that all equipment’s required for the works are available and in good condition.
To ensure that all the technical matters and changes in the plan are discussed with the foremen.
4.3HSE OFFICER:
LOYAL BUILDING CONTRACTING LLC
DEMOLITION WORK - METHOD STATEMENT, ITP AND RISK ASSESSMENT
HSE officer shall ensure implementation of all safety Procedure while formwork and Performing the
demolition activity.
He shall ensure that all controls listed in the HEMP are in place.
Necessary safety instructions are to be provided to the crew based on the site live condition.
He shall maintain continuous inspection of the site activities and advice site crew to prevent accidents,
personnel injury and property damage.
In case of emergencies, he shall initiate all recovery measures as per the emergency procedures.
4.4FIRST AIDER:
First Aider is responsible for maintaining first aid facilities while formwork and performing the demolition
activity.
He shall administer first aid, monitor and report risks and incidents.
To provide first aid to crew working on the demolition activity, in the event of any injury.
He shall undertake quarterly checks of the office first aid kit to ensure it is compliant with the checklist
issued by HSE staff.
Assist the HSE Officer to carry out quarterly facility inspections.
Assist with any incident investigations and unresolved issues connected with the use of first aid supplies, or
action by the HSE Officer at the site.
Promote good safety practice within the site.
LOYAL BUILDING CONTRACTING LLC
DEMOLITION WORK - METHOD STATEMENT, ITP AND RISK ASSESSMENT
He will coordinate with the Site Engineer on a daily basis and will ensure proper distribution of the
workforce and equipment at required locations.
He will be aware of the possible risk hazards involved with the works and comply with all safety
requirements prior to start of the activity.
He should give proper Tool Box Talk to his crew for safe handling of work.
4.6 OPERATOR:
Will be responsible for safe operation of excavator with pneumatic hammer and place the machine in a safe
and the suitable position.
4.7BANKSMAN:
He will be responsible for guiding the excavator and crane operator for the safe operation.
5. MATERIALS:
LOYAL BUILDING CONTRACTING LLC
DEMOLITION WORK - METHOD STATEMENT, ITP AND RISK ASSESSMENT
Wheel Loader
Excavator with pneumatic hammer
Back Hoe Loader.
Hand shovel.
Hand tools.
7. HSE Requirements:
The crew must complete the compulsory HSE training like HSE Induction, Initial Fire Response (IFR),
dealing with Hazard and Risks (DHR) and to possess a valid PDO Passport as a minimum to work in this
project.
Site HSE induction will be completed for the crew prior to entering the site with a sticker labelled ”HSE
INDUCTED” affixed on to their helmet.
All Crew will wear Helmet, Safety Shoe & High Visibility Jacket and will use need based PPE like Hand
Gloves, Dust mask and Goggles etc.
The supervisor to make an assessment of the hazards & risks with respect to the Demolition works and to
fill the Risk Assessment communication form.
The site Supervisor/ Forman will conduct Tool Box Talk (TBT) and will obtain attendance of the crew.
Supervisor will ensure that all control measures for the specific task are in place as per Risk Assessment.
Barricade must be done around the area of the demolition to be carried out.
LOYAL BUILDING CONTRACTING LLC
DEMOLITION WORK - METHOD STATEMENT, ITP AND RISK ASSESSMENT
Proper access to the work areas will be maintained throughout the working period for easy working. In case
of emergency and the crew should gather at assembly point located nearby.
Equipment’s like wheel loader will be provided with Banks man for giving directions.
All operators & banks man should be trained and must have the DDA Approved 3rd party certificate.HSE
inspection/ training will be verified for all the plant/ equipment / vehicle operators / drivers prior to
commencement of work.
Right type of machinery / tools for the work will be used.
First Aider, First aid box will be available at site.
Drinking water facility will be provided by the company management.
The crew members will make use of the welfare facilities and the first aid arrangements and must have a
valid 3rd party certificate.
The Crew will work only if the climatic conditions are favourable for the tasks.
An emergency Vehicle will be made available at site.
If hazards are found, the operator will refer to supervisor and establish a safe working method before
commencement of work.
All the rebar edges will be covered with padding protection.
All scaffolding will be fitted with guard rails and toe boards.
All scaffolding more than the height of 9 M should be inspected by approved 3rd party.
Person working at height will wear Safety harness.
TBT will be conducted regularly prior to start of work.
Open excavations will be barricaded at least one meter away from the opening.
All necessary sign boards & barricades should be placed in position in all required places.
LOYAL BUILDING CONTRACTING LLC
DEMOLITION WORK - METHOD STATEMENT, ITP AND RISK ASSESSMENT
8. METHODOLOGY:
The scope of works involved in the demolition of the existing structures is as follows:
a) Obtain NOC’s from Etisalat, DEWA, and Drainage or any required NOC’s from the authorities.
b) Obtain demolition permit from DDA
c) Isolation of the Area.
d) Disconnection of services
e) Removal of loose and soft materials
f) Removal of roofing sheets
g) Dismantling truss, rafters, purlins etc.
h) Demolition of RCC slabs and masonry walls
i) Dismantling Structural Columns & Beams
j) Removal of salvage materials.
k) Demolition of flooring
l) Demolition of foundations
m) Cart away the demolition debris to the approved dumping yard
n) Backfilling and levelling the ground.
a) Local authority’s approval:
All the requirements of Local and Statutory Authorities regarding notification of demolition works shall
be complied.
Before starting the demolishing work, all the available drawings and documents will be studied and carry
out a through survey and examination of the building, structure or service to be demolished.
All the details with record drawings will be provided to client, showing the level, size, position and
contents of any abandoned services, foundations, underground chambers, wells, underground tanks or any
other work discovered during the demolition.
Any building, structure or services to be retained at site and any adjoining property or services liable to
be affected by demolition shall be examined before demolishing and any existing crack or other evidence of
damage shall be noted.
d) . Disconnection of Services:
Obtain necessary NOCs from the respective authority prior to start the work.
Before starting demolition, the contractor shall arrange with the client and Statutory Authorities, if
applicable for the locating and marking of the position of all known services affected by the work and
for the proper disconnection of their mains supplies and cables.
Any electrical cabling will be removed for recycling prior to soft stripping and the demolition of the
structure.
LOYAL BUILDING CONTRACTING LLC
DEMOLITION WORK - METHOD STATEMENT, ITP AND RISK ASSESSMENT
No cable-stripping work will commence until the electrical supplies to the site have been irreversibly
isolated either to the main distribution board by the local electricity supply company or from the main
distribution board by a suitably qualified electrician.
Hand tools will be used by the demolishing operatives to cut all the exposed electrical cables and
which are easily extracted, but which are not exposed.
MEWPS will be used to remove the cables in the trays or the wire present above the floor level.
The removal of cable insulation and armor is to be undertaken using a machine
All waste generated by the cable-stripping is to be disposed of appropriately.
9. Soft Stripping:
Materials that are to be removed by the internal soft strip can include doors, door frames, fixed and
non-fixed furniture, carpets and floor coverings and other materials which obstruct the construction
of asbestos removal enclosures.
Operatives will strip out all doors, frames, and windows, timber of any description, toilets, pipe
work, electrical items and any debris.
Any clean, unpainted constructional timber will be segregated from the general waste. Where this
material is free of nails, screws, hinges etc. it will be segregated for recycling and any materials
deemed as not suitable for recycling will be removed from site.
Where possible the materials will be loaded by hand method into skips and removed from the site.
Where access for skips is not available the materials will be segregated and stored within the
building where they will be removed at a later stage.
Operatives will use Step ladder for stripping the fall ceiling tile and AC ducts.
Ensure the step ladder is damage free and 3 point contact must 3-point contact (two hands and a foot,
or two feet and a hand) when climbing/ descending a ladder.
Ensure that the ladder has been placed on a stable and level surface that is not slippery.
All the waste generated during the removal of fall ceiling tile is to be disposed of appropriately.
First wall cladding panel to be removed from the ridge area of the end wall, removing the ridge wall
panel first and progressing towards the rear side.
Follow the same pattern till removing the last wall panel.
The entire removed wall panel should be secured properly and stored.
All the removed panels to be attacked in a bundle not exceeding 8 panels.
More caution to be taken during the shifting of the damaged wall panel.
The entire waste panel must be removed from the site.
The demolition works shall be executed for any existing structure only after obtaining the requisite
permission from the authorities.
The demolition area will be isolated prior to any kind of demolition.
The building to be demolished on site is of steel framed type structure, clad in corrugated single ply
steel sheeting.
All workers and staff will be given induction training and job specific instructions by the site in
charge.
Workers will be provided with PPE’s such as reflective jackets, safety belt, shoes, masks, goggles,
full body harness etc.
Prior to dismantling the block, all the fittings along the wall such as Windows, doors, duct etc. to be
removed.
The masonry walls and RCC slabs of the building will be dismantled thereafter using Excavators
fitted with bucket and breakers.
LOYAL BUILDING CONTRACTING LLC
DEMOLITION WORK - METHOD STATEMENT, ITP AND RISK ASSESSMENT
Care to be taken that, while the block wall dismantling area should be isolated and no person should
trespass.
Ensure the excavator is certified and the operator is 3rd party certified.
The Concrete debris to be cleared from Site periodically.
The office area consists of the roof panel and a mezzanine floor consisting of hollow core slab.
After the removal of the roof panel, proceed with the removal of secondary members and the hollow
core slab bay by bay.
Start from any one side of the office; consider one sequence frame consists of 4 columns.
First remove the roof flange brace, sag rods and purling in this bay by soft stripping.
Proceed to remove the hollow core slab. Make 4 to 6 holes of 4” dia (depending on the panel size) in
the hollow core, lift each panel with the help of chain and crane arrangement.
Once the secondary members and slab is removed, remove the steel beams and then steel column.
Repeat this pattern for the entire bay.
The removed slab to be stacked properly and removed periodically.
The removed steel member to be stacked properly and barricade should be provided.
3rd party certified rigger should give signal to the crane.
Experienced team will be appointed for the execution of the work.
No person should stand below the suspended load or below the lifting area.
Removal of bolts to be carried out by spanners and power tool such as tighter.
Now that roof sheet and wall sheet is removed, proceed with the dismantling of steel structure.
Start with the end wall and proceed bay by bay pattern.
In the first bay, remove the roof flange brace, cross bracing, sag rods and then purling by soft
stripping.
Once secondary members are removed, proceed with the primary members.
Mobile crane of 25 ton to be used for all the primary members dismantling.
Remove the end wall rafters, section by section depending up on the size of the rafter.
Remove the wall purlin bay by bay and remove the particular end wall column.
For the remaining main frame, remove secondary members, followed by dismantling of rafters
section by section depending on the size. Review the wall purling along the eave side and remove the
column along the eave side.
Repeat this pattern towards the other end wall.
Prior to the removal of the floor slab the area must be isolated and warning signboards must be displayed.
Once the steel structure is removed, the floor slab shall be demolished from any side.
The demolition of flooring will be done using excavators fitted with breakers and buckets. The tie beams
will be demolished along with the flooring. The debris will be removed intermittently.
LOYAL BUILDING CONTRACTING LLC
DEMOLITION WORK - METHOD STATEMENT, ITP AND RISK ASSESSMENT
All the worker and the operator involved in the activity must be induced and RA must be communicated to
the work force.
The debris that is generated during the activity will be stacked properly and removed appropriately.
Once the floor is demolished excavation will be done to demolish the foundations. The foundations are
exposed and will be demolished using breakers. The reinforcement bars will be cut and separated. The
concrete debris etc. will be carted away to approved dump yard using dump trucks.
Contractor
Premises of
Consultant Review point - Representative of indicated party to review
Inspection / Site R
Approval submitted documents, result of test etc..
Work Area
Coordinates
Consultant Owner
Contractor
Acceptance
Criteria Specific
Activity Description of Inspection Drawing N" of
(Controlling Quality
NO & Test Activity reference Contractor CEC Punchlist
Procedure, Report
Signature Signature Item N"
Specifications, Code (If
Standars etc..) H W R H W R H W R any)
SAFETY MEASURES
1 TAKEN BEFORE
DEMOLITION WORK
2
Main Contractor: LOYAL BUILDING CONTRACTING LLC. Project: PROPOSED G+M OFFICE, WAREHOUSE AND Risk Assessor:
Client: AL MANAR SCAFFOLDING RENTALS LLC. ALLIED SERVICES ON PLOT NO: 5320248 DUBAI Mr. JAMES NEEL (SO)
Consultant: DESIGN HOUSE ENGINEERING INDUSTRIAL CITY, DUBAI – UAE.
Date : 05-02-2020 Date Next Review: 05-08-2020 Approved By: Reviewed By:
Mr. MUTHUKUMAR (PM) Mr. JOSHUA PRAVIN (SR.SO)
Recommended PPE: Hard Hat, Safety shoes, Safety Harness, coveralls, dust mask,
Equipment Required: Excavator
goggles, gloves
Remarks
Legal compliance
Risk
Consequences
Residual
Control E/I/R
Rating/
Risk
be Harm/
/Potential Hazards
Job steps/ Activities
Hazard identified
Risk level
Sl no
4 Preparation of the Major/ Minor injury Accident due to not Yes 3 5 H R Site engineer together with safety officer 1 5 L
workers. due to unprotected following the safety will conduct a tool box talk, with the
unprotected procedures. involved group before commencing the
job.
MS and RA must be communicated to the
site operatives and is recorded.
demolition area. Only competent person shall be permitted
to carry out the demolition activity.
Full time supervisor to facilitate and look
over and monitor the whole operation.
6 Gas cutting and DEATH, FIRE, Injury to the No 3 3 M R Eye protection, gloves and suitable 2 2
EXPLOSION OR workers involved in clothing to be worn.
burning L
BURNS and ILL the activity. Ensure all staff who undertake cutting/
burning duties are competent to do so.
Hot work to be supervised closely and
undertaken only under A Hot Work
Permit issued by Safety officer.
EFFECTS ON HEALTH Flashback arresters and non-return
valves must be fitted to gas hoses and
bottles.
Hose lengths should be kept to a
minimum
Make sure that the area is isolated
Keep the area clean such that no
machines or materials are stored in the
area
Major Injury to
Collapse of block wall Keep adequate signboards 2 4 M
7 Block Wall person, or property Yes 4 4 H R
on material or Person The Excavators and its operator to be 3rd
damage
party certified
Spray water periodically to avoid dust
pollution
Remove the concrete waste periodically
1. Identify Hazards
2. List Hazard Event
3. Calculate Risk Factor with Initial Risk Rating. I.E. Probability x Severity
4. Detail Controls
5. Calculate Residual Risk Rating with Final Risk Rating
4 16 12 8 4 6 Medium Risk
2 8 6 4 2
Severity
4. Catastrophic – Imminent danger exists, hazard capable of causing death or illness on a wide scale
3. Critical – Hazard can result in serious illness, severe injury, and property and equipment damage
2. Marginal – Hazard can cause illness, injury or equipment damage, but the results would not be expected to be serious
1. Negligible – Hazard will not result in serious injury or illness, remote possibility of damage beyond minor first aid case
Probability
4. Probable – Likely to occur immediately or shortly