LOYAL BUILDING CONTRACTING LLC

DEMOLITION WORK - METHOD STATEMENT, ITP AND RISK ASSESSMENT

M/S MANAR AL OMRAN SCAFFOLDING RETALS


PROJECT: PROPOSED G+M OFFICE, WAREHOUSE AND ALLIED SERVICES ON PLOT NO: 5320248
DUBAI INDUSTRIAL CITY, DUBAI – UAE.

Main Contractor: LOYAL BUILDING CONTRACTING LLC


Project Manager
Name: MUTHUKUMAR Date: 26/04/2020
Signature:

Consultant: DESIGN HOUSE ENGINEERING CONSULTANCY


Project Manager
Name: Date:
Signature:
LOYAL BUILDING CONTRACTING LLC
DEMOLITION WORK - METHOD STATEMENT, ITP AND RISK ASSESSMENT

INDEX:
REVISION STATUS
1. PURPOSE
2. WORK LOCATION AND WORK HOURS
3. PROGRAMME
4. RESPONSIBILITIES
4.1 PROJRCT MANAGER
4.2 PROJECT ENGINEER
4.3 HSE OFFICER
4.4 FIRST AIDER
4.5 SITE SUPERVISOR
4.6 OPERATOR
4.7 BANKSMAN
5. MATERIALS
6. PLANT AND EQUIPMENT
7. HSE REQUIREMENT
8. METHODOLOGY
a) Local authority’s approval
b) Survey before Commencement
c) Record of unrestrained work and services / existing damages
d) Disconnection of Services
I. Disconnection of electrical cables
II. Disconnection of water service
LOYAL BUILDING CONTRACTING LLC
DEMOLITION WORK - METHOD STATEMENT, ITP AND RISK ASSESSMENT

9. SOFT STRIPPING
10.REMOVING OF ROOF SHEET
11.REMOVAL OF WALL CLADDING
12.DEMOLITION OF BLOCK WALL
13.REMOVAL OF STEEL STRUCTURE OFFICE AREA
14.REMOVAL OF STEEL WAREOUSE AREA
15.REMOVAL OF FLOOR SLAB
16.REMOVAL OF FOUNDATION
17.INSPECTION AND TEST PLAN
18.RISK ASSESSMENT

REVISION STATUS:

REV NO DATE DESCRIPTION PREPARED BY APPROVED BY


Rev N. 00 25-04-2020 Method Statement James Neel

1. PURPOSE:
The method is prepared to ensure that construction of warehouse for the project shall comply on plans specifications
and all relevant standard and code requirements in the execution of different work activities to be performed in the
LOYAL BUILDING CONTRACTING LLC
DEMOLITION WORK - METHOD STATEMENT, ITP AND RISK ASSESSMENT

construction of warehouse and other relevant structures associated with the project. In addition this will serve as a tool to
guide all technical personnel and layman execute proper construction procedures complied with the quality and safety plan
for the projects.

2. WORK LOCATION AND WORK HOURS:

3. PROGRAMME:

4. RESPONSIBILITIES:

4.1PROJECT MANAGETR:
LOYAL BUILDING CONTRACTING LLC
DEMOLITION WORK - METHOD STATEMENT, ITP AND RISK ASSESSMENT

 Implementing the work program / tracking day-to-day Demolition Work and associated activities as per the
program scheduled.
 Ensuring that personnel involved in demolition activity and associated works meets the minimum
qualifications for their assignment and are properly trained.
 In-charge of maintaining the safety standards by all staff and ensuring that they have required HSE
Training.

4.2PROJECT ENGINEER:

 Responsible for the entire activities of Demolition work and associated work complying with the safety
standard requirements.
 To ensure that the team engineers and foreman are aware of the Method statement and all resource area
available to carry out the work as planned.
 To liaise with the CMCS to ensure timely approval of WIR, Shop drawing etc.
 Responsible for the supervision of the work activity and associated work as per approved method statement
and drawings.
 To ensure that all equipment’s required for the works are available and in good condition.
 To ensure that all the technical matters and changes in the plan are discussed with the foremen.

4.3HSE OFFICER:
LOYAL BUILDING CONTRACTING LLC
DEMOLITION WORK - METHOD STATEMENT, ITP AND RISK ASSESSMENT

 HSE officer shall ensure implementation of all safety Procedure while formwork and Performing the
demolition activity.
 He shall ensure that all controls listed in the HEMP are in place.
 Necessary safety instructions are to be provided to the crew based on the site live condition.
 He shall maintain continuous inspection of the site activities and advice site crew to prevent accidents,
personnel injury and property damage.
 In case of emergencies, he shall initiate all recovery measures as per the emergency procedures.

4.4FIRST AIDER:

 First Aider is responsible for maintaining first aid facilities while formwork and performing the demolition
activity.
 He shall administer first aid, monitor and report risks and incidents.
 To provide first aid to crew working on the demolition activity, in the event of any injury.
 He shall undertake quarterly checks of the office first aid kit to ensure it is compliant with the checklist
issued by HSE staff.
 Assist the HSE Officer to carry out quarterly facility inspections.
 Assist with any incident investigations and unresolved issues connected with the use of first aid supplies, or
action by the HSE Officer at the site.
 Promote good safety practice within the site.
LOYAL BUILDING CONTRACTING LLC
DEMOLITION WORK - METHOD STATEMENT, ITP AND RISK ASSESSMENT

4.5 SITE SUPERVISIOR:

 He will coordinate with the Site Engineer on a daily basis and will ensure proper distribution of the
workforce and equipment at required locations.
 He will be aware of the possible risk hazards involved with the works and comply with all safety
requirements prior to start of the activity.
 He should give proper Tool Box Talk to his crew for safe handling of work.

4.6 OPERATOR:

 Will be responsible for safe operation of excavator with pneumatic hammer and place the machine in a safe
and the suitable position.

4.7BANKSMAN:

 He will be responsible for guiding the excavator and crane operator for the safe operation.

5. MATERIALS:
LOYAL BUILDING CONTRACTING LLC
DEMOLITION WORK - METHOD STATEMENT, ITP AND RISK ASSESSMENT

6. PLANT & EQUIPMENTS:

 Wheel Loader
 Excavator with pneumatic hammer
 Back Hoe Loader.
 Hand shovel.
 Hand tools.

7. HSE Requirements:

 The crew must complete the compulsory HSE training like HSE Induction, Initial Fire Response (IFR),
dealing with Hazard and Risks (DHR) and to possess a valid PDO Passport as a minimum to work in this
project.
 Site HSE induction will be completed for the crew prior to entering the site with a sticker labelled ”HSE
INDUCTED” affixed on to their helmet.
 All Crew will wear Helmet, Safety Shoe & High Visibility Jacket and will use need based PPE like Hand
Gloves, Dust mask and Goggles etc.
 The supervisor to make an assessment of the hazards & risks with respect to the Demolition works and to
fill the Risk Assessment communication form.
 The site Supervisor/ Forman will conduct Tool Box Talk (TBT) and will obtain attendance of the crew.
 Supervisor will ensure that all control measures for the specific task are in place as per Risk Assessment.
 Barricade must be done around the area of the demolition to be carried out.
LOYAL BUILDING CONTRACTING LLC
DEMOLITION WORK - METHOD STATEMENT, ITP AND RISK ASSESSMENT

 Proper access to the work areas will be maintained throughout the working period for easy working. In case
of emergency and the crew should gather at assembly point located nearby.
 Equipment’s like wheel loader will be provided with Banks man for giving directions.
 All operators & banks man should be trained and must have the DDA Approved 3rd party certificate.HSE
inspection/ training will be verified for all the plant/ equipment / vehicle operators / drivers prior to
commencement of work.
 Right type of machinery / tools for the work will be used.
 First Aider, First aid box will be available at site.
 Drinking water facility will be provided by the company management.
 The crew members will make use of the welfare facilities and the first aid arrangements and must have a
valid 3rd party certificate.
 The Crew will work only if the climatic conditions are favourable for the tasks.
 An emergency Vehicle will be made available at site.
 If hazards are found, the operator will refer to supervisor and establish a safe working method before
commencement of work.
 All the rebar edges will be covered with padding protection.
 All scaffolding will be fitted with guard rails and toe boards.
 All scaffolding more than the height of 9 M should be inspected by approved 3rd party.
 Person working at height will wear Safety harness.
 TBT will be conducted regularly prior to start of work.
 Open excavations will be barricaded at least one meter away from the opening.
 All necessary sign boards & barricades should be placed in position in all required places.
LOYAL BUILDING CONTRACTING LLC
DEMOLITION WORK - METHOD STATEMENT, ITP AND RISK ASSESSMENT

8. METHODOLOGY:

The scope of works involved in the demolition of the existing structures is as follows:
a) Obtain NOC’s from Etisalat, DEWA, and Drainage or any required NOC’s from the authorities.
b) Obtain demolition permit from DDA
c) Isolation of the Area.
d) Disconnection of services
e) Removal of loose and soft materials
f) Removal of roofing sheets
g) Dismantling truss, rafters, purlins etc.
h) Demolition of RCC slabs and masonry walls
i) Dismantling Structural Columns & Beams
j) Removal of salvage materials.
k) Demolition of flooring
l) Demolition of foundations
m) Cart away the demolition debris to the approved dumping yard
n) Backfilling and levelling the ground.
a) Local authority’s approval:

All the requirements of Local and Statutory Authorities regarding notification of demolition works shall
be complied.

b) Survey before Commencement:


LOYAL BUILDING CONTRACTING LLC
DEMOLITION WORK - METHOD STATEMENT, ITP AND RISK ASSESSMENT

Before starting the demolishing work, all the available drawings and documents will be studied and carry
out a through survey and examination of the building, structure or service to be demolished.

c) Record of unrestrained work and services / existing damages:

All the details with record drawings will be provided to client, showing the level, size, position and
contents of any abandoned services, foundations, underground chambers, wells, underground tanks or any
other work discovered during the demolition.
Any building, structure or services to be retained at site and any adjoining property or services liable to
be affected by demolition shall be examined before demolishing and any existing crack or other evidence of
damage shall be noted.

d) . Disconnection of Services:

1. Disconnection of electrical cables:

 Obtain necessary NOCs from the respective authority prior to start the work.
 Before starting demolition, the contractor shall arrange with the client and Statutory Authorities, if
applicable for the locating and marking of the position of all known services affected by the work and
for the proper disconnection of their mains supplies and cables.
 Any electrical cabling will be removed for recycling prior to soft stripping and the demolition of the
structure.
LOYAL BUILDING CONTRACTING LLC
DEMOLITION WORK - METHOD STATEMENT, ITP AND RISK ASSESSMENT

 No cable-stripping work will commence until the electrical supplies to the site have been irreversibly
isolated either to the main distribution board by the local electricity supply company or from the main
distribution board by a suitably qualified electrician.
 Hand tools will be used by the demolishing operatives to cut all the exposed electrical cables and
which are easily extracted, but which are not exposed.
 MEWPS will be used to remove the cables in the trays or the wire present above the floor level.
 The removal of cable insulation and armor is to be undertaken using a machine
 All waste generated by the cable-stripping is to be disposed of appropriately.

2. Disconnection of water services:

 All the water lines must be inspected before disconnecting it.


 Obtain NOC from DEWA, drainage or any other NOC if required.
 Safety induction program must be conducted to the workers involved in the activity.
 Hand tools like grinders and PVC fittings will be used for the execution of work.

9. Soft Stripping:

1. Removal of doors/ windows, Aluminium Louvers


 An internal soft strip of the buildings will be carried out by demolition operatives to remove as
much of the waste materials from the building ahead of the demolition works.
LOYAL BUILDING CONTRACTING LLC
DEMOLITION WORK - METHOD STATEMENT, ITP AND RISK ASSESSMENT

 Materials that are to be removed by the internal soft strip can include doors, door frames, fixed and
non-fixed furniture, carpets and floor coverings and other materials which obstruct the construction
of asbestos removal enclosures.
 Operatives will strip out all doors, frames, and windows, timber of any description, toilets, pipe
work, electrical items and any debris.
 Any clean, unpainted constructional timber will be segregated from the general waste. Where this
material is free of nails, screws, hinges etc. it will be segregated for recycling and any materials
deemed as not suitable for recycling will be removed from site.
 Where possible the materials will be loaded by hand method into skips and removed from the site.
Where access for skips is not available the materials will be segregated and stored within the
building where they will be removed at a later stage.

2. Removal of false ceiling tile, Ac duct, Electrical Fittings

 Operatives will use Step ladder for stripping the fall ceiling tile and AC ducts.
 Ensure the step ladder is damage free and 3 point contact must 3-point contact (two hands and a foot,
or two feet and a hand) when climbing/ descending a ladder.
 Ensure that the ladder has been placed on a stable and level surface that is not slippery.
 All the waste generated during the removal of fall ceiling tile is to be disposed of appropriately.

10.Removing of roof sheet:


LOYAL BUILDING CONTRACTING LLC
DEMOLITION WORK - METHOD STATEMENT, ITP AND RISK ASSESSMENT

 Obtain work at height permit before the commencement of work.


 PPE must be worn at all times.
 Inspect the roof panel for any damage/ crack or broken panel.
 Locate skylight on the roof and check for any damage.
 Prior to start, provide the roof edge protection with the help of mewp
 Provide safety net at the work area and should be shifted as the work area shifts.
 First roof sheet panel to be removed from the ridge area of end wall. Removing the ridge panel first
and progress toward the rear side.
 Follow the pattern line by line towards the other side end wall.
 Ensure that the MEWP is certified and all the operators are 3rd party certified.
 All the equipment involved in the demolishing activity will be inspected and all the personal shall be
inducted and trained before they commence the work on site.
 All the removed screw should be secured properly and stored
 The entire removed panel to be packed in a bundle, not exceeding 8 panels.
 More caution to be considered while addressing the skylight panels.
 The old panel bundle to be offloaded to ground with mobile crane as the work progress.
 Stack the bundle properly in the ground and clear at the earliest.
 Remove the edge protection with the help of MEWP.

11.Removal of Wall cladding:


LOYAL BUILDING CONTRACTING LLC
DEMOLITION WORK - METHOD STATEMENT, ITP AND RISK ASSESSMENT

 First wall cladding panel to be removed from the ridge area of the end wall, removing the ridge wall
panel first and progressing towards the rear side.
 Follow the same pattern till removing the last wall panel.
 The entire removed wall panel should be secured properly and stored.
 All the removed panels to be attacked in a bundle not exceeding 8 panels.
 More caution to be taken during the shifting of the damaged wall panel.
 The entire waste panel must be removed from the site.

12.Demolition of Block Wall

 The demolition works shall be executed for any existing structure only after obtaining the requisite
permission from the authorities.
 The demolition area will be isolated prior to any kind of demolition.
 The building to be demolished on site is of steel framed type structure, clad in corrugated single ply
steel sheeting.
 All workers and staff will be given induction training and job specific instructions by the site in
charge.
 Workers will be provided with PPE’s such as reflective jackets, safety belt, shoes, masks, goggles,
full body harness etc.
 Prior to dismantling the block, all the fittings along the wall such as Windows, doors, duct etc. to be
removed.
 The masonry walls and RCC slabs of the building will be dismantled thereafter using Excavators
fitted with bucket and breakers.
LOYAL BUILDING CONTRACTING LLC
DEMOLITION WORK - METHOD STATEMENT, ITP AND RISK ASSESSMENT

 Care to be taken that, while the block wall dismantling area should be isolated and no person should
trespass.
 Ensure the excavator is certified and the operator is 3rd party certified.
 The Concrete debris to be cleared from Site periodically.

13.Removal of steel structure office area.

 The office area consists of the roof panel and a mezzanine floor consisting of hollow core slab.
 After the removal of the roof panel, proceed with the removal of secondary members and the hollow
core slab bay by bay.
 Start from any one side of the office; consider one sequence frame consists of 4 columns.
 First remove the roof flange brace, sag rods and purling in this bay by soft stripping.
 Proceed to remove the hollow core slab. Make 4 to 6 holes of 4” dia (depending on the panel size) in
the hollow core, lift each panel with the help of chain and crane arrangement.
 Once the secondary members and slab is removed, remove the steel beams and then steel column.
 Repeat this pattern for the entire bay.
 The removed slab to be stacked properly and removed periodically.
 The removed steel member to be stacked properly and barricade should be provided.
 3rd party certified rigger should give signal to the crane.
 Experienced team will be appointed for the execution of the work.
 No person should stand below the suspended load or below the lifting area.
 Removal of bolts to be carried out by spanners and power tool such as tighter.

14.Removal of steel warehouse area.


LOYAL BUILDING CONTRACTING LLC
DEMOLITION WORK - METHOD STATEMENT, ITP AND RISK ASSESSMENT

 Now that roof sheet and wall sheet is removed, proceed with the dismantling of steel structure.
 Start with the end wall and proceed bay by bay pattern.
 In the first bay, remove the roof flange brace, cross bracing, sag rods and then purling by soft
stripping.
 Once secondary members are removed, proceed with the primary members.
 Mobile crane of 25 ton to be used for all the primary members dismantling.
 Remove the end wall rafters, section by section depending up on the size of the rafter.
 Remove the wall purlin bay by bay and remove the particular end wall column.
 For the remaining main frame, remove secondary members, followed by dismantling of rafters
section by section depending on the size. Review the wall purling along the eave side and remove the
column along the eave side.
 Repeat this pattern towards the other end wall.

15.Removal of floor slab:

Prior to the removal of the floor slab the area must be isolated and warning signboards must be displayed.
Once the steel structure is removed, the floor slab shall be demolished from any side.
The demolition of flooring will be done using excavators fitted with breakers and buckets. The tie beams
will be demolished along with the flooring. The debris will be removed intermittently.
LOYAL BUILDING CONTRACTING LLC
DEMOLITION WORK - METHOD STATEMENT, ITP AND RISK ASSESSMENT

All the worker and the operator involved in the activity must be induced and RA must be communicated to
the work force.
The debris that is generated during the activity will be stacked properly and removed appropriately.

16. Removal of foundation:

Once the floor is demolished excavation will be done to demolish the foundations. The foundations are
exposed and will be demolished using breakers. The reinforcement bars will be cut and separated. The
concrete debris etc. will be carted away to approved dump yard using dump trucks.

17. INSPECTION AND TEST PLAN:


LOYAL BUILDING CONTRACTING LLC
DEMOLITION WORK - METHOD STATEMENT, ITP AND RISK ASSESSMENT

INSPECTION & TEST PLAN (ITP)


Main Identfication Information
Document Revision Status Type of Inspection
System Subsystem
Plan Rev / Date
00M 01M 02M 03M H Hold point - Representative of indicated party to attened
(Mandatory)
Project Phase
(Manufacturing / Contractor Witness point - Representative of indicated party to be
Construction
Construction / Issuing W notified. If not attending at specified time, inspection may
Commossioning) proceed.

Contractor
Premises of
Consultant Review point - Representative of indicated party to review
Inspection / Site R
Approval submitted documents, result of test etc..
Work Area
Coordinates
Consultant Owner
Contractor
Acceptance
Criteria Specific
Activity Description of Inspection Drawing N" of
(Controlling Quality
NO & Test Activity reference Contractor CEC Punchlist
Procedure, Report
Signature Signature Item N"
Specifications, Code (If
Standars etc..) H W R H W R H W R any)

SAFETY MEASURES
1 TAKEN BEFORE
DEMOLITION WORK
2

Task/Job/Operation: DEMOLITION Ref No: RA- REV-00


LBC-001
LOYAL BUILDING CONTRACTING LLC
DEMOLITION WORK - METHOD STATEMENT, ITP AND RISK ASSESSMENT

Main Contractor: LOYAL BUILDING CONTRACTING LLC. Project: PROPOSED G+M OFFICE, WAREHOUSE AND Risk Assessor:
Client: AL MANAR SCAFFOLDING RENTALS LLC. ALLIED SERVICES ON PLOT NO: 5320248 DUBAI Mr. JAMES NEEL (SO)
Consultant: DESIGN HOUSE ENGINEERING INDUSTRIAL CITY, DUBAI – UAE.

Date : 05-02-2020 Date Next Review: 05-08-2020 Approved By: Reviewed By:
Mr. MUTHUKUMAR (PM) Mr. JOSHUA PRAVIN (SR.SO)

Recommended PPE: Hard Hat, Safety shoes, Safety Harness, coveralls, dust mask,
Equipment Required: Excavator
goggles, gloves

Risks / Who might

Remarks
Legal compliance
Risk

Consequences
Residual

Control E/I/R
Rating/
Risk
be Harm/
/Potential Hazards
Job steps/ Activities

Hazard identified

Risk level
Sl no

Mitigation action to be taken/ Hazard/Risk


Control Method L S R
L S R

Accident to other  The whole working area must be properly


Major/Minor injury people who is isolated from other unauthorized
Isolation of the due to not involved in personnel. Watch person to be provided
1 1 3 L
area unprotected the activity. No 3 3 M R
to aware other people of the ongoing
demolition area. activity.
 All the utility services including water line
and Cables should be disconnected before
demolition process start.
 Respective NOC’s should be obtained
from the concerned Authority prior to
commencement of work.
 Tool box must be conducted and it must
Physical injury to
Major/ minor injury be documented.
Dis connection of all the workers
2 due to utility  Supervisor must be available at site during 1 4 L
the services. involved in the Yes 3 4 M R
services. dismantling the electrical cables.
activity.  Waste debris raised during this process
must be removed immediately.
 Hand gloves must be issued to workers
who are handling sharp edge object.
 3rd party certified MEWP must be used.
 Ensure the operator has a valid 3rd party
training card.

 The whole working area must be properly


Accident to other isolated from unauthorized personnel.
people who is not Watch person to be provided to aware
Major/ Minor injury involved in the other people of the on- going activity.
Preparation of the due to unprotected activity.  The slab and other structure to be
3 No 3 5 H R
area unprotected demolished must be protected to prevent 1 5 L
demolition area. All workers from toppling over.
involved in the  Safe access must be provided for going in
activity. and out of the working area.

4 Preparation of the Major/ Minor injury Accident due to not Yes 3 5 H R  Site engineer together with safety officer 1 5 L
workers. due to unprotected following the safety will conduct a tool box talk, with the
unprotected procedures. involved group before commencing the
job.
 MS and RA must be communicated to the
site operatives and is recorded.
demolition area.  Only competent person shall be permitted
to carry out the demolition activity.
 Full time supervisor to facilitate and look
over and monitor the whole operation.

 Edge protection must be provided over


the roof sheet.
 Edge protection post to be installed using
MEWP. Ensure that MEWP and operator
is 3rd party certified
 Provide roof access and avoid using
MEWP for accessing roof.
 Safety net will be provided beneath the
roof sheet to prevent the person falling
from height.
Removing of roof Fall from height. Injury to the  Tool box talk must be conducted regarding the
5 sheet and wall workers involved in Yes 3 5 H R hazard and risk associated with the removal of 1 5 L
Object falling from
existing roof sheet.
cladding height, the activity.
 Where tools or equipment are being
used adjacent to a roof edge and there is
a risk of falling of objects, in order to
prevent, the objects must be attached to
the safety lanyard.

 The Old panels should be brought to


ground periodically to avoid over stacking
of panels in the roof.

6 Gas cutting and DEATH, FIRE, Injury to the No 3 3 M R  Eye protection, gloves and suitable 2 2
EXPLOSION OR workers involved in clothing to be worn.
burning L
BURNS and ILL the activity.  Ensure all staff who undertake cutting/
burning duties are competent to do so.
 Hot work to be supervised closely and
undertaken only under A Hot Work
Permit issued by Safety officer.
EFFECTS ON HEALTH  Flashback arresters and non-return
valves must be fitted to gas hoses and
bottles.
 Hose lengths should be kept to a
minimum
 Make sure that the area is isolated
 Keep the area clean such that no
machines or materials are stored in the
area
Major Injury to
Collapse of block wall  Keep adequate signboards 2 4 M
7 Block Wall person, or property Yes 4 4 H R
on material or Person  The Excavators and its operator to be 3rd
damage
party certified
 Spray water periodically to avoid dust
pollution
 Remove the concrete waste periodically

 Tool box talks to be given before


commencing the activity
 Suitable PPE like Safety shoe and safety
Physical injury and
8 Soft Stripping Minor Injury gloves to be worn by the workers. 1
hand injury to the Yes 3 4 H R 4 L
 Ear protection to be provided for the
workers involved.
workers.
 All debris to be segregated and stockpile
by plant ready for disposal.
9 Use of crane for 1.Serious injury, Equipment No 3 5 M R  Strictly comply with PTW system. 1 5 L
lifting. death due to person damage, personal
being knocked by injury  All the crane operators and riggers must
crane part. have trakhees approved 3rd party
certificate.
2.unstable groung
 Ensure all safety and operational
causing machine to
instructions are followed as per the MS.
tip over and trap
 Only trakhees approved third party
operator or other
workers.
3. high wing causing
loss of control of laod riggers would be authorized to give signal.
 Work will not be permitted, if wind speed
4.Unauthorized reaches 30 KM/HR
person using crane.
5.load falling due to
improper securing

 Competent supervisor must monitor the


working area to ensure that the proper
procedure of demolition is followed as
mentioned in MS
1.Trip, slip, fall  Full body Harness must be worn by the
2.over exposed to worker, where there is a tendency of
vibration. All the workers falling from height.
Demolition of the 2 3
10 involved in the No 3 3 M R  Suitable PPE like safety shoe and safety L
area. 3. Dust generated activity. gloves to be worn by workers.
during demolition.  Dust mask to be provided for the workers
involved in the activity.
 Worker handling hilti/ Jackhammers must
be given ample time to recover from the
impact of this equipment.

 Spray Water periodically to avoid dust


pollution
Respiratory Problems, Workers health  Provide dust mask to Labors as per the 1 2 L
11 Dust Pollution No 3 2 L R
Poor Visibilty issues requirement
 Provide Goggles to labors as per the
requirement
12 Noise Pollution Noise emitted during All the workers No 3 3 M R  Noise to be controlled and reduced to as 2 2 L
demolition work. involved in the low as is reasonably practical through the
activity. careful selection of plant and method of
demolition.
 when noise is believed to be above 80
dBA (i.e. when you have to raise your
voice to be heard two metre away).
Appropriate hearing protection to be
issued and worn.
 Provide information, instruction and
supervision when and how to correctly
use hearing protection

 Debris collection and disposal must be


supervised to avoid congestion of the
Accumulation of
Slip, trip and fall working area.
12 Housekeeping waste/ working 2 3
hazard. Yes 4 3 H R  Housekeeping shall be provided as the M
area congestion work is on- going were accumulated
debris are to be removed to sustain a
workable area.

Health and Safety


1. In case of Near Miss, Accidents or Emergencies call – (HSE Incharge-0551099321)
2. This Standard Risk Assessment may be revised to suit the site condition.
3. All persons will familiarize themselves and conform to project HSE rules and requirements and wear Basic PPE (Hard Hat, High-Viz Vest and Steel Toe Safety Shoes) at all
times – use additional PPE required by the job.
4. Only trained and certified operators shall operate vehicles and mobile construction machinery. Proof of competence will be available with the operator at all times for site
verification
5. Use of mobile phones during working hours is prohibited, except for emergency reporting only.
6. No eating, smoking and sleeping at the construction worksite. Use the facilities provided on site
7. Do not use defective PPE, tools, machinery, or equipment – get them replaced before you start your work
8. Report all near misses and accidents immediately to HSE In charge and your work leader
9. Work leaders are accountable for the behaviour of their operatives
10. Conduct a Tool Box Talk, Risk Assessment Review or issue safety instructions before the start of the day’s work.
11. Copy of this Risk Assessment available on site
Environmental
1. All waste materials will removed daily from the wok area and transferred to the designated waste skip
2. All Hazardous waste shall be immediately removed as per UAE regulation and dispatched slip maintained.
Risk Assessment Methodology

1. Identify Hazards
2. List Hazard Event

3. Calculate Risk Factor with Initial Risk Rating. I.E. Probability x Severity
4. Detail Controls
5. Calculate Residual Risk Rating with Final Risk Rating

6. Enter Risk Priority


7. Evaluate Acceptability of Risk

Risk Factor Matrix


Probability RISK PRIORITY

4 3 2 1 8-16 High Risk


Severity

4 16 12 8 4 6 Medium Risk

3 12 9 6 3 1-4 Low Risk

2 8 6 4 2
Severity
4. Catastrophic – Imminent danger exists, hazard capable of causing death or illness on a wide scale
3. Critical – Hazard can result in serious illness, severe injury, and property and equipment damage

2. Marginal – Hazard can cause illness, injury or equipment damage, but the results would not be expected to be serious
1. Negligible – Hazard will not result in serious injury or illness, remote possibility of damage beyond minor first aid case
Probability
4. Probable – Likely to occur immediately or shortly

3. Reasonably Probable – Probably will occur in time


2. Remote – May occur in time
1. Extremely Remote – Unlikely to occur