LOYAL BUILDING CONTRACTING LLC

DEMOLITION - METHOD STATEMENT, ITP AND RISK ASSESSMENT

 Demolition works
The scope of works involved in the demolition of the existing structures is as follows:

a) Obtain NOC’s from Etisalat, DEWA, and Drainage or any required NOC’s from the authorities.

b) Obtain demolition permit from DDA

c) Isolation of the Area.

d) Disconnection of services

e) Removal of loose and soft materials

f) Removal of roofing sheets

g) Dismantling truss, rafters, purlins etc.

h) Demolition of RCC slabs and masonry walls

i) Dismantling Structural Columns & Beams


1-Improbable 1-Negligible Likelihood X E-Eliminate Review by Approved by
Severity

Severity
Control

2-Remote 2-Minor
Likely

Risk

3-Occassional 3-Reportable High 15-25 I-Isolate


4-Probable 4-Serious Medium 7-12
5-Frequent 5-Catastrophic Low 1-6 R-Reduce
LOYAL BUILDING CONTRACTING LLC
DEMOLITION - METHOD STATEMENT, ITP AND RISK ASSESSMENT

j) Removal of salvage materials.

k) Demolition of flooring

l) Demolition of foundations

m)Cart away the demolition debris to the approved dumping yard

n) Backfilling and levelling the ground

METHODOLOGY

a) Local authority’s approval:

All the requirements of Local and Statutory Authorities regarding notification of demolition
works shall be complied.

1-Improbable 1-Negligible Likelihood X E-Eliminate Review by Approved by


Severity

Severity
Control

2-Remote 2-Minor
Likely

Risk

3-Occassional 3-Reportable High 15-25 I-Isolate


4-Probable 4-Serious Medium 7-12
5-Frequent 5-Catastrophic Low 1-6 R-Reduce
LOYAL BUILDING CONTRACTING LLC
DEMOLITION - METHOD STATEMENT, ITP AND RISK ASSESSMENT

b) Survey before Commencement:

Before starting the demolishing work, all the available drawings and documents will be studied
and carry out a through survey and examination of the building, structure or service to be demolished.

c) Record of unrestrained work and services / existing damages:

All the details with record drawings will be provided to client, showing the level, size, position
and contents of any abandoned services, foundations, underground chambers, wells, underground
tanks or any other work discovered during the demolition.

Any building, structure or services to be retained at site and any adjoining property or services
liable to be affected by demolition shall be examined before demolishing and any existing crack or
other evidence of damage shall be noted.

d) . Disconnection of Services:

1. Disconnection of electrical cables:

1-Improbable 1-Negligible Likelihood X E-Eliminate Review by Approved by


Severity

Severity
Control

2-Remote 2-Minor
Likely

Risk

3-Occassional 3-Reportable High 15-25 I-Isolate


4-Probable 4-Serious Medium 7-12
5-Frequent 5-Catastrophic Low 1-6 R-Reduce
LOYAL BUILDING CONTRACTING LLC
DEMOLITION - METHOD STATEMENT, ITP AND RISK ASSESSMENT

 Obtain necessary NOCs from the respective authority prior to start the work.

 Before starting demolition, the contractor shall arrange with the client and Statutory
Authorities, if applicable for the locating and marking of the position of all known services
affected by the work and for the proper disconnection of their mains supplies and cables.

 Any electrical cabling will be removed for recycling prior to soft stripping and the demolition of
the structure.
 No cable-stripping work will commence until the electrical supplies to the site have been
irreversibly isolated either to the main distribution board by the local electricity supply
company or from the main distribution board by a suitably qualified electrician.
 Hand tools will be used by the demolishing operatives to cut all the exposed electrical cables
and which are easily extracted, but which are not exposed.
 MEWPS will be used to remove the cables in the trays or the wire present above the floor level.
 The removal of cable insulation and armor is to be undertaken using a machine
 All waste generated by the cable-stripping is to be disposed of appropriately.

2. Disconnection of water services:

 All the water lines must be inspected before disconnecting it.


 Obtain NOC from DEWA, drainage or any other NOC if required.
 Safety induction program must be conducted to the workers involved in the
activity.

1-Improbable 1-Negligible Likelihood X E-Eliminate Review by Approved by


Severity

Severity
Control

2-Remote 2-Minor
Likely

Risk

3-Occassional 3-Reportable High 15-25 I-Isolate


4-Probable 4-Serious Medium 7-12
5-Frequent 5-Catastrophic Low 1-6 R-Reduce
LOYAL BUILDING CONTRACTING LLC
DEMOLITION - METHOD STATEMENT, ITP AND RISK ASSESSMENT

 Hand tools like grinders and PVC fittings will be used for the execution of work.

8. Soft Stripping:

1. Removal of doors/ windows, Aluminum Louvers

 An internal soft strip of the buildings will be carried out by demolition operatives to remove as
much of the waste materials from the building ahead of the demolition works.
 Materials that are to be removed by the internal soft strip can include doors, door frames, fixed
and non-fixed furniture, carpets and floor coverings and other materials which obstruct the
construction of asbestos removal enclosures.
 Operatives will strip out all doors, frames, and windows, timber of any description, toilets, pipe
work, electrical items and any debris.
 Any clean, unpainted constructional timber will be segregated from the general waste. Where
this material is free of nails, screws, hinges etc. it will be segregated for recycling and any
materials deemed as not suitable for recycling will be removed from site.

1-Improbable 1-Negligible Likelihood X E-Eliminate Review by Approved by


Severity

Severity
Control

2-Remote 2-Minor
Likely

Risk

3-Occassional 3-Reportable High 15-25 I-Isolate


4-Probable 4-Serious Medium 7-12
5-Frequent 5-Catastrophic Low 1-6 R-Reduce
LOYAL BUILDING CONTRACTING LLC
DEMOLITION - METHOD STATEMENT, ITP AND RISK ASSESSMENT

 Where possible the materials will be loaded by hand method into skips and removed from the
site. Where access for skips is not available the materials will be segregated and stored within
the building where they will be removed at a later stage.

2. Removal of false ceiling tile, Ac duct, Electrical Fittings

 Operatives will use Step ladder for stripping the fall ceiling tile and AC ducts.
 Ensure the step ladder is damage free and 3 point contact must 3-point contact (two
hands and a foot, or two feet and a hand) when climbing/ descending a ladder.

 Ensure that the ladder has been placed on a stable and level surface that is not
slippery.

 All the waste generated during the removal of fall ceiling tile is to be disposed of
appropriately.

1-Improbable 1-Negligible Likelihood X E-Eliminate Review by Approved by


Severity

Severity
Control

2-Remote 2-Minor
Likely

Risk

3-Occassional 3-Reportable High 15-25 I-Isolate


4-Probable 4-Serious Medium 7-12
5-Frequent 5-Catastrophic Low 1-6 R-Reduce
LOYAL BUILDING CONTRACTING LLC
DEMOLITION - METHOD STATEMENT, ITP AND RISK ASSESSMENT

9. Removing of roof sheet:

 Obtain work at height permit before the commencement of work.


 PPE must be worn at all times.
 Inspect the roof panel for any damage/ crack or broken panel.
 Locate skylight on the roof and check for any damage.
 Prior to start, provide the roof edge protection with the help of mewp
 Provide safety net at the work area and should be shifted as the work area shifts.
 First roof sheet panel to be removed from the ridge area of end wall. Removing the ridge
panel first and progress toward the rear side.
 Follow the pattern line by line towards the other side end wall.
 Ensure that the MEWP is certified and all the operators are 3rd party certified.
 All the equipment involved in the demolishing activity will be inspected and all the
personal shall be inducted and trained before they commence the work on site.
 All the removed screw should be secured properly and stored
 The entire removed panel to be packed in a bundle, not exceeding 8 panels.
 More caution to be considered while addressing the skylight panels.

1-Improbable 1-Negligible Likelihood X E-Eliminate Review by Approved by


Severity

Severity
Control

2-Remote 2-Minor
Likely

Risk

3-Occassional 3-Reportable High 15-25 I-Isolate


4-Probable 4-Serious Medium 7-12
5-Frequent 5-Catastrophic Low 1-6 R-Reduce
LOYAL BUILDING CONTRACTING LLC
DEMOLITION - METHOD STATEMENT, ITP AND RISK ASSESSMENT

 The old panel bundle to be offloaded to ground with mobile crane as the work progress.
 Stack the bundle properly in the ground and clear at the earliest.
 Remove the edge protection with the help of MEWP.

10. Removal of Wall cladding:

 First wall cladding panel to be removed from the ridge area of the end wall, removing
the ridge wall panel first and progressing towards the rear side.
 Follow the same pattern till removing the last wall panel.
 The entire removed wall panel should be secured properly and stored.
 All the removed panels to be attacked in a bundle not exceeding 8 panels.
 More caution to be taken during the shifting of the damaged wall panel.
 The entire waste panel must be removed from the site.

1-Improbable 1-Negligible Likelihood X E-Eliminate Review by Approved by


Severity

Severity
Control

2-Remote 2-Minor
Likely

Risk

3-Occassional 3-Reportable High 15-25 I-Isolate


4-Probable 4-Serious Medium 7-12
5-Frequent 5-Catastrophic Low 1-6 R-Reduce
LOYAL BUILDING CONTRACTING LLC
DEMOLITION - METHOD STATEMENT, ITP AND RISK ASSESSMENT

11. Demolition of Block Wall


1. The demolition works shall be executed for any existing structure only after obtaining the
requisite permission from the authorities.

2. The demolition area will be isolated prior to any kind of demolition.

3. The building to be demolished on site is of steel framed type structure, clad in corrugated
single ply steel sheeting.

4. All workers and staff will be given induction training and job specific instructions by the site
in charge.

5. Workers will be provided with PPE’s such as reflective jackets, safety belt, shoes, masks,
goggles, full body harness etc.

1-Improbable 1-Negligible Likelihood X E-Eliminate Review by Approved by


Severity

Severity
Control

2-Remote 2-Minor
Likely

Risk

3-Occassional 3-Reportable High 15-25 I-Isolate


4-Probable 4-Serious Medium 7-12
5-Frequent 5-Catastrophic Low 1-6 R-Reduce
LOYAL BUILDING CONTRACTING LLC
DEMOLITION - METHOD STATEMENT, ITP AND RISK ASSESSMENT

6. Prior to dismantling the block, all the fittings along the wall such as Windows, doors, duct
etc. to be removed.

7. The masonry walls and RCC slabs of the building will be dismantled thereafter using
Excavators fitted with bucket and breakers.

8. Care to be taken that, while the block wall dismantling area should be isolated and no person
should trespass.

8. Ensure the excavator is certified and the operator is 3 rd party certified.

9. The Concrete debris to be cleared from Site periodically.

12. Removal of steel structure office area.

 The office area consists of the roof panel and a mezzanine floor consisting of hollow core slab.

1-Improbable 1-Negligible Likelihood X E-Eliminate Review by Approved by


Severity

Severity
Control

2-Remote 2-Minor
Likely

Risk

3-Occassional 3-Reportable High 15-25 I-Isolate


4-Probable 4-Serious Medium 7-12
5-Frequent 5-Catastrophic Low 1-6 R-Reduce
LOYAL BUILDING CONTRACTING LLC
DEMOLITION - METHOD STATEMENT, ITP AND RISK ASSESSMENT

 After the removal of the roof panel, proceed with the removal of secondary members and the
hollow core slab bay by bay.
 Start from any one side of the office; consider one sequence frame consists of 4 columns.
 First remove the roof flange brace, sag rods and purling in this bay by soft stripping.
 Procced to remove the hollow core slab. Make 4 to 6 holes of 4” dia (depending on the panel
size) in the hollow core, lift each panel with the help of chain and crane arrangement.
 Once the secondary members and slab is removed, remove the steel beams and then steel
column.
 Repeat this pattern for the entire bay.
 The removed slab to be stacked properly and removed periodically.
 The removed steel member to be stacked properly and barricade should be provided.
 3rd party certified rigger should give signal to the crane.
 Experienced team will be appointed for the execution of the work.
 No person should stand below the suspended load or below the lifting area.
 Removal of bolts to be carried out by spanners and power tool such as tighter.

13. Removal of steel warehouse area.

 Now that roof sheet and wall sheet is removed, proceed with the dismantling of steel
structure.
 Start with the end wall and proceed bay by bay pattern.
 In the first bay, remove the roof flange brace, cross bracing, sag rods and then purling by soft
stripping.
1-Improbable 1-Negligible Likelihood X E-Eliminate Review by Approved by
Severity

Severity
Control

2-Remote 2-Minor
Likely

Risk

3-Occassional 3-Reportable High 15-25 I-Isolate


4-Probable 4-Serious Medium 7-12
5-Frequent 5-Catastrophic Low 1-6 R-Reduce
LOYAL BUILDING CONTRACTING LLC
DEMOLITION - METHOD STATEMENT, ITP AND RISK ASSESSMENT

 Once secondary members are removed, proceed with the primary members.
 Mobile crane of 25 ton to be used for all the primary members dismantling.
 Remove the end wall rafters, section by section depending up on the size of the rafter.
 Remove the wall purlin bay by bay and remove the particular end wall column.
 For the remaining main frame, remove secondary members, followed by dismantling of rafters
section by section depending on the size. Review the wall purling along the eave side and
remove the column along the eave side.
 Repeat this pattern towards the other end wall.

14. Removal of floor slab:

 Prior to the removal of the floor slab the area must be isolated and warning signboards must
be displayed.
 Once the steel structure is removed, the floor slab shall be demolished from any side.
 The demolition of flooring will be done using excavators fitted with breakers and buckets. The
tie beams will be demolished along with the flooring. The debris will be removed
intermittently.
 All the worker and the operator involved in the activity must be induced and RA must be
communicated to the work force.
 The debris that is generated during the activity will be stacked properly and removed
appropriately.

1-Improbable 1-Negligible Likelihood X E-Eliminate Review by Approved by


Severity

Severity
Control

2-Remote 2-Minor
Likely

Risk

3-Occassional 3-Reportable High 15-25 I-Isolate


4-Probable 4-Serious Medium 7-12
5-Frequent 5-Catastrophic Low 1-6 R-Reduce
LOYAL BUILDING CONTRACTING LLC
DEMOLITION - METHOD STATEMENT, ITP AND RISK ASSESSMENT

15. Removal of foundation:

 Once the floor is demolished excavation will be done to demolish the foundations. The
foundations are exposed and will be demolished using breakers. The reinforcement bars will
be cut and separated. The concrete debris etc. will be carted away to approved dump yard
using dump trucks.
 Excavation permit must be taken before doing the excavation work.

 The reinforcement bars will be cut and removed using gas cutters. The demolition will be done
up to the floor level. The debris will be removed using dump trucks at regular intervals.

 After clearing the debris, the foundation pits etc. will be backfilled and the area will be
levelled properly.

 The site will be then handed over to the Client.

1-Improbable 1-Negligible Likelihood X E-Eliminate Review by Approved by


Severity

Severity
Control

2-Remote 2-Minor
Likely

Risk

3-Occassional 3-Reportable High 15-25 I-Isolate


4-Probable 4-Serious Medium 7-12
5-Frequent 5-Catastrophic Low 1-6 R-Reduce
LOYAL BUILDING CONTRACTING LLC
DEMOLITION - METHOD STATEMENT, ITP AND RISK ASSESSMENT

INSPECTION & TEST PLAN (ITP)


Main Identfication Information
Document Revision Status Type of Inspection
System Subsystem
Plan Rev / Date
00M 01M 02M 03M H Hold point - Representative of indicated party to attened
(Mandatory)
Project Phase
(Manufacturing / Contractor Witness point - Representative of indicated party to be
Construction
Construction / Issuing W notified. If not attending at specified time, inspection may
Commossioning) proceed.

Contractor
Premises of
Consultant Review point - Representative of indicated party to review
Inspection / Site R
Approval submitted documents, result of test etc..
Work Area
Coordinates
Consultant Owner
Contractor
Acceptance
Criteria Specific
Activity Description of Inspection Drawing N" of
(Controlling Quality
NO & Test Activity reference Contractor CEC Punchlist
Procedure, Report
Signature Signature Item N"
Specifications, Code (If
Standars etc..) H W R H W R H W R any)

SAFETY MEASURES
1 TAKEN BEFORE
DEMOLITION WORK
2

1-Improbable 1-Negligible Likelihood X E-Eliminate Review by Approved by


Severity

Severity
Control

2-Remote 2-Minor
Likely

Risk

3-Occassional 3-Reportable High 15-25 I-Isolate


4-Probable 4-Serious Medium 7-12
5-Frequent 5-Catastrophic Low 1-6 R-Reduce
LOYAL BUILDING CONTRACTING LLC
DEMOLITION - METHOD STATEMENT, ITP AND RISK ASSESSMENT

Task/Job/Operation: DEMOLITION Project: : PROPOSED G-OLY OFFICE, G+M WORKERS Ref No: RA- REV-00
LBC-001
FACILITY, G-ONLY SHED, OPENSHED & OPEN WASH AREA
Main Contractor: LOYAL BUILDING CONTRACTING LLC. ON PLOT NO. 5337865 @ SAIH SHUAIB 4, DUBAI Risk Assessor:
Client: SILVERLINE CONSTRUCTION AND MACHINERY RENTAL LLC Mr. JAMES NEEL (SO)
Consultant: DESIGN HOUSE ENGINEERING

Date : 05-02-2020 Date Next Review: 05-08-2020 Approved By: Reviewed By:
Mr. MUTHUKUMAR (PM) Mr. JOSHUA PRAVIN (SR.SO)

Recommended PPE: Hard Hat, Safety shoes, Safety Harness, coveralls, dust mask,
Equipment Required: Excavator
goggles, gloves

Legal compliance
Harm/ Consequences

Remarks
Risk

Risks / Who might be


Residual
Rating/
Risk
Risk level

Control E/I/R
Job steps/ Activities

/Potential Hazards
Hazard identified

L S R
Sl no

Mitigation action to be taken/ Hazard/Risk


Control Method
L S R

 The whole working area must be properly


Accident to other
Major/Minor injury isolated from other unauthorized
Isolation of the people who is not
1 due to unprotected personnel. Watch person to be provided 1 3 L
area involved in the No 3 3 M R
demolition area. to aware other people of the ongoing
activity. activity.

2 Dis connection of all Major/ minor injury Physical injury to Yes 3 4 M R  All the utility services including water line 1 4 L
the workers and Cables should be disconnected before

1-Improbable 1-Negligible Likelihood X E-Eliminate Review by Approved by


Severity

Severity
Control

2-Remote 2-Minor
Likely

Risk

3-Occassional 3-Reportable High 15-25 I-Isolate


4-Probable 4-Serious Medium 7-12
5-Frequent 5-Catastrophic Low 1-6 R-Reduce
LOYAL BUILDING CONTRACTING LLC
DEMOLITION - METHOD STATEMENT, ITP AND RISK ASSESSMENT

complianceLegal

Remarks
Risks / Who

E/I/RControl
Risk
Job steps/

/Potential
identified
Residual
Activities

Hazards

might be
Hazard
Rating/
Sl no

Harm/
Mitigation action to be taken/ Hazard/Risk Risk
Risk level Control Method
L S R L S R
demolition process start.
 Respective NOC’s should be obtained
from the concerned Authority prior to
commencement of work.
 Tool box must be conducted and it must
be documented.
 Supervisor must be available at site during
involved in the
the services. due to utility services. dismantling the electrical cables.
activity.  Waste debris raised during this process
must be removed immediately.
 Hand gloves must be issued to workers
who are handling sharp edge object.
 3rd party certified MEWP must be used.
 Ensure the operator has a valid 3rd party
training card.

 The whole working area must be properly


Accident to other isolated from unauthorized personnel.
people who is not Watch person to be provided to aware
Major/ Minor injury involved in the other people of the on- going activity.
Preparation of the due to unprotected activity.  The slab and other structure to be
3 No 3 5 H R
area unprotected demolished must be protected to prevent 1 5 L
demolition area. All workers from toppling over.
involved in the  Safe access must be provided for going in
activity. and out of the working area.

Preparation of the Major/ Minor injury Accident due to not  Site engineer together with safety officer 1 5 L
4 Yes 3 5 H R
workers. due to unprotected following the safety will conduct a tool box talk, with the
1-Improbable 1-Negligible Likelihood X E-Eliminate Review by Approved by
Severity

Severity
Control

2-Remote 2-Minor
Likely

Risk

3-Occassional 3-Reportable High 15-25 I-Isolate


4-Probable 4-Serious Medium 7-12
5-Frequent 5-Catastrophic Low 1-6 R-Reduce
LOYAL BUILDING CONTRACTING LLC
DEMOLITION - METHOD STATEMENT, ITP AND RISK ASSESSMENT

complianceLegal

Remarks
Risks / Who

E/I/RControl
Risk
Job steps/

/Potential
identified
Residual
Activities

Hazards

might be
Hazard
Rating/
Sl no

Harm/
Mitigation action to be taken/ Hazard/Risk Risk
Risk level Control Method
L S R L S R
involved group before commencing the
job.
 MS and RA must be communicated to the
unprotected site operatives and is recorded.
procedures.
demolition area.  Only competent person shall be permitted
to carry out the demolition activity.
 Full time supervisor to facilitate and look
over and monitor the whole operation.
5 Removing of roof Fall from height. Injury to the Yes 3 5 H R  Edge protection must be provided over 1 5
sheet and wall workers involved in the roof sheet.
Object falling from
cladding the activity.  Edge protection post to be installed using L
height,
MEWP. Ensure that MEWP and operator
is 3rd party certified
 Provide roof access and avoid using
MEWP for accessing roof.
 Safety net will be provided beneath the
roof sheet to prevent the person falling
from height.
 Tool box talk must be conducted regarding the
hazard and risk associated with the removal of
existing roof sheet.
 Where tools or equipment are being
used adjacent to a roof edge and there is
a risk of falling of objects, in order to
prevent, the objects must be attached to
the safety lanyard.

 The Old panels should be brought to


1-Improbable 1-Negligible Likelihood X E-Eliminate Review by Approved by
Severity

Severity
Control

2-Remote 2-Minor
Likely

Risk

3-Occassional 3-Reportable High 15-25 I-Isolate


4-Probable 4-Serious Medium 7-12
5-Frequent 5-Catastrophic Low 1-6 R-Reduce
LOYAL BUILDING CONTRACTING LLC
DEMOLITION - METHOD STATEMENT, ITP AND RISK ASSESSMENT

complianceLegal

Remarks
Risks / Who

E/I/RControl
Risk
Job steps/

/Potential
identified
Residual
Activities

Hazards

might be
Hazard
Rating/
Sl no

Harm/
Mitigation action to be taken/ Hazard/Risk Risk
Risk level Control Method
L S R L S R
ground periodically to avoid over stacking
of panels in the roof.

 Eye protection, gloves and suitable


clothing to be worn.
 Ensure all staff who undertake cutting/
burning duties are competent to do so.
DEATH, FIRE,  Hot work to be supervised closely and
Gas cutting and Injury to the
EXPLOSION OR undertaken only under A Hot Work 2 2 L
6 workers involved in No 3 3 M R
burning BURNS and ILL Permit issued by Safety officer.
the activity.
EFFECTS ON HEALTH  Flashback arresters and non-return
valves must be fitted to gas hoses and
bottles.
 Hose lengths should be kept to a
minimum
 Make sure that the area is isolated
 Keep the area clean such that no
machines or materials are stored in the
area
Major Injury to
Collapse of block wall  Keep adequate signboards 2 4 M
7 Block Wall person, or property Yes 4 4 H R
on material or Person  The Excavators and its operator to be 3rd
damage
party certified
 Spray water periodically to avoid dust
pollution
 Remove the concrete waste periodically
8 Soft Stripping Minor Injury Physical injury and Yes 3 4 H R  Tool box talks to be given before 1 4 L
hand injury to the commencing the activity
workers involved.  Suitable PPE like Safety shoe and safety

1-Improbable 1-Negligible Likelihood X E-Eliminate Review by Approved by


Severity

Severity
Control

2-Remote 2-Minor
Likely

Risk

3-Occassional 3-Reportable High 15-25 I-Isolate


4-Probable 4-Serious Medium 7-12
5-Frequent 5-Catastrophic Low 1-6 R-Reduce
LOYAL BUILDING CONTRACTING LLC
DEMOLITION - METHOD STATEMENT, ITP AND RISK ASSESSMENT

complianceLegal

Remarks
Risks / Who

E/I/RControl
Risk
Job steps/

/Potential
identified
Residual
Activities

Hazards

might be
Hazard
Rating/
Sl no

Harm/
Mitigation action to be taken/ Hazard/Risk Risk
Risk level Control Method
L S R L S R
gloves to be worn by the workers.
 Ear protection to be provided for the
workers.
 All debris to be segregated and stockpile
by plant ready for disposal.
1.Serious injury,
death due to person
being knocked by
 Strictly comply with PTW system.
crane part.
2.unstable groung  All the crane operators and riggers must
causing machine to have trakhees approved 3rd party
tip over and trap Equipment certificate.
Use of crane for operator or other 1
9 damage, personal No 3 5 M R  Ensure all safety and operational 5 L
lifting. workers. injury instructions are followed as per the MS.
3. high wing causing  Only trakhees approved third party
loss of control of laod riggers would be authorized to give signal.
4.Unauthorized  Work will not be permitted, if wind speed
person using crane. reaches 30 KM/HR
5.load falling due to
improper securing
10 Demolition of the 1.Trip, slip, fall All the workers No 3 3 M R  Competent supervisor must monitor the 2 3 L
area. involved in the working area to ensure that the proper
2.over exposed to
activity. procedure of demolition is followed as
vibration.
mentioned in MS
3. Dust generated  Full body Harness must be worn by the
during demolition. worker, where there is a tendency of
falling from height.
1-Improbable 1-Negligible Likelihood X E-Eliminate Review by Approved by
Severity

Severity
Control

2-Remote 2-Minor
Likely

Risk

3-Occassional 3-Reportable High 15-25 I-Isolate


4-Probable 4-Serious Medium 7-12
5-Frequent 5-Catastrophic Low 1-6 R-Reduce
LOYAL BUILDING CONTRACTING LLC
DEMOLITION - METHOD STATEMENT, ITP AND RISK ASSESSMENT

complianceLegal

Remarks
Risks / Who

E/I/RControl
Risk
Job steps/

/Potential
identified
Residual
Activities

Hazards

might be
Hazard
Rating/
Sl no

Harm/
Mitigation action to be taken/ Hazard/Risk Risk
Risk level Control Method
L S R L S R
 Suitable PPE like safety shoe and safety
gloves to be worn by workers.
 Dust mask to be provided for the workers
involved in the activity.
 Worker handling hilti/ Jackhammers must
be given ample time to recover from the
impact of this equipment.

 Spray Water periodically to avoid dust


pollution
Respiratory Problems, Workers health  Provide dust mask to Labors as per the 1 2 L
11 Dust Pollution No 3 2 L R
Poor Visibilty issues requirement
 Provide Goggles to labors as per the
requirement
 Noise to be controlled and reduced to as
low as is reasonably practical through the
careful selection of plant and method of
demolition.
 when noise is believed to be above 80
All the workers
Noise emitted during dBA (i.e. when you have to raise your 2 2 L
12 Noise Pollution involved in the No 3 3 M R
demolition work. voice to be heard two metre away).
activity.
Appropriate hearing protection to be
issued and worn.
 Provide information, instruction and
supervision when and how to correctly
use hearing protection
12 Housekeeping Accumulation of Slip, trip and fall Yes 4 3 H R  Debris collection and disposal must be 2 3 M
waste/ working area hazard. supervised to avoid congestion of the

1-Improbable 1-Negligible Likelihood X E-Eliminate Review by Approved by


Severity

Severity
Control

2-Remote 2-Minor
Likely

Risk

3-Occassional 3-Reportable High 15-25 I-Isolate


4-Probable 4-Serious Medium 7-12
5-Frequent 5-Catastrophic Low 1-6 R-Reduce
LOYAL BUILDING CONTRACTING LLC
DEMOLITION - METHOD STATEMENT, ITP AND RISK ASSESSMENT

complianceLegal

Remarks
Risks / Who

E/I/RControl
Risk
Job steps/

/Potential
identified
Residual
Activities

Hazards

might be
Hazard
Rating/
Sl no

Harm/
Mitigation action to be taken/ Hazard/Risk Risk
Risk level Control Method
L S R L S R
working area.
 Housekeeping shall be provided as the
congestion work is on- going were accumulated
debris are to be removed to sustain a
workable area.

Health and Safety


1. In case of Near Miss, Accidents or Emergencies call – (HSE Incharge-0551099321)
2. This Standard Risk Assessment may be revised to suit the site condition.
3. All persons will familiarize themselves and conform to project HSE rules and requirements and wear Basic PPE (Hard Hat, High-Viz Vest and Steel Toe Safety
Shoes) at all times – use additional PPE required by the job.
4. Only trained and certified operators shall operate vehicles and mobile construction machinery. Proof of competence will be available with the operator at all
times for site verification
5. Use of mobile phones during working hours is prohibited, except for emergency reporting only.
6. No eating, smoking and sleeping at the construction worksite. Use the facilities provided on site
7. Do not use defective PPE, tools, machinery, or equipment – get them replaced before you start your work
8. Report all near misses and accidents immediately to HSE In charge and your work leader
9. Work leaders are accountable for the behaviour of their operatives
10. Conduct a Tool Box Talk, Risk Assessment Review or issue safety instructions before the start of the day’s work.
11. Copy of this Risk Assessment available on site
Environmental
1. All waste materials will removed daily from the wok area and transferred to the designated waste skip
2. All Hazardous waste shall be immediately removed as per UAE regulation and dispatched slip maintained.
Risk Assessment Methodology

1. Identify Hazards

2. List Hazard Event


1-Improbable 1-Negligible Likelihood X E-Eliminate Review by Approved by
Severity

Severity
Control

2-Remote 2-Minor
Likely

Risk

3-Occassional 3-Reportable High 15-25 I-Isolate


4-Probable 4-Serious Medium 7-12
5-Frequent 5-Catastrophic Low 1-6 R-Reduce
LOYAL BUILDING CONTRACTING LLC
DEMOLITION - METHOD STATEMENT, ITP AND RISK ASSESSMENT

3. Calculate Risk Factor with Initial Risk Rating. I.E. Probability x Severity

4. Detail Controls

5. Calculate Residual Risk Rating with Final Risk Rating

6. Enter Risk Priority

7. Evaluate Acceptability of Risk

Risk Factor Matrix


Probability RISK PRIORITY

4 3 2 1 8-16 High Risk


Severity

4 16 12 8 4 6 Medium Risk

3 12 9 6 3 1-4 Low Risk

2 8 6 4 2

Severity

4. Catastrophic – Imminent danger exists, hazard capable of causing death or illness on a wide scale

3. Critical – Hazard can result in serious illness, severe injury, and property and equipment damage
1-Improbable 1-Negligible Likelihood X E-Eliminate Review by Approved by
Severity

Severity
Control

2-Remote 2-Minor
Likely

Risk

3-Occassional 3-Reportable High 15-25 I-Isolate


4-Probable 4-Serious Medium 7-12
5-Frequent 5-Catastrophic Low 1-6 R-Reduce
LOYAL BUILDING CONTRACTING LLC
DEMOLITION - METHOD STATEMENT, ITP AND RISK ASSESSMENT

2. Marginal – Hazard can cause illness, injury or equipment damage, but the results would not be expected to be serious

1. Negligible – Hazard will not result in serious injury or illness, remote possibility of damage beyond minor first aid case

Probability

4. Probable – Likely to occur immediately or shortly

3. Reasonably Probable – Probably will occur in time

2. Remote – May occur in time

1. Extremely Remote – Unlikely to occur

1-Improbable 1-Negligible Likelihood X E-Eliminate Review by Approved by


Severity

Severity
Control

2-Remote 2-Minor
Likely

Risk

3-Occassional 3-Reportable High 15-25 I-Isolate


4-Probable 4-Serious Medium 7-12
5-Frequent 5-Catastrophic Low 1-6 R-Reduce