SITE VISIT REPORT

CONVOCATIONAL HALL

EAT357

CONSTRUCTION MANAGEMENT

NAME: TUAN MOHD SHAHRIL ARIF BIN TUAN MOHD


NASIR

MATRIC NUMBER: 171200490

SCHOOL: PUSAT PENGAJIAN KEJURUTERAAN ALAM


SEKITAR

COURSE: RK01 KEJURUTERAAN AWAM

LECTURER’S NAME: DR SALWA MOHD ZAINI MAKHTAR


INTRODUCTION:

A site visit to Universiti Malaysia Perlis convocational hall was organized on 25


October 2019 by Dr Salwa Mohd Zaini Makhtar. All the safety precautions was gave by the
lecturer such as wearing safety helmet and safety shoes. Based on the plan, all the students of
EAT357 gathered at station bus at Kolej Kediaman Tan Sri Aishah Ghani around 8:00am to
take a bus to go the convocational hall. We arrived at the convocational hall at 8:30am, then
we gathered at the site cabin to meeting with the people in charge of guiding us, a short brief
about the project was given by contractor and safety health officer of the convocational hall
project. After that, we started the tour around the site.

The project that we visited is located at Universiti Malaysia Perlis campus Pauh Putra.
This convocational hall started at 30 October 2017 and expected to be completed by
September 2019 but this project delayed about 70 days because not enough worker and will
complete by February 2020. This project cost approximately RM26.5 Million. The size of
this convocational hall is around 50m x 60m and can enter 3000-4000 capacity. The height of
this convocational hall is 22m. This project have complete 60% and 40% is not complete.
This project use 95% conventional system and 5% IBS system.
DETAILS OF CONTRACT:

TITLE OF PROJECT UNIVERSITI MALAYSIA PERLIS –


CONSTRUCTION CONVOCATIONAL HALL
OWNER MINISTRY OF EDUCATION MALAYSIA HIGH
SCHOOL SECTOR
Jalan P5/6 Presint 56200 Putrajaya
Wilayah Persekutuan Putrajaya
ENFORCEMENT OFFICER DIRECTOR OF THE DEPARTMENT OF PUBLIC
WORKS
KM 3, Jalan Raja Syed Alwi
01000 Kangar , Perlis
ARCHITECT ARCHITECTURE OF THE OFFICE OF THE
PUBLIC WORKSHOP DEPARTMENT
KM 3, Jalan Raja Syed Alwi
01000 Kangar , Perlis
ELECTRIC ENGINEER HEAD OF STATE ELECTRICAL ENGINEERING
Jabatan Kerjaraya Negeri Perlis
KM 3, Jalan Raja Syed Alwi, 01000 Kangar, Perlis.
MECHANICAL ENGINEER HEAD OF STATE MECHANICAL ENGINEERING
Jabatan Kerjaraya Negeri Perlis
KM 3, Jalan Raja Syed Alwi,
01000 Kangar, Perlis.
MAIN CONTRACTOR AMNA CONSTRUCTION SDN BHD
No. 297, Tingkat Atas, Jalan Shahab 1,
Kompleks Shahab Perdana,
05150 Alor Setar, Kedah Darul Aman.
No Tel: 04-7354588 Fax:04-7304588
PRICE OF CONTRACT RM 26563647.48
PERIOD OF CONTRACT 100 Weeks
START DATE 30 October 2017
FINISH DATE 29 September 2019
FINISH DATE (EXTEND) 3 February 2020
SCOPE OF CONTRACT

CONTRACT VALUE RM 26,563,647.48


CONTRACT VALUE 100 WEEKS
COMMENCEMENT DATE 30 0CTOBER 2017
COMPLETION DATE 29 SEPTEMBER 2019

ADDITIONAL PERIOD: 03 FEBRUARI 2020


SCOPE OF WORK INVOLVE PRELIMINARIES

BUILDING WORKS
• MAIN HALL BLOCK
• MAIN SUPPLY BASE HOUSE
• PUMP HOUSE
• CHILLER ROOM
EXTERNAL WORK
INTERNAL COLD WATER SUPPLY
SYSTEM

PRIME COST

S-CURVE FOR FINANCE


S-CURVE PHYSICAL

S-CURVE FINANCE VS PHYSICAL