Batch 1. Compiled Oblicon Cases

You might also like

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 30

Case 1: JUAN F. VILLARROEL, defendant, vs.

RULING:

BERNARDINO ESTRADA, plaintiff. Findings of the lower Court:

TOPIC: Article 1156. An obligation is a juridical necessity to give, to do or The Court of First Instance of Laguna, in which this action was
not to do. filed, ordered the defendant to pay the plaintiff the amount claimed of
P1,000 with his legal interests of 12 percent a year from August 9, 1930
Doctrine:
to its full payment. Appeal of this sentence. Villaroel (defendant)
Natural Obligation - cannot be enforced by action, but appealed.
which is binding on the party who makes it in conscience and
Findings of the Court of Appeals: not stated in the full case
according to the natural law.
Rule: Yes. On August 9, 1930. He assumed the fulfillment of the
FACTS:
obligation. Villaroel voluntarily wanted to assume this obligation. The
On May 9, 1912, Alejandro F. Callao, the mother of the defendant appealed sentence is confirmed, with costs to the defendant.
Juan F. Villarroel, obtained from the Mariano Estrada and Severina
APPLICATION:
spouses a loan of P1,000 payable after seven years. Alejandra, passed
away, leaving Villaroel (defendant) as sole heir. The spouses Mariano The present action is not based on the original obligation
Estrada and Severina also passed away, leaving Bernardino Estrada contracted by the defendant's mother, which has already been
(plaintiff) as sole heir. On August 9, 1930, the defendant signed a prescribed, but on the one contracted by the defendant on August 9,
document in which he declared in owing the amount of P1,000, with an 1930 upon assuming compliance with that obligation, already
interest of 12 percent per year. This action is about the collection of this prescribed. The defendant being the sole heir of the original debtor, with
amount. the right to succeed him in his inheritance, that debt legally brought by
his mother, although it lost its effectiveness by prescription, is now,
A. Defendant Arguments – the action to recover the original debt
however, for him a moral obligation.
has already prescribed when the claim was filed in this case
B. Plaintiff Arguments – action is not based on the original The rule that a new promise to pay a prescreened debt must be
obligation contracted by the defendant's mother, which has made by the same obligated person or by another legally authorized by
already been prescribed, but on the one contracted by the it, is not applicable to the present case in which it is not required
defendant on August 9, 1930 upon assuming compliance with compliance with the obligation of the obligor originally, but which you
that obligation, already prescribed voluntarily wanted to assume this obligation.

ISSUE: WON Villaroel should pay the amount despite the prescription of CONCLUSION:
the original debt
The case was not being based on the positive law but on equity and Case 2: Fisher vs. Robb (69 Phil 101)
natural law that do not grant a right of action to enforce their
Facts:
performance, but only after voluntary fulfillment by the obligor, they
authorize what has been delivered or rendered by reason thereof. Defendant John C. Robb was told by the board of directors of the
Philippine Greyhound Club, Inc. to make a business trip to Shanghai to
study the operation of a dog racing course. In Shanghai, defendant met
plaintiff A.O. Fisher who was a manager of a dog racing course. Plaintiff
upon knowing defendant’s purpose of his trip, became interested in the
Philippine Greyhound Club and asked defendant if he could be one of
the stockholders. Defendant answered in affirmative which thereupon
filed a blank subscription and sent Greyhound Club Php3,000 in payment
of the first installment of his subscription. Upon receiving a call from the
said club, he paid the second installment amounting to Php2,000. Due to
manipulations of those who control the said club and during defendant’s
absence, the company was changed to “Philippine Racing Club.”
Defendant endeavored the investments of those who subscribed,
particularly of that of plaintiff. Defendant,. through sending a letter,
assured plaintiff for any loss which he might suffer in connection with
Philippine Greyhound Club in the same that he could not expect anyone
to reimburse him for his own losses which were more than that of
plaintiff.

Issue:

Whether a moral obligation will sustain an express executory promise?

Held:

No. Defendant, although morally responsible because of the failure of


the enterprise, is not a consideration under Article 1261 of the Civil Code
as an essential element for the legal existence for an onerous contract
which could bind the promisor to comply with his promise.
Article 1261 states, “there is no contract unless the following requisites Case 3: BARREDO (Defendant-Petitioner) v. GARCIA AND ALMIRIO
exists: consent of the contracting parties; definite object; consideration.” (Plaintiff-Respondents)
In the present case, it does not appear that plaintiff consented to the
Facts:
said form of reimbursement. The first requisite of 1261 is lacking.
May 3, 1936 on the road between Malabon and Navotas, province of
With regards of the third requisite, it is now a well-established rule that
Rizal, there was a head-on collision between a taxi of the Malate Taxicab
a mere moral obligation arising from wholly ethical motives not
driven by Pedro Fontanilla and a carretela guided by Pedro Dimapalis.
connected with any legal obligation will not furnish a consideration from
The carretela was overturned, and one of its passengers, 16 years old
an executory promise. boy Faustino Garcia, suffered injuries from which he died two days later.
A criminal action was filed against Fontanilla and he was convicted.

Severino Garcia and Timotea Almario, parents of the deceased on March


7, 1939, brought an action in the Court of First Instance of Manila
against Fausto Barredo as the sole proprietor of the Malate Taxicab and
employer of Pedro Fontanilla.

Fausto Barredo is shown to be careless in employing Fontanilla who had


been caught for several times for violation of the automobile law and
speeding. The defense is that the liability is only subsidiary, and as there
has been no civil action against Pedro Fontanilla, the person criminally
liable, Barredo cannot be held responsible in the case.

Issue:

Whether or not they can file for a separate civil action against Fausto
Barredo making him primarily and directly responsible.

Ruling: (Note: The Barredo case was decided by the Supreme Court prior
to the present Civil Code. However, the principle enunciated in said case,
that responsibility for fault or negligence as quasi-delict
is distinct and separate from negligence penalized under
the Revised Penal Code, is now specifically embodied in Art. 2177 of the
Civil Code.)
Yes. Authorities support the proposition that a quasi-delict or “culpa “1. That crimes affect the public interest, while quasi-delitos are only of
aquiliana” is a separate legal institution under the Civil Code with a private concern.
substantivity all its own, and individually that is entirely apart and
independent from delict or crime. “2. That consequently, the Penal Code punishes or corrects the
criminal act, while the Civil Code, by means of indemnification, merely
To decide the main issue, we must cut thru the tangle that has, in the repairs the damage.
minds of many, confused and jumbled together delitos and cuasi delitos,
or crimes under the Penal Code and fault “3. That delicts are not as broad as quasi-delicts, because for the former
or negligence under Articles 1902-1910 of the Civil Code. According to are punished only if there is a penal law clearly covering them, while the
the Supreme Tribunal of Spain: latter, cuasi-delitos, include all acts in which ‘ any kind of fault
or negligence intervenes.’ However, it should be noted that not all
“Authorities support the proposition that a quasi-delict or ‘culpa violations of the penal law produce civil responsibility, such as begging in
aquiliana’ is a separate legal institution under the Civil Code, with a contravention of ordinances, violation of the game laws, infraction of the
substantivity all its own, and individuality that is entirely apart and rules of traffic when nobody is hurt.
independent from a delict or crime. Upon this principle, and on the
wording and spirit of Article 1903 of the Civil Code, the primary and “The foregoing authorities clearly demonstrate the separate individuality
direct responsibility of employers may be safely anchored. of cuasi-delitos or culpa aquiliana under the Civil Code. Specifically they
show that there is a distinction between civil liability arising from
“It will thus be seen that while the terms of Article 1902 of the Civil Code criminal negligence (governed by the Penal Code) and responsibility for
seem to be broad enough to cover the driver’s negligence in the instant fault or negligence under Articles 1902 to 1910 of the Civil Code, and
case, nevertheless Article 1903 limits cuasi-delitos TO ACTS OR that the same negligent act may produce either a civil liability arising
OMISSIONS ‘NOT PUNISHABLE BY LAW.’ But inasmuch as Article 365 of from a crime under the Penal Code, or a separate responsibility for fault
the Revised Penal Code punishes not only reckless but even simple or negligence under Articles 1902 to 1910 of the Civil Code. Still more
imprudence or negligence, the fault or negligence under Article 1902 of concretely the authorities above cited render it inescapable to conclude
the Civil Code has apparently been crowded out. It is this overlapping that the employer – in this case the defendant-petitioner – is primarily
that makes the “confusion worse confounded.’ However, a closer study and directly liable under Article 1903 of the Civil Code.”
shows that such a concurrence of scope in regard to negligent acts does
not destroy the distinction between the civil liability arising from a crime
and the responsibility for cuasi-delitos or culpa extra-contractual. The
same negligent act causing damages may produce civil liability arising
from a crime under Article 100 of the Revised Penal Code; or create an
action for cuasi-delito or culpa extra-contractual under Articles 1902-
1910 of the Civil Code. “Some of the differences between crimes under
the Penal Code are:
Case 4: Mendoza v. Arrieta In Timbol’s case, the respondent judge wrongfully sustained
G.R. No. L-32599, June 29, 1979, 91 SCRA 113 Timbol’s allegations that the civil suit is barred by the prior joint
judgment in a criminal case filed against him, wherein no reservation to
file a separate case was made by petitioner and where the latter actively
FACTS: A three- way vehicular accident involving a Mercedes Benz
participated in the trial and tried to prove damages against Salazar only.
owned and driven by petitioner; a private jeep owned and driven by
For petitioner’s cause of action against Timbol in the civil case is based
respondent Rodolfo Salazar; and a gravel and sand truck owned by
on quasi-delict. Respondent Judge committed reversible error when he
respondent Felipino Timbol and driven by Freddie Montoya. As a
dismissed the civil suit against the truck-owner, as said case may
consequence of said mishap, two separate Informations for Reckless
proceed independently of criminal proceedings and regardless of the
Imprudence Causing Damage to Property were filed against Rodolfo
result of the latter. Article 31 if the Civil Code provides that, “When the
Salazar and Freddie Montoya. The trial Court absolved jeep-owner-driver
civil action is based on an obligation not arising from the act or omission
Salazar of any liability, civil and criminal, in view of its findings that the
complained of as a felony, such civil action may proceed independently
collision between Salazar’s jeep and petitioner’s car was the result of the
of the criminal proceedings and regardless of the result of the latter.”
former having been bumped from behind by the truck driven by
Timbol’s submission that petitioner’s failure to make a reservation in the
Montoya. Neither was petitioner awarded damages as he was not a
criminal action of his right to file an independent civil action, as required
complainant against truck-driver Montoya but only against jeep- owner-
under Section 2, Rule 111, Rules of Court, bars the institution of such
driver Salazar.
separate civil action is untenable. For inasmuch as Article 31 of the Civil
After the termination of the criminal cases, petitioner filed a civil Code creates a civil liability distinct and different from the civil action
case against respondents jeep-owner-driver Salazar and Felino Timbol, arising from the offense of negligence under the RPC, no reservation is
the latter being the owner of the gravel and sand truck driven by required to be made in the criminal case. And so, the civil case filed
Montoya, for indemnification for the damages sustained by his car as a against Timbol is not barred by the fact that petitioner failed to reserve,
result of the collision involving their vehicles. Jeep-owner-driver Salazar in the criminal action, his right to file an independent civil action based
and truck- owner Timbol were joined as defendants, either in the on quasi-delict.
alternative or in solidum allegedly for the reason that petitioner was
Insofar as Salazar is concerned, petitioner had opted to base his
uncertain as to whether he was entitled to relief against both on only
cause of action against jeep-owner-driver Salazar on culpa criminal and
one of them. Respondent Judge dismissed the Complaint against truck-
not on culpa aquiliana as evidenced by his active participation and
owner Timbol and jeep- owner-driver Salazar.
intervention in the prosecution of the criminal suit against said Salazar.
ISSUE: Whether or not the lower court in dismissing petitioner’s The latter’s civil liability continued to be involved in the criminal action
complaint for damages based on quasi-delict against private until its termination. Such being the case, there was no need for
respondents petitioner to have reserved his right to file a separate civil action as his
action for civil liability was deemed impliedly instituted in criminal case.
RULING: Timbol was liable for damages, Salazar was not. Jeep-owner-driver Salazar cannot be held liable for the damages
sustained by petitioner’s car. In other words, “the fact from which the Case 5: SONG Fo. & Company, plaintiff-appellee vs.
civil might arise did not exist.” And even if petitioner’s cause of action as HAWAIIAN PHILIPPINE Co., defendant-appelant
against jeep-owner-driver Salazar were not ex-delictu, the end result G.R # 47 Phil 821
would be the same, it being clear from the judgment in the criminal case September 16, 2019
that Salazar’s acquittal was not based upon reasonable doubt,
consequently, a civil action for damages can no longer be instituted. This TOPIC: Obligations
is explicitly provided for in Article 29 of the Civil Code quoted here
FACTS: A written contract between Song Fo & Co. and Hawaiian-
under: Art. 29. When the accused in a criminal prosecution is acquitted
Philippine Co. was made. They have agreed to deliver 300,000 gallons of
on the ground that his guilt has not been proved beyond reasonable
molasses. Mr. Song Heng, the representative of Song Fo & Co.,
doubt, a civil action for damages for the same act or omission may be
demanded that an additional 100,000 gallons be delivered. It was
instituted. Such action requires only a preponderance of evidence … If in written as follows: “Mr. Song Fo also asked if we could supply him with
a criminal case the judgment of acquittal is based upon reasonable another 100,000 gallons of molasses, and we stated we believe that this
doubt, the court shall so declare. In the absence of any declaration to is possible and will do our best to let you have these 100,000 gallons….”
that effect, it may be inferred from the text of the decision whether or The payment of these molasses shall be done at the end of the month.
not the acquittal is due to that ground.
a.) Plaintiff-Appellee’s arguments (SONG Fo & Company – WON)
Thus, the case filed by Mendoza against Timbol may prosper as
Filed a case for damages against Defendant-Appelant for breach
the liability is based on the responsibility of the employer to the quasi-
of contract for failure of the latter to deliver the remaining
delict of his employee. The case filed against Salazar cannot prosper as molasses.
the same is barred by res judicata.
b.) Defendant-Appelant ‘s Arguments (Hawaiian Philippine Co. –
LOST)
Argued that it was compelled to cancel and rescind the said
contract because Plaintiff-Appellee had defaulted in the
payment for the molasses delivered to it under the contract
between the parties.

ISSUE: Whether or not Hawaiian Philippine Co. had the right to rescind
the contract of sale made with Song Fo & Co.?

Findings of the Lower Court:


In favour of Song Fo & Company.
Ordered the Hawaiian Philippine Co. to pay 70,369.50 with legal Case 6: Sps. Velarde v. Court of Appeals, G.R. No. 108346, [July 11,
interests and costs. 2001], 413 PHIL 360-376

Findings of the Court of Appeals: FACTS:


In favour of Song Fo & Company Petitioners entered into a deed of sale with assumption of mortgage
The judgement condemned Hawaiian Philippine Co. to pay 35,317.93
with private respondents paying a downpayment of P800,000 and
with legal interest from the date of the presentation of the complaint,
assuming the mortgage amount of P1.8M in favor of BPI. Petitioners
and with costs.
further agreed "to strictly and faithfully comply with all the terms and
RULING: conditions appearing in the real estate mortgage signed and executed by
No, Defendant-appellant cannot rescind. the vendor in favor of BPI . . . as if the same were originally signed and
executed by the vendee." As part of the deed, petitioner Avelina with
RULE: her husband's consent executed an undertaking that during the
Rescission will not be permitted for a slight or casual breach of contract, pendency of the application for the assumption of mortgage she agreed
but only for such breaches as are so substantial and fundamental as to to continue paying said loan in accordance with the mortgage deed and
defeat the object of properties in making the agreement. A delay in the that in the event of violation of any of the terms and conditions of the
payment for a small quantity of molasses for some twenty days is not deed of real estate mortgage, she agreed that the P800,000
such a violation of an essential condition of the contract as warrants downpayment shall be forfeited as liquidated damages and the deed of
rescission for non performance. sale with assumption of mortgage shall be deemed automatically
cancelled. When the bank denied the application for assumption of
Application: mortgage, petitioners stopped making payments. Thus, notice of
Hawaiian Philippine Co. waived this condition when it arose by accepting cancellation/rescission was sent to petitioners for non-performance of
payment of the overdue accounts and continuing with the contract. their obligation. Aggrieved, petitioners filed a complaint against private
Thereafter, Song Fo & Company was not default in payment so that the
respondent for specific performance, nullity of cancellation, writ of
Hawaiian Philippine Co. had in reality no excuse for writing its letter of
possession and damages. Both parties admitted that their agreement
April 2, 1923,
mandated that petitioners should pay the purchase price balance of
We rule that the appellant had no legal right to rescind the contract of
sale because of the failure of Song Fo & Company to pay for the P1.8M to private respondents in case the request to assume the
molasses within the time agreed by the parties. mortgage would be disapproved. The trial court dismissed the
complaint, but on reconsideration, directed the parties to proceed with
Conclusion: the sale. On appeal, the Court of Appeals upheld the validity of the
Thus, defendant-appellee cannot rescind. Defendant-Appellee is ordered rescission. Hence, this recourse.
to pay to Plaintiff-Appellee 3,000 pesos with legal interest from October
2, 1923 until payment.
a) Petitioner’s Arguments: Findings of the Court of Appeals: Set aside the prior ruling and
dismissed petitioner’s complaint.
Petitioners aver that their nonpayment of private respondents'
mortgage obligation did not constitute a breach of contract, considering Ruling of the Supreme Court: Affirmed CA’s decision.
that their request to assume the obligation had been disapproved by the
Rule:
mortgagee bank. Accordingly, payment of the monthly amortizations
ceased to be their obligation and, instead, it devolved upon private 1.) In a contract of sale, the seller obligates itself to transfer the
respondents again. ownership of and deliver a determinate thing, and the buyer to pay
therefor a price certain in money or its equivalent. 13
Petitioners likewise claim that the rescission of the contract by private
respondents was not justified, inasmuch as the former had signified their Private respondents had already performed their obligation through the
willingness to pay the balance of the purchase price only a little over a execution of the Deed of Sale, which effectively transferred ownership of
month from the time they were notified of the disapproval of their the property to petitioner through constructive delivery. Prior physical
application for assumption of mortgage. Petitioners also aver that the delivery or possession is not legally required, and the execution of the
breach of the contract was not substantial as would warrant a rescission. Deed of Sale is deemed equivalent to delivery. 14
b) Respondent’s Arguments: Petitioners, on the other hand, did not perform their correlative
obligation of paying the contract price in the manner agreed upon.
Defendants sent plaintiffs a notarial notice of cancellation/rescission of
Worse, they wanted private respondents to perform obligations beyond
the intended sale of the subject property allegedly due to the latter's
those stipulated in the contract before fulfilling their own obligation to
failure to comply with the terms and conditions of the Deed of Sale with
pay the full purchase price.
Assumption of Mortgage and the Undertaking.
2.) The right of rescission of a party to an obligation under Article 1191
Issues:
of the Civil Code is predicated on a breach of faith by the other party
1.) The Court of Appeals erred in holding that the non-payment of the who violates the reciprocity between them. 16 The breach contemplated
mortgage obligation resulted in a breach of the contract. in the said provision is the obligor's failure to comply with an existing
obligation. 17 When the obligor cannot comply with what is incumbent
2.) The Court of Appeals erred in holding that the rescission (resolution)
upon it, the obligee may seek rescission and, in the absence of any just
of the contract by private respondents was justified.
cause for the court to determine the period of compliance, the court
shall decree the rescission.

Findings of the Lower Court: Dismissed but later granted the parties to In the instant case, the breach committed did not merely consist of a
proceed with the sale after a motion for reconsideration from the slight delay in payment or an irregularity; such breach would not
petitioners. normally defeat the intention of the parties to the contract. Here,
petitioners not only failed to pay the P1.8 million balance, but they also Case 7: BUENAVENTURA ANGELES, ET AL.,  plaintiffs-appellees, 
imposed upon private respondents new obligations as preconditions to
vs. URSULA TORRES CALASANZ, ET AL.,  defendants-appellants.||| 
the performance of their own obligation. In effect, the qualified offer to
pay was a repudiation of an existing obligation, which was legally due G.R. No. L-42283, [March 18, 1985], 220 PHIL 10-23
and demandable under the contract of sale. Hence, private respondents TOPIC: Art. 1191
were left with the legal option of seeking rescission to protect their own
interest. FACTS:
This is an appeal from the decision of the Court of First Instance
Rescission creates the obligation to return the object of the contract. It
of Rizal|||  declaring the contract to sell as not having been validly
can be carried out only when the one who demands rescission can
return whatever he may be obliged to restore. 20 To rescind is to declare cancelled and ordering the defendants-appellants to execute a final
a contract void at its inception and to put an end to it as though it never deed of sale in favor of the plaintiffs-appellees
was. It is not merely to terminate it and release the parties from further Defendants-appellants|||  and plaintiffs-appellees|||  entered
obligations to each other, but to abrogate it. from the beginning and into a contract to sell a piece of land located in Cainta, Rizal for the
restore the parties to their relative positions as if no contract has been amount of P3,920.00 plus 7% interest per annum.|||  plaintiffs-appellees
made. made a downpayment of P392.00 upon the execution of the contract.
They promised to pay the balance in monthly installments of P41.20
until fully paid, the installments being due and payable on the 19th day
of each month. The plaintiffs-appellees paid the monthly installments
until July 1966, when their aggregate payment already amounted to
P4,533.38. The defendants-appellants accepted and received delayed
installment payments from the plaintiffs-appellees|||  .Defendants-
appellants wrote the plaintiffs-appellees a letter requesting the
remittance of past due accounts but the later cancelled the said contract
because the plaintiffs-appellees failed to meet subsequent payments.
The plaintiffs' letter with their plea for reconsideration of the said
cancellation was denied by the defendants-appellants.|||  Then the
plaintiffs-appellees filed a case with the Court of First Instance of Rizal to
compel the defendants-appellants to execute in their favor the final
deed of sale alleging inter alia that after computing all subsequent
payments for the land in question.
Defendants-appellants argue that the plaintiffs-appellees failed
a) Petitioner’s Arguments (BUENAVENTURA ANGELES, ET AL – “WON” ) to pay the August, 1966 installment despite demands for more than four
(4) months. The defendants-appellants point to Jocson  v. Capitol
They alleged that they have already paid the total amount of Subdivision  where this Court upheld the right of the subdivision owner
P4,533.38 including interests, realty taxes and incidental expenses for to automatically cancel a contract to sell on the strength of a provision
the registration and transfer of the land. or stipulation similar to paragraph 6 of the contract in this case. They
Plaintiffs-appellees on the other hand contend that also argue that even in the absence of the aforequoted provision, they
the Jocson ruling does not apply. They state that paragraph 6 of the had the right to cancel the contract to sell under Article 1191 of the Civil
contract to sell is contrary to law insofar as it provides that in case of Code of the Philippines.|||
specified breaches of its terms, the sellers have the right to declare the
contract cancelled and of no effect, because it granted the sellers an ISSUE:
absolute and automatic right of rescission.|||  Whether or not the defendants-appellants have the right to rescind the
contract when the plaintiffs-appellees violate the contract to sell.
whether or not the contract to sell has been automatically and validly
b) Respondent’s Argument’s ( URSULA TORRES CALASANZ, ET AL. - cancelled by the defendants-appellants.||| 
“LOST” )
Alleged in their answer that the complaint states no cause of FINDINGS OF THE Lower Court:
action and that the plaintiffs-appellees violated paragraph six (6) of the Rendered judgment in favor of the plaintiffs-appellees||| 
contract to sell when they failed and refused to pay and/or offer to pay
the monthly installments corresponding to the month of August, 1966 FINDINGS OF THE Court of Appeals:
for more than five (5) months, thereby constraining the defendants-
appellants to cancel the said contract. LLp RULING:
Petition is DENIED for lack of merit.|||Decision appealed from is
A motion for reconsideration was filed by the defendants- AFFIRMED with the modification that the plaintiffs-appellees should
appellants but was denied. They stated that the lower court erred in not pay the balance of SIX HUNDRED SEVENTY ONE PESOS AND SIXTY-
holding the contract to sell as having been legally and validly cancelled SEVEN CENTAVOS (671.67) without any interests. Costs against the
and assuming that the said contract to sell has not been validly cancelled defendants-appellants.|||
, the LC erred in ordering the defendants to execute aq final deed of
sale in favor of plaintiffs Rule:
Article 1191 is explicit. In reciprocal obligations, either party already paid the monthly installments for a period of almost nine (9)
has the right to rescind the contract upon the failure of the other to years. In other words, in only a short time, the entire obligation
perform the obligation assumed thereunder. Moreover, there is would have been paid. Furthermore, although the principal
nothing in the law that prohibits the parties from entering into an obligation was only P3,920.00 excluding the 7 percent interests, the
agreement that violation of the terms of the contract would cause plaintiffs-appellees had already paid an aggregate amount of
its cancellation even without court intervention P4,533.38.
"Well settled is, however, the rule that a judicial action \
for the rescission of a contract is not necessary where the Application:
contract provides that it may be revoked and cancelled for In this case, if we were to allow to sanction the rescission made by
violation of any of its terms and conditions' (Lopez v. the defendants-appellants will work injustice to the plaintiffs-
Commissioner of Customs, appellees. It would unjustly enrich the defendants-appellants.
Conclusion:
The rule that it is not always necessary for the injured party
Thus, the defendants-appellants' contention is without merit.
to resort to court for rescission of the contract when the contract
When the defendants-appellants, instead of availing of their alleged
itself provides that it may be rescinded for violation of its terms and
right to rescind, have accepted and received delayed payments of
conditions, was qualified by this Court in University of the
installments, though the plaintiffs-appellees have been in arrears
Philippines  v. De los  Angeles
beyond the grace period mentioned in paragraph 6 of the contract,
The right to rescind the contract for non-performance of one the defendants-appellants have waived and are now estopped from
of its stipulations, therefore, is not absolute. In Universal Food exercising their alleged right of rescission.
Corp.  v. Court of Appeals  the Court stated that — "The general rule
is that rescission of a contract will not be permitted for a slight or
casual breach, but only for such substantial and fundamental breach
as would defeat the very object of the parties in making the
agreement. (Song Fo & Co. v. Hawaiian-Philippine Co., 47 Phil. 821,
827) The question of whether a breach of a contract is substantial
depends upon the attendant circumstances.|||  (Angeles v. Calasanz
The breach of the contract adverted to by the defendants-
appellants is so slight and casual when we consider that apart from
the initial downpayment of P392.00 the plaintiffs-appellees had
Case #8: Delta Motor Corporation vs. Genuino compel Delta to deliver the pipes. Meanwhile, Delta, in its answer
170 SCRA 29, Feb. 8, 1989 prayed for rescission of the contracts pursuant to Art. 1191 of the New
Civil Code
DOCTRINES:
 Rescission will be ordered only where the breach complained of RTC: Complaint for specific performance w/ damages seeking to compel
is substantial as to defeat the object of the parties in entering Delta to deliver the pipes
into the agreement. It will not be granted where the breach is  Delta prayed for the rescission pursuant to NCC Art. 1191 1.
slight or casual. Further, the question of whether a breach of a  Ruled in favor of Delta, ordering Delta to return the 15,900
contract is substantial depends upon the attendant downpayment to the Genuinos and the Genuinos to pay 10k
circumstances. attorney’s fee to Delta. RTC rescinded the contracts.

FACTS: COURT OF APPEALS: Ruled in favor of the Genuinos.


 Reversed RTC ruling. Ordered the Genuinos to pay the remaining
Private Respondents are owners of an ice plant and cold storage
installments to Delta and to execute the Promissory Note
who ordered black iron pipes from Delta Motors (petitioner) for which
required in the contract and thereafter, for Delta to immediately
the latter provided two letter quotations indicating the selling price and deliver pipes.
delivery of said pipes. The terms of payment are also included in the  Reasoning of CA:
letter quotations which must be complied with by the respondents. 1. Delta was aware that the construction was ongoing and
Private respondents made initial payments on both contracts but should have included in said contracts (Delta was the one
who prepared the contracts) a deadline of delivery, but it did
delivery of the pipes was not made by Delta Motors so that the
not. Neither did Delta insist on delivery when the Genuinos
Genuinos were not willing to give subsequent payments notwithstanding
refused to accept its offer of delivery.
the agreed terms of payment requiring them of such.
2. Delta’s refusal to make delivery in 1975 unless the Genuinos
In July 1972 Delta offered to deliver the iron pipes but the Genuinos pay a higher price would mean an amendment of the
did not accept the offer because the construction of the ice plant contracts. Delta already made us of the advance payments
building where the pipes were to be installed was not yet finished. made by the Genuinos. That would be unjust enrichment on
the part of Delta at the expense of the Genuinos and is
Three years later, on April 15, 1975, Hector Genuino, in behalf of considered an abominable business practice.
España Extension Ice Plant and Cold Storage, asked Delta to deliver the 1
The power to rescind obligations is implied in reciprocal ones, in case one of the obligors should
iron pipes within thirty (30) days from its receipt of the request. But not comply with what is incumbent upon him.
petitioner Delta is unwilling to deliver said iron pipes unless the The injured party may choose between the fulfillment and the rescission of the obligation, with
the payment of damages in either case. He may also seek rescission, even after he has chosen
Genuinos agree to a new quotation price set by the former.
fulfillment, if the latter should become impossible.
The court shall decree the rescission claimed, unless there be just cause authorizing the fixing of
Private Respondents rejected the new quoted prices and instead a period.
filed a complaint for specific performance with damages seeking to
 MR by Delta denied. Thus, this petition. The conduct of Delta indicates that the Genuinos’ non-
performance was not a substantial breach, let alone a breach of contract
as would warrant a rescission.
ISSUE: WON the contract of sale should be rescinded?  Delta did not do anything, as testified by its Technical Service
RULING: No. While there is merit in Delta's claim that the sale is subject department manager Crispin Villanueva, when respondents
to suspensive conditions, the Court finds that it has, nevertheless, refused their offer to deliver.
waived performance of these conditions and opted to go on with the  3 years later, when respondents demanded delivery, Delta did
not raise any argument but merely demanded higher prices.
contracts although at a much higher price. Art. 1545 of the Civil Code
provides:
Delta cannot ask for increased prices based on the price offer
Art. 1545. Where the obligation of either party to a contract of sale is stipulation in the contracts and in the increase in the cost of goods.
subject to any condition which is not performed, such party may refuse Reliance by Delta on the price offer stipulation is misplaced. Said
to proceed with the contract or may waive performance of the condition. stipulation makes reference to Delta’s price offer as remaining firm for
thirty (30) days and thereafter will be subject to its review and
It would be highly inequitable for petitioner Delta to rescind the two (2) confirmation.
contracts considering the fact that not only does it have in its possession The offers of Delta, however, were accepted by the private
and ownership the black iron pipes, but also the down payments private respondents within the thirty (30)-day period. And as stipulated in the
respondents have paid. Delta cannot ask for increased prices based on two (2) letter-quotations, acceptance of the offer gives rise to a contract
the price offer stipulation in the contracts and in the increase in the cost between the parties:
of goods. Reliance by Delta on the price offer stipulation is misplaced.
The moment private respondents accepted the offer of Delta, the “In the event that this proposal is acceptable to you,
contract of sale between them was perfected and neither party could please indicate your conformity by signing the space
provided herein below which also serves as a contract
change the terms thereof. Neither could petitioner Delta rely on the
of this proposal.”
fluctuation in the market price of goods to support its claim for
rescission.
Thus, the moment private respondents accepted the offer of
APPLICATION: Delta, the contract of sale between them was perfected and neither
Rescission will be ordered only where the breach complained of is party could change the terms thereof.
substantial as to defeat the object of the parties in entering into the
agreement. It will not be granted where the breach is slight or casual.
CONCLUSION: CA decision affirmed. The parties should comply with the
Further, the question of whether a breach of a contract is substantial
original terms of their contracts.
depends upon the attendant circumstances.”
Case 9: VERMEN REALTY DEVELOPMENT CORPORATION, petitioner, vs.  In 1982, the Vermen repossessed unit 602. Seneca requested
THE COURT OF APPEALS and SENECA HARDWARE CO., INC., for a clarification of Vermen’s action and had to rent another
respondents. unit for their use. Petitioner replied that Room 602 was
leased to another tenant because private respondent
TOPICS: corporation had not paid anything for purchase of the
1. Reciprocal Obligations, its Nature condominium unit.
2. Rescission (better term is “resolution”) of reciprocal obligation  In 1983, loan application for the construction of the Vermen
Pines Condominium Phase II was denied, thus construction
FACTS: was stopped.
1. Agreement. Petitioner Vermen Realty and private respondent 3. Regional Trial Court – Seneca lost. Seneca Hardware filed a
Seneca Hardware entered into a contract denominated as complaint with the RTC of Quezon City for the rescission of the
"Offsetting Agreement". Stipulations of the agreement include: Offsetting Agreement with damages.
 Seneca Hardware desires to buy from Vermen Realty two Respondent’s (Seneca) arguments in RTC. They alleged that
residential condominium units, studio type, more or less Vermen Realty had stopped issuing purchase orders of
worth P276,000. construction materials, without valid reason, thus resulting in
 Vermen Realty desires to buy construction materials from the stoppage of deliveries of construction materials on its
Seneca Hardware worth P552,000. (Seneca Hardware) part, in violation of the =Agreement.
 Vermen Realty shall pay Seneca Hardware P276,000 in cash Petitioner’s (Vermen) arguments in RTC. Petitioner alleged
upon delivery of the construction materials and the other that they issued purchase orders, it was private respondent
P276,000 shall be paid in the form of 2 condominium units, who could not deliver the supplies ordered, alleging that they
studio type worth P276,000. were out of stock. However, when Treasurer was asked to
 Pending the completion of VERMEN PINES CONDOMINIUM produce the POs, she was unable to do so.
PHASE II which is the subject of this contract, shall deliver to It also alleged that respondent quoted higher prices thus they
the Seneca Hardware the possession of residential had to resort to other suppliers. Also for the leasing of Unit 602
condominium, Phase I, Unit Nos. 601 and 602, studio type. to another, it was because Seneca had not paid for anything.
 Upon completion of Phase II, Seneca Hardware has first RTC’s Decision. Dismissed Seneca’s complaint and ordered the
option to transfer from Phase I to Phase II under the same payment of the balance for Unit 601. Seneca appealed before
price, terms and conditions. the CA.
2. Subsequent events. 4. Court of Appeals – Seneca won. Reversed RTC’s decision.
 As found by the appellate court and admitted by both parties, 5. Supreme Court – Seneca won. Petitioner Vermen sought a
Seneca Hardware had paid and delivered construction review of CA’s decision with the SC.
materials to Vermen Realty. Vermen delivered Units 601 and Petitioner’s (Vermen) arguments in SC. Petitioner alleged
602. that they issued purchase orders, it was private respondent
who could not deliver the supplies ordered, alleging that they
were out of stock. Respondent's own witness admitted that performance of one is conditioned on the simultaneous fulfillment of the
petitioner had the discretion to order or not to order the other obligation.
construction material from the former. Hence, when no Application: The provisions of the Offsetting Agreement are reciprocal in
purchase orders were issued, no provision of the agreement nature. Under the agreement, private respondent shall deliver to
was violated. Furthermore, mere stoppage of the loan for the petitioner construction materials worth P552,000.00. Petitioner's
construction of Phase II of the Vermen Pines Condominiums obligation is three-fold: he shall pay private respondent P276,000.00 in
should not have had any effect on the fulfillment of the cash; he shall deliver possession of units 601 and 602, Phase I, Vermen
obligations set forth in the Offsetting Agreement. Pines Condominiums (with total value of P276,000.00) to private
Respondent’s (Seneca) arguments in RTC. They alleged that respondent; upon completion of Vermen Pines Condominiums Phase II,
Vermen Realty had stopped issuing purchase orders of private respondent shall be given option to transfer to similar units
construction materials, without valid reason, thus resulting in therein.
the stoppage of deliveries of construction materials on its
(Seneca Hardware) part, in violation of the Offsetting Rule: Article 1191 of the Civil Code provides the remedy of rescission in
Agreement. Further, it points out that the subject of the (more appropriately, the term is "resolution") in case of reciprocal
Offsetting Agreement is Phase II of the Vermen Pines obligations, where one of the obligors fails to comply with what is
Condominiums. It alleges that since construction of Phase II incumbent upon him. The general rule is that rescission of a contract will
has failed to begin it has reason to move for rescission of the not be permitted for a slight or causal breach, but only for such
agreement, as it cannot forever wait for the delivery of the substantial and fundamental breach as would defeat the very object of
condominium units to it. the parties in executing the agreement. The question of whether a
breach of contract is substantial depends upon the attendant
ISSUES: circumstances.
1. WON the circumstances of the case warrant rescission of the Application: The discontinuance of delivery of construction materials to
Offsetting Agreement as prayed for by Private Respondent when petitioner stemmed from the failure of petitioner to send purchase
he instituted the case before the trial court orders to private respondent. The allegation that petitioner had been
2. WON the non-fulfillment of the obligation constitutes sending purchase orders to private respondent, which the latter could
substantial breach of the agreement to warrant rescission. Note: not fill, cannot be given credence. Furthermore, petitioner would never
rescission of a contract will not be permitted for a slight or be able to fulfill its obligation in allowing private respondent to exercise
causal breach, but only for such substantial and fundamental the option to transfer from Phase I to Phase II, as the construction of
breach. Phase II has ceased and the subject condominium units will never be
available.
RULING: The impossibility of fulfillment of the obligation on the part of
Rule: Reciprocal obligations are those created or established at the same petitioner necessitates resolution of the contract for indeed, the non-
time, out of the same cause, and which results in a mutual relationship fulfillment of the obligation aforementioned constitutes substantial
of creditor and debtor between parties. In reciprocal obligations, the breach of the Agreement. The possibility of exercising the option of
whether or not to transfer to condominium units in Phase II was one of For failure of the private respondents to vacate the premises as demanded in
the factors which were considered by private respondent when it the latter dated October 9, 1984, the petitioner with the Metropolitan Trial
entered into the agreement. Since the construction of the Vermen Pines Court of Manila complaints for ejectment against the former.
Condominium Phase II has stopped, petitioner would be in no position to
In their respective answers, the six (6) private respondents interposed a
perform its obligation to give private respondent the option to transfer
common defense. They claimed that their non-payment of the rentals for the
to Phase II. It would be the height of injustice to make private months of July, August and September, 1984, was due to the failure of the
respondent wait for something that may never come. petitioner (as the new owner) to send its collector; that they were at a loss as to
where they should pay their rentals.

Case 10: CETUS DEVELOPMENT INC., petitioner, vs. COURT OF APPEALS The private respondents, thru counsel, later 􏰀filed a motion for was
This is a petition for review on certiorari of the decision dated January 30, 1987 consolidation of the six cases, the said cases were consolidated in The
of the Court of Appeals in CA-GR Nos. SP-079450 entitled, "Cetus Development, Metropolitan Trial Court of Manila, Branch XII. On June 4, 1985, the trial court
Inc., Petitioner vs. Hon. Conrado T. Limcaoco, Presiding Judge, Regional Trial rendered its decision dismissing the six cases.
Court of Manila, Branch XI, Ederlina Navalta, et. al., respondents.”
Not satis􏰀ed with the decision of the Metropolitan Trial Court, the petitioner
Facts: The six (6) private respondents, (1) Ederlina Navalta, (2) Ong Teng, (3) appealed to the Regional Trial Court of Manila and the same was assigned to
Jose Liwanag, (4) Leandro Canlas, (5) Victoria Sudario, and (6) Flora Nagbuya Branch IX thereof. In its decision dated November 19, 1985, the Regional Trial
were the lessees of the premises located at No. 512 Quezon Boulevard, Quiapo, Court dismissed the appeal for lack of merit.
Manila, originally owned by the Susana Realty. These individual verbal leases
In due time, a petition for review of the decision of the Regional Trial Court was
were on a month-to-month basis paid by the lessees to a collector of the Susana
􏰀filed by the petitioner with the Court of Appeals. Said petition was dismissed
Realty who went to the premises monthly.
on January 30, 1987, for lack of merit.
Sometime in March, 1984, the Susana Realty sold the leased premises to the
Aggrieved by the decision of the Court of Appeals, petitioner now comes to Us
petitioner, Cetus Development, Inc. From April to June, 1984, the private
in this petition.
respondents continued to pay their monthly rentals to a collector sent by the
petitioner. In the succeeding months of July, August and September 1984, the
Issue/s: Whether or not there exists a cause of action when the complaints for
respondents failed to pay their monthly individual rentals as no collector came.
unlawful detainer were 􏰀filed considering the fact that upon demand by
petitioner from private respondents for payment of their back rentals, the latter
On October 9, 1984, the petitioner sent a letter to each of the private
immediately tendered payment which was accepted by petitioner.
respondents demanding that they vacate the subject premises and to pay the
back rentals for the months of July, August and September, 1984, within
Ruling: There is no cause of action for unlawful detainer and/or action for
􏰀fifteen (15) days from the receipt thereof. Immediately upon the receipt of the
ejectment.
said demand letters on October 10, 1984, the private respondents paid their
respective arrearages in rent which were accepted by the petitioner subject to
Section 2, Rule 70 of the Rules of Court, is interpreted as follows ". . . the right
the unilateral condition that the acceptance was without prejudice to the 􏰀ling
to bring an action of ejectment or unlawful detainer must be counted from
of an ejectment suit.
the time the defendants failed to pay rent after the demand therefor. It is not
the failure per se to pay rent as agreed in the contract, but the failure to pay the demand to vacate was premature as it was an exercise of a non- existing right to
rent after a demand therefor is made, that entitles the lessor to bring an action rescind.
for unlawful detainer. In other words, the demand contemplated by the above-
quoted provision is not a demand to vacate, but a demand made by the While it is true that a lessor is not obligated to send a collector, it has been duly
landlord upon his tenant for the latter to pay the rent due. If the tenant fails to established that it has been customary for private respondents to pay the
comply with the said demand within the period provided, his possession rentals through a collector. Besides Article 1257, New Civil Code provides that
becomes unlawful and the landlord may then bring the action for ejectment." where no agreement has been designated for the payment of the rentals, the
(p. 28, Rollo, G.R. No. 77647) place of payment is at the domicile of the defendants. Hence, it could not be
said that they were in default in the payment of their rentals as the delay in
Thus, for the purpose of bringing an ejectment suit, two requisites must concur, paying the same was not imputable to them. Rather, it was attributable to
namely: (1) there must be failure to pay rent or comply with the conditions of petitioner's omission or neglect to collect.
the lease and (2) there must be demand both to pay or to comply and vacate
with in the period specified in Section 2, Rule 70, namely 15 days in case of
lands and 5 days in case of buildings.
Case 12: RAFAEL REYES TRUCKING CORPORATION, petitioner vs.
There was no failure yet on the part of private respondents to pay rents for
PEOPLE and ROSARIO DY (for herself and on behalf of the minors),
three consecutive months. As the terms of the individual verbal leases which
were on a month-to-month basis were not alleged and proved, the general rule respondents
on necessity of demand applies, to wit: there is default in the fulfillment of an
obligation when the creditor demands payment at the maturity of the G.R. No. 129029. April 3, 2000.
obligation or at anytime thereafter. TOPIC: Obligations and Contracts – Enforcement of Civil Liability
This is explicit in Article 1169, New Civil Code which provides that "(t)hose FACTS:
obliged to deliver or to do something incur in delay from the time the obligee
judicially or extrajudicially demands from them the fulfi􏰀llment of their The petitioner, RAFAEL REYES TRUCKING CORPORATION, employed a
obligation." Petitioner has not shown that its case falls on any of the following certain Romeo Dunca who was charged with the crime of reckless
exceptions where demand is not required: (a) when the obligation or the law so imprudence resulting in double homicide and damage to property for
declares; (b) when from the nature and circumstances of the obligation it can be
inferred that time is of the essence of the contract; and (c) when demand would
recklessly and negligently driving the vehicle registered in the name of
be useless, as when the obligor has rendered it beyond his power to perform. the petitioner, causing it to hit and bump another vehicle driven by a
certain Feliciano Balcita and Francisco Dy, Jr., families of the aggrieved
The facts on record fail to show proof that petitioner demanded the payment of private respondents. The said persons sustained injuries which resulted
the rentals when the obligation matured. Coupled with the fact that no to the death of the Francisco. Thereafter, the offended parties made a
collector was sent as previously done in the past, the private respondents
reservation to file a separate civil action against the accused. On
cannot be held guilty of mora solvendi or delay in the payment of rentals. Thus,
when petitioner 􏰀first demanded the payment of the 3-month arrearages and November 29, 1989, the offended parties filed with the RTC a complaint
private respondents lost no time in making tender and payment, which against the petitioner, as employer of the accused, based on quasi-
petitioner accepted, no cause of action for ejectment accrued. Hence, its delict. At the same time, the offended parties pursued the criminal
action without withdrawing the civil case quasi ex delicto filed against Revised Penal Code; and (2) a separate action for quasi delict under
the employer. In December of the same year, private respondents Article 2176 of the Civil Code of the Philippines. Once the choice is made,
withdrew the reservation to file separate civil action against the accused the injured party can not avail himself of any other remedy because he
and manifested to prosecute the civil aspect ex delicto in the criminal may not recover damages twice for the same negligent act or omission
action. However, there was no withdrawal of separate civil action based of the accused. This is the rule against double recovery. In other words,
on quasi delict against the petitioner. Thereafter, Regional Trial Court "the same act or omission can create two kinds of liability on the part of
found the petitioner subsidiarily liable in its supplemental decision in the the offender, that is, civil liability ex delicto, and civil liability quasi
criminal case of the accused, which was then affirmed by the Court of delicto" either of which "may be enforced against the culprit, subject to
Appeals, hence the petition before the Supreme Court. the caveat under Article 2177 of the Civil Code that the offended party
can not recover damages under both types of liability." In the instant
ISSUE:
case, the offended parties elected to file a separate civil action for
Whether or not petitioner as owner of the truck involved in the accident damages against petitioner as employer of the accused, based on quasi
may be held subsidiarily liable for the damages awarded to the offended delict, under Article 2176 of the Civil Code of the Philippines.”
parties in the criminal case against the truck driver despite the filing of a
separate civil action by the offended parties against the employer of the
truck driver

RULING: Case 13: LRT Authority vs. Navidad


[G.R. No. 145804/ 397 Scra 75. February 6, 2003.]
No, the Supreme Court ruled that RAFAEL REYES TRUCKING
CORPORATION, as the employer of the accused who had been found FACTS:
guilty in the criminal case, cannot be held subsidiarily liable. On 14 October 1993, Nicanor Navidad, then drunk, entered the
EDSA LRT station after purchasing a "token" (representing payment of
In this case, the offended parties elected to file a separate civil action for
the fare). Junelito Escartin, the security guard assigned to the area,
damages against the petitioner as employer of the accused, based on
approached Navidad. A misunderstanding or an altercation between the
quasi delict. In view of the reservation to file and the subsequent filing of two apparently ensued that led to a fist fight. At the exact moment that
a separate civil action, the same was not instituted with the criminal Navidad fell, an LRT train, operated by petitioner Rodolfo Roman, was
action. As a rule, when private respondents reserved the right to file the coming in.
separate civil action, they waived other available civil actions predicated Navidad was struck by the moving train, and he was killed
on the same act or omission of the accused, which includes recovery of instantaneously. Private respondent Marjorie Navidad, the widow of
indemnity from reckless imprudence under Revised Penal Code. Nicanor, along with her children, filed a complaint for damages against
Junelito Escartin, Rodolfo Roman, the LRTA, the Metro Transit
“In negligence cases, the aggrieved party has the choice between (1) an
Organization, Inc. and Prudent Security Agency for the death of her
action to enforce civil liability arising from crime under Article 100 of the husband. The trial court ruled in favor of private respondent by awarding
actual, moral and compensatory damages. Prudent Security Agency
appealed to the CA. The appellate court exonerated Prudent from any
liability for the death of Nicanor and instead held LRTA and Roman APPLICATION:
jointly and severally liable. In exempting Prudent from liability, the
appellate court stressed that there was nothing to link the security Law and jurisprudence dictate that a common carrier, both from
agency to the death of Navidad. the nature of its business and for reasons of public policy, is burdened
with the duty of exercising utmost diligence in ensuring the safety of
passengers.
ISSUE: The foundation of LRTA's liability is the contract of carriage and
Whether or not the LRTA and Roman are liable for the death of its obligation to indemnify the victim arises from the breach of that
Navidad. contract by reason of its failure to exercise the high diligence required of
the common carrier. In either case, the common carrier is not relieved of
RULING: its responsibilities under the contract of carriage.
When an act which constitutes a breach of contract would have
The law requires common carriers to carry passengers safely itself constituted the source of a quasi-delictual liability had no contract
using the utmost diligence of very cautious persons with due regard for existed between the parties, the contract can be said to have been
all circumstances. Such duty of a common carrier to provide safety to its breached by tort, thereby allowing the rules on tort to apply.
passengers so obligates it not only during the course of the trip but for
so long as the passengers are within its premises and where they ought CONCLUSION:
to be in pursuance to the contract of carriage. The statutory provisions
render a common carrier liable for death of or injury to passengers (a) Regrettably for LRT, as well as perhaps the surviving spouse and
through the negligence or wilful acts of its employees or b) on account heirs of the late Nicanor Navidad, this Court is concluded by the factual
of wilful acts or negligence of other passengers or of strangers if the finding of the Court of Appeals that "there is nothing to link (Prudent) to
common carrier's employees through the exercise of due diligence could the death of Nicanor (Navidad), for the reason that the negligence of its
have prevented or stopped the act or omission. In the absence of employee, Escartin, has not been duly proven.
satisfactory explanation by the carrier on how the accident occurred, This finding of the appellate court is not without substantial
which petitioners, according to the appellate court, have failed to show, justification in the review of the records of the case. There being,
the presumption would be that it has been at fault, an exception from similarly, no showing that petitioner Rodolfo Roman himself is guilty of
the general rule that negligence must be proved. any culpable act or omission, he must also be absolved from liability.
There being, similarly, no showing that petitioner Rodolfo
Roman himself is guilty of any culpable act or omission, he must also be
absolved from liability. Needless to say, the contractual tie between the
LRT and Navidad is not itself a juridical relation between the latter and
Roman; thus, Roman can be made liable only for his own fault or
negligence.
Case 14: EDSEL LIGA, petitioner, vs. FACTS:

ALLEGRO RESOURCES CORP., respondent. -On October 10 1975, Ortigas & Company Limited Partnership entered
into an agreement with La Paz Investment & Realty Corporation (La Paz)
[G.R. No. 175554. December 23, 2008]
where Ortigas leased to La Paz a parcel of land in San Juan city which
TOPIC: Art. 1159 and Art. 1169 of the Civil Code consisted of 5,514 sqm for a 25 year period from January 1, 1976 to
December 31 of 2000.
Art. 1159. Obligations arising from contracts have the force of law
between the contracting parties and should be complied with in good - In the agreement, La Paz undertook to construct a 3 or 2 storey
faith. commercial building which will contain first class stores subdivided in
stalls for lease to those interested.
Art. 1169. Those obliged to deliver or to do something incur in delay
from the time the obligee judicially or extrajudicially demands from - In compliance with this, La Paz constructed the Greenhills Shopping
them the fulfillment of their obligation. Arcade and then divided the same into several stalls which were
subleased to other people.
However, the demand by the creditor shall not be necessary in order
that delay may exist: - Petitioner Edsel Liga, one of the lessees, with the Unit No. 26 as the
space he leased.
(1) When the obligation or the law expressly so declare; or
- Since the lease expired in December 31, 2000, the stallholders through
(2) When from the nature and the circumstances of the obligation it Greenhills Shoppesville Unit Lessees Assoc. Inc. (GSULAI) made attempts
appears that the designation of the time when the thing is to be to extend their leasehold rights, however these efforts were futile
delivered or the service is to be rendered was a controlling motive for because they were all denied by Ortigas.However, petitioner was
the establishment of the contract; or allowed to continue his lease.
(3) When demand would be useless, as when the obligor has rendered it - On August 30 of 2001, Ortigas formally informed GSULAI of the
beyond his power to perform. impending lease to respondent Allegro. On Sept. 3 of that year, Ortigas
and Allegro executed a contract of lease. That same day, the parties
executed the Addendum to the agreement, with Section 1 providing that
In Reciprocal Obligations, neither party incurs in delay if the other does Allegro shall take immediate possession and control of the leased
not comply or is not ready to comply in a proper manner with what is promises upon signing the contract, it also empowers respondent to
incumbent upon him. From the moment one of the parties fulfills his assist in the collection of back rentals due to Ortigas for a certain period
obligation, delay by the other begins. of time.
- As the new lessee, respondent offered the same unit to petitioner ruling runs counter to the doctrine that judgment cannot bind persons
which eventually led to a lease agreement titled as Rental Information who are not parties to the action.
where it was stipulated that Liga would pay P40k montly rental starting
September 1st. This also covered the back rentals in January through
August due to Ortigas. A P40k payment as one month advance and RESPONDENT’S ARGUMENTS:
another P40k as security deposit was also given pursuant to the
agreement. However, her compliance with the agreement ended as Respondent questions why petitioners would want to reinstate the RTC
soon it was executed. decision when in fact they had already applied for a writ of execution of
the 8 March 1997 Decision. Respondent is of the view that since
- Despite repeated demands from Allegro, Liga failed to pay the rentals petitioners had already moved for the execution of the decision
as well as such back rentas from January to August of 2001. This led awarding a smaller amount of damages or fair rental value, the same is
Allegro to file an ejectment complaint against Liga with the MeTC of San inconsistent with a petition asking for a greater fair rental value and,
Juan, who ruled in favor of Allegro and ordered Liga to vacate the stall therefore, a possible case of unjust enrichment in favor of the
and pay the back rentals. The lower court ruled that Allegro has rightful petitioners.
ownership over the stall since Liga’s continued occupation was only by
mere tolerance which ceased when the contract was executed. Liga
managed to pay the P80k (advance + deposit). ISSUE:
- The lower court ordered the payment of P210k as back rentals from Whether or not the Court of Appeals erred in ordering Liga to pay:
October of 2001 to February of 2002, and P20k per monthas
compensation for the use of the stall from the filing of the ejectment 1. to Ortigas the back rentals from January to August, 2001.
suit. 2. to Allegro back rentals of P40k per month until such time she
vacates it
- RTC affirmed this but modified the monthly rental rate to P20k per 3. to Allegro the amount of P20k for attorney’s fees and cost of the
month, thus modifying the back rentals to P80,000. suit.
- Respondent filed a petition before the CA for review assailing the
modified decision, which was granted. FINDINGS OF THE LOWER COURT:

-MeTC ruled in favor of Allegro and ordered Liga to vacate the stall and
pay the back rentals. The lower court ruled that Allegro has rightful
PETITIONER’S ARGUMENTS:
ownership over the stall since Liga’s continued occupation was only by
Petitioner argued that the CA erred in ordering her to pay the back mere tolerance which ceased when the contract was executed. Liga
rentals to Ortigas because the latter is not a party to the case, that the managed to pay the P80k (advance + deposit).
- The lower court ordered the payment of P210k as back rentals from award as a legal representative by virtue of a provision
October of 2001 to February of 2002, and P20k per monthas contained in its lease agreement with Ortigas. Allegro did not
compensation for the use of the stall from the filing of the ejectment aver in the complaint that it was acting as the legal rep of ortigas
suit. and that it sought the payment of back rentals due to Ortigas. -
There was no allegation in the complaint that Allegro was
seeking such back rentals. The remedies to be granted should be
limited to the issues presented by the parties in their pleadings.
- RTC affirmed this but modified the monthly rental rate to P20k per
month, thus modifying the back rentals to P80,000.
2. No. The Court cannot countenance the refusal to pay P40k
montly to allegro since she had already accepted to pay such
rental rate when she signed the contract titled as Rental
FINDINGS OF THE COURT OF APPEALS: Information. The contract is the law between the parties.
Furthermore, Article 1159 of the Civil Code states that
-CA granted Allegro's petition and set aside the RTC's decision.It held
“Obligations arising from contracts have the force of law
that after the expiration of La Paz's lease with Ortigas on 31 December
between the contracting parties and should be complied with in
2000, Liga occupied the property merely by tolerance of Ortigas and that
good faith.” Unless the contract’s stipulations are contrary to
it was incorrect for the RTC to extend the lease contract for two years law, public order, morals, etc., the contract is binding. It is a
since it would infringe on the parties right to contract and Liga herself general principle of law that no one may be permitted to change
had never raised as an issue the extension of the lease contract before his mind or disavow and go back upon his own acts, or to
the MeTC. It found that Liga signed the Rental Information with Allegro proceed contrary thereto, to the other party’s prejudice.
and agreed to a monthly rental of P40,000.00 starting 1 September
2001. The appellate court ordered Liga to pay Ortigas back rentals of 3. No. Law and jurisprudence support the award of attorney's fees
P20,000.00 per month for the period of 1 January 2001 to 31 August and costs of suit in favor of Allegro. The award of damages and
2001 and P40,000.00 per month as rentals to Allegro starting 1 attorney's fees is left to the sound discretion of the court, and if
September 2001 until the property is vacated. such discretion is well exercised, as in this case, it will not be
disturbed on appeal. Attorney's fees and costs of litigation are
-In a Resolution dated 22 November 2006, the Court of Appeals denied awarded in instances where "the defendant acted in gross and
Liga's motion for reconsideration. evident bad faith in refusing to satisfy the plaintiff's plainly valid,
just and demandable claim."Having delivered possession over
the leased property to Liga, Allegro had already performed its
RULING: (SUPREME COURT) obligation under the lease. However, interest in favor of Allegro
is also awarded, pursuant to the following guidelines:
1. Yes. Liga is correct in stating that Ortigas is not a party to the
case so no relief can be extended to it. Allegro cannot justify the
With regard particularly to an award of interest in the concept of *Unless the stipulations in a contract are contrary to law, morals, good
actual and compensatory damages, the rate of interest, as well customs, public order or public policy, the same are binding as between
as the accrual thereof, is imposed, as follows: the parties. It is a general principle of law that no one may be permitted
1. When the obligation is breached, and it consists in the to change his mind or disavow and go back upon his own acts, or to
payment of a sum of money, i.e., a loan or forbearance of proceed contrary thereto, to the prejudice of the other party. Likewise, it
money, the interest due should be that which may have been is settled that if the terms of the contract clearly express the intention of
stipulated in writing. the contracting parties, the literal meaning of the stipulations would be
Furthermore, the interest due shall itself earn legal interest from controlling.
the time it is judicially demanded. In the absence of stipulation,
Art. 1169 application:
the rate of interest shall be 12% per annum to be computed
from default, i.e., from judicial or extrajudicial demand under Those obliged to deliver or to do something incur in delay from the time
and subject to the provisions of Article 1169 of the Civil Code.” the obligee judicially or extrajudicially demands from them the
The back rentals in this case being equivalent to a loan or fulfillment of their obligation.
forbearance of money, the interest due thereon is twelve
percent (12%) per annum from the time of extrajudicial demand However, the demand by the creditor shall not be necessary in order
on 15 December 2001. that delay may exist:
Petition denied, with the ff. modifications: (1) When the obligation or the law expressly so declare; or
that the award of back rentals for the period of 1 January 2001
to 31 August 2001 to Ortigas & Company, Limited Partnership is (2) When from the nature and the circumstances of the obligation it
DELETED and Edsel Liga is ORDERED to pay respondent Allegro appears that the designation of the time when the thing is to be
Resources Corporation legal interest of twelve percent (12%) per delivered or the service is to be rendered was a controlling motive for
annum on the back rentals from the date of extrajudicial the establishment of the contract; or
demand on 15 December 2001 until fully paid. (3) When demand would be useless, as when the obligor has rendered it
beyond his power to perform.
RULE: -In reciprocal obligations, neither party incurs in delay if the other does
Article 1159 and Article 1169 not comply or is not ready to comply in a proper manner with what is
incumbent upon him. From the moment one of the parties fulfills his
APPLICATION: obligation, delay by the other begins.
Art. 1159 application:

-Obligations arising from contracts have the force of law between the
contracting parties and should be complied with in good faith.
*In the absence of stipulation, the rate of interest shall be 12% per Case 15: MAKATI STOCK EXCHANGE, INC., MA. VIVIAN YUCHENGCO,
annum to be computed from default, i.e., from judicial or extrajudicial ADOLFO M. DUARTE, MYRON C. PAPA, NORBERTO C. NAZARENO,
demand under and subject to the provisions of Article 1169 of the Civil GEORGE UY-TIOCO, ANTONIO A. LOPA, RAMON B. ARNAIZ, LUIS J.L.
Code. The back rentals in this case being equivalent to a loan or VIRATA, and ANTONIO GARCIA, JR. Petitioners, vs. MIGUEL V. CAMPOS,
forbearance of money, the interest due thereon is twelve percent (12%) substituted by JULIA ORTIGAS VDA. DE CAMPOS, Respondent
per annum from the time of extrajudicial demand on 15 December 2001.

TOPIC:
CONCLUSION:
Art. 1157. Obligations arise from: (1) Law; (2) Contracts; (3) Quasi-
The petition for review is DENIED. The Decision of the Court of Appeals contracts; (4) Acts or omissions punished by law; and (5) Quasi-delicts.
in CA-G.R. SP No. 86331 is AFFIRMED with the MODIFICATIONS that the
An obligation imposed on a person, and the corresponding right granted
award of back rentals for the period of 1 January 2001 to 31 August 2001
to another, must be rooted in at least one of these five sources
to Ortigas & Company, Limited Partnership is DELETED and that
petitioner Edsel Liga is ORDERED to pay respondent Allegro Resources FACTS:
Corporation legal interest of twelve percent (12%) per annum on the
back rentals from the date of extrajudicial demand on 15 December Campos (respondent) filed with Securities, Investigation and Clearing
2001 until fully paid. Department (SICD) of SEC a petition against MKSE and its directors for,
among others (petitioners), the nullification of MKSE Board Resolution
which allegedly deprived him of his right to participate equally in the
allocation of Initial Public Offerings (IPOs) of corporations registered with
MKSE. He further prayed for the issuance of TRO to enjoin petitioners
from implementing or enforcing the subject Board Resolution. The TRO
was granted by the SICD, and subsequently, granted the application for
the issuance of Writ of Preliminary Injunction, which order was assailed
by the petitioners via Petition for Certiorari before the SEC Enbanc.
Meanwhile, a Motion to Dismiss was filed by the petitioners before the
SICD alleging that the petition became moot due to the cancellation of
MKSE’s license; that SICD had no jurisdiction; and for failure to state
cause of action. Said MTD was denied by SICD. The said denial was also
assailed by the petitioners before the SEC Enbanc.
C. Respondent, in said Petition, sought: (1) the nullication of the Exchange Commission e n b a n c in SEC-EB Case No. 393 and No. 403,
Resolution dated 3 June 1993 of the MKSE Board of Directors, respectively, are hereby reinstated.
which allegedly deprived him of his right to participate equally in
APPLICATION:
the allocation of Initial Public Offerings (IPO) of corporations
registered with MKSE; (2) the delivery of the IPO shares he was A cause of action is the act or omission by which a party violates a right
allegedly deprived of, for which he would pay IPO prices; and (3) of another.
the payment of P2 million as moral damages, P1 million as
exemplary damages, and P500,000.00 as attorney's fees and It contains three essential elements: 1) the legal right of the plaintiff 2)
litigation expenses the correlative obligation of the defendant and 3) the act or omission of
the defendant in violation of said legal right. If these elements are
absent, the complaint will be dismissed on the ground of failure to state
a cause of action.
D. Petitioners led a Motion to Dismiss based on the following grounds:
(1) the Petition became moot due to the cancellation of the license Furthermore, the petition filed by respondent failed to lay down the
of MKSE; (2) the SICD had no jurisdiction over the Petition; and (3) source or basis of respondent’s right and/or petitioner’s obligation.
the Petition failed to state a cause of action
Article 1157 of the Civil Code, provides that Obligations arise from: law,
Contracts, Quasi Contracts, Acts or omissions punished by law and quasi
delicts. Therefore an obligation imposed on a person and the
ISSUE: Whether or not the petition failed to state a cause of action
corresponding right granted to another, must be rooted in at least one
RULING: of these five sources.

SEC Enbanc: Nullifies the order granting the issuance of Writ of The Respondent merely quoted in his Petition the MKSE Board
Preliminary Injuction, and orders the dismissal of petition filed by Resolution, passed sometime in 1989, granting him the position of
Campos before the SICD. Chairman Emeritus of MKSE for life. However, there is nothing in the
said Petition from which the Court can deduce that respondent, by
Court of Appeals: Granted Campo’s petition, rendering as null
virtue of his position as Chairman Emeritus of MKSE, was granted by law,
and void SEC Enbanc orders, and subsequently denied the MR filed by
contract, or any other legal source, the right to subscribe to the IPOs of
the petitioners.
corporations listed in the stock market at their offering prices. The
Rule: The petition filled by the respondent, Miguel Campos allocation of IPO shares was merely alleged to have been done in accord
should be dismissed for failure to state a cause of action. The Decision of with a practice normally observed by the members of the stock
the Court of Appeals dated 11 February 1997 and its Resolution dated 18 exchange. There is no such law in this case that converts the practice of
May 1999 in CA-G.R. SP No. 38455 are REVERSED and SET ASIDE. The allocating IPO shares to MKSE members, for subscription at their offering
Orders dated 31 May 1995 and 14 August 1995 of the Securities and prices, into an enforceable or demandable right.
CONCLUSION: Case 16: Diesel Construction Co., Inc V. UPSI Property Holdings, Inc.G.R.
No. 154885, March 24, 2008
The mere assertion of a right and claim of an obligation in an
initiatory pleading, whether a Complaint or Petition, without identifying UPSI Property Holdings, Inc., V. Diesel Construction Co., Inc. and FGU
the basis or source thereof, is merely a conclusion of fact and law. A Insurance Corp.,G.R. No. 154937, March 24, 2008
pleading should state the ultimate facts essential to the rights of action
Facts:
or defense asserted, as distinguished from mere conclusions of fact or
conclusions of law. On August 26, 1995, Diesel, as contractor, and UPSI, as
Owner, entered into a Construction Agreement for the interior
architectural construction works for the 14 th to the 16th floors of the UPSI
Building 3 Meditel/Condotel Project located on Gen. Luna St., Ermita,
Manila. Under the Agreement, as amended, Diesel, for PHP 12,739,099,
agreed to undertake the Project, payable by progress billing. As
stipulated, Diesel posted, through FGU Insurance corp.(FGU), a
performance bond in favor of UPSI. The Agreement contained provisions
and contract provisions on contract works and Project completing,
extensions of contract period, change/extra work orders, delays and
damages for negative slippage. Under the Agreement, the Project
Prosecution proper was to run for a period of 90 days from August 2,
1999 to November 8, 1999. They later agreed to move the
commencement date to August 21, 1999 and the completion was moved
to November 20, 1999. Also this includes the section obliging the
contractor, in case of unjustifiable delay, to pay the owner liquidated
damages in the amount equivalent to one-fifth (1/5) of one (1) percent
of the total Project cost for each calendar day of delay. During the
course of Project implantation, change orders were effective and
extensive sought. Diesel requested for extension owing to the following
causes or delaying factors: (1) manual hauling of materials from the 14th
to 16th floors; (2) delayed supply of marble; (3) various change orders;
and (4) delayed in the installation of shower assembly. UPSI disapproved
the desired extensions on the basis of the foregoing causes, thus putting
Diesel in default for a given contract of work. Furthermore, for every
default situation, UPSI assessed Diesel for liquidated damages in the
form of deductions from Diesel’s progress payments, as stipulated in the
Agreement. On March 16, 2000, Diesel sent a letter notice to UPSI CASE # 18 Pantaleon v. American Express International, Inc.
stating that the Project has been completed as of the date. UPSI, G.R. No. 174269, May 8, 2009
however, disregarded the notice, and refused to accept delivery of the
contracted premises, claiming that Diesel abandoned the Project
FACTS: Petitioner Atty. Polo Pantaleon and his family joined a Western
unfinished Diesel then filed a complaint compelling to pay the unpaid
Europe tour. In Coster Diamond House, Amsterdam, Mrs. Pantaleon was
balance of UPSI of the contract price, plus damages and attorney’s fees.
about to bought a 2.5 karat diamond brilliant cut, a pendant and a chain,
UPSI denied liability.
all of which totaled U.S. $13,826.00.
Issue:
To pay these purchases, around 9:15am, Pantaleon presented his
Whether or not Diesel can be entitled to full payment of the contract American Express Credit Card together with his passport. Pantaleon was
amount? already worried about further inconveniencing the tour group, he asked
the store clerk to cancel the sale. The store manager though asked him
Held:
to wait a few more minutes. Around 45 minutes after Pantaleon had
As evidenced, by UPSI’s Progress Report No. 19 for the period ending presented his AmexCard, Coster Diamond House decided to release the
March 22, 2000, Diesel’s scope of work, as of that date, was already items even without American Express International, Inc.’s approval of
97.56% complete. Such level of work accomplishment would, by any the purchase.
natural norm, be considered as substantial to warrant full payment
The spouses Pantelon returned. Their offers of apology were
of the contract amount, less actual damages suffered by UPSI. Article
met by their tourmates with stony silence. The tour group’s visible
1234 of the Civil Code says as much, “If the obligation had substantially
irritation was aggravated when the tour guide announced that the city
performed in good faith, the obligor may recover as though there had
tour of Amsterdam was to be canceled due to lack of remaining time.
been and complete fulfillment, less damages suffered by the obligee.
Mrs. Pantaleon ended up weeping.

After the star-crossed tour had ended, the Pantaleon family


proceeded to the United States before returning to Manila. Before
heading home to Manila, the family stopped over in the US and the
same delay happened with several purchases that they made with the
AmEx credit card.

After the Amsterdam incident that happened involving the delay


of American Express Card, Pantaleon commenced a complaint for moral
and exemplary damages before the RTC against American Express. He
said that he and his family experienced inconvenience and humiliation
due to the delays in credit authorization. RTC rendered a decision in mental anguish, serious anxiety, wounded feelings and social humiliation
favor of Pantaleon. CA reversed the award of damages in favor of sustained by Pantaleon, as concluded by the RTC.
Pantaleon, holding that AmEx had not breached its obligations to
Case 19: Solar Harvest Inc., petitioner vs. Davao Corrugated Carton
Pantaleon, as the purchase at Coster deviated from Pantaleon's
Corp, respondent
established charge purchase pattern.
GR No. 176868, 26 July 2010
ISSUE: Whether or not AmEx is liable for breach of its contractual
obligations and is liable for damages TOPIC: Article 1169 of the Civil Code

RULING: FACTS:
In the first quarter of 1998, petitioner, Solar Harvest Inc.,
AmEx had committed a breach of its obligations to Pantaleon.
entered into an agreement with respondent, Davao Corrugated Carton
The popular notion that credit card purchases are approved “within Corporation, for the purchase of corrugated carton boxes, specifically
seconds,” there really is no strict, legally determinative point of designed for petitioner’s business of exporting fresh bananas, at US
demarcation on how long must it take for a credit card company to $1.10 each. The agreement was not reduced into writing. To get the
approve or disapprove a customer’s purchase, much less one specifically production started, petitioner deposited full payment in respondent’s US
contracted upon by the parties. One hour appears to be patently Dollar Savings Account. Despite such payment, petitioner did not receive
unreasonable length of time to approve or disapprove a credit card any boxes from respondent.
purchase. The culpable failure of AmEx herein is not the failure to timely
approve petitioner’s purchase, but the more elemental failure to timely a. Petitioner’s Aggreement (Solar Harvest Incorporated – LOST)
act on the same, whether favorably or unfavorably. Even assuming that - Petitioner filed a complaint for sum of money and damages
AmEx’s credit authorizers did not have sufficient basis on hand to make a against respondent. The Complaint stated that the parties
judgment, there is no reason why it could not have promptly informed agreed that the boxes will be delivered within 30 days from
Pantaleon the reason for the delay, and duly advised him that resolving payment but respondent failed to manufacture and deliver
the same could take some time. the boxes with such time.
- The repeated follow-up was made by the plaintiff for the
AmEx is liable for damages. The reason why Pantaleon is entitled immediate production of the ordered boxes , but everytime ,
to damages is not simply because AmEx incurred delay, but because the defendant would only show samples of boxes and make
delay, for which culpability lies under Article 1170, led to the particular repeated promises to deliver the said ordered boxes.
injuries under Article 2217 of the Civil Code for which moral damages are - That because of the failure of the defendant to deliver the
remunerative. The somewhat unusual attending circumstances to the ordered boxes, plaintiff had to cancel the same and demand
purchase at Coster – that there was a deadline for the completion of payment and/or refund from the defendant but the latter
that purchase by petitioner before any delay would redound to the refused to pay and/or refund the US$40,150.00 payment
injury of his several traveling companions – gave rise to the moral shock, made by the former for the ordered boxes.
b. Respondent’s Aggreement (Davao Corrugated Carton Corp. – The Court of Appeals decision is affirmed.
WON)
- As early as April 3, 1998, it had already completed RULE:
production of the 36,500 boxes, contrary to petitioner’s In reciprocal obligations, as in a contract of sale, the general rule is that
allegation. According to respondent, petitioner, in fact made the fulfilment of the parties’ respective obligation should be
an additional order of 24,000 boxes, out of which, 14,000 simultaneous. Hence, no demand is generally necessary because, once a
had been completed without waiting for petitioner’s party fulfils his obligation and the other party does not fulfil his, the
payment. Respondent stated that that petitioner was to pick latter automatically incurs in delay. But when the different dates for the
up the boxes at the factory as agreed upon, but petitioner performance of obligation are fixed., the default for each obligation
failed to do so. must be determined by the rules given in the first paragraph of the
- Respondent claimed that the boxes were occupying present article, that is, the other party would incur in delay only from
warehouse space and that petitioner should be made to pay the moment the other party demands fulfilment of the formers
storage fee at 60.00 per square meter for every month from obligation. Thus, even in reciprocal obligations, if the period for the
April 1998. Respondent prayed that judgement be rendered fulfilment of the obligation is fixed, demand upon the obligee is still
ordering petitioner to pay $15,400.00, plus interest, moral necessary before the obligor can be considered in default and before a
and exemplary damages, attorney’s fees, and costs of the cause of action for recission will accrue.
suit.
APPLICATION:
ISSUE: Evident from the records and even from the allegations in the complaint
Whether or not petitioner may claim reimbursement under Article 1191 was the lack of demand by petitioner upon respondent to fulfill its
of Civil Code. obligation to manufacture and deliver the boxes. The Complaint only
alleged petitioner made a “follow-up” upon respondent, which,
FINDINGS OF THE LOWER COURT: however, would not qualify as a demand for the fulfilment of the
Judgement is rendered in favour of defendant and accordingly, plaintiff’s obligation. Petitioner’s witness also testified that they made a follow-up
complaint is hereby dismissed without pronouncement as to cost. of the boxes, but not a demand. Note is taken on the fact that, with
Defendant’s counterclaims are similarly dismissed for lack of merit. respect to their claim for reimbursement, the complaint alleged and
witness testified that a demand letter was sent to respondent. Without a
FINDINGS OF THE COURT OF APPEALS: previous demand for the fulfilment of obligation, petitioner would not
The Court of Appeals denied the appeal of Solar Harvest Inc. for lack of have a cause of action for rescission against respondent as the latter
merit. The appellate court held that petitioner failed to discharge its would not yet be considered in breach of its contractual obligation.
burden of proving what it claimed to be the parties agreement with
respect to the delivery of the boxes. CONCLUSION:
The CA decision is affirmed, petitioner is given a period of 30 days from
RULING OF THE SUPREME COURT: notice within which to cause the removal of the 36,500 boxes from
respondent’s warehouse. After the lapse of said period and petitioner
fails to effect such removal, respondent shall have the right to dispose of
the boxes in any manner it may fit deem.

You might also like