Professional Documents
Culture Documents
Procedure Fabrication Pt. HAMON - Comment
Procedure Fabrication Pt. HAMON - Comment
(with cover)
Distribution
Dept. Copy
Checked by AR.W
Approved by DJ.S
This page is a record all of revision of the Fabrication Procedure and the following
revision (s) had (have) been made to the documents.
1 Scope 4 of 6
2 Applicable Documents 4 of 6
3 List of Item 4 of 6
4 Procedure 4 of 6
4.3 Welding 5 of 6
Nondestructive
4.4 Nondecstructive Examination 6 of 6
4.6 Paiting 6 of 6
Sheet No. :
FABRICATION AND 4 of 6
PT. TUBAN STEEL WORK
INSPECTION PROCEDURE
Doc. No.:
Job No. : OP - 013 013 -16 Eng.Pro - 001
1. Scope
1.1 This procedure covers the details instruction of shop fabrication and inspection necessary
for manufacturing of Fabrication Motor Frame & Support ordered by PT. Hamon
Indonesia.
1.2. Shop fabrication of equipment shall be based on approved drawing and approved
applicable procedures.
1.3 Prior to witness inspection, the shop tests and inspection shall be performed and
confirmed to satisfy the requirements of applicable codes and purchaser specifications.
1.4 The Fabrication and Inspection item to be witnessed shall be in accordance with
approved quality plan.
2. Applicable Documents
3. List of Item
4. Procedure
4.1 Receiving Inspection of Material
4.1.1 Material Certificate
All material shall have mill certificate issued by mill maker or inspection
agencies. Material certificate shall identify charge no. and/or heat no. of material.
It shall contain following states:
a. Chemical compositions.
b. Mechanical properties.
c. Dimension.
d. Other tests as specified by applicable codes / standard and material specification.
Sheet No. :
FABRICATION AND 5 of 6
PT. TUBAN STEEL WORK
INSPECTION PROCEDURE
Doc. No.:
Job No. : OP - 013 013-16 – Eng.Pro - 001
4.1.3 Storing
Material shall be store in appropriate place and gives clear identification by
mean of label ( for small parts ) and color mark / lettering ( for plates, pipes,
bars, etc.).
4.3 Welding
4.3.1 Welder qualification
Welders and welding operators shall be qualified as per Section IX ASME Code
and to be certified by MIGAS.DISNAKER OR MIGAS
4.3.2 Welding Procedure shall be performed as per WPS / PQR which shall be qualified
in according with Section IX of ASME Code.
4.3.3 Tack welding
Tack welds shall be made to a qualified welding procedure and by approved
welders. Tack weld shall be completely removed prior to welding.
4.3.4 Temporary welding
Temporary welds for temporary handling attachments, lug, etc. shall be minimized.
When temporary welding is deemed necessary, welding shall be performed with the
same approved procedures as for main fabrication welding and shall be done by
approved welders.
The temporary welds shall subsequently be ground flush and then inspected by liquid
penetrant test. The method of removing attachments shall not injure the metal surface
(i.e. removing by hammering off is not permitted).
Sheet No. :
FABRICATION AND 6 of 6
PT. TUBAN STEEL WORK INSPECTION PROCEDURE
Doc. No.:
Job No. : OP - 013 013-16 – Eng.Pro. - 001
4.3.5 Prior to start welding, QC shall check the edge preparation and cleanliness
of edge. All surfaces to be welded shall be visually inspected to ensure free
from lamination or other injurious defect.
4.3.6 After completion of welding the spatters or slag shall be removed by wire brush or
grinding. Visual inspection shall be performed to the surface of weld and it should meet
the following allowance :
a. The joint shall have completed penetration .
b. Crack or pit : none
c. Undercut : none
4.6 Painting
Painting shall be performed as per ‘Painting Procedure’. Document submitted separately.