RENOVATION OF MARISSA-CARLOS

APARTMENT
8302 Dapitan St., Guadalupe Nuevo, Makati City

PROGRESS REPORT NO. 4


April 25, 2020 – May 04, 2020

Prepared by:

VBDC Construction
ENGINEERS * BUILDERS * STRUCTURAL SOLUTIONS
RENOVATION OF MARISSA-CARLOS APARTMENT
8302 Dapitan St., Guadalupe Nuevo, Makati City
Accomplishment Status Report No. 4
Period Covering April – May 2020

A. Manpower Deployment

To date, the total manpower deployment during this period averaged to about 8
workforces this week. Work schedule is done in a single shift from 8:00 AM to 5:00 PM
Mondays to Saturdays .

B. Weather Update

Sunny weather. No rainfall experienced. Viable for work conditions.

C. Projected Project Schedule


Look-ahead schedule for daily activities for May 2020. See Accomplishment Report
Table. Page 2.

D. Various Progress Project Photographs.

1.) Finished Restoration of Walls Along Perimeter Fence (Unit A Second Floor)
2.) Finished Ceiling Replacement and Painting Works (Unit A Second Floor)

3.) Finished Cabinet Replacement and Painting Works (Unit A Ground Floor)
4.) Replaced Wall Partitions and Ceiling (Unit B- Second Floor)

5.) Finished Restoration Works and Ceiling and Wall Replacement, Painting Works in
Selected Areas Remaining (Unit B Ground Floor)
6.) Installation of Plumbing Fixtures and Tiling Works done (Unit C - CR)

Prepared by:

VBDC CONSTRUCTION:

Samuel M. Baculo
Project Engineer

Romani Noel S. Chavez Jr.


Project Engineer

Noted by:

ENGR. VEN LEE G. VILVAR


Project Manager/Consultant