Professional Documents
Culture Documents
TTA-NDT-PMI-001 Rev.00 PDF
TTA-NDT-PMI-001 Rev.00 PDF
: TTA/NDT/PMI/001
Page : 1 of 8
Page : 2 of 8
Page : 3 of 8
CONTENTS
Section Content Page
1. Scope 5
2. References 5
3. Qualification of personnel 5
4. Examination equipment 5
5. Preparation condition 5
6. Calibration 5
7. Extent of examination 6
8. Examination 6
9. Evaluation 7
10. Identification of acceptable materials 8
11. Documentation 8
Doc No. : TTA/NDT/PMI/001
Page : 4 of 8
1. SCOPE
This procedure is applicable to use the portable X-ray Fluorescence (XRF) equipment for
positive metal identification of alloy materials in critical process or pressure retaining services,
as defined in engineering standards of client.
X-Ray Fluorescent analysis shall be carried out to this instruction, an in accordance with
National Regulations of Radiation Protection, and any local requirements.
All Personnel using the equipment must wear a personnel radiation dose meter.
2. REFERENCE
XRF – Niton operation manual
Project’s specification of pipework according to ASME & ASTM Standards; Stainless steel
(SS), Alloy steel, UNS Material; A335; A312; E352; E353; E372.
3. QUALIFICATION OF PERSONNEL
All Test technicians shall have received training in the use of this equipment and passed an
appropriate examination.
4. EXAMINATION EQUIPMENT
The following will be used:
- XRF Unit
- Calibration sample
The calibration sample used during the set-up procedure shall be of known alloy with
traceability to National Standards.
Doc No. : TTA/NDT/PMI/001
Page : 5 of 8
5. PREPARATION CONDITIONS
The under test must be treated by any suitable process to remove surface oxide layers and
the alloy-depleted zone. Exceptions are 300-series stainless steels and other non-corroding
superalloys. The XRF source and detector must rest on the weld or be positioned with respect
to the weld in a precisely repeatable manner. Weld temperature limites are from -11 to 600C
6. CALIBRATION
Calibration shall be performed as specified in Operation Manual and maybe verified by using
standard test blocks of known composition.
7. EXTENT OF EXAMINATION
PMI maybe perform be the material manufacture, fabricator, supplier or authorized third-party
representative. It is responsibility of the contractor to ensure that implementation and conduct
of the PMI program is performed in accordance with this specification.
The test methods outline in this specification are intended to identify the nominal composition
of alloy materials. The test method are not intended to establish the conformance of a material
to a particular alloy specification.
PMI shall be performed at the point in time that ensure that proper materials have been used
in the fabrication of an identifiable assembly (Such as plate welder into a vessel or pipe length
welded into spool). This is typically at the supplier’s shop during fabrication or at the project
site for welds and for field assembled item not previously positively identified.
PMI of weld material shall be performed in the same manner as for the adjacent base metal.
PMI shall not be considered as substitute for required mill test reports listing chemical
composition. Mill test report shall not be considered as confirming alloy verification.
The requirement of PMI shall be in accordance with the specification and will be indication on
data sheet and/or requisition.
8. EXAMINATION
Set-up Procedure:
- Switch on equipment and configure the unit in accordance to weld being tested.
- Carry out a test with the supplied sample to attain the units of accuracy.
- Reading outside this value shall render the equipment un-calibrated and it shall be
returned for service
Doc No. : TTA/NDT/PMI/001
Page : 6 of 8
Timing of PMI:
- Timing of PMI shall be after assembly of component or equipment but prior to final
inspection.
- This shall be done by vendor at vendor’s work.
Operating procedure:
PMI results shall, within the following limits, comply with the Material Specification or welding
consumable procurement specification and shall be checked against the applicable material
certificated:
- For base material components, the recorded concentration shall be within the stated
tolerance range for the instrument but in no case less the minimum specified value
or greater than maximum specified value in the material specification.
Doc No. : TTA/NDT/PMI/001
Page : 7 of 8
- For deposited weld metal between similar base materials using matching
consumables, the recorded concentration shall be with the stated tolerance range
for the instrument but in no case less than the minimum specified value or greater
than maximum specified value in the material specification.
- For the deposited weld metal between dissimilar base materials, the recorded
concentration shall take account of dilution from the base materials, CONTRACTOR
will propose acceptance criteria for OWNER review and the approval, based on the
base materials, proposed welding consumables and expected dilution prior to
commencement of welding.
- Whenever material is identified as incorrect, the option is given to either perform a
more accurate test (e.g. wet chemical analysis) to verify the material composition or
to replace the material.
- Where any material is found to be unacceptable it shall be rejected. Rejected
material shall be suitably marked and segregated. The markings shall spoil any
existing marking or color coding to prevent accidental supply of the rejected item.
- Material and welds which is unacceptable test result shall be replaced and new
replaced material and welds shall be re-tested on 100% basic. If original sampling
frequency is not 100% (e.g. 5 or 10%). Additional 10% alloy verification test is
required in the same lot.
11. DOCUMENTATION
All PMI test shall be reported in a standard format to be approved by Owner
Report No. :
POSITIVE MATERIAL INDENTIFICATION Request No. :
EXAMINATION REPORT Date of inspected :
Page : 01 of 01