REPUBLIC OF THE PHILIPPINES

OFFICE OF THE BUILDING OFFICIALS


BEAM/SLAB TALISAY CITY

DRILLED DOWEL BARS W/

10db
EPOXY TO MATCH VERTICAL
GENERAL STRUCTURAL/CONSTRUCTION NOTES AND SPECIFICATIONS REINFORCEMENT
RECOMMENDING FOR ISSUANCE

200
(A) GENERAL REQUIREMENTS
1. ALL STRUCTURAL MATERIALS AND WORK SHALL CONFORM TO THE REQUIREMENTS 6. MAINTAIN MINIMUM CONCRETE COVER FOR REINFORCING STEEL AS FOLLOWS: CHB WALL REINF. BOND BEAM REINFORCED SECTION HEAD, STRUCTURAL DATE
OF THE LATEST EDITION OF THE NATIONAL STRUCTURAL CODE OF THE PHILIPPINES (SEE SCHEDULE) WITH 2-Ø10 H.B. AND Ø10
FOOTINGS (CAST AGAINST & EXPOSED TO EARTH) . . . . . 75MM (3") @300 O.C STIRRUPS
(NSCP 2001).
EXTERIOR CHB WALL APPROVED:
WHERE CONCRETE IS EXPOSED TO
2. VERIFY ALL DIMENSIONS, ELEVATIONS AND SITE CONDITIONS BEFORE STARTING
EARTH BUT POURED AGAINST FORMS . . . . . . . . . . . . . . . . 50MM (2")
WORK. NOTIFY THE ENGINEER IMMEDIATELY OF ANY DISCREPANCIES.
3. NOTES AND DETAILS ON THE DRAWINGS TAKE PRECEDENCE OVER THE GENERAL
SLAB ON GRADE . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 40MM ( 1 1/2")
EXTERIOR WALL SUPPORT AT
NOTES AND TYPICAL DETAILS IN CASE OF CONFLICT. COLUMN TIES OR SPIRALS AND BEAM STIRRUPS . . . . . . . 40MM ( 1 1/2") BOTT. OF BEAM OR SLAB SOFFIT BUILDING OFFICIAL DATE
4. WHERE CONSTRUCTION DETAILS ARE NOT SHOWN OR NOTED FOR ANY PART OF THE SUSPENDED SLABS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20MM ( 3/4")
WORK, SUCH DETAILS SHALL BE THE SAME AS FOR SIMILAR WORK SHOWN ON THE
7. SPLICES SHALL BE SECURELY WIRED TOGETHER AND SHALL LAP AT LEAST 40 TIMES
SPOT DETIAL A
DRAWINGS.
DIAMETER OR 600MM WHICHEVER IS GREATER. STAGGER BOTTOM AT LEAST 1.50M
5. PIPES, DUCTS, SLEEVES, CHASES, ETC. SHALL NOT BE PLACED IN SLABS, BEAMS, OR FROM SPLICES IN OTHER BOTTOM REINFORCEMENT. STAGGER SPLICES FOR TOP
WALLS UNLESS SPECIFICALLY SHOWN OR NOTED NOR SHALL ANY STRUCTURAL REINFORCEMENT SIMILARLY.
MEMBER BE CUT FOR PIPES, DUCTS, ETC. UNLESS SPECIFICALLY SHOWN. OBTAIN H
PRIOR WRITTEN APPROVAL FROM THE ENGINEER FOR INSTALLATION OF ANY 8. ALL ANCHOR BOLTS, DOWELS, AND OTHER INSERTS SHALL BE PROPERLY
ADDITIONAL PIPES, DUCTS, ETC. POSITION AND SECURED IN PLACE PRIOR TO PLACING OF CONCRETE.
H
LOCATE AND PROTECT UNDERGROUND OR CONCEALED CONDUIT, PLUMBING OR 9. ALL CONCRETE SHALL BE KEPT MOIST FOR A MINIMUM OF 7 CONSECUTIVE DAYS
OTHER UTILITIES WHERE NEW WORK IS BEING PERFORMED. IMMEDIATELY AFTER POURING BY THE USE OF CURING COMPOUNDS, OR OTHER
6. LOCATE AND PROTECT UNDERGROUND OR CONCEALED CONDUIT, PLUMBING OR APPROVED METHODS.
OTHER UTILITIES WHERE NEW WORK IS BEING PERFORMED. 10. STRIPPING OF FORMS AND SHORES:
FOUNDATION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 24 HRS.

H
7. TAKE NECESSARY PRECAUTIONS TO MAINTAIN AND INSURE THE INTEGRITY OF THE
STRUCTURE DURING CONSTRUCTION. NEITHER THE OWNER NOR SUSPENDED SLAB EXCEPT WHEN
ARCHITECT/ENGINEER WILL ENFORCE SAFETY MEASURES OR REGULATIONS. IT ADDITIONAL LOADS ARE IMPOSED . . . . . . . . . . . . . . . . . . . . . . . . 8 DAYS CRITICAL SECTION
(INTERIOR FACE OF
SHALL BE THE CONTRACTORS RESPONSIBILITY TO PROVIDE ADEQUATE SHORING BEAMS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14 DAYS SUPPORT)
AND BRACING OF THE STRUCTURE FOR ALL THE LOADS THAT MAYBE IMPOSED
DURING CONSTRUCTION. FURTHER, THE CONTRACTOR SHALL DESIGN, CONSTRUCT (E) CAMBER REQUIREMENTS
AND MAINTAIN ALL SAFETY DEVICES AND SHALL BE SOLELY RESPONSIBLE FOR WHERE:
1. UNLESS OTHERWISE NOTED ON THE PLANS OR SPECIFICATIONS CAMBER ALL RC Ldh = DEVELOPMENT LENGTH FOR
CONFORMING TO ALL SAFETY AND HEALTH STANDARDS, LAWS AND REGULATIONS. STANDARD HOOK
BEAMS AT LEAST 10mm FOR EVERY 4000mm OF CLEAR SPAN EXCEPT CANTILEVERS H = EXTENSION
8. OBTAIN PRIOR WRITTEN APPROVAL FROM THE ENGINEER IN CASE OF CHANGES TO WHICH WHICH SHALL BE 50mm FOR EVERY 3000mm OF CLEAR SPAN. r = INSIDE RADIUS OF BEND
THE WORKING DRAWINGS.
*ONLY WHEN USED AS COMPRESSION MEMBER IN FOOTING,
2. UNLESS OTHERWISE NOTED ON THE PLANS OR SPECIFICATIONS CAMBER ALL SLABS SPLICED WITH DOWELS OR WHEN LAP SPLICED
WITH SMALLER BAR.
(B) DESIGN CRITERIA 8mm PER 3000mm OF SHORTER SPAN AND 14mm FOR EVERY 2000mm OF SLABS H
CANTILEVER SPAN. Ldh STIRRUPS AND TIE HOOKS
- - - REFER TO STRUCTURAL COMPUTATIONS
(F) MASONRY AND CONCRETE BLOCKS
(C) FOUNDATION STANDARD HOOKS SEE CONSTRUCTION NOTES
FOR MASONRY WALL REIN-
1. CONCRETE HOLLOW BLOCKS, UNLESS OTHERWISE SPECIFIED SHALL BE 150MM FORCEMENTS (TYPICAL)
1. FOOTINGS SHALL BEAR ON SOLID UNDISTURBED EARTH (CONTROLLED, COMPACTED THICK. LOAD BEARING BLOCKS SHALL HAVE A MINIMUM COMPRESSIVE STRENGTH OF
STRUCTURAL FILL OR BOTH) AT LEAST 450MM BELOW LOWEST ADJACENT FINISHED 750 PSI (5.175 MPa) WHILE NON-LOAD BEARING SHALL HAVE A MINIMUM
GRADE. COMPRESSIVE STRENGTH OF 400 PSI (2.76 MPa). BEAM/SLAB
FIN. FLR. LVL.
2. FOOTING IS DESIGNED FOR ALLOWABLE SOIL/FOUNDATION PRESSURE OF 909.72kPa. DOWEL BARS TO MATCH
2. PROVIDE 1-16MMØ VERTICAL BARS AT CORNERS, INTERSECTIONS, END OF WALLS,

VARIES
CHB VERT. BARS
EACH SIDE OF OPENINGS.
DRILLED DOWEL BARS W/ N.G.L
3. SUB-GRADE PREPARATION INCLUDING DRAINAGE, EXCAVATION, COMPACTION, 3. LINTEL BEAMS SHALL BEAR AT LEAST 200MM (8") ON EACH SIDE OF MASONRY WALL

10db

DIAMETER
EPOXY TO MATCH VERTICAL

DOWELS
30 BAR
AND FILLING REQUIREMENTS, SHALL CONFORM STRICTLY WITH THE OPENING. REINFORCEMENT
RECOMMENDATIONS GIVEN IN THE SOILS REPORT OR AS DIRECTED BY THE SOILS

600 (MIN.)
4. WALL REINFORCEMENTS SHALL BE AS FOLLOWS:

200
ENGINEER.
WALL THICKNESS VERTICAL BARS HORIZONTAL BARS
4. THE CONTRACTOR SHALL NOTIFY THE ENGINEER AFTER FOOTING EXCAVATION

250
HAVE BEEN COMPLETED AND PRIOR TO CONCRETING TO CONFIRM THE DESIGN 8 IN. (200 mm) . . . . . . . . . . 12MMØ @ 400 mm 10MMØ @ 600 mm 3-10MM Ø BOT. BARS
6 IN (150 mm) . . . . . . . . . . . 10MMØ @ 400 mm 10MMØ @ 600 mm CHB WALL REINF. BOND BEAM REINFORCED
FOUNDATION CAPACITY. (SEE SCHEDULE) WITH 2-Ø10 H.B. AND Ø10
4 IN. (100 mm) . . . . . . . . . . 10MMØ @ 400 mm 10MMØ @ 600 mm @300 O.C STIRRUPS
5. ROOF AND AREA DRAINAGE SHALL BE DIRECTED AWAY FROM THE FOUNDATIONS.
INTERIOR CHB WALL 10MM Ø BOT. BARS
5. BLOCK WALL REINFORCING BARS SHALL BE LAPPED OF 30 BAR DIAMETERS WHERE
6. EXCAVATIONS SHALL BE PROPERLY BACKFILLED. BACKFILL FOR WALLS SHALL BE 400 @ 300 O.C.
SPLICED, HORIZONTAL/VERTICAL DOWELS FROM FOOTINGS, COLUMNS/WALLS OR
PERVIOUS MATERIAL ACCEPTABLE TO THE GEOTECHNICAL ENGINEER. DO NOT PLACE
SLABS SHALL EXTEND INTO THE BLOCK WALL A MINIMUM OF 30 BAR DIAMETERS OR A
BACKFILL BEHIND WALLS BEFORE THEY HAVE ATTAINED THEIR DESIGN STRENGTH.
SHORE AND PROTECT WALLS FROM LATERAL LOADS UNTIL THE SUPPORTING
MINIMUM OF 400MM WHICHEVER IS LONGER AND DOWELS TO MATCH VERTICAL INTERIOR WALL SUPPORT AT BOTTOM AT EDGE / PERIMETER CHB WALL
REINFORCEMENTS OF WALL.
MEMBERS ARE IN PLACE AND HAVE DEVELOPED SPECIFIED STRENGTHS.
OF SLAB/BEAM
(G) STRUCTURAL STEEL
(D) REINFORCED CONCRETE
1. ALL STRUCTURAL STEELS SUCH AS ANGLES, WIDE FLANGE SECTIONS, PIPES,
1. CONCRETE SHALL BE MIXED, PROPORTIONED, CONVEYED AND PLACED IN STIFFENER PLATES, BASE PLATES, ETC. SHALL CONFORM TO ASTM A-36.
ACCORDANCE WITH THE PROVISIONS SET BY THE NSCP 2001. DOWEL TO MATCH
2. ALL STRUCTURAL STEEL SHALL BE DETAILED, FABRICATED AND ERECTED BASED ON CHB VERT. BARS
THE SPECIFICATION FOR DESIGN, FABRICATION, AND ERECTION OF STRUCTURAL DOWEL TO MATCH
2. ALL CONCRETE SHALL DEVELOP A MINIMUM COMPRESSIVE STRENGTH AT 28 DAYS CHB VERT. BARS
WITH CORRESPONDING MAXIMUM SLUMP AND MAXIMUM SIZE AGGREGATE AS STEEL GIVEN BY THE NATIONAL STRUCTURAL CODE OF THE PHILIPPINES (NSCP).
WHERE SLAB
FOLLOWS: 3. CONNECTION BOLTS (34
ROUND, UNLESS SHOWN OTHERWISE) SHALL CONFORM TO DEPRESSION OCCURS

STRUCTURAL MEMBER 28 DAY STRENGTH MAX. SLUMP MAX. SIZE AGG. ASTM A-325. ANCHOR BOLTS (EMBEDDED IN MASONRY OR CONCRETE) SHALL 300
(TYP.) 300

DIAMETER
CONFORM TO ASTM A307 UNLESS NOTED OTHERWISE ON THE DRAWINGS.

DOWELS
(TYP.)

30 BAR

DIAMETER
DOWELS
A. SLAB ON GRADE 27.6 MPa (4,000 PSI) 100MM (4") 25MM (1")

30 BAR
B. FOOTINGS & RETAINING WALLS 27.6 MPa (4,000 PSI) 100MM (4") 19MM (3/4") 4. ALL STRUCTURAL STEEL SHALL BE CLEAN, RUST FREE AND SHOP COATED WITH THE
C. COLUMNS / SHEARWALLS 27.6 MPa (4,000 PSI) 100MM (4") 19MM (3/4") APPROPRIATE PAINT. STRUCTURAL STEEL AND ANCHOR BOLTS SHALL BE MINIMUM
D. BEAMS & SLABS 27.6 MPa (4,000 PSI) 100MM (4") 19MM (3/4") ASTM A-36 DOMESTIC, LATEST REVISION. FIN. FLR. LVL.

250
5. NON - SHRINK GROUT - PRE-MIXED, NON-METALLIC, CEMENT-BASED GROUT, MEETING

250
3. ALL REINFORCING STEEL BARS SHALL CONFORM TO ASTM A615 GRADE 40 FOR THE REQUIREMENT OF ASTM C827, ASTM C109 & CRD-C621, WITH A MINIMUM
12MMØ AND SMALLER BARS WHILE BARS 16MMM Ø AND LARGER SHALL BE GRADE 60. COMPRESSIVE STRENGTH OF 7000psi AT 28 DAYS.
6. PROVIDE MISCELLANEOUS PLATES, ANGLES AND ANCHORS AS SHOWN OR NOTED ON 6-10MM Ø BARS (AS SHOWN)
4. ALL FABRICATION, DETAILING AND PLACING SHALL CONFORM TO THE PROVISIONS DRAWINGS. 6-10MM Ø BARS (AS SHOWN)
SET BY THE NSCP 2001 EDITION. 10MM Ø BOT. BARS @ 300 O.C.
7. ALL CUTTING AND BLOCKING OF STEEL SHALL BE SHOWN ON SHOP DRAWINGS AND 10MM Ø BOT. BARS @ 300 O.C.
PERFORMED IN SHOP. 400
5. CLEAR DISTANCE SPACING BETWEEN PARALLED BARS IN A LAYER SHALL NOT BE 400
LESS THAN 1.50 TIMES THE NOMINAL DIAMETER OF THE BAR, OR 1.33 TIMES MAXIMUM 8. PROVIDE TEMPORARY BRACING AS REQUIRED FOR A SAFE STRUCTURE UNTIL ALL
SIZE AGGREGATE, NOR LESS THAN 38MM (1 21"). FINAL CONNECTIONS ARE MADE. AT INTERIOR WALLS WITH
AT INTERIOR CHB WALLS
SLAB ELEVATION DIFFERENCE

WALL FOOTING DETAILS (WHERE APPLICABLE)

PREPARED BY : PROJECT TITLE : OWNER


PRC REG. NO. : 0113495
ALTHEA RAMIREZ SMITH
S
VALID UNTIL : AUG. 12, 2019 DATE REG. : JUNE 01, 2009
PROPOSED 4- STOREY RESIDENTIAL married to 01 21
ENGR. WILBERT WOODROW C. REUYAN PTR NO. : 3290982 BRADLEY STEWART SMITH
Civil Engineer BUILDING W/FENCE SHEET CONTENT:

DATE : JAN. 04, 2019

TIN NO. : 283 - 570 - 417 - 000 LOCATION : LOT 32,33,34&35 BLOCK 6, VISTA GRANDE SUBDIVISION CANDULAWAN TALISAY CITY CEBU ADDRESS : BLOCK 6, LOT 34 PACIFIC HEIGHTS CANDULAWAN TALISAY CITY CEBU
CAD by: Engr. Reuyan