JSRG - Mom - DRM - 04 (13.12.2018) PDF

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 3

Minutes of Meeting – Design Review Meeting – 04

DATE : 13.12.2018.
TIME : 3:30 PM
PROJECT : Jain’s Sri Ram Gardens at Suchitra
VENUE : Genesis office, Jubilee Hills, Hyderabad.
SUBJECT : Design Review Meeting – 004

ATTENDEES:
S.No Organization Attendees
1 Genesis Planners (Architects) Mr. Sabir Pasha, Mr. Nandeeswar, Mr. Suresh, Mr. Anil
2 Jain Constructions (Client) Mr. Anuj Jain
3 Tata Projects Ltd (PMC) Mr.Venugopal, Mr.Senthilkumar, Mr.Srikanth, Mr.Kenneth
4 Ralys MEP Consultants Mr.Giridhar, Mr. Hanumanth Reddy

Status /
S.No Item Description Target
Action
Review of Open Issues Log & Agenda points:

1. TPL Requested Genesis to provide List of drawings (structural)


with revised dates.
15th Dec’18 GENESIS
GENESIS agreed to provide the list of drawings without dates
due to delay in Tower A finalization.

2. TPL Requested Genesis to provide tower A (Commercial &


Residential floors).
th
GENESIS informed tower A drawings will be shared after 17 Dec’18 GENESIS
finalization of PT designs.

3. TPL Requested Genesis to provide the car wash & driver toilet
provision .

GENESIS informed that same has been considered at Tower B, Info GENESIS/RALY
Cellar 1 Level. S

4. TPL Requested Genesis Car parking zone for commercial &


residential at tower A
Info GENESIS
GENESIS informed that it has been done in the floor plan. Same
will be released after getting approval.

5. TPL Requested Genesis all sumps, pump room, Ramp & staircase
details & drawings for Tower A

PROJECT: Jain’s Sri Ram Gardens Page 1 of 3 Date: 15th December 2018
Minutes of Meeting – Design Review Meeting – 04
Genesis informed that after finalization of Tower A drawings, it 22ndDec’18 GENESIS
will be released by 22nd Dec’18.

6. TPL Requested Genesis Tower A commercial PT vendor


finalization status.

Jain Constructions has to finalize vendor with all details. Info GENESIS/JAIN’
s
7. TPL Requested Genesis to release the Civil & Landscape BOQ at
the earliest.

GENESIS informed BOQ under preparation same will be released


month of Jan’19. Info GENESIS

8. TPL Requested Genesis to discuss with landscape consultant to


update the status of BOQ & drawings for Tower A & B. Info GENESIS/ELE
MENTS
9. TPL Requested Genesis for Tower A, access to lift machine room
provision for commercial Lifts with detailed drawing required at
the transfer slab level.

GENESIS to be worked out the same and release the drawing. Info GENESIS
10. TPL discussed about 9” thick Brick Masonry as per DGPA, as all
columns & Beams designed with 8” thick.

Genesis informed as decision has to take by M/s Jain


Construction only. Info GENESIS/JAIN
S
11. Storm water Sump location has changed from South- East corner
to North- East Corner at Tower A Info GENESIS

12. Genesis informed as Service Lift & Staircase has changed the
sizes, some of columns are changed the orientation & added Info GENESIS
additional footings at Tower A.

MEP Points:

13. TPL requested Ralys to release Tower A,B & Club house all MEP
GFC & BOQ .

Ralys informed that tower B electrical drawings & BOQ already


shared with Genesis. Waiting for their confirmation. Same
22ndDec’18 RALYS
Genesis yet to be reviewed and approved. After getting Genesis
approval Ralys will release drawings & BOQ on or before 22nd
Dec’18. Firefighting drawings & BOQ will be released within 15
working days.

PROJECT: Jain’s Sri Ram Gardens Page 2 of 3 Date: 15th December 2018
Minutes of Meeting – Design Review Meeting – 04

14. Ralys confirmed that No sleeves provision in beams. Info RALYS


15. TPL Requested Ralys to share revised master list of drawings
15th Dec’18 GENESIS/RALY
RALYS has confirmed the same shall be provided on 15th Dec’18.
S
16. TPL Requested Ralys to release the revised storm water line
Drawings & BOQ for tower A & B.

Ralys has confirmed same shall be provide on or before 17th 17th Dec’18 GENESIS/RALY
Dec’18. S

Next Meeting:

Next Meeting will be intimated as per the requirement. Records

PROJECT: Jain’s Sri Ram Gardens Page 3 of 3 Date: 15th December 2018

You might also like