Professional Documents
Culture Documents
Original Cost Proposal PDF
Original Cost Proposal PDF
CIVIL/STRUCTURAL WORKS
MATERIALS LABOUR TOTAL
# PARTICULAR UNIT QTY
U-RATE AMOUNT U-RATE AMOUNT PHP
PRELIMINARY WORKS
1 EXCAVATION -BULK M3 1,273.01 Incl. - 305 388,268.05 388,268.05
2 HAULING, DISPOSAL M3 1,738.85 Incl. - 275 478,183.75 478,183.75
3 STRUCTURE EXCAVATION M3 440.44 Incl. - 450 198,198.00 198,198.00
4 SURFACE PREP. (TRIMMING + COMPACTION) M2 550.00 Incl. - 25 13,750.00 13,750.00
5 BACKFILLING , COMPACTION M3 678.22 Incl. - 350 237,377.00 237,377.00
6 GRAVEL/SAND BEDDING M3 41.25 850.00 35,062.50 367 15,138.75 50,201.25
7 DAMP PROTECTION M2 550.00 12.75 7,012.50 5.15 2,832.50 9,845.00
8 SAFETY PROVISION LOT 1.00 Incl. - 100,000.00 100,000.00
9 SUMP (PROVISIONAL AMOUNT) LOT 1.00 - 16,625.58 - 40,003.75 56,629.33
COLUMNS - SPECIAL MOMENT FRAMES RESISTING FORCES
GRIDLINE - 1
A. CONCRETE M3 5.07 3200 16,220.40 2800 14,192.85 30,413.25
10
B. REINFORCEMENT BAR KGS 1,729.04 41.5 71,755.19 12.5 21,613.01 93,368.20
C. FORMWORKS M2 57.04 525 29,944.69 575 32,796.56 62,741.25
GRIDLINE - 2
A. CONCRETE M3 5.30 3200 16,944.00 2800 14,826.00 31,770.00
11
B. REINFORCEMENT BAR KGS 1,637.38 41.5 67,951.18 12.5 20,467.22 88,418.41
C. FORMWORKS M2 65.12 525 34,185.38 575 37,441.13 71,626.50
GRIDLINE - 3
A. CONCRETE M3 5.56 3200 17,785.60 2800 15,562.40 33,348.00
12
B. REINFORCEMENT BAR KGS 1,657.70 41.5 68,794.73 12.5 20,721.30 89,516.04
12
26
A. FORMWORKS M2 78.65 525 41,291.25 575.0 45,223.75 86,515.00
26
B. CONCRETE M3 10.20 3,200 32,640.00 2,500.0 25,500.00 58,140.00
C. REINFORCEMENT BAR KGS 1,200.00 41.5 49,800.00 12.5 15,000.00 64,800.00
ROOF DECK LEVEL BEAMS/GIRDERS
A. FORMWORKS M2 273.99 525 143,844.75 575.0 157,544.25 301,389.00
27
B. CONCRETE M3 19.76 3,200 63,232.00 2,500.0 49,400.00 112,632.00
C. REINFORCEMENT BAR KGS 5,631.60 41.5 233,711.40 12.5 70,395.00 304,106.40
ROOF DECK LEVEL SLAB & CANOPY
A. FORMWORKS M2 218.25 525 114,581.25 575.0 125,493.75 240,075.00
28
B. CONCRETE M3 28.97 3,200 92,688.00 2,500.0 72,412.50 165,100.50
C. REINFORCEMENT BAR KGS 3,632.50 41.5 150,748.75 12.5 45,406.25 196,155.00
ROOF FRAMING
A. FORMWORKS M2 105.00 525 55,125.00 575.0 60,375.00 115,500.00
29
B. CONCRETE M3 8.40 3,200 26,880.00 2,800.0 23,520.00 50,400.00
C. REINFORCEMENT BAR KGS 1,554.00 41.5 64,491.00 12.5 19,425.00 83,916.00
PERIMETER FENCE / RETAINING WALL
L-FTG2 + L-FTG1
A. CONCRETE M3 32.85 3200 105,120.00 2,500.0 82,125.00 187,245.00
30
B. REINFORCEMENT BAR KGS 4,106.25 41.5 170,409.38 12.5 51,328.13 221,737.50
C. FORMWORKS NO FORMWORKS ALLOWED - EXCAVATION WILL BE EXACT TO THE FOOTING AREA LIMITS
COLUMNS (COLM -5)
A. CONCRETE M3 11.52 3200 36,864.00 2500 28,800.00 65,664.00
31
B. REINFORCEMENT BAR KGS 2,022.27 41.5 83,924.29 12.5 25,278.40 109,202.69
C. FORMWORKS M2 158.08 525 82,992.00 350 55,328.00 138,320.00
RETAINING WALL
A. CONCRETE M3 46.92 3200 150,144.00 2500 117,300.00 267,444.00
32
B. REINFORCEMENT BAR KGS 8,236.55 41.5 341,816.63 12.5 102,956.82 444,773.45
32
M2 PANEL WORKS
1 SUPPLY OF M2 PANEL LOT 1.00 By Others - Direct to Supplier
INSTALLATION OF M2 PANEL-ROOF M2 274.00 - - 35.0 9,590.00 9,590.00
2 STRUCTURAL CONCRETE-60mm Thk. TOP M3 16.44 3,200 52,608 2,500.0 41,100.00 93,708.00
SHOTCRETING SLAB SOFFIT M2 274.00 155 42,470 137.5 37,675.00 80,145.00
INSTALLATION OF M2 PANEL-WALL M2 1,493.80 - - 35.0 52,283.00 52,283.00
3
SHOTCRETING WORKS- M2 WALLS M2 2,987.60 155 463,078 98.65 294,726.74 757,804.74
9.85m X 4.15m - BASKETBALL COURT CONCRETING
4 M2 40.88 705 28,818.64 474.0 19,375.94 48,194.57
WORK- SLAB ONLY
POND
STAIRS METAL STRUCTURE - REQUIRES METAL FABRICATOR