Methodology-TG DECK-rev0 (4feb12)
Methodology-TG DECK-rev0 (4feb12)
Revision Status
Rev. No. Date of Description
Rev./1st
Issue
Name
Designation
Signature
Date
TABLE OF CONTENTS
1) Objective
2) Scope of Work
3) Raw Materials
4) Deployment of Equipment/Tools
5) Deployment of Labour
7) Reference Drawings
8) Concrete Transportation
9) Placement of Concrete.
12) Curing
15) Methodology
18) Staging and Form work for Track Hopper Concrete Pouring Plan
1. Objective:
2. Scope of Work:
3. Raw Materials:
The following Bulk materials are to be used for Track Hopper Concrete concreting.
Machineries Quantity
1. Batching Plant (Capacity- 45 cum/Hour) 1
2. Batching Plant (Capacity:- 30 cum/Hour) 1
3. Transit Mixer (Capacity:- 6 cum) 9
5. Deployment of Labour:
7. Reference Drawings:
8. Concrete Transportation:
Concrete shall be conveyed from Batching Plant to the concrete pumps by transit
mixers. Nine transit mixers shall be engaged for concrete transportation and one
additional shall be kept as stand-by.
All equipment used for transporting and placing of concrete shall be thoroughly
cleaned after each pour.
9. Placement of Concrete:
Two pumps and one boom placer shall be deployed for pumping Concrete. The
pumps, that shall be used here, have a concrete pumping capacity of Pump-1 is
60 m3/ hr., Pump-2 is 75 m3/hr. and boom placer is 120 m3/hr.
The pipelines shall be made of seamless steel pipes. At the end of the placing
boom, a heavy-duty flexible hose may be attached to facilitate Concrete Pouring
at sequenced locations. Strong Couplings shall be used to clamp both the flexible
and rigid pipes in proper alignment.
Cement mortar shall be flowed through the pipeline to lubricate the inner surface
of the pipes. Concrete shall then be pumped in continuation with cement mortar.
11.Compaction of Concrete:
12.Curing:
Post concrete inspection shall be carried out after removal of shuttering for
identifying defects like honeycombed surface, unset concrete or any other defects.
Report of the same, if any, shall be submitted to JVUNL/ DESIEN/ DPSI in the
approved format. Rectification measures, as necessary, shall be executed as per
mention in technical specification.
Concrete testing shall be as per the details in Test & Inspection Plan of Project
Quality Specifications/ IS Codes/ Manuals.
15.Methodology:
Start
IF OK
Concrete Casting (9)
Curing (10)